HomeMy WebLinkAbout#14 - 31st & Stillwater Blvd Feasibility STAFF REPORT
DATE: February 4, 2020
REGULAR
AGENDA ITEM: Approve Resolution Receiving Feasibility Report and Calling Hearing on
Improvement for the 31st Street & Stillwater Blvd Watermain Improvements
SUBMITTED BY: Jack Griffin, City Engineer
REVIEWED BY: Kristina Handt, City Administrator Sarah Sonsalla, City Attorney
Marty Powers, Public Works Director
Chad Isakson, Assistant City Engineer
ISSUE BEFORE COUNCIL: Should the City Council accept the Feasibility Report and call a public
hearing for the 31st Street & Stillwater Blvd Watermain Improvements to be held at the March 4th, 2020
Council meeting?
BACKGROUND: On November 19, 2019, the City Council authorized the preparation of a feasibility
report for the 31st Street & Stillwater Blvd Watermain Improvements. The project neighborhood is located
just south of Stillwater Boulevard (CSAH 14) and the Union Pacific Railroad, and just east of 31st Street
North. The neighborhood has six homes on lots ranging in size from 0.5 to 7.3 acres. The properties reside
in an area where per- and polyfluoroalkyl substances (PFAS) contamination exceeds Health Based Values
(HBVs) and well advisories have been issued.
The City of Lake Elmo was approved to receive grant funding from the Minnesota Pollution Control
Agency (MPCA) under the 2018 3M Settlement Agreement as an expedited project to extend municipal
water and connect each of the six homes. The grant is in the not to exceed amount of $449,100. The terms
of the grant are outlined in the grant agreement between the City of Lake Elmo and the MPCA dated
October 2, 2019. The grant agreement was approved by the City Council on October 1, 2019.
PROPOSAL DETAILS/ANALYSIS: The project extends the public watermain south across Stillwater
Boulevard (CSAH 14) from the north side, approximately 800 feet east of the intersection at 31st Street
North. On the south side of CSAH 14, watermain will be extended approximately 780 feet further south
along a shared private driveway. Individual water service stubs will be installed for each of the six
residential properties. The project will include grant funding and administrative processes for ensuring each
property completes the private service connection from the right-of-way to each home, including water
meter installation, removal of granular activated carbon treatment systems (if applicable), sealing of any
private well, and all permitting and connection fees. The private water connection and well sealing
improvements will be contracted separately by each property owner.
As part of the grant agreement with the MPCA, all households within the project limits, regardless of Health
Based Values (HBVs), are required to connect to municipal water and to have the private wells properly
sealed and abandoned as part of the project and within the timeframe of the grant agreement. To implement
these State requirements for the project the City intends to levy assessments for the public improvements
in accordance with the City’s Special Assessment Policy and current practices. Each property will be
required to connect to city water and abandon all private wells, unless exempted by the MPCA as a
monitoring well, within one year after water service is made available and following written notice from
the City to connect. Once the private improvements are completed the public improvement assessments
levied for this project will be considered paid in full and removed from the property.
In order to assess all or a portion of the improvements, the City must prepare a feasibility report as required
by the statutory process for public improvements that are specially assessed. The feasibility report has been
completed and provides the scope of recommended improvements; estimated project costs; identifies
easement and right-of-way, permits and other requirements needed to implement the improvements;
recommends whether the improvements should be best made as proposed or in connection with some other
improvement; and advises that the improvements are necessary, cost effective, and feasible. The report
also includes a preliminary assessment roll for each of the benefitting properties based upon the City’s
Special Assessment Policy for Local Improvements.
The total estimated project cost is $449,100. This includes $370,000 for the watermain improvements and
service stubs, and $79,100 for the private water service connections and well sealing improvements. The
proposed public watermain assessment is $61,700 for each of the six residential properties in the
neighborhood, based on assessing 100% of the public watermain improvements on a per REC basis.
Assessments for new watermain improvements will be levied over a 20-year period. All assessments that
are not waived and removed from the property will be charged an interest rate of 1% over the bond rate for
the project.
FISCAL IMPACT: The total estimated project cost is $449,100. The improvements will be funded
through a grant from the MPCA under the 2018 3M Settlement Agreement as an expedited project, and in
accordance with the MPCA-Lake Elmo Grant Agreement dated October 2, 2019.
The City will contract for the public improvements located within the public right-of-way, make payment
to the contractors and submit invoices for reimbursement through the MPCA Grant. The City intends to use
fund reserves for the public improvements to pay the up-front project costs and to cover any city cost
participation. Project invoices will be periodically submitted to the MPCA for grant reimbursement in
accordance with the terms of the grant agreement. The private water service connection and well sealing
work will be contracted separately by each individual property owner. Eligible private property costs will
be paid from the MPCA Grant on a reimbursement basis through the City. This reimbursement applies to
the contractor costs to install the water service line to the home connection, the costs to abandon the private
well(s) on the property, and all permit fees including a $3,000 Water Availability Charge (WAC), a $1,000
Water Connection Charge, a $1,040 Meter Fee, and a $61 Plumbing Permit Fee. If the property currently
has a granular activated carbon (GAC) treatment system, the removal of the system from the home will also
be reimbursed.
RECOMMENDATION: Staff is recommending that the City Council approve a Resolution, receiving
the Feasibility Report and calling a public hearing for the 31st Street & Stillwater Blvd Watermain
Improvements. The recommended motion for this action is as follows:
“Move to approve Resolution No. 2020-015, receiving the Feasibility Report and Calling a Public
Hearing for the 31st Street & Stillwater Blvd Watermain Improvements.”
ATTACHMENTS:
1. Resolution Receiving Report and Calling for Hearing on Improvements.
2. Notice of Hearing on Improvement.
3. 31st Street & Stillwater Blvd Watermain Improvements – Location Map.
4. 31st Street & Stillwater Blvd Watermain Improvements – Project Schedule.
Feasibility Report (available for review at City Hall).
CITY OF LAKE ELMO
WASHINGTON COUNTY
STATE OF MINNESOTA
RESOLUTION NO. 2020-015
A RESOLUTION RECEIVING A FEASIBILITY REPORT FOR THE
31ST STREET & STILLWATER BLVD WATERMAIN IMPROVEMENTS
AND CALLING HEARING ON IMPROVEMENT
WHEREAS, pursuant to City Council authorization, adopted on November 19, 2019, a
feasibility report has been prepared by FOCUS Engineering, Inc. for the 31st Street & Stillwater Blvd
Watermain Improvements; and
WHEREAS, the feasibility report recommends that benefitting properties be assessed all or a
portion of the cost of the improvements pursuant to the City’s Special Assessment Policy and Minnesota
Statutes, Chapter 429; and
WHEREAS, the feasibility report provides information regarding whether the proposed
improvement is necessary, cost-effective, and feasible; whether it should best be made as proposed or in
connection with some other improvement; the estimated cost of the improvements as recommended; and a
description of the methodology used to calculate individual assessments for affected parcels.
NOW, THEREFORE, BE IT RESOLVED,
1. That the City Council will consider the improvements in accordance with the report and the
assessments of the abutting properties for all or a portion of the cost of the improvements
pursuant to Minnesota Statues, Chapter 429 at an estimated total project cost of $449,100.
2. A public hearing shall be held on such proposed improvements on the 4th day of March, 2020, in
the council chambers of the City Hall at or approximately after 7:00 P.M. and the clerk shall give
mailed and published notice of such hearing and improvement as required by law.
ADOPTED BY THE LAKE ELMO CITY COUNCIL ON THE FOURTH DAY OF FEBRUARY,
2020.
CITY OF LAKE ELMO
By: __________________________
Mike Pearson
(Seal) Mayor
ATTEST:
________________________________
Julie Johnson
City Clerk
CITY OF LAKE ELMO
NOTICE OF HEARING ON IMPROVEMENT
31ST STREET & STILLWATER BLVD WATERMAIN IMPROVEMENTS
Notice is hereby given that the City Council of Lake Elmo will meet in the council
chambers of the city hall at or approximately after 7:00 P.M. on Wednesday, March 4,
2020, to consider the making of the following improvements, pursuant to Minnesota
Statutes, Sections 429.011 to 429.111;
The extension of municipal water along a private driveway located just south of
Stillwater Boulevard and the Union Pacific Railroad, and just east of 31st Street
North, to provide clean drinking water to 6 residential properties, including the
extension of a private water service stub for each home.
The area proposed to be assessed for the watermain improvements include all six
properties located in the neighborhood that will be receiving access to connect to city
water. The estimated total cost for the project is $449,100. A reasonable estimate of the
impact of the assessments will be available at the hearing. Such persons as desiring to be
heard with reference to the proposed improvements will be heard at this meeting.
DATED: February 4, 2020
BY ORDER OF THE LAKE ELMO CITY COUNCIL
Mike Pearson, Mayor
(Published in the Stillwater Gazette on February 7, 2020 and February 14, 2020)
LOCATION MAP
FIGURE NO. 1
31ST STREET & STILLWATER BLVD
CITY OF
LAKE ELMO
PRIVATE DRIVE
LEGEND
PROJECT NO. 2019.124
31ST STREET &
STILLWATER BLVD
WATERMAIN EXTENSION
PROPERTIES SERVED
PROJECT SCHEDULE
CITY OF LAKE ELMO
31ST STREET AND STILLWATER BLD WATERMAIN IMPROVEMENTS
PROJECT NO. 2019.124
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
OCTOBER 1, 2019 Council Approves MPCA Grant Agreement for 31st Street and Stillwater
Boulevard Watermain Improvements.
OCTOBER 15, 2019 Council Authorizes Topographic Survey and Final Design Services.
NOVEMBER 19, 2019 Council orders preparation of Feasibility Report.
FEBRUARY 4, 2020 Presentation of Feasibility Report. Council accepts Report and calls for
Improvement Hearing.
MARCH 4,2020 Public Improvement Hearing. Council Orders the Improvement (4/5th Vote).
Council approves Plans and Specifications and orders Advertisement for Bids.
APRIL 2, 2020 Project Bid Date: Receive contractor bids.
APRIL 21, 2020 Council accepts Bids and awards Contract.
MAY 19, 2020 Conduct Pre‐Construction Meeting and issue Notice to Proceed.
SEPTEMEBER 25, 2020 Substantial Completion.
NOVEMBER 13, 2020 Final Completion.
SEPTEMBER 7, 2021 Council Declares Costs to be Assessed and Calls for Hearing on Assessment.
OCTOBER 5, 2021 Final Assessment Hearing. Council adopts the Final Assessment Roll.