HomeMy WebLinkAbout#16 - Sunfish Lake Park Mountain Bike Trail STAFF REPORT
DATE: 3-4-2020
REGULAR
TO: City Council
FROM: Ben Prchal, City Planner
AGENDA ITEM: Sunfish Lake Park Trail Request for Proposal (RFP) – Proposal Review
REVIEWED BY: Kristina Handt, City Administrator
Parks Commission
BACKGROUND:
Over the course of 2018 and 2019 the City actively discussed and ultimately approved the construction of
a bike trail plan and an RFP for Sunfish Lake Park (November 5th, 2019). After the project received approval,
the RFP was published from December 2019 to January 2020. During that time the City received one bid
for review.
ISSUE BEFORE THE PARKS COMMISSION:
Would the City Council like to accept the recommended proposal from Trail Source LLC.?
PROPOSAL DETAILS/ANALYSIS:
The bid that was received to implement the approved trail plan came from Tim Wegner, owner operator of Trail
Source. As a side note Tim has been involved with the City regarding trail development in other parks as well.
During the review of Reid Park and the High School trail proposal Tim assisted with their trail design. Consequently,
that was the same time the City was reviewing Sunfish Park for its viability to acquire trials. Although Tim was the
only builder to submit a bid to the City, Staff is inclined to recommend the offer. Tim has visited the park and
designed the initial trail layout that was proposed to the City for review. Furthermore, Tim has provided a written
response to the RFP which is briefly addressed below. Nonetheless, Staff encourages the Council to review page 4
of the Trail Source response as it lists out the lead workers and their skill sets.
Trail Source History:
- Trail Source has been in business since 2000.
- A member of the Professional Trail Builders Association in 2002.
- Owner served on the American Trails Board for 4 years.
- Served on the Minnesota Off Road Cyclists (MORC) board for 10 years.
- Member of the Minnesota Recreational Trail Users Association for 10 years.
- 10 year International Mountain Bicycling Association (IMBA) volunteer.
The RFP made many references to the IMBA guidelines, Tim’s business Trail Source was used as a reference in
“IMBA’s Guide to Building Sweet Single Track” as a source for IMBA affiliated trail building. Trail Source is also
referenced in a blog post on the IMBA website from 2011 (Click Here). During Tim’s time with IMBA he taught
school 1-2 times a year for sustainable trail design.
Relevant Projects:
There are many projects listed in the submittal but Staff has chosen to pull out a few for review in the report.
Hillside Park, Elk River – Was experiencing significant erosion issues, Trail Source stepped in to reconstruct the
trials which subsequently eliminated the existing erosion issues. Now erosion maintenance no longer remains in
focus. A reference letter from the trail manager is attached.
Theodore Wirth Park, Minneapolis – Trail Source built and designed the trial system with coordination from the City
Staff. Theodore Wirth Park is actively used by more than just bike riders and is a popular park within the metro area.
2
Lebanon Hills, Dakota County – Similar to Sunfish Lake Park, Lebanon Hills had existing user groups. The bike
trails were designed around the existing walking trails to minimize the impact to the existing users. This park also
happens to be one of the most widely used parks in the Metropolitan area. A reference letter from the project manager
is attached.
Staff Comments – Staff spoke to Josh Kelly regarding Trail Source. Josh had positive things to say about the trail
builder. Stating that Tim has worked with them since 2008, commenting that Tim is a solid contractor who
incorporates sustainable trail building techniques into the trail. Sections of the trail were plagued with erosion, to
which gravel was brought in periodically to fix the issue. Tim was inevitably allowed to come in and redesign the
trails, now there is no issue of erosion.
FISCAL IMPACT (Estimated):
Trail Source submitted a bid for $111,682.21. This is a favorable bid as it came in $8,317.8 below the approved
expenditure to build the trails.
Trail Source will be providing a two year warranty after construction. Once the warranty period has expired the
yearly maintenance cost(s) are not expected to exceed $2,500.
PARKS COMMISSION AND STAFF RECOMMENDATION:
Parks Commission:
The Parks Commission reviewed the proposal and voted for approval by a 5-0 vote. There were quite a few questions
from the Commission which Tim Wegner was able to answer. With many of the questions being specific to how the
trial would be built, Staff did not have much to say beyond the report.
Staff Comment:
At this time, and although only one bid was received, Staff is confident that Trail Source will provide strong value to
the City throughout the build and would not have any reservations accepting Trail Source as the contractor.
“Motion to approve Resolution 2020-024 which approves a contract between The City of Lake Elmo and Trail
Source LLC. For the construction of trails within Sunfish Lake Park”
ATTACHMENTS:
Advertised RFP (Staff removed pages 22-32 to reduce the document size)
RFP Submittal Response
Lebanon Hills Reference Letter
Hillside Trail Reference Letter
Resolution Awarding Contract
Contract
February 12, 2020
Letter of Recommendation
For: Trail Source
13282 Derryglenn Ct
Rosemount, MN 55068
Mr. Prchal,
I understand that Trail Source has an opportunity to help Lake Elmo with a trail
building project and I want to speak up on their behalf. My perspective on Trail
Source has been informed by eleven years of experience with them working for
Dakota County Facilities Management and Parks Departments. I am pleased to
provide a letter of recommendation for Trail Source, builder of recreational trails and
boardwalks.
Over the past eleven years Trail Source has been the go to resource for trail
development and trail rehabilitation for Dakota County. Time and again Trail Source
went above and beyond to provide superior craftsmanship and increased
sustainability for the trails in our parks, both hiking and mountain biking. Trail Source
always employs their experience with sustainable trail Best Management Practices
(BMP) to find the best solutions for any project, either new trails or rehabilitation of
failing existing trails.
One project I am particularly proud of is the rehabilitation of the trail system at
Lebanon Hills Regional Park. Trail Source was able to turn a maintenance and
erosion nightmare into one for the most used trail systems in the metro. When Trail
Source arrived at the site it became immediately clear that they were able to visualize
solutions based on what they knew worked. They quickly outlined and implemented
an approach which over time has proven to save on staff time and use of tax payer
dollars.
The on-site personnel of Trail Source did a great job in keeping the existing parking
area and trail operational throughout the project. The project workmanship was
excellent, and all issues were addressed in a timely manner.
In summary, Dakota County would not hesitate to recommend the services of Trail
Source to you and others and plan to hire them again in the future.
Sincerely,
Josh Kinney, PLA, ASLA
Senior Project Manager – Dakota County Capital Project Management
DAKOTA COUNTY ADMINISTRATION CENTER
1590 Hwy 55 Hastings, MN 55033
952-891-7016 cell – 612-387-6260
Capital Projects
Dakota County
Administration Center
1590 Highway 55
Hastings, MN 55033
651.438.4388
Fax: 651.438.8455
www.co.dakota.mn.uss
Ben Prchal
3800 Laverne Avenue North
Lake Elmo, MN 55042
Dear Ben,
This is a letter of reference for Tim Wegner, owner of Trail Source LLC. I have worked with Trail Source
on a couple of singletrack trail projects in the Northwest metro area. The most recent project was at
Hillside City Park, in Elk River. This project was done in two phases, the Eastern half of the park had
trails constructed in 2017, and the Western half had trails constructed in 2018. The Eastern half of the
park was constructed by YRU Trail Building LLC. The Western half of the park was constructed by Trail
Source. Both halves of the park have similar topography with the South side flatter than the North side,
and same soil content. The soil is a mixture of gravel and sand in many areas, which can be challenging
to work with for a natural surface trail.
The East side of the park has required maintenance from day one. Keeping the outslope established and
defined has been a challenge in some areas, and we have needed to add grade reversal features to
prevent erosion and cupping of the trail. A couple of areas need tread resurfacing once a year. All this
does not mean it is badly constructed trail, as maintenance is often expected as an ongoing need.
However, how the trail was constructed is inferior to the West side of the park regarding erosion control
and overall engineering.
The West side of the park was constructed by Trail Source. This half of the park has required almost no
maintenance whatsoever. Grade reversal features were engineered into the trail to do a much better
job of preventing erosion, resulting in much lower maintenance needs, and a lower environmental
impact over the long term life of the trail. The trail is constructed in a manner where it is more popular
with mountain bikers, and is considered the favorite side of the park for many riders.
Tim was very nice to work with from day one, and explained their process in detail to both City staff and
the park volunteers. He communicated well throughout the project, checking in and occasionally
clarifying smaller details to ensure the finished product would meet or exceed everyone’s expectations.
During the construction of the trail, Trail Source employees suggested minor changes in the proposed
trail alignment for a couple of areas, and those suggestions were approved and implemented, resulting
in a better overall layout in that area as compared to the initial proposed trail alignment.
I would recommend Trail Source for any trail construction project, as Tim and his crew have mastered
the art of building enjoyable trails for all users, while minimizing maintenance costs. Communication is
great throughout the process, and expectations are always exceeded with his work.
Sincerely,
Graydon Betts
MORC Trail Steward – Hillside City Park Elk River, Bertram Chain of Lakes Monticello
1
640160v1LA515-1
TRAIL CONSTRUCTION PROJECT AGREEMENT
This Trail Construction Project Agreement (this “Agreement”), made and entered into this
_____ day of __________________, 2020, by and between the City of Lake Elmo, a Minnesota
municipal corporation, whose business address is: 3800 Laverne Avenue North, Lake Elmo, MN
55042 (the “City”) and TrailSource, LLC, a Minnesota Limited Liability Company, whose business
address is: 13282 Derryglen Court, Rosemount, MN 55068 (the “Contractor”).
In consideration of the payments and agreements hereinafter mentioned, the parties agree as
follows:
Article 1. Project.
1.1. The Contractor shall provide labor, supervision, materials, and equipment to perform
specified trail construction for a cross country/flow single track mountain bike trail system
within Sunfish Lake Park located at: 10000 Stillwater Lane North, Lake Elmo, MN 55042
(the “Site”). The trail specifications are set forth in the attached Exhibit A (the “Project”). The
Contractor agrees that all work and labor shall be done in the best and most diligent manner
and that all materials, equipment and labor shall be in entire and strict conformity in every
respect with the specifications set forth in attached Exhibit A. The Project must be performed
by the Contractor in compliance with all laws and regulations. Any trail construction which
does not comply with the specifications will be rejected by the City and Contractor must bring
the trail into compliance with the specifications at the Contractor’s expense.
Article 2. Execution, Correlation and Intent.
2.1. Execution of this Agreement by the Contractor is a representation that the Contractor has
visited the Site, is familiar with local conditions under which the Project is to be performed,
and correlated personal observations with requirements of this Agreement. The Contractor
further contracts and declares that it is thoroughly familiar with the nature, location, and
character of the general area in which the Project is located including, without limitation,
available equipment supply and equipment costs, the quantity and quality of all required
materials, supplies, tools, and labor needed to complete the Project in the manner and within
the costs and time frame required by this Agreement. Further, the Contractor recognizes the
extra degree of care required under the Site construction circumstances with respect to the
safety, protection of individuals and property at the Site, cleanliness of the Site, and protection
of existing property. In arriving at the Project cost and the completion date, Contractor has,
as an experienced and prudent contractor, exercised its best judgment and expertise to include
the impact of such circumstances in the Project cost and completion date.
Article 3. Rights, Responsibilities and Duties of the Contractor.
3.1. The Contractor shall supervise and direct the work using the Contractor’s best skill and
attention. The Contractor shall be solely responsible for and have control over construction
means, methods, techniques, sequences, and procedures and for coordinating all portions of
the work under this Agreement.
2
640160v1LA515-1
3.2. The Contractor shall be responsible for all acts and omissions of the Contractor’s employees,
subcontractors, and their agents and employees, and other persons performing portions of the
work under a contract with the Contractor. The Contractor shall not enter into subcontracts
for services provided under this Agreement without the express written consent of the City.
3.3. The Contractor has the responsibility to ensure that any equipment or material suppliers and
subcontractors, and their agents and employees adhere to this Agreement and that they order
equipment and materials on time, taking into account the current market and delivery
conditions and that they provide the equipment and materials on time. The Contractor shall
have the duty to coordinate all of its work and the work of its subcontractors and suppliers.
3.4. The Contractor agrees to indemnify, defend and hold the City harmless from and against any
and all claims, suits, actions, damages, causes of action, or attorneys’ fees, arising from any
personal injury, loss of life, or damage to person or property sustained by reason of or as a
result of the work performed by the Contractor under the contract. The Contractor agrees to
indemnify, defend and hold the City harmless from any and all claims, suits, actions, damages,
causes of action or attorneys’ fees arising from any personal injury, loss of life, or damage to
person or property sustained by reason of or as a result of the negligence of the Contractor, its
employees, contractors, agents, or assigns.
3.5. The City hereby retains the Contractor as an independent contractor upon the terms and
conditions set forth in this Agreement. The Contractor is an independent contractor and not
an employee of the City. The Contractor is free to contract with other entities as provided
herein. The Contractor shall be responsible for obtaining and furnishing equipment, materials,
and labor necessary for the Contractor’s performance under this Agreement. The City and
the Contractor agree that the Contractor shall not at any time or in any manner represent that
the Contractor is in any manner an agent or employee of the City. The Contractor shall be
exclusively responsible under this Agreement for the Contractor’s own FICA payments,
workers’ compensation insurance, unemployment compensation insurance, withholding
amounts, or self-employment taxes if any such payments, amounts, or taxes are required to
be paid by law or regulation.
Article 4. Changes to the Project.
4.1. Changes to the scope of the Project may be accomplished after execution of the Agreement,
and without invalidating the Agreement, by a change order, subject to the limitations stated
in this Article and elsewhere in this Agreement.
4.2. No extra work shall be done nor any obligation incurred for payment therefore except upon a
written change order fully signed by the City and approved by the City Council.
4.3. Each change order issued shall contain the following: 1) a detailed description of the change;
2) the Contractor’s written proposal; 3) a statement as to the resulting change in price or
completion time; 4) a statement that all work involved in the change shall be performed in
3
640160v1LA515-1
accordance with this Agreement’s requirements except as modified by the change order; and
5) signatures of the City and the Contractor.
Article 5. Project Completion Date.
5.1. The Contractor shall commence the work as soon hereafter as all conditions precedent have
been met, including but not limited to submission of the certificates of insurance and the
performance required by this Agreement. The Contractor shall complete construction and
installation of the Project no later than October 16, 2020. Liquidated damages of $500 per
week will be assessed by the City if the Project is not completed by this date. If the Contractor
is unable to complete construction of the trail within 30 days of the delivery date, the City
reserves the right to reject the trail and shall not be responsible for payment for the trail or any
consequential damages incurred by the Contractor.
Article 6. Protection of Persons and Property.
6.1. The Contractor shall be responsible for initiating, maintaining, and supervising all safety
precautions in connection with the performance of this Agreement.
6.2 The Contractor shall take reasonable precautions for the safety of, and shall provide
reasonable protection to prevent damage, injury, or loss to:
a. Employees and subcontractors on the Site performing the work and other persons who
may be affected thereby;
b. The Project and materials and equipment to be incorporated therein, whether in
storage on or off the Site, under the care, custody, or control of the Contractor or the
Contractor’s subcontractors or sub-subcontractors; and
c. Other property at the Site or adjacent thereto, such as any existing improvements not
designated for removal, relocation, or replacement in the course of the Project.
6.3. The Contractor shall, in the performance of the work under this Agreement, conform to all
applicable federal, state, and local laws, codes, ordinances, and regulations.
Article 7. Insurance.
7.1. The Contractor shall secure and maintain the following insurance:
a. Workers’ compensation insurance that meets the requirements of Minnesota law (if
required by statute). The Contractor shall execute the City’s workers’ compensation
form.
b. General liability insurance with bodily injury and property damage limits of
$1,500,000 to protect the Contractor and the City from claims and liability for injury
4
640160v1LA515-1
or damages to persons or property for all work performed by the Contractor under this
Agreement. The Contractor shall name the City as an additional insured under the
Contractor’s policy. Prior to performing any services under this Agreement, the
Contractor shall provide evidence to the City that acceptable insurance coverage is in
effect.
c. Automobile liability insurance with limits of $1,500,000.
7.2. The City shall not be liable or responsible for any loss or damage whatsoever to equipment,
tools, or property of a similar kind and the Contractor shall indemnify and hold harmless the
City from any claims or causes of action brought by any person or party as a result of the loss
or damage to the Contractor’s equipment, tools, or other property.
7.3. The Contractor shall provide a certificate of insurance in the amounts above. The required
insurance must name the City as an additional insured and shall state that the City shall receive
10 days written notice prior to cancellation or termination. Acceptance of the certificate of
insurance by the City shall not relieve, limit, or decrease the liability of the Contractor. The
City does not represent that this Agreement’s insurance requirements are sufficient to protect
the Contractor’s interests or provide adequate coverage.
Article 8. Performance and Payment Bonds.
8.1. The Contractor shall pay the premiums and shall furnish to the City performance and payment
bonds as required by Minnesota law. The bonds shall be in the amount of 100 percent of the
Contract Price as security for the faithful performance of this Agreement. The surety on each
bond shall be a surety company duly authorized to do business in Minnesota and that is
acceptable to the City Attorney.
Article 9. Correction of Work.
9.1 The Contractor shall promptly correct work rejected by the City or failing to conform to the
requirements of this Agreement, whether observed before or after completion and whether or
not fabricated, installed, or completed. The Contractor shall bear the costs of correcting such
rejected work.
Article 10. Miscellaneous Provisions.
10.1. The laws of the State of Minnesota shall control this Agreement.
10.2. Neither party shall assign this Agreement, or any interest arising herein, without the written
consent of the other party.
10.3. This Agreement constitutes the entire Agreement between the parties, and no other agreement
prior to or contemporaneous with this Agreement shall be effective, except as expressly set
forth or incorporated herein. Any purported amendment to this Agreement is not effective
unless it is in writing and executed by both parties.
5
640160v1LA515-1
10.4. The Contractor shall provide the City access to any books, documents, papers, and records
which are directly pertinent to the Agreement, for the purpose of making audit, examination,
excerpts, and transcriptions, for three years after final payments and all other pending matters
related to this Agreement are closed.
10.5. The Contractor shall have access to data collected or maintained by the City as deemed
necessary to perform the Contractor’s obligations under this Agreement. Such data will be
provided to the Contractor as governed by the Minnesota Government Data Practices Act,
Minnesota Statutes Chapter 13. The Contractor will not release or disclose the data classified
as not public to any person except at the written direction of the City. The Contractor agrees
to defend and indemnify the City from any claim, liability, damage, or loss asserted against
the City as a result of the Contractor’s failure to comply with the requirements of Minnesota
Statutes Chapter 13.
10.6. All plans, diagrams, and information generated in connection with performance of the
Agreement shall become the property of the City. The City may use the information as it sees
fit. Such use by the City shall not relieve any liability on the part of the Contractor.
10.7. By entering into this Agreement, the City does not waive its entitlement to any immunities
under statute or common law.
10.8. Each of the undersigned warrants it has the full authority to execute this Agreement.
10.9 The provisions of this Agreement are severable. If any portion of this Agreement is, for any
reason, held by a court of competent jurisdiction to be contrary to law, such decision shall not
affect the remaining provisions of this Agreement.
10.10 Any waiver by either party of a breach of any provision of the executed Agreement shall not
affect, in any respect, the validity of the remainder of the executed Agreement.
Article 11. Termination or Suspension of this Agreement.
11.1. Either party, without cause, may terminate this Agreement by 30 days’ written notice
delivered to the other party at the address written above. After termination, the City shall have
no further obligation to the Contractor except to compensate the Contractor for the equipment
and materials provided and services performed prior to the date of the notice of termination.
The City may also procure the outstanding work and the Contractor shall be liable to the City
for any excess costs for similar work, unless the Contractor provides acceptable evidence that
failure to perform the Agreement was due to a cause beyond the control and without fault or
negligence of the Contractor.
11.2. Upon termination of the Agreement, the Contractor agrees to return data to the City, as
requested by the City. All books, records, documents, and accounting procedures and
practices of the Contractor relevant to this Agreement, shall, pursuant to Minnesota Statutes,
be subject to examination at all times by the City, the Legislative Auditor, or the State Auditor.
6
640160v1LA515-1
Article 12. Payment and Completion.
12.1. The City agrees to pay the Contractor a total of $111,682.21 for the Project (the “Contract
Price”). The Contractor may invoice the City on a monthly basis for the equipment, materials
and services that have been provided to the City to the current date, but upon the City paying
75 percent of the Contract Price to the Contractor, the remaining 25 percent of the Contract
Price will be retained until the Project is complete and the City has accepted it.
12.2. Upon receipt of notice from the Contractor that the Project is ready for final inspection and
acceptance, the City shall promptly make such inspection and, when it finds the Project
acceptable and this Agreement fully performed, it shall make final payment to the Contractor
of the outstanding balance in accordance with all applicable laws. Acceptance of final
payment by the Contractor shall constitute a waiver of claims by the Contractor except those
previously made in writing and identified by the Contractor as unsettled at the time of final
payment.
12.3. The City may withhold payment to the Contractor in whole or in part to the extent reasonably
necessary to protect it from loss because of:
a. Defective work not remedied;
b. Third party claims filed or reasonable evidence indicating probable filing of such
claims;
c. Failure of the Contractor to make payments to subcontractors or for labor, materials,
or equipment; or
d. Persistent failure by the Contractor to carry out the work in accordance with this
Agreement.
(Remainder of this page intentionally left blank)
7
640160v1LA515-1
IN WITNESS WHEREOF, the parties hereto have executed or caused to be executed this
Agreement as of the day and year written above.
CITY OF LAKE ELMO
By: _________________________________
Mike Pearson
Its: Mayor
By: _________________________________
Julie Johnson
Its: City Clerk
CONTRACTOR
By: _________________________________
Its: _________________________________
8
640160v1LA515-1
EXHIBIT A
1.0 SCOPE OF WORK. The Scope of Work is divided into three sections: (1.1) Project
Scope; (1.2) Tools and Mechanized Equipment; and (1.3) Meetings and Progress Reviews. All
specified construction and materials must be furnished by the Contractor unless otherwise
indicated. It should be noted that the City of Lake Elmo is an instrumentality of the State of
Minnesota and is subject to the general state tax provisions although the City is exempt from the
state sales tax for certain purchases. The Contractor must provide all services necessary to
engineer, procure, install, test and certify the Project described below in conformance with the
manufacturer’s specifications and applicable industry standards.
1.1 Project Scope. The City has reserved funding to help support the Project and the Project’s
scope of work includes at least 22,158 feet of new construction. There is an existing trail
system within the Site and appropriate slowing methods will need to be used to aide in
safety at when the Project trails intersect with existing trails. Completed work must meet
the specifications outlined below:
A. Trail Design. The construction of this trail must be guided by the sustainable trail
principles promulgated by accepted resources such as the current editions of the
Trail Solutions; the International Mountain Bicycling Association’s (IMBA) Guide
to Building Sweet Single-track, Managing Mountain Biking; IMBA’s Guide to
Providing Great Riding, Bike Parks; IMBA’s Guide to New School Trails, and the
USDA’s Trail Construction and Maintenance Notebook.
B. Bike Specific Trail Flow. The bike trails proposed for Sunfish Lake would be
narrow trails called single-track. Once established, single-track trails average
eighteen to twenty-four (18-24”) inches in width, are not paved, reach a broad range
of riders and are designed to flow through natural areas with gradual inclines and
declines in topography. The City is hopeful of modern trail design and construction
uses sustainable trail building techniques. The City would like the Contractor to
build single-track trails that can have minimal impact on the environment, resist
erosion through proper design, construction and maintenance, co-exist with the
natural environment and blend with the surrounding area:
a. Synergy with the landscape: Making the most of what the natural terrain
contours present.
b. Opposition to user forces: Flow trails maximize the efficiencies afforded by
using a bicycle, and are designed to counteract forces that direct a user off
the trail. Bermed turns and cambered tread surfaces, for example, promote
traction, safety, sustainability, and enjoyment.
c. Conservation of momentum: The ideal trail avoids “flow killers” such as
sharp turns, incongruent features, and disjointed climbs and descents.
Instead, it utilizes undulations and cambered turns to reward smooth,
deliberate riding and maximize forward motions. A flow trail encourages a
9
640160v1LA515-1
better understanding of the bicyclist/bicycle interface, allowing riders to
reach that unique sensation of floating through the landscape.
d. Leading the user forward: A sense of discovery, combined with a design
that maximizes a rider’s forward momentum, helps to draw the user
forward. The trail is never repetitive or predictable, nor is it “awkward”,
with a variety and innovation combining to create an intuitive feel.
C. Trail Construction Best Practices – At all times possible, the Contractor will
need to build the trail to conform to the standards depicted in Exhibit B. To
satisfy erosion and sediment control requirements, the trail must be finished as the
project advances. Ideally, all roughed-in corridor will be finished the same day.
Any segments requiring delayed finishing should be planned out in advance to
finish as quickly as possible.
D. Corridor Clearing. Corridor clearing shall be confined to within five (5’) feet of
the trail and back-slope edges. The City may expect wider clearing where the
mountain bike trail crosses over an existing walking trail.
E. Trail Flagging. A flag line or marked line will be pre-installed by the Contractor,
at a minimum of every fifty (50’) feet, marking the desired corridor, but only
suggests the tread location based on the Master Trail Plan. The actual tread location
depends on finer analysis and will need to be laid out using pin flags at a minimum
of twenty (20’) foot intervals.
F. Debris. Cut and scatter all branches and brush cut as part of the trail development.
No debris shall be left within ten (10’) feet of the trail. Butt-ends of any sawed
limbs must face away from the trail.
G. Rocks. All rock embedded in the trail surface should be stable. When used in
structures, care will be taken to match construction rock to rocks native to the area.
Non-native rock may not be imported into the park or work area without approval
of the City.
H. Woody Material. Woody material such as stumps, logs and brush shall be removed
from the trail tread. No stumps less than twelve (12”) inches in diameter shall be
left within five (5’) feet of the trail tread.
I. Fall Zone Clearing. Areas adjacent to dynamic trail segments where visitors have
a greater potential to exit the immediate trail corridor will be cleared of impact
focusers; butt-end branches, stumps under six (6”) inches in diameter, and rocks
under six (6”) inches in diameter.
J. Back-Slope/ Out-Slope. Back-slope of trail should be graded to three-to-one (3:1)
slope or until it matches the existing slope. In areas where the back-slope has the
potential to become part of the active tread it must be finished to trail tread
10
640160v1LA515-1
specifications. Out-slope should range between three and five percent (3-5%)
towards the downhill side of the trail.
K. Trail, Finished Condition. Hand finishing and grading of the trail tread, back-
slope, down-slope spoils, and drainage features shall result in a surface that matches
the texture of the surrounding forest floor while enabling water to drain off the trail.
L. Spoils Stabilization. All excavated material not used in the trail tread or other trail
structures must be stabilized. Spoils shall be distributed in a thin layer adjacent to
the trail tread. When possible, spoils should be mulched with native materials to
discourage erosion while native seed stocks reestablished.
M. Turns. All turns are in-sloped or "bermed" where appropriate. Use generally
acceptable values for turn radii and grades across the turns. All turns must include
an entrance and exit rolling grade dip.
N. Grade Reversals. A designed grade reversal or constructed rolling grade dip
should occur as often as necessary. Any grade reversal must be strongly anchored
to discourage short cutting. The uphill and downhill cuts of the trail also should not
exceed more than ten percent (10%) of the slope of the hill/elevation. Grade
reversals also double as flow elements: rollers and pump/rhythm sections. In this
context, grade reversal shape, size and placement should reflect its placement
within the system. Specific details will be determined by the contractor in
partnership with the City.
O. Above Grade Earthen Structures. Any portion of trail above the grade of its
surroundings must be approved by the City in terms of design and material before
construction. Fill structures must have a fill slope of at least two-to-one (2:1) or the
angle of repose of the local soil, whichever is greater. A retaining wall may be
substituted for a fill slope with prior permission of the City. Fill structures must be
completely stabilized and compacted. Acceptable techniques include track-packing
or compaction via a dedicated tamping unit. Raw soil faces that do not become
tread must be mulched and seeded in the same fashion as spoils and satisfy the
terms of the project erosion control methodologies. Examples of above-grade
earthen structures include grade-reversals (“rollers”) and turn pads on in-sloped
switchbacks.
P. Water Diversions. The majority of the tread should be out-sloped. When not
possible or desirable due to purpose-built in-sloping, resource concerns or
obstruction, water can be directed down the trail for up to six (6’) feet before a
water diversion location (grader reversal).
Q. Invasive Species To reduce the spread of invasive plant species, the following
protocols are required:
11
640160v1LA515-1
a. All hand tools and mechanized equipment must be free of invasive seeds
and clean of any dirt and mud when entering the project site.
b. Consideration should be made while trail clearing and construction through
areas occupied by invasive species (such areas to be identified by the City)
as to not propagate as construction progresses.
c. Imported surface/organic material is prohibited.
R. Filter Strips. Filter strips are vegetated areas down-slope of the trail corridor
intended to treat sheet flows coming off the tread. Filter strips function by slowing
down flow velocities, filtering out sediments, and providing an opportunity for
infiltration into the underlying soils. Properly mulched spoils may be designated as
part of the filter strip. Filter strips shall not be used as regular travel-ways for
equipment and materials. Areas with inadequate filter strip capacity above water-
ways may require installation of formal erosion control measures to satisfy erosion
and sediment control methodologies.
S. Mechanized Equipment Best Practices. All track marks will be raked smooth.
Affected area will be finished to have a natural shape, spoils piles rounded,
smoothed and cleared of significant brush, blade edges blended, etc. A spill kit
suitable for five (5) gallons of fluid will be onsite and within two hundred (200)
yards of mechanized equipment whenever equipment is being operated.
T. Preservation of Vegetation. The Contractor shall exercise care to preserve the
natural landscape, including trees and shrubs, and shall conduct construction
operations to prevent any unnecessary destruction, scarring, or defacing of the
natural surroundings in the vicinity of the work. Except where clearing is required
for permanent works or excavation operations, all trees, native shrubbery, and
vegetation, shall be preserved and protected from damage by the Contractor's
construction operations and equipment. The City would not like to see trees larger
than eight (8”) inches in diameter removed. All unnecessary destruction, scarring,
damage or defacing of the landscape resulting from the Contractor's operations,
shall be repaired, replanted, reseeded or otherwise corrected as directed by the City
and at the Contractor's expense. After completion of the work, all areas disturbed
by construction that do not require landscaping or planting, shall be scarified and
left in a condition which will facilitate natural vegetation, provide for proper
drainage and prevent erosion.
U. Ground Disturbance. The grading limits along the trail corridor are defined by the
approved tread width plus additional width defined by the required back-sloping,
unless further excavation is required for prescribed features, as approved, and
performed according to Section 1.1 (T). Rutting should be avoided outside grading
limits along the corridor, by limiting traffic intensity and avoiding wet soil
conditions, and corrected as per Section 1.1 (T).
12
640160v1LA515-1
1.2 Tools and Equipment.
A. Tools. The Contractor shall perform the required work using hand tools and/or
small mechanized equipment that is a maximum of fifty (50”) inches in width.
Equipment with adjustable width tracks should be able to reduce track width to less
than fifty (50”) inches for building the new trail. Some sites may not be suitable for
equipment this large and other sites may not be suitable for any mechanized
equipment regardless of size due to terrain and environmental constraints.
Permanent modification of trail outside the scope of work to accommodate
equipment access is not desirable and must be approved by the City before building
the modification.
B. Mechanized Equipment. All mechanized equipment shall be in good mechanical
condition, free of any fluid leaks. All equipment will be clean and free of debris
before introduced to work site. Equipment is subject to inspection at the start and
during the project. Any equipment that appears to not meet these criteria shall be
removed from the project site at the request of the Client’s representative and at no
additional cost to the Client.
1.3 Meetings and Progress Reviews. The Contractor shall meet with City Staff as necessary
or as otherwise agreed upon by both parties to review progress and project expectations
throughout the build. When determining a course of action regarding build technique or
design expectation(s), the International Mountain Biking Association (IMBA) standards
shall be referred to determine the appropriate technique.
2.0 INSTALLATION, CLEANING AND PROTECTION OF EQUIPMENT.
A. The Contractor will be required to obtain and pay for any required permits, licenses,
approvals or inspections necessary for the work. The Contractor must perform all
tests that are required by regulatory authorities at its expense.
B. The Contractor must protect all equipment and materials from theft, injury, or
damage during the project. The Contractor must provide temporary protection to
uninstalled materials.
C. The Contractor must provide adequate storage for all equipment and materials
delivered to the site. The City is not required to provide secure storage but will
attempt to accommodate the Contractor’s storage requirements.
3.0 DOCUMENTATION AND TRAINING.
A. At the conclusion of the project, all documentation is to be compiled by the
Contractor into an organized, comprehensive package.
13
640160v1LA515-1
B. The Contractor must provide the City with a GIS file of the final trail route.
Handwritten drawings are not acceptable.
4.0 WARRANTY.
A. The Contractor agrees that it will warrant the Project to be free of defects of
workmanship or products and will inspect and repair the system at no cost to the
City within the first year of the In Service Date. During the one (1) year period,
the Contractor will respond to the City and remedy the problem within seven days
of the City’s contact, or within a longer timeframe, if approved by the City.
B. The Contractor’s one (1) year warranty period shall begin at the date of City
acceptance of the project (the “In Service Date”). It is the responsibility of the
Contractor to request this acceptance, in writing. Final payment of twenty-five
(25%) percent of the Contract Price to the Contractor will be withheld by the City
until the City has accepted the project.
C. The City shall not be responsible for any additional charges (i.e., service, labor,
shipping charges, trip charges, etc.) during the Contractor warranty period of any
manufacturer warranty period of the construction materials.
14
640160v1LA515-1
Exhibit B
CITY OF LAKE ELMO
WASHINGTON COUNTY
STATE OF MINNESOTA
RESOLUTION NO. 2020-024
A RESOLUTION APPROVING A CONTRACT WITH TRAIL SOURCE
LLC FOR THE CONSTRUCTION OF MOUNTAIN BIKE TRAILS IN
SUNFISH LAKE PARK
WHEREAS, the City of Lake Elmo issued a Request for Proposals on December ___, 2019 to
solicit proposals from interested contractors to develop and construct a mountain bike trail system
within the City’s Sunfish Lake Park; and
WHEREAS, the City received one proposal; and
WHEREAS, City Staff and the City Parks Commission reviewed the submitted proposal and have
provided a report to the City Council dated March 4th, 2020 recommending that the City enter into
a contract with Trail Source LLC in the amount of $111,682.21 for the development of the
mountain bike trail system in Sunfish Lake Park; and
NOW, THEREFORE, IT IS HEREBY RESOLVED,
1. That the Mayor and City Clerk are hereby authorized and directed to enter into the attached
Trail Construction Project Agreement with Trail Source LLC in the amount of
$111,682,21.
ADOPTED BY THE LAKE ELMO CITY COUNCIL ON MARCH 4, 2020.