HomeMy WebLinkAbout#09 - Hamlet Sanitary Sewer STAFF REPORT
DATE: April 21, 2020
REGULAR
AGENDA ITEM: Approve Resolution Receiving Feasibility Report and Calling Hearing on
Improvement for the Hamlet on Sunfish Lake Sanitary Sewer Extension
SUBMITTED BY: Jack Griffin, City Engineer
REVIEWED BY: Kristina Handt, City Administrator
Sarah Sonsalla, City Attorney Marty Powers, Public Works Director
Chad Isakson, Assistant City Engineer
ISSUE BEFORE COUNCIL: Should the City Council accept the Feasibility Report and call a public
hearing for the Hamlet on Sunfish Lake Sanitary Sewer Extension to be held at the May 19, 2020 Council
meeting?
BACKGROUND: On October 16, 2018, the City Council authorized the preparation of a feasibility report
for the Hamlet on Sunfish Lake Sanitary Sewer Extension. A petition requesting municipal sanitary sewer
service was received from the Hamlet on Sunfish Lake property owners in August 2018. The petition was
signed by 27 of the 41 properties benefitting from the requested improvements.
Hamlet on Sunfish Lake is located along the northwest side of the Old Village MUSA at the intersection of
Kindred Way North and 43rd Street North, just west of the Legacy at North Star subdivision. The
subdivision was constructed in 1998 as a cluster open space development consisting of 41 residential
properties. Each property is served by a private water supply well and a shared sanitary sewer conveyance
system and shared community wastewater treatment system. The privately owned and operated community
wastewater treatment system was determined to be non-compliant in 2006 due to several system
deficiencies. The Hamlet on Sunfish Lake HOA is currently operating the system in accordance with a
Schedule of Compliance dated March 13, 2014 and Amended January 18, 2017 through the Minnesota
Pollution Control Agency (MPCA), and per the Stipulation Agreement dated May 1, 2007 with the City of
Lake Elmo. The Schedule of Compliance requires the subdivision to connect to the city sanitary sewer
system and decommission the private wastewater system by December 31, 2020, or to abandon and replace
the private wastewater treatment system altogether.
The Stipulation Agreement, dated May 1, 2007 between the City of Lake Elmo and Hamlet on Sunfish
Lake HOA contains provisions requiring the Hamlet on Sunfish Lake HOA to connect the HOA System to
the city sanitary sewer system when the city sewer becomes available for connection. Prior to connection
of the HOA System the city shall inspect the HOA system to determine if it is in good working order. The
inspection may include televising of the sanitary sewer pipes. The Stipulation Agreement also requires the
HOA to pay all costs, including construction, engineering, legal and administrative, and all city connection
charges from the city fee schedule that is current at the time of connection, to connect the HOA System to
the city sanitary sewer, to decommission the HOA wastewater treatment system, to inspect the HOA sewer
collection system for deficiencies, and to make system repairs of the HOA sewer system. The agreement
indicates that all costs are to be paid by the HOA prior to the city awarding a construction contract for the
work.
Hamlet on Sunfish Lake and the City of Lake Elmo have been planning for the neighborhood’s connection
to the city sanitary sewer since 2007 as outlined in the Stipulation Agreement. As part of this planning
process the city has completed its Comprehensive Plan Amendment to bring the subdivision into the Old
Village Area MUSA.
PROPOSAL DETAILS/ANALYSIS: The Hamlet on Sunfish Lake Sanitary Sewer Extension Feasibility
Report identifies the scope of improvements necessary to extend the city sanitary sewer to the Hamlet on
Sunfish Lake subdivision to replace the ongoing use of the non-compliant wastewater treatment system.
The report also identifies the improvements necessary to decommission the private wastewater treatment
system and to make repairs and correct deficiencies in the HOA private sanitary sewer system to ready the
private sewer system to be transferred to city ownership and maintenance.
In order to connect the HOA system to the city sanitary sewer, the city sewer system must be extended from
its current location in the Legacy at North Star development, extending the 10-inch sewer main
approximately 550 feet to the property line, then another 410 feet to the west side of the HOA wastewater
treatment system. At this location the HOA sewer conveyance system can be directly connected to the city
sanitary sewer to remove the HOA wastewater treatment system from operation.
Minimum requirements have been identified to decommission the HOA wastewater treatment system,
including pumping out and disposing of the remaining wastewater from two septic tanks and 1 lift station,
bulkheading and abandoning in place all tanks and structures, and disconnecting and salvaging control
panels and equipment. In the wetland treatment cell, the PVC stand pipes must be exposed and removed
and the liner must be perforated. The decommission work to be completed by the city project does not
include any grading or fill of the wetland cell or infiltration basin. Additional site work will likely be
required to be completed by the HOA before the site can be repurposed for alternative use.
The recommended HOA sanitary sewer conveyance system repair and replacement work is more extensive
and involved than originally anticipated. The detailed televising and inspections of the HOA sanitary sewers
revealed extensive defects and deficiencies that must be corrected before the city can assume ownership
and operation and before the street pavements get reconstructed in 2021. Deficiencies include extensive
major sags in the main line sewer piping, often exceeding 20% of pipe depth and including several pipe
runs at negative grade. With backfall occurring throughout the pipe system the sewer mains hold standing
water on a permanent basis, and the system becomes susceptible to frequent blockage, backups, and reduced
capacity. To address these deficiencies this report provides two options. The first option addresses the
minimum repairs and replacements intended to address only the most severe deficiencies in the system.
This option includes complete replacement of approximately 3,000 feet of sewer pipe and 7 manhole
structures. The second option provides for the complete replacement of approximately 4,000 feet of sewer
main and 13 manhole structures to assure a more comprehensive repair and more reliable functioning sewer
system. For the second option it also provides the opportunity to upsize the sewer main to provide a route
with sufficient capacity to address future municipal sewer beyond the Tapestry neighborhood. To account
for this additional capacity the city sewer fund could be used to pay for the pipe oversizing.
A project schedule for the Hamlet on Sunfish Lake Sanitary Sewer Extension Improvements is outlined
within this report. The improvements to extend and connect the HOA system to city sanitary sewer and
decommission the existing HOA wastewater treatment system is recommended to be completed as one
project during the 2020 construction season to meet the MPCA Schedule of Compliance date of December
31, 2020. However, it is recommended that the HOA sewer collection system repairs and replacement be
completed together with the Hamlet on Sunfish Lake Street and Watermain Improvements scheduled for
construction in 2021.
The total estimated project cost is $1,319,500. This includes $544,500 for the improvements to be
completed in 2020, including $160,630 to extend the public sanitary sewer and connect to the HOA system,
$72,000 to decommission the HOA wastewater treatment system, $265,885 for payment by the HOA for
City and Met Council sewer availability and connection charges, and $45,923 for city trunk sewer oversize
recovery costs. The 2021 improvement costs total $775,000 including $620,000 for the HOA Sanitary
Sewer Repair and Replacement work, and $155,000 to oversize the sanitary sewer through the Hamlet
subdivision with 10-inch sanitary sewer pipe.
FISCAL IMPACT: The total estimated project cost is $544,500 for the improvements to be completed in
2020 and $775,000 for the improvements to be completed in 2021.
All costs are required to be paid upfront in accordance with the 2007 Stipulation Agreement between the
city and Hamlet on Sunfish Lake HOA. Payment must be made from the HOA in the estimated amount of
$489,500 for the 2020 improvements and $620,000 for the 2021 improvements. Payment must be made
from GWSA Land Development LLC (Legacy at North Star developer) in the estimated amount of $55,000
for completing a portion of the developer’s required improvements. The city sewer fund would cover the
optional oversizing cost in the estimated amount of $155,000 if the 10-inch sewer is installed as part of the
2021 improvements. Contractor bids should be received and the estimated project costs amended following
bid receipt and prior to awarding any respective contracts.
As an alternative to upfront payment, this report has also prepared preliminary assessment rolls in the event
that the HOA requests and the council is agreeable to allow all or a portion of the project costs to be assessed
against the individual benefiting properties. Special assessments would be levied in accordance with MN
Statutes Chapter 429 and consistent with the city’s Special Assessment Policy. If assessed, the assessable
amount of the of the improvements would be assessed 100% to the benefitting properties using a residential
equivalent unit method. Each benefitting residential property would be assessed 1 Residential Equivalent
Connection (REC), or 1 SAC unit. There are 41 residential properties within the Hamlet on Sunfish Plat
and 1 property owned by GWSA Land Development LLC. A preliminary assessment roll has been prepared
for the sanitary sewer extension and connection improvements, and for the HOA sanitary sewer repair and
replacement improvements. Both assessment rolls can be found in the Appendix of this report and are based
on 100% of the improvements being assessed 100% to the benefitting properties. The sanitary sewer
assessments are typically payable over 20 years.
RECOMMENDATION: Staff is recommending that the City Council approve a Resolution, receiving
the Feasibility Report and calling a public hearing for the Hamlet on Sunfish Lake Sanitary Sewer
Extension. The recommended motion for this action is as follows:
“Move to approve Resolution No. 2020-040, receiving the Feasibility Report and Calling a Public
Hearing for the Hamlet on Sunfish Lake Sanitary Sewer Extension.”
ATTACHMENTS:
1. Resolution Receiving Report and Calling for Hearing on Improvements.
2. Notice of Hearing on Improvement.
3. Hamlet on Sunfish Lake Sanitary Sewer Extension – Location Map.
4. Hamlet on Sunfish Lake Sanitary Sewer Extension – Project Schedule.
Feasibility Report (available for review at City Hall).
CITY OF LAKE ELMO
WASHINGTON COUNTY
STATE OF MINNESOTA
RESOLUTION NO. 2020-040
A RESOLUTION RECEIVING A FEASIBILITY REPORT FOR THE
HAMLET ON SUNFISH LAKE SANITARY SEWER EXTENSION
AND CALLING HEARING ON IMPROVEMENT
WHEREAS, pursuant to City Council authorization, adopted on October 16, 2019, a feasibility
report has been prepared by FOCUS Engineering, Inc. for the Hamlet on Sunfish Sanitary Sewer
Extension; and
WHEREAS, the feasibility report recommends that benefitting properties be assessed all or a
portion of the cost of the improvements pursuant to the City’s Special Assessment Policy and Minnesota
Statutes, Chapter 429; and
WHEREAS, the feasibility report provides information regarding whether the proposed
improvement is necessary, cost-effective, and feasible; whether it should best be made as proposed or in
connection with some other improvement; the estimated cost of the improvements as recommended; and a
description of the methodology used to calculate individual assessments for affected parcels.
NOW, THEREFORE, BE IT RESOLVED,
1. That the City Council will consider the improvements in accordance with the report and the
assessments of the abutting properties for all or a portion of the cost of the improvements
pursuant to Minnesota Statues, Chapter 429 at an estimated total project cost of $1,319,500.
2. A public hearing shall be held on such proposed improvements on the 19th day of May, 2020 and
conducted by electronic means pursuant to Minnesota Statutes Section 13D.021 because of the
COVID-19 pandemic during a regularly scheduled City Council meeting, at or approximately
after 7:00 P.M. and the clerk shall give mailed and published notice of such hearing and
improvement as required by law.
ADOPTED BY THE LAKE ELMO CITY COUNCIL ON THE TWENTY-FIRST DAY OF
APRIL, 2020.
CITY OF LAKE ELMO
By: __________________________
(Seal) Mike Pearson
ATTEST: Mayor
________________________________
Julie Johnson
City Clerk
CITY OF LAKE ELMO
NOTICE OF HEARING ON IMPROVEMENT
HAMLET ON SUNFISH LAKE SANITARY SEWER EXTENSION
Notice is hereby given that the City Council of Lake Elmo will conduct a public hearing
on Tuesday, May 19, 2020, at or approximately after 7:00 P.M. to consider the making
of the following improvements, pursuant to Minnesota Statutes, Sections 429.011 to
429.111;
The improvements to connect the Hamlet on Sunfish Lake subdivision to city
sanitary sewer services, including the extension of city sanitary sewer to
neighborhood and connection to the privately owned sanitary sewer, improvements
to decommission the privately owned homeowner’s association (HOA) wastewater
treatment system; and repair and replacement improvements to the HOA owned
sanitary sewer conveyance system with turnover of operation to the city.
The hearing will be conducted by electronic means pursuant to Minnesota Statutes
Section 13D.021 because of the COVID-19 pandemic. The meeting can be viewed online
by going to the City’s website (http://www.lakeelmo.org/). Instructions for participating
in the meeting via computer will be posted on the City’s website prior to the meeting.
During the meeting the city will also be accepting call‐ins at 213.929.4212, access code
569‐187‐751. Comments can also be provided prior to the meeting which will be
presented to the council. Written comments prior to the meeting must be sent to Julie
Johnson, City Clerk (jjohnson@lakeelmo.org) or voicemails left at (651.747.3914) prior
to the meeting.
The area proposed to be assessed for the sanitary sewer extension and connection
improvements include each of the 41 properties located in the Hamlet on Sunfish
subdivision that will be receiving access to connect to city sewer. The estimated total cost
for the project is $1,319,500. A reasonable estimate of the impact of the assessments will
be available at the hearing. Such persons as desiring to be heard with reference to the
proposed improvements will be heard at this meeting.
.
DATED: April 21, 2020
BY ORDER OF THE LAKE ELMO CITY COUNCIL
Mike Pearson, Mayor
(Published in the Oakdale-Lake Elmo Review on April 24, 2020 and May 1, 2020)
LOCATION MAP
FIGURE NO. 1
HAMLET ON SUNFISH NEIGHBORHOOD
CITY OF
LAKE ELMO
HAMLET ON SUNFISH LAKE
LEGEND
PROJECT NO. 2018.128
HAMLET ON SUNFISH LAKE
SANITARY SEWER
EXTENSION
PROJECT STREETS
KINDRED WAY, FROM KIMBRO AVE N TO
KINDRED COURT;
KINDRED COURT, FROM KINDRED WAY TO
THE SOUTH CUL-DE-SAC
PROJECT SCHEDULE
CITY OF LAKE ELMO
HAMLET ON SUNFISH LAKE SANITARY SEWER IMPROVEMENTS
PROJECT NO. 2018.128
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
OCTOBER 16, 2018 Council accepts Petition; authorizes preparation of Feasibility Report and
Preliminary Design.
APRIL 21, 2020 Presentation of Feasibility Report. Council accepts Report and calls Hearing on
Improvement.
MAY 19, 2020 Public Improvement Hearing. Council Orders the Improvement (4/5th Vote);
approves the Plans and Specifications; and orders the advertisement for bids.
Declare Costs to be Assessed and Calls for Hearing on Assessment.
JUNE 11, 2020 Project Bid Date: Receive contractor bids.
JUNE 16, 2020 Final Assessment Hearing. Council adopts the Final Assessment Roll. Council
accepts Bids and awards Contract.
JULY 14, 2020 Conduct Pre‐Construction Meeting and issue Notice to Proceed.
OCTOBER 9, 2020 Substantial completion date for Construction.
NOVEMBER 20, 2020 Final completion date for Construction.
**2021 Construction Season: HOA sanitary sewer conveyance system repair and replacement to be completed with