HomeMy WebLinkAbout#02 - Manning Ave-TH 36 InterchangeSTAFF REPORT DATE: June 9, 2020 DISCUSSION AGENDA ITEM: Highway 36 (TH36) and Manning Avenue (CSAH 15) Interchange Project SUBMITTED BY: Jack Griffin, City Engineer REVIEWED BY: Kristina Handt, City Administrator ISSUE BEFORE COUNCIL: Should staff bring this issue before a future council meeting with recommendations for adopting a Resolution of Municipal Support? BACKGROUND: Washington County is leading a project to design and construct a grade separated intersection at Trunk Highway 36 (TH 36) and County State Aid Highway 15 (CSAH 15). The intersection is partially located within the City of Lake Elmo, Grant, Stillwater and Stillwater Township. Traffic studies have shown that the current intersection is insufficient to meet the current and projected traffic volumes. A second project, the South Segment to connect the north and south legs of Manning Avenue through Oak Park Heights is also in the planning stages to coordinate the two project designs. Two proposed developments to be located at the northeast and southeast quadrants of the interchange have informed several of the design configurations. The interchange project is planned for construction in 2021 and the South Segment project is planned for construction in 2022. PROPOSAL DETAILS/ANALYSIS: Washington County has developed an Approved Interchange Layout to be constructed at TH36 and Manning Avenue. The environmental work for the project has also been completed. The County is currently in the process of completing the final design and is seeking a Resolution of Municipal Support from each community. The city recently received an estimate of total project costs together with the funding breakdown and expected cost participation from each community. A cost participation graphic is attached with this report together with a proposed post-project right-of-way exhibit. OPTIONS: 1) Direct staff to bring this issue before a future council meeting with recommendations for adopting a Resolution of Municipal Support. 2) Direct staff to bring this issue before a future council meeting with recommendations for adopting a Resolution of Municipal Support with conditions as directed and outlined by council. 3) Direct staff to take no action and to schedule future workshop for additional and continuation of council discussion. ATTACHMENTS: • Project Informational Boards. • Approved Layout. • Proposed Right-of-Way Exhibit. • Cost Participation Graphic. • Costs and Funding Exhibit. • Updated Cost Estimate Details. HIGHWAY 36 & MANNING AVENUE (CSAH 15) INTERCHANGE PROJECT PUBLIC OPEN HOUSE WELCOME MARCH 19, 2020 THE BIRTHPLACE OF MINNESOTA HIGHWAY 36 & MANNING AVENUE (CSAH 15) INTERCHANGE PROJECT HIGHWAY 36 CORRIDOR Highway 36 is a vital principal arterial serving the north and northeast area of the Twin Cities metropolitan area. Commuter, freight, and recreational traffic use this route as a critical link to key regional, interregional, and interstate destinations. MI N N E S O T A WI S C O N S I N RamseyWashingtonLake St Croix Lake Jane Lake ElmoL a k e O l s o n 0 0.7 mi MINNESOTA 36 MINNESOTA 36 MINNESOTA 36 MINNESOTA 95 MINNESOTA 95 17COUNTY 15 COUNTY 15 COUNTY 5 COUNTY 694 694 Stillwater BlvdLake Elmo AveKeats AveHilton TrManning AveGreeley StOakgreen AveOsgood AveSTILLWATER BAYPORT OAK PARK HEIGHTS LAKE ELMO NORTH ST. PAUL MAHTOMEDI GRANT Highway 36/I-694 Existing Cloverleaf Interchange Highway 36/Hadley Ave Grade Separated Interchange in Design Complete 2020 Highway 36/Keats Ave Reduced Conflict Intersection Constructed 2006 Highway 36/Manning Ave Existing At-Grade Intersection Shovel Ready Highway 36/Greenley St/ Oakgreen Ave At-Grade Intersection with Traffic Signal Constructed 2014 Highway 36/Highway 95 Diamond Interchange Constructed 2017 St. Croix River Crossing River Bridge Constructed 2017 Highway 36/Hilton Trail Grade Separated Interchange with Roundabouts Constructed 2014 Highway 36/Lake Elmo Ave Existing At-Grade Intersection Highway 36/Stillwater Blvd Existing Grade Separated Diamond Interchange Highway 36/Osgood At-Grade Intersection with Traffic Signal Constructed 2014 Highway 36/Norell Existing At-Grade Intersection with Traffic Signal HIGHWAY 36 & MANNING AVENUE (CSAH 15) INTERCHANGE PROJECT PROJECT PURPOSE & GOALSPROJECT PURPOSE & GOALS PROJECT TIMELINE 2017 2018 2019 2020 2021 CONCEPTUAL DESIGN & TRAFFIC ANALYSIS DESIGN PROCESS, NEPA & RIGHT OF WAY BIDDING CONSTRUCTION The primary purpose of this project is to improve safety and mobility at Highway 36 & Manning Avenue Other Goals and Objectives: • Maintain access to neighborhoods and future development • Accommodate local road connectivity • Provide safe, non-motorized access (trails, walks, etc.) We are here Open House #1 Accomplished Since Open House #1: • Evaluated Alternatives • Screened Against Project Goals • Coordinated with Local Governments Accomplished Since Open House #2: • Identified Recommended Alternative • Completed Preliminary Design (Approved by MnDOT) • Documented Environmental Impacts Open House #2 Open House #3 HIGHWAY 36 & MANNING AVENUE (CSAH 15) INTERCHANGE PROJECT NEED FOR PROJECT Why do we need to do something? If we do nothing... Intersection is approaching its full capacity (long delays/ frustrations) Delays will become intolerable 56 Reported Crashes (2011 to 2015)1 Fatality Traffic trying to turn onto Manning will spill back onto Hwy 36 Intersection ranked 75 (out of 8,000) based on statewide crash cost comparisons Crashes will likely increase 20-30% Increase in traffic expected by 2040. In addition to 20% increase since the opening of the St. Croix Crossing Bridge HIGHWAY 36 & MANNING AVENUE (CSAH 15) INTERCHANGE PROJECT DAILY TRAFFIC VOLUME – EXISTING & FORECASTED Developer Owned Developer Owned MINNESOTA 36 MINNESOTA 36MINNESOTA 36 17COUNTY 15 COUNTY 15 COUNTY 5 COUNTY LEGEND Interchange Concept Full Access Intersection Potential Local Road Future Extension Closed Access/ Roadway Realignment Direction of Traffic Pedestrian Trail xxxxxx NLake Elmo Ave17,000 20,000 25% Increase NoIncrease 500 500 41,000 51,000 42,000 49,000 33,000 14,500 63,00058,000 15% Increase 20% Increase STILLWATER STILLWATER TWP OAK PARK HEIGHTS LAKE ELMO GRANT STILLWATER STILLWATER TWP OAK PARK HEIGHTS LAKE ELMO GRANT Lake Elmo AveManning AveStillwater BlvdLake Elmo AveManning AveStillwater Blvdx,xxx Existing 2018 x,xxx Potential 2040 with full development Legend Future 2040 NOTE: Future traffic volumes do not account for potential development areas shown. x,xxx Traffic Distribution 14%16% 69%1% MINNESOTA 36 MINNESOTA 36 15 COUNTY Manning AveManning Ave HIGHWAY 36 & MANNING AVENUE (CSAH 15) INTERCHANGE PROJECT CONCEPT VISUALIZATION Interchange Concept: Not for Construction - Looking North East Bridge Detail Concept: Not for Construction - Looking North WestExisting View: Looking North East HIGHWAY 36 & MANNING AVENUE (CSAH 15) INTERCHANGE PROJECT ENVIRONMENTAL DOCUMENTATION: Environmental Review Summary • The project includes federal-aid highway funding; therefore, an environmental review under the National Environmental Policy Act (NEPA) has been completed. • The NEPA document provides information about the purpose and need; alternatives evaluation and identification of a preferred alternative; environmental impacts; and proposed mitigation measures. • Potential impacts of the project studied in the environmental review include: Traffic Noise • Field measurements were collected in fall 2018. • Modeled noise levels at most all locations in the project area are below Federal noise abatement criteria. • A noise wall along the trail on the east side of Manning Avenue does not meet MnDOT’s reasonableness criteria and is not desired for current and future land uses. Wetlands • Wetlands delineated in spring 2019. • It is not possible to avoid all wetland impacts with the project. • Features have been incorporated into the project design to minimize wetland impacts (e.g., retaining walls). • Mitigation for wetland impacts will be acquired prior to construction. Water Resources • The project will increase impervious surface area compared to existing conditions. • Existing drainage patterns will be maintained to the extent practicable. • Stormwater basins will be constructed to treat and control runoff. • Project includes construction of a water re-use system to irrigate Applewood Hills Golf Course. HIGHWAY 36 & MANNING AVENUE (CSAH 15) INTERCHANGE PROJECT TRAFFIC NOISE ANALYSIS HIGHWAY 36 & MANNING AVENUE (CSAH 15) INTERCHANGE STUDY TRAFFIC NOISE ANALYSIS FIELD MEASUREMENTS - Document existing noise levels at representative sites - Validate noise models (measured levels +/- 3 dBA of model levels) NOISE LEVEL MODELING - Develop noise models of project area roadways and topology - Model noise levels at receptor sites (homes, businesses, parks, etc.) - Model existing, future no-build and future build conditions (Use 20-year traffic projections) NOISE MITIGATION MODELING (FEASIBILITY AND REASONABLENESS) Defined in MnDOT Noise Requirements Feasibility - Acoustic feasibility (5 dBA reduction to be considered benefited) - Site Constraints Reasonableness - Noise reduction design goal (reduction of at least 7 dBA at minimum of one benefited receptor) - Cost effectiveness ($78,500 per benefited receptor) - Noise wall voting (viewpoints of benefited residents and property owners) - Noise levels approaching or exceeding FHWA noise abatement criteria - 66 dBA (Leq for residential use) - Substantial noise increase (5 dBA or more increase between future build noise levels) NOISE ANALYSIS IS COMPLETE IMPACTS IDENTIFIED? YESNO NOISE ANALYSIS IS COMPLETE FEASIBLE AND REASONABLE NOISE WALLS ARE PROPOSED FOR CONSTRUCTION MEETS FEASIBILITY AND REASONABLENESS ? YESNO Source: Minnesota Pollution Control Agency Decibel level of common noise sources Field Measurement Source: Minnesota Pollution Control Agency HIGHWAY 36 & MANNING AVENUE (CSAH 15) INTERCHANGE PROJECT NOISE ANALYSIS SUMMARY 0 800 1,600 US Feet [ Legend Approach or exceed the noise abatement criteria Proposed Hwy 36/Manning Ave Interchange Below the noise abatement criteria Noise abatement criteria (NAC): upper limit of highway traffic noise levels for different land uses and activities. Noise abatement measures (e.g., noise walls) must be evaluated when modeled noise levels approach or exceed NAC limits at a receptor location. 36 15 COUNTY Manning Ave5 COUNTY Stillwater Blvd17COUNTY Lake Elmo AveOAK PARK HEIGHTS LAKE ELMO GRANT STILLWATER Sanctuary Neighborhood Noise Analysis Results Existing noise levels (Leq, dBA) 2040 No Build noise levels (Leq, dBA) 2040 Build noise levels (Leq, dBA) Change in noise levels (2040 Build - Existing) (Leq, dBA) 47.2 - 54.2 47.9 - 55.1 48.6 - 55.8 0.5 - 2.4 • Includes modeled noise levels along trail • Approaching the noise abatement criterion is 66 dBA (Leq) Summary • Noise levels at one residence on the south side of Hwy 36 exceeds the Federal noise abatement criterion. A noise wall at this location would not meet MnDOT’s cost effectiveness threshold to be considered reason- able. • Noise levels in the Sanctuary neigh- borhood are below the Federal noise abatement criterion for residential uses with the Hwy 36/Manning Avenue interchange. • A noise wall along the trail on the east side of Manning Avenue does not meet MnDOT’s reasonableness criteria and is not desired for current and future land uses. HIGHWAY 36 & MANNING AVENUE (CSAH 15) INTERCHANGE PROJECT PROJECT FUNDING Project Website www.co.washington.mn.us/Manning36Interchange $29 MILLION CURRENT FUNDING $2 MILLION LOCAL GOVERNMENTS $5 MILLION STATE AID (WASHINGTON COUNTY C.I.P.) $5 MILLION MNDOT/METROPOLITAN COUNCIL MOBILITY FUNDS $7 MILLION METROPOLITAN REGIONAL SOLICITATION (FEDERAL FUNDING) $10 MILLION TRANSPORTATION ECONOMIC DEVELOPMENT (TED) GRANT $32 MILLION TOTAL PROJECT COST $3 MILLION FUNDING DEFICIT POTENTIAL FUNDING SOURCES: - GENERAL OBLIGATION BONDS (NOT SECURED) LEGEND MNDOT OWNED RIGHT OF WAY CITY OF STILLWATER OWNED RIGHT OF WAY 4000200 SCALE IN FEET { NB MANNING AVE { SB MANNING AVE { NE LOOP { NE RAMP { EB LINDEN AVE N { SW LOOP { SW RAMP { NW RAMP { EB 60TH ST N { WB TH 36 { EB TH 36 CITY OF LAKE ELMO OWNED RIGHT OF WAY WASHINGTON COUNTY OWNED RIGHT OF WAY CITY OF STILLWATERCITY OF GRANT CITY OF LAKE ELMO STILLWATER TOWNSHIP CITY OF OAK PARK HEIGHTS { RWALL 1 (20' CIP) { RWALL 3 (25' MSE) { RWALL 2 (30' CIP) { RWALL 4 (20' CIP) { RWALL 5 (10' BLOCK)H:\Projects\10000\10207\CAD_BIM\Graphics\ROW Graphic\10207_Right Of Way.dgn2/13/2020 Job #10207 Figure 1 PROPOSED RIGHT OF WAY TH 36/Manning Avenue Interchange Washington County, MN SEPARATE COUNTY PROJECT PROPOSED ROW REQUIRED FOR FUTURE DEVELOPMENT PLANS AREA SUBJECT TO CHANGE WITH FUTURE DEVELOPMENT PLANS AREA SUBJECT TO CHANGE WITH UNKNOWN TOWERS. WIDTH OF UTILITY EASEMENT LOCATION OF XCEL POWER LINES/ GROUNDLINE. THE HIGHEST POINT BASED ON THE EXISITNG ALL WALL HEIGHTS WERE MEASURED FROM WALLS FOR MAINTENANCE REQUIREMENTS. 2. 10 FEET FROM THE FACE OF RETAINING TOE OF SLOPE AND BACK OF DITCH. LIMITS INCLUDING LIMITS TO THE 1. THE ROADWAY CONSTRUCTION PROPOSED ROW WAS PLACED BASED ON: ROW ASSUMPTIONS: RW 5 Cost Participation Policy Grant Lake Elmo Stillwater Stillwater Township 36 Temporary Bypass RW 1 RW 3 RW 2 RW 4 Key County/MnDOT City of Stillwater (or township) City of Lake Elmo City of Stillwater/County County Per Washington County Cost Participaton Policy City Limits Traffic Signal Retaining WallRW# - ESTIMATED CONSTRUCTION COSTS $17,279,662 $3,986,460 $1,554,682 $1,534,592 $24,355,396 ESTIMATED R/W ACQUISITIONS $2,295,000 $1,705,000 $4,000,000 DESIGN ENG & CONSTRUCTION ADMIN $3,143,371 $229,799 $226,830 $3,600,000 TOTAL PROJECT COST $17,279,662 $9,424,831 $3,489,481 $1,761,422 $31,955,396 FUNDING SOURCES REGIONAL SOLICITATION $7,000,000 TED GRANT $10,000,000 MNDOT MOBILITY FUNDS $5,000,000 STATE BONDING $0 TOTAL $22,000,000 FUNDING REMAINING AFTER INTERCHANGE COSTS $4,720,338 PROJECT COST SHARE AFTER INTERCHANGE 64%24%12%100% REMAINING FUNDING SPLIT $3,031,425 $1,122,365 $566,548 $4,720,338 COST SHARE AFTER APPLYING FUNDING $0 $6,393,406 $2,367,116 $1,194,874 $9,955,396 5/21/2020 CITY OF LAKE ELMO TOTALINTERCHANGEWASHINGTON COUNTY CITY OF STILLWATER SRF Comm No 10207 R:\11509 - CSAH 15 at TH 36 Interchange\Cost Tables\20200515 Draft Cost and Breakouts\Draft\20200521_TH 36 & CSAH 15 PRINTED: 5/21/2020 9:27 AM TH 36 AND MANNING AVENUE INTERCHANGE Concept Cost Estimate (based upon 2018 bid price information) 5/21/2020 UNIT EST. EST.EST. EST.EST. EST.EST. EST.EST. EST. ITEM DESCRIPTION UNIT PRICE QUANTITY AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT PAVING AND GRADING COSTS GrP 1a 2106 Excavation - common & subgrade cu. yd.$17.00 60,870 $1,034,790 10,635 $180,795 1,820 $30,940 9,790 $166,430 83,115 $1,412,955GrP 1b 2106 Excavation - ponds cu. yd.$7.00 84,000 $588,000 84,000 $588,000GrP 2a 2106 Common Embankment (CV)cu. yd.$5.00 95,100 $475,500 73,500 $367,500 27,880 $139,400 8,120 $40,600 204,600 $1,023,000GrP 2b 2106 Select Granular Embankment (CV)cu. yd.$16.00 28,815 $461,040 11,150 $178,400 3,390 $54,240 3,590 $57,440 46,945 $751,120GrP 2c 2106 Common Embankment (CV) - ponds cu. yd.$15.00 83,000 $1,245,000 83,000 $1,245,000GrP 2d 2106 Select Granular - Structural Backfill (CV) cu. yd.$20.00 4,600 $92,000 3,160 $63,200 755 $15,100 765 $15,300 9,280 $185,600GrP 2e 2411 Granular Material (CV) cu. yd.$15.00 4,790 $71,850 3,370 $50,550 685 $10,275 1,020 $15,300 9,865 $147,975GrP 2f Retaining Wall Preload (CV)cu. yd.$10.00 15,000 $150,000 2,000 $20,000 2,000 $20,000 19,000 $190,000GrP 3a Mainline Pavement (1)sq. yd.$25.00 4,945 $123,625 4,945 $123,625GrP 3b Mainline Shoulder Pavement (1)sq. yd.$25.00 9,650 $241,250 9,650 $241,250GrP 3c Ramp/Loop Pavement (1)sq. yd.$25.00 13,215 $330,375 13,215 $330,375GrP 3d Ramp/Loop Shoulder Pavement (1)sq. yd.$25.00 3,015 $75,375 3,015 $75,375GrP 3e County Road Pavement (1)sq. yd.$25.00 11,790 $294,750 3,800 $95,000 350 $8,750 15,940 $398,500GrP 3f County Road Shoulder Pavement (1)sq. yd.$25.00 910 $22,750 15 $375 925 $23,125GrP 3g Frontage Road Pavement (1)sq. yd.$25.00 4,425 $110,625 4,425 $110,625GrP 3h Frontage Road Shoulder Pavement (1)sq. yd.$25.00 1,025 $25,625 1,025 $25,625GrP 3i Local Road Pavement (1)sq. yd.$25.00 1,495 $37,375 1,495 $37,375GrP 3j Bypass Road Pavement (1)sq. yd.$20.00 5,470 $109,400 5,470 $109,400GrP 3k Bridge Approach Panels sq. ft.$200.00 449 $89,800 449 $89,800GrP 4a 4" Concrete Walk / Median (2)sq. yd.$25.00 1,065 $26,625 1,890 $47,250 335 $8,375 3,290 $82,250GrP 4b 6" Concrete Walk / Median (Includes ADA (2)sq. yd.$25.00 5 $125 150 $3,750 60 $1,500 35 $875 250 $6,250GrP 4c Bituminous Walk Trail (2)sq. yd.$20.00 965 $19,300 773 $15,450 678 $13,550 2,415 $48,300GrP 4d Truncated Domes sq. ft.$60.00 202 $12,120 96 $5,760 40 $2,400 338 $20,280GrP 5 Concrete Curb and Gutter lin. ft.$25.00 9,430 $235,750 4,513 $112,813 1,343 $33,563 1,885 $47,125 17,170 $429,250GrP 6 Guardrail lin. ft.$120.00 5,400 $648,000 200 $24,000 5,600 $672,000GrP 7 Pavement Edge Drains lin. ft.$9.00 7,250 $65,250 3,105 $27,945 695 $6,255 835 $7,515 11,885 $106,965GrP 8a Removals - Pavement sq. yd.$5.50 24,900 $136,950 11,010 $60,555 1,160 $6,380 2,290 $12,595 39,360 $216,480GrP 8b Removals - Curb and Gutter lin. ft.$5.50 155 $853 2,990 $16,445 465 $2,558 3,610 $19,855GrP 8c Removals - Drainage Pipe lin. ft.$10 530 $5,300 1,210 $12,100 25 $250 395 $3,950 2,160 $21,600GrP 8d Removals - Drainage Structure each $500 18 $9,000 5 $2,500 23 $11,500GrP 8e Removals - Clearing and Grubbing acre $3,000 7.9 $23,700 0.8 $2,400 0.5 $1,500 1.5 $4,500 10.7 $32,100 SUBTOTAL PAVING AND GRADING COSTS:$6,257,408 $1,525,623 $435,987 $556,537 $8,775,555 DRAINAGE, UTILITIES AND EROSION CONTROL Dr 1 Water Quality Ponds - clay liner l.s.$130,000 1 $130,000 1 $130,000Dr 2 Wetland Mitigation l.s.$127,000 1 $127,000 1 $127,000Dr 3 Drainage - rural and urban l.s.$1,700,000 0.88 $1,500,000 0.03 $45,000 0.06 $110,000 0.03 $45,000 1 $1,700,000Dr 4 Turf Establishment & Erosion Control 10%$626,000 $153,000 $44,000 $56,000 $879,000 SUBTOTAL DRAINAGE, UTILITIES AND EROSION CONTROL $2,383,000 $198,000 $154,000 $101,000 $2,836,000 BRIDGE COSTS Br 1 Bridge l.s.$3,171,389 1 $3,171,389 1 $3,171,389Br 2 Bridge - Trail l.s.$241,711 1 $241,711 1 $241,711 SUBTOTAL BRIDGE COSTS:$3,413,100 $3,413,100 RETAINING WALLS & OTHER MINOR STRUCTURAL COSTS RW 1 Wall 1 - CIP Ret. Walls (spread foundation (3)lin. ft.$2,367 197 $466,299 451 $1,067,517 648 $1,533,816RW 2 Wall 2 - CIP Ret. Walls (spread foundation (3)lin. ft.$2,020 191 $385,820 105 $212,100 296 $597,920RW 3 Wall 3 - CIP Ret. Walls (spread foundation (3)lin. ft.$2,945 559 $1,646,255 224 $659,680 783 $2,305,935RW 4 Wall 4 - CIP Ret. Walls (spread foundation (3)lin. ft.$1,780 299 $532,220 299 $532,220 SUBTOTAL RETAINING WALLS & OTHER MINOR STRUCTURAL COSTS:$2,112,554 $1,453,337 $744,320 $659,680 $4,969,891 SIGNAL. TMS AND LIGHTING COSTS SGL 1 Signals (permanent)each $275,000 0.75 $206,250 1.00 $275,000 0.125 $34,375 0.125 $34,375 2 $550,000SGL 2 TMS l.s.$180,080 1 $180,080 1 $180,080SGL 3 Mainline Lighting (permanent)l.s.$445,270 1 $445,270 1 $445,270 SUBTOTAL SIGNAL AND LIGHTING COSTS:$831,600 $275,000 $34,375 $34,375 $1,175,350 SIGNING & STRIPING COSTS SGN 1 Mainline Signing (C&D)mile $35,000 1.9 $65,000 0.4 $13,500 0.1 $2,500 0.1 $3,000 2.4 $84,000SGN 2 Mainline Striping mile $20,000 2.0 $40,000 0.7 $14,000 0.1 $2,500 0.1 $2,000 2.9 $58,500SGN 3 Mainline Signing (A, OH, Br Mtd)each $47,000 4 $188,000 1 $47,000 5 $235,000 SUBTOTAL SIGNING & STRIPING COSTS:$293,000 $74,500 $5,000 $5,000 $377,500 SUBTOTAL CONSTRUCTION COSTS:$15,290,662 $3,526,460 $1,373,682 $1,356,592 $21,547,396 TOTALCITY OF STILLWATERINTERCHANGEWASHINGTON COUNTY CITY OF LAKE ELMO SRF Comm No 10207 R:\11509 - CSAH 15 at TH 36 Interchange\Cost Tables\20200515 Draft Cost and Breakouts\Draft\20200521_TH 36 & CSAH 15 PRINTED: 5/21/2020 9:27 AM TH 36 AND MANNING AVENUE INTERCHANGE Concept Cost Estimate (based upon 2018 bid price information) 5/21/2020 UNIT EST. EST.EST. EST.EST. EST.EST. EST.EST. EST. ITEM DESCRIPTION UNIT PRICE QUANTITY AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT TOTALCITY OF STILLWATERINTERCHANGEWASHINGTON COUNTY CITY OF LAKE ELMO MISCELLANEOUS COSTS M 1 Mobilization 4%$612,000 $142,000 $55,000 $55,000 $864,000M 2 Non Quantified Minor Items 3%$459,000 $106,000 $42,000 $41,000 $648,000M 3 Temporary Pavement & Drainage 3%$459,000 $106,000 $42,000 $41,000 $648,000M 4 Traffic Control 3%$459,000 $106,000 $42,000 $41,000 $648,000 SUBTOTAL MISCELLANEOUS COSTS:$1,989,000 $460,000 $181,000 $178,000 $2,808,000 ESTIMATED TOTAL CONSTRUCTION COSTS:$17,279,662 $3,986,460 $1,554,682 $1,534,592 $24,355,396 OTHER PROJECT COSTS: R/W ACQUISITIONS Lump Sum $2,295,000 $1,705,000 $4,000,000 DESIGN ENG. & CONSTRUCTION ADMIN.Lump Sum $3,600,000 $3,143,371 $229,799 $226,830 $3,600,000 SUBTOTAL OTHER PROJECT COSTS $5,438,371 $1,934,799 $226,830 $7,600,000 TOTAL PROJECT COST $17,279,662 $9,424,831 $3,489,481 $1,761,422 $31,955,396 TOTAL PROJECT COST (OPENING YEAR DOLLARS)$17,279,662 $9,424,831 $3,489,481 $1,761,422 $31,955,396 NOTE: (1) Includes aggregate base class 5. (2) Includes aggregate base class 5 and PASB or OGAB, as appropriate.. (3) Assumes Mn/DOT Standard Plan Sheet designs; does not include excavation or backfill. R/W Acquisitions based upon: Proposed R/W acquisition for ramps, frontage road, and pond areas.