Loading...
HomeMy WebLinkAbout#04 - 2020 Mill and Overlay STAFF REPORT DATE: September 1, 2020 CONSENT AGENDA ITEM: 2020 Mill and Overlay Project – Change Order No. 1 SUBMITTED BY: Cara Geheren, Project Engineer REVIEWED BY: Kristina Handt, City Administrator Marty Powers, Public Works Director Jack Griffin, City Engineer ISSUE BEFORE COUNCIL: Should the City Council approve Change Order No. 1 for the 2020 Mill and Overlay project? BACKGROUND: Minnesota Paving and Materials was awarded a construction contract on June 2, 2020 to complete the 2020 Mill and Overlay Project. Work has been delayed after investigating a sink hole along the project corridor resulting in the discovery of a 24-inch RCP culvert crossing Jamaca Avenue that is in need of replacement. The project has a substantial completion date of August 28, 2020 and final completion date of September 18, 2020. PROPOSAL DETAILS/ANALYSIS: Minnesota Paving and Materials has submitted a change order to address additional work required to fully replace a 24-inch RCP culvert crossing Jamaca Avenue N. The project bid included an item to make repairs to the culvert but upon excavation it was discovered that a 16- inch HDPE watermain pipe installed in 2005 was drilled through the culvert creating a near full blockage. Given the discovered condition, a full culvert removal and replacement is necessary prior to completing the mill and overlay of the roadway. Due to the delay and added work, a contract time extension is also being recommended for the project, extending the substantial completion date to September 18, 2020 and final completion date to October 2, 2020. FISCAL IMPACT: This change order will increase the contract in the amount of $33,100.00 bringing the revised construction contract to $333,060.18. Since the correction is due to a storm sewer pipe staff is recommending that 50% of the culvert replacement, or $16,550, be funded through the storm water fund and 50% be funded through the street maintenance fund. With this change order both funds remain within their respective 2020 budgets. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Change Order No. 1 for the 2020 Mill and Overlay Project. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve Change Order No. 1 for the Mill and Overlay Project, thereby increasing the contract amount by $33,100.00”. ATTACHMENTS: 1. Change Order No. 1. CONTRACT CHANGE ORDER FORM CHANGE ORDER NO. DATE: TO: UNIT LS LS Amount of Original Contract $ Sum of Additions/Deductions approved to date $ Contract Amount to date $ Amount of this Change Order (ADD) (DEDUCT) (NO CHANGE)$ Revised Contract Amount $ The Contract Period for Completion will be (UNCHANGED) (INCREASED) (DECREASED) APPROVED BY ENGINEER: FOCUS Engineering, inc. APPROVED BY CONTRACTOR DATE DATE APPROVED BY OWNER: CITY OF LAKE ELMO, MINNESOTA DATE DATE $33,100.00 CITY OF LAKE ELMO, MINNESOTA BYBY CHANGE ORDER DESCRIPTION / JUSTIFICATION: This change order is being processed at the direction of the City to amend the Contract to complete additional work. The Change Order includes additional work to replace an existing 24-inch RCP culvert that was collapsed by the installation of watermain in 2005. The culvert was discovered through exporatory digging to investigate a known sinkhole. A new pay item shall be added as follows: CO1-1 : CULVERT REPLACEMENT. This item shall include payment for all work necessary for replacing an existing 24-inch RCP culvert, including traffic control, exploratory excacation, removal and replacement of bituminous pavement, removal and replacement of storm sewer including installation of flared end sections and rip rap. This Change Order shall also eliminate Bid Item No. 19 - CORRECT FAILED CULVERT as the culvert correction/repair work is not needed on the project. This Change Order also provides for a change in the Substantion Completion date as outlined in Section 0520, Article 3.02.A. from August 18, 2020 to September 18, 2020. The Final Completion date in Article 3.02.B shall be changed to October 2, 2020. Attachments (list documents supporting change):None DESCRIPTION OF PAY ITEM QTY UNIT PRICE CO1-2 CULVERT REPLACEMENT NET CONTRACT CHANGE CORRECT FAILED CULVERT ITEM $45,150.001 $45,150.00 OMG Midwest DBA MN Paving & Materials 2020 MILL AND OVERLAY PROJECT PROJECT NO. 2020.110 1 September 1, 2020 see above This Document will become a supplement to the Contract and all provisions will apply hereto. The Contract Documents are modified as follows upon execution of this Change Order. BYENGINEER 299,960.18 0.00 299,960.18 33,100.00 333,060.18 INCREASE/(DECREASE) ($12,050.00)NO. 19 $12,050.00-1 FOCUS Engineering, inc.CHANGE ORDER FORM