HomeMy WebLinkAbout03-01-05 CCMPMayor:
Dean Johnston
Council members:
Rita Conlin
Steve DeLapp
Liz Johnson
Anne Smith
Please read:
Lake Elmo City Council
Tuesday
March 1, 2005
3800 Laverne Avenue No.
Lake Elmo, MN 55042
777-5510 777-9615 (fax)
Since the City Council does not have time to discuss every point presented, it may appear that
decisions are preconceived. However, staff provides background information to the City
Council on each agenda item in advance; and decisions are based on this information and
experience. In addition, some items may have been discussed at previous council meetings.
If you are aware of information that has not been discussed, please fill out a "Request to
Appear Before the City Council form; or, if you came late, raise your hand to be recognized.
Comments that are pertinent are appreciated. Items may be continued to a future meeting if
additional time is needed before a decision can be made.
5:30 p.m. — Interviews for Planning Commission Vacancies
Agenda
City Council Meeting Convenes 7:00 PM
Pledge of Allegiance
1. Agenda
2. Minutes:
3. PUBLIC INOUIRIES/INFORMATIONAL:
A. PUBLIC INQUIRIES:
B. PUBLIC INFORMATIONAL:
) Water Ski Show:Joe Kiesling
V(2) St. Croix Valley Family
Center:Doris Karls
(3) Planning Commission Appointments
4. CONSENT AGENDA
A. Resolution No. 2005-019:Approving
Claims
Ppprz,trAtE-- 5 0
5. FINANCE
A.
6. NEW BUSINESS
February 15, 2005
Public Inquiries/Informational is an opportunity for citizens to
bring the Council's attention any items not currently on the
agenda. In addressing the Council, please state your name and
address for the record, and a brief summary of the specific item
being addressed to the Council. To allow adequate time for
each person wishing to address the Council, we ask that
individuals limit their comments to three (3) minutes. Written
documents may be distributed to the Council prior to the
meeting or as bench copies, to allow a more timely presentation.
Those items listed under the Consent Calendar are considered to
be routine by the City Council and will be enacted by one
motion under a Consent Calendar format. There will be no
separate discussion of these items unless a Council member so
requests, in which event, the item will be removed from the
general order of business and considered separately in its normal
sequence on the agenda.
t 7. MAINTENANCE/PARK/FIRE/BUILDING:
A.
8. CITY ENGINEER'S REPORT:
A. Water Tower Storage Tank Design
B. Resolution No. 2005-020: Approve Plans
and Authorize Advertisement for Bids, Water
System Interconnect — Phase II
9. PLANNING. LAND USE & ZONING:
A. Septic and Shoreland Setback Variance,
8784 Lake Jane Trail:Gibson
B. Comprehensive Plan Modifications (From
February 28th Planning Commission Meeting)
10. CITY ATTORNEY'S REPORT:
A.
11. CITY ADMINISTRATOR'S REPORT:
A. RE.c.tet."111( PAW( C.: ea Pi.Atk)
12, CITY COUNCIL REPORTS:
A. Mayor Hunt
B. Council Member Conlin
C. Council Member DeLapp---)
D. Council Member Johnson
E. Council Member Smith
March 2nd, 7 P.M- INFORMATIONAL
MEETING: City's Surface Water Pollution
Prevention Plan
March 8, 5:30 -p.m. Council Committee
Meetings
March 9, 7 P.M. Community Improvement
Committee Meeting
March 10, 5:30 p.m., SPECIAL Finance,
Legal, Legislative, Personnel Council
Committee Meeting
Lake Elmo City Council Agenda
March 1, 2005
Page 2
Tom Prew
C. Dillerud
BOARD OF REVIEW: May 4, 4-6 n.m.
CLEAN UP DAY: May 21st, 8-Noon
LAKE ELMO CITY COUNCIL MINUTES
FEBRUARY 15, 2005
1. AGENDA
2, MINUTES: February 1, 2005
3. PUBLIC 1NQUIRIES/INFORMATIONAL:
A. Susan Kane — Housing for Disabled
4. CONSENT AGENDA:
A. Resolution No. 2005-016 and Resolution No. 2005-017: Approve Claims
B. Lease Agreement with Washington County Fairgrounds for Clean Up Day
C. Escrow Reduction Prairie Ridge Office Park
5. FINANCE:
A. Monthly Operating Report
.
6. OLD BUSINESS: (Moved to Item 11)
APlanning Commission
(1) Vacancies
(2) 60-day Appointments
B. Fire Study Status
C. Library Tax
7. MAINTENANCE/PARK/FIRE/BUILD
A. Update on Building Dept.
8. CITY ENGIEER'S REPORT:
A. Approve Design for Water T
B. Public Works Building
9. PLANNING, LAND USE
A. Letter of Credit—Fieldst and Little Bluestem
B. Resolution 200 ncil Draft Water Resources Plan
C. Street Naming' tce
D. Reso1utionNq 2d5p12, 013, 014:Preliminary/Final Plan, Section 520
Sit Plan epciment — City, County Credit Union, Eagle Point
E. C act PlannititServices — Comp Plan Modifications
10. CITY AT EY' S REPORT:
11. CITY AD R'S REPORT:
A. Ordinanc 7-147:Planning Commission Composition
B. Ordinance N. 97-148:Parks Commission Composition
C. Council Committee Appointments — Council member Conlin
12, CITY COUNCIL REPORTS:
A. Council Input on Comprehensive Plan
13. ADJOURN Council Meeting
14. Finance, Legal, Legislative, Personnel Council Workshop
(a) Council input to the planning Commission on
Comprehensive Pan
(b) Guidelines for Council Meetings (Postponed to Council
Committee Meeting
(c) Discussion with Developers (Postponed to Council
Committee Meeting
LAKE ELMO CITY COUNCIL MINUTES FEBRUARY 15, 2005
Mayor Johnston called the Council meeting to order at 7:00 p.m. in the Council
chambers. PRESENT: Conlin, Smith, Johnston, Johnson, DeLapp, City Engineer Prew,
City Attorney Filla, Maintenance Supervisor Mike Bouthilet, City Planner Dillerud,
Finance Director Tom Bouthilet and Administrator Rafferty,
1. AGENDA
ADD: Discussion with developers, 8B. Public Works Building, 9F. Calendar for
Planning Commission meetings on the Comprehensive Plan, Library Tax
Move 11B,
M/S/P Johnson/Smith - to approve the February 15, 2005 City Council agenda, as
amended, (Motion passed 5-0).
2. MINUTES: February 1, 2005
M/S/P Johnson/Smith - to approve the February 1, 2005 City Council
amended. (Motion passed 5-0).
3. PUBLIC INOUIRIES/INFORMATIONAL:
A. Susan Kane — Housing for Disabled
Lake Elmo residents, Susan and Dennis Kane, expned they are parenteof a child with
special needs and wished to call the Council's atteiitrn tothe lack of homes for adults
with special needs or developmental disorders in Lake Elino. Ms, Kane stated this is the
Council's opportunity as they work on thet hensive Plan to make possible such
housing in the Old Village that would meetdren's needs. She noted as children
,
with developmental delays grow intoadults,'''repts wouldUlike to have them live in the
community they have grown up in..
4. CONSENT AGENDA:
A. Resolution No 2OOi16 andResolution No. 2005-017: Approve
Clairria,V4
M/S/P Jolmson/conlin - to adt Resolution No. 2005-016 approving claim numbers
240, 241, DD339 iirjgh DD34 26863 through 26869 that were used for staff payroll
dated February 3, 20�I1aim4n:Urnbers 242, 26871 through 26922, in the total amount of
$133,330,43. (Motion pa-0).
M/S/P DeLapp/Smith — to adopt Resolution No. 2005-017 approving claim number
26870 in the total amount of $180,00. (Motion passed 4-0-1:Abstain:Johnson recluse
herself from the vote because she had a personal interest in Johnson Construction.).
B. Lease Agreement with Washington County Fairgrounds for Clean Uo
Day
Clean Up Day is scheduled for Saturday, May 21, 8 a.m. until Noon, at the Washington
County Fairgrounds. Staff requested approval of the lease agreement with the
Washington County Ag Society in the rent amount of 103 and a $50 damage deposit.
LAKE ELMO CITY COUNCIL MINUTES FEBRUARY 15, 2005 2
M/S/P Johnson/Conlin — to authorize the Mayor to sign the Lease Agreement with
Washington County Ag Society for use of the Washington County Fairgrounds for Clean
Up Day and approve the rental fee of $153.00. (Motion passed 5-0,)
C. Escrow Reduction Prairie Ride Office Park
The City Engineer recommended a reduction in the escrow placed with the City for
grading and landscaping improvements at the Prairie Ridge Office Park. The engineer
certified reduction of the Letter of Credit from $190,000 to $20,000 to cover the
landscaping improvements that remain to be completed, The City Planner advised that
the Letter of Credit expires on April 30, 2005 and should be extended to at least October,
2006 to cover two full growing seasons on the landscaping yet to be installed on the site,
Council member DeLapp pointed out that lighting has been an is ue, Planner Dillerud
reported he wrote a letter to the developer asking him to get hts turned off at an
earlier hour and to take care of the two lights at each exits e planner has not
seen a response to that letter.
M/S/P DeLapp/Johnson — to approve reduction ofthe Site Plan escrowcscrow foithe Prairie
Ridge Office Park (Bremer Bank Letter of Credit 10221) from $190,000 to
$25,000 until the lighting issue is corrected and on the -condition that said Letter of Credit
be renewed to a date no earlier than Octob2006.(Motion passed 5-0).
5.
FINANCE:
A. Monthly Oneratina Repoti hir r:tin
6. OLD BUSINESS: *0 irokyr
A. Planning CommisSitinkAr
(1)Vacancieselb,„
(2)60-dayrAppoilitfants NIL
7. MAINTLNAN U D NG:
A. Update on'Unilding41561A.
`""1114010
The Summary Building Report provided for January, 2005 reported one new residential
building permit issued and no new commercial building permits. Council member
DeLapp commented that the building permit detail summary provided each month does
not state where the permit is located. He would prefer being alerted on areas of septic
problems, etc. This will be a topic for a Public Safety Council Committee Meeting
The City Planner reported code enforcement began semi-monthly meetings to review
complaints, and they have picked out four complaints to follow through legally. Attorney
Filla is preparing an update for the next council committee meeting. A systematic code
enforcement program for 2006 budget should be considered because there will be a cost
involved and probably not covered by penalties.
LAKE ELMO CITY COUNCIL MINUTES FEBRUARY 15, 2005
8. CITY ENGINEER'S REPORT:
A. Approve Design for Water Tower
The City Council agreed to place a new water storage tank in Sunfish Lake Park, The
two questions needed to be addressed was what will be the design of the tower and
exactly where it will be sited in the park.
A few residents, whose properties abut the park area, expressed concern that the water
tank would be an eyesore within the park and have potential impact on their property
values, The cost to move it as far west as possible would cost the city $30,000-$40,000,
This water tower would serve not only the new Tapestry development, but also serves
future neighborhoods.
M/S/P DeLapp/Johnson - to advise the property owners, located one half mile radius
from the location of the storage tank in Sunfish Lake Park, of informational meeting to
discuss the design of the tower at the March lst Council nte4ti otion passed 5-0.)
B. Public Works Building,
"ke
Terry Olsen, TKDA architect, presented a drawing the,pu It works building resembling
a barn and showing the pitch roof was eliminated and aipdated floor plan, Council
member DeLapp asked that the barn door and thecupola a little larger. The
Public Works Supervisor stated he has been tnvohd ineThnrnng stage and approved
the design proposal.
M/S/P Johnson/DeLapp - to author
Public Works building, as prsente
ate plans and specifications for the
asked 5-0.)
9. PLANNING,IM ZONING:
A. Letter oftredi iand Little Bluestem
The Planner adviseckthe Counciliiat the City Park improvements required to be
constructed by Robert Engstiom"Companies as a condition of approval for the Fields of
St. Croix II and Tana Ridgep1ats have not been completed as of this date. The most
significant improvement inebmplete is the City Park that lies between Fields II and Tana
Ridge. That park was to have been constructed by the developer per plans approved by
the Park Commission as satisfaction of the Park Dedication requirements for Fields II,
Little Bluestem and Tana Ridge, In addition, the developer -installed landscaping within
the plat remains short of that of the approved landscape plan, and there may be
infrastructure "punch list" items to be completed as well.
The Planner requested direction from the Council whether the City should present a sight
draft in the full amount of Letter of Credit #1804 (on or before February 27, 2005) and
utilize the funds to complete the required improvements within the plat, or approve
renewal of the Letter of Credit.
LAKE ELMO CITY COUNCIL MINUTES FEBRUARY 15, 2005 4
The most recent Letter of Credit renewal/extension expire on February 27, 2005. The
development agreement between Robert Engstrom Companies and the City specifies that
all public infrastructure and landscape improvements within the Fields of St. Croix 2nd
Addition were to be completed by September, 2000.
M/S/P Johnson/DeLapp - to notify Robert Engstrom Companies that it may renew the
subject Letter of Credit in the full amount for not more than 30 days (i.e. to March 27,
2005.) During that 30 day period Robert Engstrom Companies must present to the
Council both complete plans for project improvements that remain incomplete (primarily
the park and project landscaping), and a detailed schedule for the completion of those
improvements. A council decision regarding further extension of the Letter of Credit will
be based on their approval of the plans and schedule presented. Any plans/schedules
presented by the developer must be on one of the March 1st or March 15 city council
agendas. (Motion passed 5-0).
If the lender does not approve a 30-day extension of Lette 04 at the close of
business on February 25, 2005, the City will present the der wi Sight Draft for the
full amount of the Letter of Credit.
B. Resolution 2005-018, Met Council Drat Wateresources Plan
The City Planner reported the Metropolitan Council is considering a draft of their Water
Resources Policy Plan as is required every l0yeras by State Statute. The draft plan
covers Regional Policy regarding Waste Water ewer orm.Surface Water and Water
Supply. On February 8, the Public Works Council e reviewed the proposed
City comments on the draft plan that b.40 been prepared by staff and directed that those
comments be incorporated into a resolution for iiy Council consideration. A draft
Resolution was submitted for,p rovabINW,
M/S/P JohnsonSmitli4
comments on the Metropo
0).
C. Street aming Ordinance
At their February 8 meeting, the Council's Public Health and Safety Committee directed
staff to draft Council action that would reintroduce a unifoiiii street naming system
within the City that followSthe general pattern (Alphabetical west -to -east) of the 1971
Agreement, but which also allows some street naming latitude as long as the alphabetical
range is adhered to. This reintroduction of the uniform street naming system was brought
to the City's attention by the Lake Elmo Fire Department and the Washington County
Sheriff's Department.
elution No. 2005-018 offering City Council
at Dr ft Water Resources Plan, (Motion passed 5-
M/S/P DeLapp/Smith — to adopt Ordinance No 97-149, A Uniform Street naming And
Numbering System. (Motion passed 5-0.)
LAKE ELMO CITY COUNCIL MINUTES FEBRUARY 15, 2005
D. Resolution Nos. 2005-012, 013, 014:Preliminary/Final Plan, Section 520 Site
Plan and PUD Amendment — City, County Credit Union, Eagle Point
On February 8, the Finance, Legal Council Committee reviewed the subject package of
applications with the applicant. The committee directed that this application be placed
back on the Council agenda to decide if it wants to reverse the Planning Commission
recommendation regarding denial of asphalt shingle substitute.
M/S/P Johnson/DeLapp — to approve Resolution No. 2005-012, A Resolution Approving
the Preliminary Plat and Final Pat of Eagle Point 4th Addition. (Motion passed 5-0).
M/S/P Johnson/Conlin — to approve Resolution No. 2005-013, A Resolution Approving
the PUD Plan Amendment for Eagle Point Business Park 4th Addition, Lot 1, Block 1 to
allow the use of asphalt shingles of a grade similar to that used o - 'e Prairie Ridge
Office Park. (Motion passed 4-lDeLapp)
M/S/P Johnson/Johnston — to adopt Resolution No. 2005(
the Section 520 Site Plan for City and County Credi
Smith)
E. Contract Planning Services — Corn
The City Planner reported the Finance, Leg
recommended the City retain TKDA plann ,,,
complete the 2005 Comprehensive Plan modifica
Planner believed the strategy wouid b xpediep''
rather than the alternative of oing thro6gh a
assistance.
A Rtion Approving
on. (Motion passed 3-2:DeLapp,
Plan ations
slativePersonnel Council Committee
meeting assistance as is required to
`t' ased on the time element, the
nd in the best interests of the City
thy RFP process to secure such
M/S/P DeLapp/Johnso qp1ii4the use of the planning and engineering contract
services of TKDA 0 the 205
tpodFflcations to the comprehensive plan, not to exceed
the $9,000 in th4Xisting planning budget as reported in the Monthly Operating Report.
The planner will brin'in a new Ooposal if the cost exceeds the $9,000. (Motion passed
5-0), .
Planning Commission Comprehensive Plan Meeting Schedule
The City Planner provided a schedule of meetings for the Planning Commission and
Council to work on the Comprehensive Plan.
M/S/P Johnson/DeLapp - that all the Planning Commission and/or City Council meetings
as scheduled, or any future meetings, related to the Comprehensive Plan be televised.
(Motion passed 5-0).
10. CITY ATTORNEY'S REPORT:
LAKE ELMO CITY COUNCIL MINUTES FEBRUARY 15, 2005 6
11. CITY ADMINISTRATOR'S REPORT;
Mayor Johnston requested that the Planning Commission appointments be moved to the
Planning Commission section of the meeting following a decision regarding the
appointment process.
Council member Johnson made the following motion because she wanted to make sure
that the Council didn't delay appointments. She said the Planning Commission has a
rigorous schedule and voiced her concern on losing the experience members.
M/S/F Johnson/DeLapp — to amend the Council agenda to address Item 6A. Planning
Commission Appointments. (Motion failed 2-3:Johnston, Smith, Conlin)
A. Ordinance No. 97-147:P1annin2 Commission Composition
The City Administrator reported the Council asked the Finance,,Legislative Council
Committee to review the code relating to Planning Commission*pointments, terms and
limits. He recommended that the appointment process for pOls bkany commission
should be consistent. The committee agreed with this proposed practiceohange. The
final changes pertaining to the appointment process 1ie been incorporated in Ordinance
No. 97-147.
M/S/P Johnson/DeLapp — to adopt Ordinance No. 97- ending Section 210.03
relating to Planning Commission Composi end- hange term to terms),
(Motion passed 5-0.)
B. Ordinance No. 970418:1Par s
M/S/P Johnson/DeLapp lo atiopt Ordinance No.97-148, amending Section 225.03
relating to Parks CommissionCornposiiion. as-ainended (change term to terms). (Motion
passed 5-0).
fission Composition
C. Q�unei1 Committee Appointments — Council Member Conlin
At an earlier Counci Aneeting, the Council approved Mayor Johnston's recommendation
for Council Commi be organized for 2005 as follows:
•• Finance, Human Resource legislative Policy, Personnel: Liz Johnson, Chair, Anne
Smith, Member
Public Health and Safety: Anne Smith: Chair, Member to be determined after filling
Council vacancy
Public Facilities: Steve DeLapp, Chair, Member to be determined after filling Council
vacancy
M/S/P Smith/DeLapp — to approve Rita Conlin as a member of the Public Health and
Public Facilities Council Committees. (Motion passed 5-0.)
LAKE ELMO CITY COUNCIL MINUTES FEBRUARY 15, 2005 7
6. OLD BUSINESS:
A. Plannin2 Commission
(1) Vacancies
(2) 60-day Appointments
The City had received the resignation from Jennifer Pelletier from the Planning
Commission. With this resignation, there are three vacancies on the Commission.
Council Member Smith indicated she talked to Ms. Pelletier, who would like an
extension of a leave of absence for six month.
M/S/P Smith/DeLapp — to approve Jennifer Pelletier's request for an extension of a leave
of absence for six months from the Planning Commission. (Motion passed 5-0).
There are six applications on file: Jule Fliflet, Gloria Knoblau
Lyzenga, Leroy Rossow and Mark Sandstrom, At its January
Council adopted a policy procedure for filling commission,*
(2) 60-day Appointments
At its January 4th meeting, the Council appointed Todd Ptacek, Rodney Sessmg, and
Charlie Schneider to the Planning Commission for
M/S/P Smith/DeLapp - appoint Charlie Sc rto his flthree year term on the
Planning Commission. (Motion passed 5-0)
M/S/P Johnson/DeLapp — to appko!'"'
appointments of Todd Ptacek
The City Administrator advi
the appointments of Fodd itace
604..
xtension of the Planning Commission
otion passed 5-0).
as n t aPpropiiate to reinterview, but consider
Sessing.
,
M/S/P Johnson/DeLapp - to advertise the Planning Commission vacancies with an
P
lieation deadline of February 25', 4:30 p.m. and schedule interviews for March 1st
startingaPat 5:30 based oithe number of applications. (Motion passed 5-0.)
B. Fire Study Staus
Mayor Johnston asked when the Council will have the opportunity to submit input on the
Final Fire Study report. The administrator responded that he, Planner Dillerud and the
Fire Chief have reviewed the study which reviews projected needs, services and
considers locations of neighboring fire services as an informational item. This is a
professional study and will be presented to the Council in 30 days.
C. LibraryTax
Mayor Johnston believes that Washington County should be spending the local tax
money of a Lake Elmo branch rather than using it to fund libraries in other parts of the
county. Washington County receives about $215,000 per year from Lake Elmo taxpayers
in the form of a library tax. He said the County is taking Lake Elmo's money with no
LAKE ELMO CITY COUNCIL MINUTES FEBRUARY 15, 2005
incentive to spend it here. Johnston suggested the City investigate the process by which
the City could remove itself from the library system and how quickly money would
become available. He requested council support for a procedure of requesting tax money
for a dedicated library account used by the City.
M/S/P DeLapp/Smith — to direct staff to define process by which the City could remove
itself from the Washington County Library system and request the tax money from Lake
Elmo taxpayers to be used for a dedicated library account used by the City. (Motion
passed 5-0,)
Council member Smith said she read the article in the Pioneer Press stating Washington
County Library System was looking at a kiosk for the City. Smith said she was not in
favor of a kiosk, but wanted a library for -herself and to take her kids,to look for books to
read.
12. CITY COUNCIL REPORTS:
Council Input on Comprehensive Plan,
Mayor Johnston and Council members Johnson, c lin sub,Mitted individual statements
of input to the Planning Commission as to the key lieinents they would like to have
considered during the planning process. Council members DeLapp requested that the
Planning Commissioners remember the diftkence be eerysplanning and implementation.
He gave his verbal comments detailing his I Ibr.comprehensive plan revision and
will submit those comments in writing. The 'c4nments have been made part of
these minutes. Council memberSmith'nuied ilull her top priority was protecting the
residents south of 10th street. he added tlmt ith i.wo residents that live south of 10
th
Street, Commissioners Ben Roth -,tace'she felt the City had a very capable
,,, ,,
Planning Commission., CounCIT Smith's verbal comments are in written form
and made part of these
Discussion was
nued to Committee workshop.
13. Adjourn Counc,
.
eetm a 10:23 p.m.
• "
14. Finance, Legal, Letds1ative, Personnel Council Workshop
Attendees: Chair Liz Johnson, Council member Anne Smith, Mayor Dean Johnson,
Council Members Rita Conlin and Steve DeLapp, Planner Dillerud, Administrator
Rafferty and Finance Director Bouthilet.
(1) Council Input to the Planning Commission on Comprehensive Plan: There
was a short discussion on the key elements submitted by the Council on what they would
like to have considered during the planning process. Planner Dillerud responded there
was a consensus on items from the Council and that the Planning Commission would not
have any difficulty considering the issues the Council members submitted, He believed
those items of input were already addressed in the existing comprehensive plan. Dillerud
noted there was not any great dispute among the Council members regarding policy.
LAKE ELMO CITY COUNCIL MINUTES FEBRUARY 15, 2005 9
(2) Guidelines for Council Meetings: (Postponed to next Council Committee
workshop)
(3) Discussion with Developers: (Postponed to next Council Committee
workshop)
(4) Adjourn workshop at 11:15 p.m.
--------- ---------------- +
Respectfully submitted by Sharon Lumby, City Clerk
Resolution No. 2005-012 Approving the Preliminary Plat and Final Plat of Eagle Point
4th Addition
Resolution No. 2005-013 Approving the PUD Plan Amendment for Eagle Point Business
Park 4th Addition to allow the use of asphalt shingles
Resolution No. 2005-014 Approving the Section 520 Site Plan for City and County
Credit Union
Resolution No. 2005-016, 2005-017 Approve Claims
Resolution No. 2005-018 Met Council Draft Water Resoure
Ordinance No. 97-147:Planning Commission Cornposii
Ordinance No. 97-148:Parks Commission Compositiol
LAKE ELMO CITY COUNCIL MINUTES FEBRUARY 15, 2005 10
Comprehensive Plan for Lake Elmo
2010, 2020, 2030
Council Input
Given that we are planning our city for the next 25 years, at which time Lake Elmo likely
will be fully developed, we must consider carefully community needs which are
important now and which will be important in 25 years. My input includes four land use
issues and three planning process issues.
LAND USE ISSUES
1, Employment Corridor — The Met Council agreement specifies that we use
1300 REG units for non-residential development. Using these REC units to
create a business park offering a diversity of jobs to match the professional
skills of our residents provides a real benefit for our citizens. Doing so will
use approximately 2% of the land in Lake Elmo while providing residents with
the opportunity to work near where we live. This reduces commuting time
and contributes to our quality of life.
2. Residential Development south of Tenth Street — Under the terms of the
Met Council Agreement, we have the opportunity to create a model senior
community. This type of community can be based around a care center and
contain a diversity of housing types and price ranges to fit the varied needs of
our aging population while having only a minimal impact on surrounding
neighborhoods. Many cities fail at creating a senior community because they
rush to complete a discrete "project" rather than planning a comprehensive
community.
3 Middle Income Housing — By requiring that every homeowner purchase 2.5
acres of land to build a housing unit, Lake Elmo is raising the cost of home
ownership beyond the reach of our teachers, firefighters, police officers, and
other middle income professionals. By zoning a portion of Lake Elmo for 1
acre lots we have an opportunity to make living in Lake Elmo an affordable
option for professional 'families in the middle income range. Creating an area
where the density requirement is one home per acre will preserve the
possibility for moderately priced housing in the future. As an example, the
area north of Stillwater Blvd, east of County 13, and south of Highway 5 is a
potential location for a more dense neighborhood where there may be less
upward pressure on home prices in the future. Most people on one acre lots
are very pleased with the rural pharacterthese lots provide in comparison to
other housing options available elsewhere.
4. Housing for the Disabled — Every community has a small number of
children with disabilities. As these children grow into adulthood, they need
housing options which may include care or supervision. Lake Elmo needs to
ensure that the housing needs of these citizens of Lake Elmo are addressed
in our Comprehensive Plan.
PLANNING PROCESS ISSUES
5. Buffering existing neighborhoods south of Tenth Street. — One of many
benefits of a clustered senior community is that it can contain a variety of
housing types and density levels. This gives us more flexibility to create
buffering around existing residences. For example, the density for a care
facility may range from 20 to 30 units per acre. One level townhomes are
typically built with 3 to 4 units per acre. This diversity allows us to create a
well planned, clustered senior community that meets the market needs and
allows us to place these homes in mariner which will buffer them from existing
homes.
6 Voting Demographics — Our Comprehensive Plan will define development
over the next 25 years, during which Lake Elmo will experience significant,
steady population growth. This growth must be carefully staged to ensure the
interests of voters from existing neighborhoods, who value the rural character
of our community, are not overwhelmed by new residents who do not yet
share that value. The longer we delay carefully staged development, the
higher the risk that a large influx of new residents in a short period of time will
lead to election results that could change our development philosophy and
destroy the character of our community.
7, Population Calculations — Population projections must be made using
realistic calculations — the use of artificially high projections is not acceptable
within the terms of the agreement with the Met Council. Inflated estimates
bring the potential for mandatory redevelopment if it is determined we have
not planned in substantial, good faith compliance with Met Council
requirements. The typical density for senior housing is 1.5 people per
residence. The typical density for "Active Senior" housing is 1.8 people per
residence. The typical density for single family residential housing is 2.5
people per residence. We can use 2.5 people per residence in our
calculations only when we are planning housing which justifies that density.
Dean Johnston
February 15, 2005
Feb.17 '05 2239 S DeLapp Lake Elmo MN
FAX E51-777-1001 P. 2
Febru
To:
From: Steve DeLapp
Lake Elmo Planning Commission:
RECEIVED
'ZZ
4:2,)
Subject: Approach to Comp. Plan Modifications Req ired by Met Council
My request to the Planning Commission is that we accept th requirements by the Met
Council and clearly understand the difference between "imp ement" and "plan for", With
great effort our City came out of the fight with the Met Cou+oil with some lofty planning
expectations and a minimum of "in -the -ground" repireme t . We started with a
requirement of stopping all development in the City for two ears and then beginning a
30 year plus phase -in of sewered development and redevelo ment, leading to a
population of approaching twice the population of Oakdale. 1 We ended with a far
different requirement, one that might in the end leave our City with no negative
consequences to the residents from the existing 2020 Comp. :Plan. We do not have to
grow any faster than we show in the existing 2020 Comp Phin, but we need to show how
we could accept limited urban growth south of 10th Street pest 2020.
We have agreed to allow the Met Council to bring two very estricted sewer pipes into
our City corning west from the Eagle Point Development ant corning north up Lake
Elmo Avenue. The total capaoity that the Met Council is e endin,g up to our City limits
is with enough to sewer 8,700 Residential Equivalent Conn tions, (one household of any
size, or ten employees, equal one RFC unit). We are requird to show how we could
accept 6,600 REC's,IGO existing in Eagle Point Deve1opmeit, and 6,500 new REC's. We
need to show provisions for connecting to 1,500 new or exising dwelling units and a
small number of new businesses by the end of our existing 2000 Comp Plan planning
period in 2020.
All required the REC's can be shown for installation between now and 2020, in
Cimarron, the Old and extended Old Village area. All the oil business conneotions can
be made within the existing Eagle Point Development, or immediately adjacent to it. The
only difference from the existing, rejected Comprehensive Pan, and our revised
Comprehensive Plan, is that we must create a Vogt-2020 S ' ed Urban Growth Zone",.
comparable to those in et Metro Area urbanizing cities, soutjh of 10th Street,
This is my proposal, consistent with our agreement, and con istent with maintaining the
intent of our existing 2020 Comp. Plan, and consistent with he City Council's promise of
minimizing impact on existing residents in the City. It is the,proposal that resulted
directly from the meetings with Peter Bell and is exactly wh4t the Met Council has
specified, without an implied option for the City to accelerat urban growth:
1. Continue housing and commercial development norti of 10th Street almost
exactly as currently planned, with the substitution of '.,000 REC's for existing or
new housing in the Old Village Area.
Feb.17 '05 2237 S DeLapp Lake Elmo /IN
FAX 651-777-1001 P. 1
sewer.
3. Limit pre-2020 business development south of 10th
Development and to the minimum amount ofadjce1
the 2030 Development Framework,
4. Show the undeveloped land south of 10th Street as "I
Development".
5. Allow developers to accelerate high density, urban g
of 10th Street if they transfer the permanent developr
rural land, whose owners are willing to send their ex
(TDR),
This planning work should take a minimum of time and
Comp. Plan, as post 2020 development south of 10th Street
land use will look exactly the same on the maps north of 10
numbers need to appear on the mapother than to stipulate
north of le Street and that the staged growth south of 1061
population of 24,000 people by 2030. (I would remind the
Council defines a household as something like 2.5 or 2,85 p
of new housing population north of 10th Street is counted in
will be much higher than Met council of 2.5 — perhaps appr
unit in Carriage Station -- if we do not put an emphasis on k
To summarize:
Limit change pre-2020 to the exact specifications of the Agr
of urban growth south of 10th Street with a post-2030 staged
Anything further will increase, or accelerate the increase of,
should only be considered, after the City's revised Comp. PI
Council and has the full backing of the City residents,
By our agreement with the Met Council, unlike other cities i
we cannot be forced to accept additional development mend
the "Livable Cities Act" etc., through 2030. In the end, if w
development, we may be able, to reduce overall developmeii
15 and 25 years to further reduce the impact of our Agreem
2, Show the replacement of the package sewer system i e Cimarron with Metro
treet to Eagle Point
land, if any, consistentlavith
t--2020 Staged Urban
owth in selected areas plinth
ent rights from low density
sting development rightS.
no changes to the existing
not be detailed and
et. No population
uild-out population fcir
is "planned" to reaCh a
ion that the Met
• When the final tally
020, our actual population
aching the 4 to 5 people per
w occupancy housing units.)
ment. Show the feasibility
growth area.
rbanization in the City, and
is approved by the MEt
i the 7 County Metro Ar
tes, such as compliance arith
do not induce additional
After all we have betveen
ktt•
MET COUNCIL — CO, PLAN (COCIL CPU
Liz Johnson — 2/15/05
Now that we have an agreement we need to look at bow it will be implemented to
achieve the agreement.
✓ My expectations are that we honor the agreement.
e We meet the population expectation requirement
• We meet the REC unit requirement.
• We approach this with the intentions to honoring the agreement.
My input in regards to implementation:
V We work towards finding ways in which to protect the current residents
south of 10th street.
✓ We work towards achieving the identified needs of the community
throughout the last 10 years. Example:
• Senior Housing — and place it in the area south of 100' street.
- This not only has been an identified need for many years but is a
great tool to help us reach our population goal with little or no
impact on some of our systems (less traffic than single family
housing units, no impact on the school system, less potential city
service needs as many times they take care of their own roads, etc.
in their community)
We could look at having the more full service care senior housing
complex system south of 10th street with additional senior
apartment type of housing within the old village also.
- I do not believe it is a "here" or "there" type of situation.
Middle Income Housing —
There is a need to have some middle income housing for families
that provide needed professional services in our community but
are unable to afford housing above middle income level.
(Teachers, fire fighters, etc.)
Housing for Residents with Disabilities - This could be part of the Old
Village plan.
(See Reverse Side)
MET COUNCIL — COMP PLAN (COUNCIL INPUT),
Liz Johnson — 2/15/05
Job Opportunities within our Community
This provides opportunities for our citizens to work within their
own community.
This decreases the amount of time parents are away from their
children, which increases the time that parents can spend
providing guidance to their children.
This decreases the amount of traffic throughout the Twin Cities
area.
1/ Planned growth (staging growth) of REC units so the infrastructure can
accommodate the growth.
• Starting in 2007 the business corridor along 194 could develop as REC
units are made available. This would also start provide tax revenue in
order to help manage the infrastructure needs, (Addresses REC units
and commercial development requirements.)
• Starting in 2007 the Senior Housing Complex could be developed.
(Addresses REC units and population.)
• Starting 2008 (Cottage Grove connection available) growth planned in
the old village area. (Addresses REC units and population.)
Between 2010 and 2030 have staged growth in the rest of the planned
residential development south of 10th street. (Addresses REC units and
population.)
Non-REC unit population growth (to meet the 2030 population
requirement) occurs between 2010 and 2030. (OP Developments)
en d
Concepts for Revised Comp Plan
1. Based on the settlement, we have two primary constants to work with,
6,600 recs, 24,000 pop. I believe the rest is for Lake Elmo to determine,
2. Plan for staged development & growth.
3. Prevent hopscotch development; establish controls such that each area
staged for development is 50% (??) complete before allowing
development to begin in the next area.
4. Establish buffer standards to protect existing rural residential areas south
of 10th
5. Establish landscaping standards south of 10th for streets, parking lots,
residential and business development that promotes a rural feel. The
more trees, shrubs etc, the more the sound of 194 traffic will be absorbed.
What other things can be done to lessen the impact Of dense
development???
6. Establish architectural standards south of 10th that are harmonious to the
existing landscape and rural feel.
7. Take a look at senior housing from the senior perspective, i.e,, where do
the seniors of Lake Elmo want to live, Old Village vicinity or along 194?
What type of housing do they prefer, high -riser multilevel apartment -like,
townhouse?? What amenities do they want?
8. Is a mix of life -cycle housing appropriate for south of 10th, single family,
apartments, town homes for residential south of 10th?
9. Challenge city staff to provide model city examples where the community
desired to retain a rural atmosphere or another type of unique identity.
How did they do it? Think cutting edge.
10. Ensure public hearings are adequately advertised and that the public has
opportunity for input.
Anne Smith - Elements for Revised Comp Plan
1. Protect residents south of 10th Street, Use of landscape architecture to provide buffers
between existing neighborhoods and any new developments.
2. Senior Housing; We need to address where it will go and how much we will need in
the coming two decades, (Growth Study)
3 Housing for Disabled; Needs are similar to those of seniors. Could we combine these
two or perhaps have them adjacent to each other? (Shared trail systems, access to Park
Reserve, close to services which could possibly be inside the main care facility such as
groceiy, theatre, barber and beauty salon etc...),
4. Corporate Woods Development along 1-94. Many urban areas such as Kansas City,
Houston, Boston, etc... have designed office parks that are unobtrusive. It is important to
meet our Code Requirements so that we are able to use all 1300 REC units,
5. Phased Development; It is important not to front-end load or back -end load all of our
development.
With that said, I feel we have a very capable Planning Commission with two residents
living south of 10th Street, Todd Ptacek and Ben Roth. I think it is important to let the
Commission do its job.
APPROVED: 2-15-05
LAKE ELMO CITY COUNCIL MINUTES
FEBRUARY 1, 2005
6:00 P.M. — Interviews for City Council Appointment
1. AGENDA
2. MINUTES: January 18, 2005
3, PUBLIC INQUIRIES/INFORMATIONAL:
A. PUBLIC INQUIRIES
B. PUBLIC INFORMATIONAL
(1) Introduction of Representative Mike Charron
(2) Council Appointment
4. CONSENT AGENDA:
A. Resolution No.2005-011: Approving Claims
B. Ordinance No. 97-145:2005 Fee Schedule
5. FINANCE:
6. NEW BUSINESS:
7. MAINTENANCE/PARK/FIRE/BUILDING:
A. Ordinance 97-146: Park Hours
8. C11 Y ENGINEER'S REPORT:
A. Proposed Public Works Garage:Terri Olsen, TKDA
B. Change to Water Tower Project
9. PLANNING, LAND USE & ZONING:
A. Eagle Point Business Park: Resolution No, 2005-012 Approving the
Preliminary Plat and Final Plat of Eagle Point 4th Addition, Resolution No.
2005-013:Denying the PUD Plan Amendment, Resolution No. 2005-014;
Approving the Section 520 Site Plan for City and County Credit Union
B. Trails Plan Open House
10. CITY ATTORNEY'S REPORT:
11. CITY ADMINISTRATOR'S REPORT:
A. Ordinance 97-147: Planning Commission Composition, Appointments
B. Ordinance 97-148: Parks Commission Composition
C. CIC Appointment
D. Met Council Proposed Agreement
12. CITY COUNCIL REPORTS:
Mayor Johnston called the meeting to order at 7:00 p.m. in the Council chambers. PRESENT:
Johnston, Smith, Johnson, DeLapp, City Engineer Prew, City Attorney Filla, Finance Director
Tom Bouthilet, City Planner Dillerud, Administrator Rafferty and Recording Secretary Schaffel.
1. AGENDA
Public Inquiries-B3: Oakdale Water Presentation.
City Administrator's Report-11E: Met Council Workshop with Planning Commission on
Feb. 7, 2005.
Appointment of Councilmember and Oath of Office before the Minutes.
M/S/P Johnson/DeLapp, to approve the February 1, 2005 City Council agenda, as amended.
(Motion passed 4-0).
APPROVED: 2-15-05
1.B. COUNCIL APPOINTMENT
M/S/P Johnson/DeLapp to appoint Rita Conlin as Councilmember by unanimous ballot. (Motion
passed 4:0). Administrator Rafferty administered the Oath of Office to Rita Conlin. Council
member Conlin joined the council.
2, MINUTES: January 18, 2005
No. 12 Planner Dillerud was not present. Absent council member was Liz Johnson.
M/S/P DeLapp/Smith to approve the January 18, 2005 City Council minutes, as amended.
(Motion passed 3-0-2 Abstain: Johnson -Conlin)
3. PUBLIC INQUIRIES/INFORMATIONAL:
A. PUBLIC INQUIRIES:
B. PUBLIC INFORMATIONAL
(1) Introduction of Representative Mike Charron
Mike Charron introduced himself as the new state representative for this district. He
commended the city council on the negotiations with the Met Council, Mayor Johnson said they
will create a legislative agenda at the next council committee meeting.
(3) Oakdale Water Update
Jim Kelly a Lake Elmo Environmental Commissioner who works for the Minnesota Department
of Health and Mike Santoro from 3M gave an update on newly discovered contaminants in
Oakdale water. Mr, Kelly said trace levels of PFOF and PFOA have been found in Oakdale
municipal wells sampled as a result of two disposal sites where these chemicals were found,
Concentrations are low and considered safe over a lifetime of drinking the water. They do not
anticipate finding the chemicals in Lake Elmo wells. Mr. Kelly said the ability to test for these
chemicals was discovered in the last 18 months. Mayor Johnston said we are fortunate we have
people of Jim Kelly's caliber working for the city.
4.CONSENT AGENDA:
A. Resolution No.2005-011: Approving Claims
Mayor Johnson asked the total billed by Lindquist and Venum the Met Council litigation firm,
and if we have reached the end. Finance Director Bouthilet said that the cost over 16 months
totals $364,723. Administrator Rafferty said he believes this is the end of billings.
M/S/P Johnson/DeLapp, to adopt Resolution No. 2005-011, A Resolution Approving Claim
Numbers 237, 238, DD329 through DD338, 26805 through 26816 which were used for staff
payroll dated January 20, 2005, claims 26817 through 26862 in the total amount of $115,472.62.
(Motion passed 5-0).
B. Ordinance No, 97-145:2005 Fee Schedule
M/S/P Johnson/DeLapp, to adopt Ordinance No. 97-145:2005 Fee Schedule. (Motion passed 5-
0).
5. FINANCE:
2
APPROVED: 2-15-05
6. NEW BUSINESS:
7, MAINTENANCE/PARK/FIRE/BUILDING:
A. Ordinance 97-146: Park Hours
Administrator Rafferty explained that the city has an inconsistent policy regarding parks hours.
The Council Committee directed staff to prepare an ordinance that is enforceable. A Special
Permit can be issued to groups. Councilmember Smith said we received a 10 page letter from a
woman who uses the park at night, and rerninded council to read that letter. Councilmember
DeLapp said he was sad we have to lock our parks.
M/S/P Johnson/DeLapp, To adopt Ordinance No. 97-146, an ordinance amending Section
1355.07 Public Park Hours of the Lake Elmo Municipal Code,
Administrator Rafferty said having the provision in the code does not mean a permit is granted.
Safety and other considerations will be considered. (Motion passed 4:0:1 Abstain: Conlin)
8. CITY ENGINEER'S REPORT:
A. Proposed Public Works Garage: Terri Olsen, TKDA
Administrator Rafferty said the city has been planning municipal facilities over many months.
Terri Olsen said they have separated Public Works from City Hall allowing for an agrarian
setting to blend with a rural location. If bids are low enough there are add -on amenities.
Administrator Rafferty said this facility is programmed within budget constraints, with input of
Public Works Committee and MAC. The cost of $2.1 million is well within target for this
facility meeting all interests identified. Mayor Johnston was surprised they call it rural character.
Councilmember Smith asked how much of the cost is in the appearance. Ms. Olsen will find out.
They began with a base building with a flat roof, stick built and changed to a pre-engineered
building and different roof. The council decided to review the next agenda item and this one
collectively.
B. Change to Water Tower Proiect
The City Engineer said the water system plan is to connect the Old Village with Lake Jane
moving the water tower to the new Public Works building site. Higher elevation of 20-30 feet
saves some money. A second water main will be needed between Highway 5 and Tapestry. It
will cost $200,000 more by moving it. There are practicalities to having it on the same site.
Administrator Rafferty said we would spend that $200,000 later anyway. The Finance Director
said the WAC charges should support this project. Councilmember DeLapp said he thought we
would have an linage of a farm and a silo. The City Engineer said it will take one year to build
and will not be operational until 2006. Administrator Rafferty said there is a June construction
date.
M/S/P, Smith/DeLapp to send it back to committee because this proposal may not fit in
architecturally. (Motion passed 5-0).
M/S/P DeLapp/Johnson to site the water tower in Sunfish Lake Park. (Motion passed 4-0-1
Abstain: Conlin),
9. PLANNING, LAND USE & ZONING:
A. Eagle Point Business Park: Resolution No. 2005-012 Approving the
APPROVED: 2-15-05
Preliminary Plat and Final Plat of Eagle Point 4th Addition, Resolution No.
2005-013:Denying the PUD Plan Amendment, Resolution No, 2005-014;
Approving the Section 520 Site Plan for City and County Credit Union
The Planner said the application from United Properties was unanimously recommended by the
Planning Commission. The PUD item of issue was the request to substitute asphalt shingles for
the code requirement for roofing. The Planning Commission voted 5-2-1 to deny the PUD
amendment to allow asphalt shingles.. Item 9A includes a communication from a tenant in Eagle
Point with reference to glare from the standing seam metal roofs.
Councilmember Smith said the site plan asks us to approve 10,000 square feet, and only six
thousand square feet of building are to be constructed, per the applicant.
The Planner responded that the site plan presented is for the entire 10,000 square feet, with site
area, parking and all site features sized for the 10,000 square feet. The site plan also shows the
entire 10,000 square foot building footprint. On that basis the staff and Planning Commission has
determined that the 10,000 square foot standard is complied with.
The Planner asked the City Attorney if it is okay to put and take uses when it is in the PUD. The
City Attorney said the council has latitude with PUD's because they are designed to give more
than what you get from normal zoning. He also said that if there is a variation from 10,000
square feet building requirements, Council has the right to reject a 6,000 square feet building.
Dale Glowa of United Properties introduced Pat Pierce, president of City and County Credit
Union, Steve Dowdy the architect, and George Burkards. Mr. Glowa said Eagle Point Business
Park was a thoughtful PUD they spent months developing with the City Council in 1999 The
Credit Union building site plan is sized to accommodate 10,000 square feet. He noted that
specifications regarding roof materials were silent when this PUD was approved, now they are
requesting the PUD to be amended for additional roofing material, to include a timberline asphalt
roof. He advised the Council that metal and cedar are loud in a rainstorm, with ice concern
sliding off as well. The glare is another concern. Asphalt won't do that. The Planner said we
have until March 7 to decide.
Steve Dowdy with Pope Associates said his company has been asked to redesign drive -up
canopies with metal roofs several times because of sound and ice problems.
George Burkards said United Properties has spent $4,000,000 in the park. Signs, monuments,
and bridges were created for appearance. He said the quality of all of the buildings are good.
Councilmember DeLapp said perceptions of architecture in this part of Lake Elmo are not good.
M/S/P Johnson/Conlin to table the United Properties applications until the next meeting.
Pat Pierce of City and County Credit Union said part of the plan includes a conference room to
use by the community at no cost. They are trying to be a good neighbor.
(Motion passed 4-1 Johnston- Thinks they should have approved it.)
B. Trails Plan Open House
The Planner said an Open House was not anticipated in the contract.
4
APPROVED: 2-15-05
Councilmember DeLapp said he believes it is important to involve the public, and he therefore
supports the Letter of Agreement to cover the added costs for the Open House.
M/S/P DeLapp/ Johnson to direct staff to sign the Letter of Agreement and to approve the
additional expenditure of $1,448 to cover the additional cost associated with the City's
contractual agreement for a Trails System Plan (S240) and the cost for support and materials for
the Trails Plan Open House ($1,208). (Motion passed 5-0).
10. CITY ATTORNEY'S REPORT:
13. CITY ADMINISTRATOR'S REPORT:
A. Ordinance 97-147: Planning Commission Composition, Appointments
Administrator Rafferty said terms for both commission should be the same so they should be
considered together.
B. Ordinance 97-148: Parks Commission Composition
Mayor Johnston said it was not his intention to have term limits. His idea was only to review
commissions after two terms. Councilmember DeLapp agreed -if a commissioner is here for nine
years, we almost have to change the rules to keep them.
M/S/P, Smith/DeLapp to send composition for both Planning and Parks Commissions back to
council committee for further discussion, (Motion passed 5-0)
Todd Ptacek said two commissioners were appointed for sixty days. Mayor Johnston said the
time limit will not expire. He said it is a process issue first, and then they will address
appointments.
C. CIC Appointment
Administrator Rafferty said an application was received from Brenda Anderson.
M/S/P DeLapp /Smith To appoint Brenda Anderson as a member of the Community
Improvement Commission. (Motion passed 5-0).
D. Met Council Proposed Agreement
Administrator Rafferty introduced the agreement's achievement versus the Met Council
Resolution 2002-30. The Planner explained where we stand today before we affirm the
agreement with the Met Council. A list of modifications for our Comp Plan was attached to Res.
2002-30. The most important element of this agreement is a credit for existing Cimarron and
Old Village housing and for the planned Old Village expansion. Old Village streets and water
mains can be upgraded simultaneously with sanitary sewer construction. A second key element
is that the city can continue with clustering north of 10th Street. The majority of the city will be
allowed to maintain its rural character, 31.° key element is that the Lake Elmo Interceptor has
been dropped. Instead there will be two sanitary one from the west and one from Cottage Grove
in the south. The City will have the option to use the additional units for redevelopment,
environmental issues, or other uses after 2030. Population planned was about 13,000 people at
buildout. This plan is 24,000 capped. These are the issues and numbers we have to show in our
Comprehensive Plan.
APPROVED: 2-15-05
Former Mayor Lee Hunt said he is convinced this is the best the city can do. It is consistent with
the first meeting with the governor, and he urged approval.
Administrator Rafferty introduced the ten point agreement and the process for approval.
Mayor Johnston said this is a better plan than what was originally proposed. It is not negotiable,
and he urged approval. Councilmember DeLapp said transfer of density might help to facilitate
development below 10111 Street.
M/S/P, Smith/Johnson, To approve Resolution 2005-015,
Ben Roth asked for clarification because he does not think the agreement requires that much
density below 10th Street. Mayor Johnston said the average of 3 units per acre is in the
agreement.
Todd Ptacek asked if it is the council's intention to average those units and lower density to
buffer existing neighborhoods. Mayor Johnston said that is his intention.
The Planner said units per acre or open space can be used to achieve that end.
Councilmember Conlin said this has been an open process, and it is probably the best settlement
we are going to get. She will support it. Councilmember DeLapp supports it as he interprets it,
though it was not an open process. He said he will not vote for it unless the language is changed
to protect existing residents. Councilmember Johnson said both negotiating teams got us the best
we can expect.
Former Mayor Hunt said this agreement has all of the compromises within the ranges the city
council came up with. It is not great but it is reasonable.
The City Attorney said amending a Comprehensive Plan is just the first phase of legislative
effort to adopt official controls. Substantial changes will have to be made to those controls and
regulations. Direct the planning commission as you will.
Councilmember DeLapp said if we agree, it will have the least impact on the last Comp Plan. It
does not have to be inserted. Councilmember Smith agreed. Councilmember Conlin said now is
not the time.
(Motion passed 4-1, DeLapp — Agreement can be modified, there is ambiguity among the
council.)
12. CITY COUNCIL REPORTS:
Administrator Rafferty asked for a joint workshop on 2m05 with the Planning Commission,
Mayor Johnston said the council might need a workshop first.
The council decided to meet from 6 to 8 and then join the Planning Commission at 8:00 p.m.
Councilmember Johnson congratulated John Schiltz of Lake Elmo Inn for being named one of
the top ten chefs in the metropolitan area.
6
APPROVED: 2-15-05
Councihnembers Smith and Councilmember Johnson attended the basic conference for newly
elected officials, it was a good orientation, and they would like to avail themselves of all
opportunities to get up to speed. Administrator Rafferty said March said strategic planning is
scheduled for March.
Councilmember Smith welcomed Brenda Anderson into Community Improvement and hopes
others will want to participate.
Councilmember Conlin thanked everyone for their support.
Adjourned 9:53 pm
Respectfully submitted,
Kimberly Schaffel
Recording Secretary
7
Lake Elmo
City Council
Mara 1, 2005
a Section:PUBLIC INF
Agenda Item: Water Ski Show: Joe Kiesling
Background information for March 1, 2005:
.Joe Kiesling, Tri-Lakes Assoc., is requesting Council approval of a Water Surface Use Permit for the
Annual Water Ski Show on Lake Jane, August 13, from 1-5 p.m. The Tri-Lakes Assoc. has secured
the appropriate insurance coverage and the Sheriffs Department will sign off on the permit pending
Council approval. The Fire Department will be contacted to provide an emergency vehicle.
Mr. Kiesling will be in attendance to request a variance from surface water rules for the days of this event and
a "No Parking" permit to park from Jamaca Avenue to Jane Road North.
Action Ile
M/S/ to approve the permit request of Joe Kiesling, on
behalf of the Tri-Lakes Association, to hold a Water Ski Show
on Lake Jane, August 13, 2005, from 1-5 p.m. based on the
submittal of the appropriate information and on past
favorable requests.
Attachments:
1. Water Surface Use Permit
2. Insurance certificate
rson responsible:
.Lumby
JUL 20 '00 0711PM WASHINGTON CO JAIL
P.3
WASHINGTON COUNTY
OFFICE OF THE SHERIFF
LAW ENFORCEMENT CENTER
15015 62ND STREET NORTH • P.O. BOX 3831 • STILLWATER, MINNESOTA 56082-3601
(861) 430-7800 Facsimile Machine: (661) 430.7803
etiommOommeat'agearate
WATER SURFACE USE APPLICATION
*************************************
Permit for a Contest, Race, Regatta or other
Event on or in the Waters of This County
Applicant Information:
1...(o4tAs ksso
Organization: Phone:
Address:
Contact Person:
Name
Address: C13
Lake where event will be held;
Home Phone,:
Work Phone:
What portion of the lake will be used:
Type of Event:
Date of Event:
— 0 Al tern.a.te Date:
JAMES J. FRANK
SHERIFF
STEVEN F POTT
CHIE1 DEPUTY
5-7) -1 —7 (-/ 6 3
Structures or Buoys needed for the event:
All applications must be signed by a representative of the City
or Township where the event will be held.
All applications must be received by the Sheriff's Department at
least two weeks prior to the event. All Insurance
Certificates must be received at least 10 days vrior to the
event. Send the application and proof of insurance to the
following address along with a self-addressed, stamped envelope:
Washington County Sheriff's Office Sgt, Jerry Cusick
15015 62nd St. No.
P.O. Box 3801 •
Stillwater, MN 55082-3801
Signature of Applicant:
City/Township Representative:
Printed oi Recycled Paper
Date:
Date:
EQUAL EMPLOYMENT OPPORTUNITY / AFFIRMATIVE ACTION
JUL 20 '00 07:10PM WASHINGTON CO SAIL
P.2
WASHINGTON COUNTY
OFFICE OF THE SHERIFF
LAW ENFORCEMENT CENTER
15015 6210 STREET NORTH • P.O. BOX 3801 STILLWATER, MINNESOTA 55082-3801
(651) 430-7600 Facsimile Machine: (651) 430.7603
eamexiemoge a Etediesee,e
JAMES J. FRANK
SHERIFF
STEVEN F. POTT
CHIEF DEPUTY
GENERAL REQUIREMENTS FOR A SUMMER EVENT HELD ON OR JN THE WATER
The following is a list of General Requirements for a Water
Surface Use Permit for an Event. There may be additional
requirements due to unique concerns with a particular event.
Applicant must obtain and pay for a Comprehensive General
Liability Insurance policy in the amount of $300,000 per
person and $1,000,000 per occurrence. The policy must be
non -cancellable. The policy shall name the County of
Washington, its' officials and employees, and the City or
Township where the event will be held, as additional
insureds for the term of the permit. A Certificate of
Insurance must be supplied to the Sheriff's Office at least
ten (10) days ,prior to the event. The Washington County
Risk Manager will verify that the insurance requirements are
met before the permit is issued.
The applicant must contact the local police departments that
will be affected by the traffic, spectators, or participants
of the event.
The applicant must make arrangements for emergency medical
services at the site of the event.
The applicant must provide an adequate number of approved
toilet facilities for use by the participants and spectators.
The applicant is responsible for removal of all debris,
litter and trash from the event area immediately after the
event.
The event is not allowed to interfere with any public
accesses to the lake.
All watercraft must be properly licensed and equipped as
required by Minnesota State Statutes. Any exemption from
any of these rules must be requested on the application. If
an exemption is granted, the boats are not allowed to leave
the event area.
The applicant must provide two (2) boats equipped with
first aid equipment. These boats will also be used to help
keep spectators out of the area of the event.
PrInterl on Fiecycled Paper EQUAL. EMPLOYMENT OPPORTUNITY AFFIRMATIVE ACTION 30%Pall ConinorTat
Date Issued: 26-Jan-05 CERTIFICATE OF INSURANCE
CERTIFICATEHOLDER
CITY OF LAKE ELMO AND WASHINGTON COUNTY
3800 LAVERNE AVE N.
LAKE ELMO, MN 55042
PRODUCER
American Speclalty Insurance Services, Inc.
142 North Main Street
Roanoke, Indiana 46783
This certificate is issued as a matter of
Information only and confers no rights upon
the certifcateholder. This certificate does
not amend, extend, or alter the coverage
afforded by the policy below.
INSURED
USA Water Ski Association
1251 Holy Cow Road
Polk City, FL 33868-6200
TRI LAKES ASSOCIATION
6045 LAKE ELMO AVE N.
STILLWATER, MN 55082
COVERAGES — THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE
FOR THE POLICY PERIOD INDICATED, NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER
DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES
DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITION OF SUCH POLICIES. AGGREGATE LIMITS SHOWN MAY
HAVE BEEN REDUCED BY PAID CLAIMS.
COVERAGE LIMITS IN DOLLARS
United States Fidelity and Guaranty Company GL Policy Number D255L00157 General Aggregate 5,000,000
Eifective:01-NOV-04 12:01 AM Expires:01-NOV-05 12:01 AM
Products -Completed Operations Aggregate 1,000,000
Personal and Advertising injury 1,000,000
Each Occurrence 1,000,000
Damage to Premises Rented to You (Any One 50,000
Premises)
Medical Expense Limit (Any One Person) Excluded
ADDITIONAL INFORMATION / RESTRICTIONS / SPECIAL ITEMS
• The Certificateholder Is only an Additional Insured with respect to liability caused by the negligent acts or omissions of the Named Insured.
• Owned Watercraft Liability excluded.
• Coverage is effective January 24, 2005.
• Coverage for Wakeboard School and Ski School operations is excluded.
• The General Liability policy is subject to a $50,000 per occurrence Self -Insured Retention with a $100,000 annual aggregate.
CANCELLATION - SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELED BEFORE THE EXPIRATION DATE THEREOF, THE ISSUING
COMPANY WILL ENDEAVOR TO MAIL 30 DAYS WRITTEN NOTICE TO THE CERTIFICATEHOLDER, BUT FAILURE TO MAIL SUCH NOTICE SHALL
IMPOSE NO OBLIGATION OR LIABILITY OF ANY KIND UPON THE COMPANY, ITS AGENTS OR REPRESENTATIVES.
Form No. UWSU_000D02
Certificate No. 1000328332
David Harris
Authorized Representative
Lake Eimo
City Council
March 1, 2005
Agenda Section: PUBLIC INFO.
Agenda Item: Planning Commission Appointments
No 313(3)
Background Information for March 1, 2005:
The City Council adopted a procedure for filling Commission vacancies, At the February 15'11 meeting, the
Council directed staff to follow that procedure and to advertise for Planning Commission applications with
a deadline for applications, February 25, 4:30 p.m, The Council asked that interviews be scheduled starting
at 5:30 p.m., March ls'. There were six applications on file at City Hall.
At the February 15'1' meeting. the City Council appointed Todd Ptacek and Rod Sessing to the Planning
Commission for 60 days. The City currently has two vacancies, First Alternate and Second Alternate.
Staff is requesting Council direction for filling Planning Commission vacancies.
Person responsible:
Action Items: S. Lumby
Attachments;
CITY OF' LAKE ELMO
WASHINGTON COUNTY, MINNESOTA
RESOLUTION NO. 2005-019
RESOLUTION APPROVING CLAIMS
BE IT RESOLVED THAT Claim Numbers 243, 244, DD350 through DD362,
26923 through 26954, were used for Staff 'Payroll dated February I 7`h , 2005, claims
26955 through 26993, in the total amount of 8337,401.25 are hereby approved.
ADOPTED, by the Lake Elmo City Council on the 1s day of March, 2005.
Dean A. Johnston
Mayor
ATTEST:
Martin J. Rafferty
City Administrator
Accounts Payable
Computer Check Proof List
User: administrator
Printed: 02/25/2005 - 8:52 AM
Invoice No
Vendor.10000
SESSION A
Description
10,000 Lake Chapter
Seminar - Nonstructural Fire and Safety
Check Total:
Vendor:ACEHARD Ace Hardware
02156691 Sealer, hook, nozzle stem
Check Total:
111. 4-1-11 \I: ((r 11, 1111.1 01011111110
Amount Payment Date Acct Number
Check Sequence: 1
175.00 03/01/2005 101-420-2400-44370
175.00
27.34 03/01/2005
27.34
Check Sequence: 2
101-430-3100-42150
Vendor:ADVGR Advanced Graphix, Inc. Check Sequence: 3
9302 Decals - Public Works 85.19 03/01/2005 101-430-3100-44040
Check Total: 85.19
Vendor:ARAM Aramark Check Sequence: 4
629-5654615 Linen - City Hall 50.84 03/01/2005 101-410-1940 11010
Check Total: 50.84
Vendor:ATTWI AT&T Wireless Check Sequence: 5
023-2750230 Floater Phone - Fire Dept_ 20.49 03/01/2005 101-420-2220-43210
Check Total: 20.49
Vendor:AVAYA AVAYA Inc. Check Sequence: 6
2720563369 Telephone Maint. Contract 150.36 03/01/2005 101-410-1940-44040
Check Total: 150.36
Vendor:13IFFS Biffs Inc.
W247922 Portable - Sunfish Lake Park
Check Total:
Check Sequence: 7
74.26 03/01/2005 101-450-5200-44120
74.26
Reference
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
AP - Computer Check Proof List (02/25/2005 - 8:52 AM) Page 1
Invoice No
Vendor: CADIGMC
GCCS69512
Description
Cadillac Pontiac-GMC
Repair Door - GMC Truck Public Works
Check Total:
Vendor:CARQUEST Car Quest
D371441 PVC Split
Check Total:
VendorEARLANDE Earl F. Andersen, Inc.
0064515-IN Stop Sign, Yield Sign
Check Total:
Vendor:EMAUTO
ST020805-3
Vendor:EMERGAPP
20552
20766
VendorEMSUSA
294306
294694
Vendor:FIREINST
1387
Vendor:FORCE
01221656
Vendor:FXL
March 2005
EmergencyAutomotive Technology Inc.
Emergency Lights - new loader
Check Total:
Emergency Apparatus Mahar_
Battery Replacement - 3187
Tank Leak - 3183
Check Total:
Emergency Medical Supply, Inc.
Medical Supplies - Fire Dept.
Medical Supplies - Fire Dept.
Check Total:
Fire Instructors Assoc of MN
Annual Memebership
Check Total:
Force America
Parts for PW Truck Hydraulics
Check Total:
FXL, Inc.
Assessing Services for March 2005
Check Total:
AP - Computer Check Proof List (02/25/2005 - 8:52 AM)
Amount Payment Date Acct Number
Check Sequence: 8
391.35 03/01/2005 101-430-3100-44040
391.35
Check Sequence: 9
3.37 03/01/2005 101-430-3100-42150
3.37
480.21 03/01/2005
480.21
Check Sequence: 10
101-430-3100-42260
Check Sequence: 11
279.56 03/01/2005 410-480-8000-45400
279.56
235.05 03/01/2005
1,082.90 03/01/2005
1,317.95
297.55 03/01/2005
124.15 03/01/2005
421.70
Check Sequence: 12
101-420-2220-44040
101-420-2220-44040
Check Sequence: 13
101-420-2220-42080
101-420-2220-42080
Check Sequence: 14
10.00 03/01/2005 101-420-2220-44330
10.00
24.27 03/01/2005
24.27
1,700.00 03/01/2005
1,700.00
Check Sequence: 15
101-430-3100-42210
Check Sequence: 16
101-410-1550-43100
Reference
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
Page 2
Invoice No
VendorGAR.ELICK
56283
Vendor GEN ESIS
IVC00344
IVC00344
Vendor: GRTSTILL
2038
Vendor. GUSTAF
Emp. Claim
Vendor.JOHNSBR
LSS 1005777140
Vendor:JOHNS
163919
Vendor. Leaguel2
18426
18426
18426
18426
18426
18426
18427
18427
18427
18427
18427
18427
18428
18429
Description
Garelick Steel Co, Inc
Steel, steel bars - Public Works
Check Total:
Next Genesis Productions
Greg's Laptop
Data Recovery
Check Total:
Greater Stillwater Chamber
Annual Membership
Check Total:
RichardGustafson
Boots - Public Works
Check Total:
Brian Johnson
Safety Can and Funnel
Check Total:
Johnson Radio Communications
Antenna, Mount, Charger - New Loader
Check Total:
League of MinnesotaCities Insurance Trust
Ins. Prenvum - Admin
Ins. Premium - Fire Dept_
Ins. Premium - Bldg. Dept.
Ins. Premium - Public Works
Ins. Premium - Parks
Ins. Premium - Water Dept.
Ins. Premium - Admin
Ins. Premium - Fire Dept.
Ins. Premium - Bldg Dept.
Ins. Premium - Public Works
Ins. Premium - Parks
Ins_ Premium - Water Dept.
Ins. Premium - Admin
Ins. Premium - Admin
AP - Computer Check Proof List (02/25/2005 - 8:52 AM)
Amount Payment Date Acet Number
122.47 03/01/2005
122.47
112.50 03/01/2005
112.50 03/01/2005
225.00
Check Sequence: 17
101-430-3100-42210
Check Sequence: 18
101-420-2220-44300
101-410-1520-43180
Check Sequence: 19
325.00 03/01/2005 101-410-1320-44330
325.00
183.60 03/01/2005
183.60
Check Sequence: 20
101-430-3100 14170
Check Sequence: 21
46.86 03/01/2005 101-420-2220-42400
46.86
Check Sequence: 22
51.12 03/01/2005 410-480-8000-45400
51.12
26,018.00 03/01/2005
11,507.00 03/01/2005
827.00 03/01/2005
7,197.00 03/01/2005
1,680.00 03/01/2005
6,058.00 03/01/2005
3,982.87 03/01/2005
1,689.88 03/01/2005
136.56 03/01/2005
1,820.74 03/01/2005
398.29 03/01/2005
390.66 03/01/2005
I87.00 03/01/2005
459.00 03/01/2005
Check Sequence: 23
101-410-1320-43610
101-420-2220-43630
101-420-2400-43630
101-430-3100-43630
101-450-5200-43630
601-494-9400-43610
101-410-1320-43610
101-420-2220-43630
101-420-2400-43630
101-430-3100-43630
101-450-5200-43630
601-494-9400-43610
101-410-1320-43610
101-410-1320-43610
Reference
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
Page 3
Invoke No
Description
Check Total:
Vendor:LFNDVENN Lindquist & Vennum
298770-0840 Comp Plan Appeal
Check Total:
Vendor:MALMQ
Emp. Claim
Vendor:McCarthy
20142
Vendor:METROCA
02107021
Vendor:MNDOH
Q1 1820009
GregMalmquist
Milage - LMC Training
Check Total:
McCarthy Well Company
Pump Performance Inspections
Check Total:
Metrocall Inc.
Pagers - Fire Dept
Check Total:
MN Department of Health
Quaterly Service Conn. Fee
Check Total:
Vendor:NORTHT00 HSBC Business Solutions
0261063828 Heat shrink tubing, tape, disks
Check Total:
Vendor:ONBCALL Gopher State One-CallOne Call Concepts, Inc
5010505 Line Locates for January
Check Total:
Vendor:PERA
468344
Vendor:PRESS
02/14-02/23
PERA
PR Batch 2 2 2005 PERA Employer Share
PR Batch 2 2 2005 PERA Employee Share
Overpaid
Check Total:
StevenPress
Cable Operator - Council Meeting 2/15
AP - Computer Check Proof List (02/25/2005 - 8:52 AM)
Amount Payment Date Acct Number
62,352.00
Check Sequence: 24
281.90 03/01/2005 101-410-1940-43020
281.90
27.08 03/01/2005
27.08
Check Sequence: 25
101-420-2220-43310
Check Sequence: 26
210.00 03/01/2005 601-494-94.00-42270
210.00
Check Sequence: 27
83.21 03/01/2005 101-420-2220-43210
83.21
Check Sequence: 28
816.00 03/01/2005 601-494-9400-43820
816.00
Check Sequence: 29
26.06 03/01/2005 101-430-3100-42150
26.06
118.90 03/01/2005
118.90
1,372.72 02/17/2005
1,265.95 02/17/2005
-46.68 02/17/2005
2,591.99
Check Sequence: 30
101-430-3100-44300
Check Sequence: 31
101-000-0000-21704
101-000-0000-21704
101-000-0000-21704
Check Sequence: 32
54.00 03/01/2005 101-410-1320-43620
Reference
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
Page 4
Invoice No
Description
Amount Payment Date
Acct Number Reference
02/14-02/23
Vendor. QUALAIR
8146
Vendor: QUICKSI
6228819
Vendor.QWEST
651714-2209 456
Vendor.ROGERS
12332
12332
Vendor. RUD
02/14-02/23
02/14-02/23
02/15-02/22
Vendor. S&T
0 1JR6960
01JR6960
01JR6960
01JR6960
01JS6439
01JS7146
Vendor: SPRINT
0526076028-3
Cable Operator -Planning Mtgs 2/14, 2/23
Check Total:
Quality Air
Valve Replacement - Fire Dept.
Check Total:
Quicksilver
3 Courier Deliveries
Check Total:
Qwest
Hudson Lift Station
Check Total:
Rogers Printing Services
Printing - Permit Applications
Printing - Utility Billing Envelopes
Check Total:
DianePrince-Rud
Cleaning - City Hall
Cleaning Supplies
Cleaning - Fire Hall
Check Total:
S&T Office Products, Inc.
Paper
Binders -Planning
Files - Bldg Dept.
Dividers - Fire Dept.
Ink Cartridges
Pens, Paper, Folders
Check Total:
Sprint
Laptop Connection - Fire Dept.
Check Total:
AP - Computer Check Proof List (02/25/2005 - 8:52 AM)
108.00 03/01/2005
162.00
518.00 03/01/2005
518.00
79.41 03/01/2005
79.41
35.96 03/01/2005
35.96
171.46 03/01/2005
121.42 03/01/2005
292.88
240.00 03/01/2005
18.36 03/01/2005
240.00 03/01/2005
498.36
103.26
88.18
20.41
10.91
53.76
101.90
378.42
03/01/2005
03/01/2005
03/01/2005
03/01/2005
03/01/2005
03/01/2005
66.15 03/01/2005
66.15
101-410-1910-3620
Check Sequence: 33
101-420-2220-44010
Check Sequence: 34
101-410-1910-44300
Check Sequence: 35
602-495-9450-43210
Check Sequence: 36
101-420-2400-42030
601-494-9400-42000
Check Sequence: 37
101-410-1940-44010
101-410-1940-42110
101-420-2220-44010
Check Sequence: 38
101-410-1320-42000
101-410-1910-42000
101-420-2400-42000
101-420-2220-42000
101-410-1320-42000
101-410-1320-42000
Check Sequence: 39
101-420-2220-43210
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
ACH Enabled: No
Page 5
Invoice No Description Amount Payment Date Acct Number Reference
Vendor STATETRE State Treasurer Check Sequence: 40 ACH Enabled: No
Apri15 Seminar Seminar - Karl Homing 35.00 03/01/2005 101-420-2400-44370
Check Total: 35.00
Vendor:TKDA TKDA, Inc. Check Sequence: 41
000200500629 SW Mgmt Plan & MS4 1,320.60 03/01/2005 603-496-9500- 43030
000200500635 Water Sys Interconnection 13,488.69 03/01/2005 601-494-9400-43030
000200500637 Water Tank Project 1,923.15 03/01/2005 601-494-9400-43030
000200500638 NPDES Permitting 104.56 03/01/2005 603-496-9500-43030
000200500638 Utility Permits, Staff Meetings 3,427.36 03/01/2005 101-410-1930-43030
000200500638 MSA Reporting and Meetings 418.22 03/01/2005 402-480-8000-43030
000200500638 VFW Lights Change Order 52.28 03/01/2005 404-480-8000-43030
000200500638 55th St Vacation, 8784 Lake Jane Tr Var. 731.89 03/01/2005 409-480-8000-43030
000200500638 Public Works Building 21,113.32 03/01/2005 410-480-8000-46200
000200500638 Gibson Variance, Sunfish Ponds/Lake 888.71 03/01/2005 602-495-9450-43030
000200500638 Wildflower Shores Grading, Tapestry, EPB 1,936.88 03/01/2005 803-490-9070-43030
000200500652 City Council Mtgs Attendance - T. Prew 200.00 03/01/2005 101-410-1930-3030
Check Total: 45,605.66
ACH Enabled: No
Vendor:TREMM MichaelTrernain Check Sequence: 42 ACH Enabled: No
Emp. Claim Airfare - Indianapolis - Training 271.40 03/01/2005 101-420-2220-43310
Check Total: 271.40
Vendor:WAS-SHER Washington County Check Sequence: 43 ACH Enabled: No
44094 Law Enforcement Contract Jul -Dec 2004 176,910.71 03/01/2005 101-420-2100-43150
Check Total: 176,910.71
Vendor:XCEL Xcel Energy Check Sequence: 44 ACH Enabled: No
0073-736-544048 3014 Jamley - Public Works 22.95 03/01/2005 101— 430-3100-43810
Check Total: 22.95
Total for Check Run:
Total Number of Checks:
297,549.98
44
AP - Computer Check Proof List (02/25/2005 - 8:52 AM) Page 6
DRAFT
City of Lake Elmo
Planning Commission Meeting
Minutes of February 28, 2005
Chairman Helwig called to order the meeting of the Lake Elmo Planning Commission at 7:00
p.m. COMMISSIONERS PRESENT: Sedro, Deziel, Armstrong, Ptacek, Schneider, and Roth.
STAFF PRESENT: Administrator Rafferty, Planner Dillerud, Recording Secretary Kimberly
Schaffel.
Pledge of Allegiance
Agenda
M/S/P, Ptacek/Deziel, To accept the Agenda as presented. VOTE: 7:0.
Minutes of February 14, 2005
M/S/P, Ptacek/Deziel, To accept the Minutes of February 14, 2005 as presented. VOTE: 7:0.
PUBLIC HEARING: Variance for Septic — Gibson
The Planner introduced the application for a septic system variance. The applicant's
representative was present. The site is on the south shore of Lake Jane. The applicant proposes
to replace the septic system. The location puts 75 square feet of -the new drainfield within the
shoreland setback of Lake Jane. The Planner said this plan is the second location chosen which
impacts the site less than the first site chosen. The DNR, city engineer, and the city planner
indicate this is the best location for the septic system.
The Planner said this is a septic, Chapter 700 variance. Based upon recommendations of DNR
and the City Engineer, and based upon Findings in the Staff Report, staff recommends approval.
Commissioner Schneider asked if the well for the neighbor to the west is indicated on the site
plan.
The Planner said the neighbor's site was checked and that is the well that was found.
Applicant's Representative, Mo Anderson
The square footage of the drainfield within the OHW of Lake Jane is only one little corner.
THE CHAIRMAN OPENED THE PUBLIC HEARING AT 7:09 P.M.
THE CHAIRMAN CLOSED THE PUBLIC HEARING 7:10 P.M.
M/S/P, Arrnstrong/Ptacek, To recommend approval of the variance for a septic system for Mr.
Gibson based upon the recommendation of the City Engineer that states this is the best design
and a minimal request and based upon Findings and recommendations of the City Planner.
VOTE: 7:0.
PUBLIC HEARING: DEER GLEN
The Planner explained that there this agenda item represents a series of applications to develop
more than 100 acres. The applications are for Preliminary Plat, Comprehensive Plan
Amendment, Rezoning, an OP Concept Plan, and a Conditional Use Permit to locate a church.
The site fronts on Highway 36 and Keats Avenue. The Preliminary Plat shows 40+ acres in the
Lake Elmo Planning Commission Meeting Minutes of February 28, 2005
ake Elmo
:it Council
rch 1,2095
Agenda Section: c Fry ENGINEER'S REPORT No 8A.
Agenda Item: Water Tower Design and Color Section, Water System Interconnect Project
Background information for March .1, 2005:
The City Engineer reported that at the February 1.5`h meeting. the Council requested him to review the tank
location west from the public works site. The location would be approximately 800 feet west of the public
works building. This location is as far west and north as it can he moved without placing it in the woods.
The City Engineer has determined this is a feasible alternative,
Property owners. within a one-half mile radius of the location of the water tower, have been invited to
offer their input on the water tower design.
The City Engineer requests Council direction on the style and color scheme of the tank and authorization to
proceed with plans and specifications for a water tower in Sunfish Lake Park, approximately 800 feet west
of the new Public Works Building.
Action Items:
Motion: , Second , to indicate the style of tank along
with the color scheme and authorize the City Engineer to proceed
with plans and specifications for a water tower in Sunfish Lake
Park, approximately 800 feet west of the new Public Works
Building, as verified by the City Engineer in his memo dated
February 24, 2005,
Attachments:
Letter from Tom Prew dated February 24, 2005
Person responsible:
T.Prew
TKDA
ENGINEERS • ARCHITECTS • PLANNERS
RECEIVED
FEE? 2 2115
February 24, 2005
Honorable Mayor and City Council
City of Lake Elmo, Minnesota
Re: Water Tower Design and Color Selection
Water System Interconnect Project
City of Lake Elmo, Minnesota
TKDA Commission No. 13186.000
Dear Mayor and City Council:
1500 Piper Jatfray Plaza
444 Cedar Street
Saint Paul, MN 55101-2140
(651) 292-4400
(651) 292-0003 Fax
www.thda.com
At the last City Council meeting we were requested to look at a tank location west from the public works
site. We have done that and have determined at the staff level that it is a feasible alternative.
The location would be approximately 800 feet west of the public works building. This location is as far
west and north as it can be moved, without placing it in the woods.
At Tuesday's meeting we will present a drawing with different colored water towers at this location,
We have investigated the concept of building only a stand pipe (silo) water tower, with a portion of the
standpipe being used actively and the remainder in reserve for fire protection. For this system to match
the required height and volume, it would be 25-feet in diameter, and 135 feet high. With this small
diameter, we would have severe icing problems inside the tower. Also hydraulically, the system would be
difficult and expensive to operate. High capacity pumps would be needed to maintain fire flows, along
with back-up power generators. We would also need low flow pumps to maintain sufficient pressure in
the system. Because of the cost and operational issues, we would not recommend this type of system over
the standard styles of water tower that we have discussed.
City Council Action Requested
Authorize the City Engineer to proceed with plans and specifications for a water tower in Sunfish Lake
Park, approximately 800 feet west of the new Public Works Building. Please indicate the style of tank
along with the color scheme in your motion.
Thomas D. Pre
City Engineer
TDP:arw
, P. E.
AR Employee Owned Company Promoting Affirmative Action and Equal Opportunity
GI IV OF
—"
3800 Laverip, Avenue. i\icluth Eiulc•;
February 25, 2005
TO: Lake Elmo City Council
Martin Rafferty
Chuck Dillerud
FROM: Sharon Lumby, City Clerk
SUBJECT: Planning Commission Interviews
Please find the following schedule for the Planning Commission Interviews
starting at 5:30 pm., on March rt, before the regularly scheduled Council
meeting. Applications are attached. Box lunches will be provided at 5:00
p.m. from the Lake ElmoInn.
5:30 p.m. LeRoy Rossow
5:45 p.m. Mark Sandstrom
6:00 p.m. Deb Lyzenga )
6:15 p.m. Tom Kreimer
6:30 p.m. Gloria Knoblauch
6:45 p.m. Julie Fliflet
recycjec', pa per
City of Lake Elmo
3800 Laverne Avenue North
Lake Elmo, Minnesota 55042
651.777.5510 Fax 777.9615
RECEIVED
Hau 105
arm
LAK E
ELMO
APPLICATION FOR PLANNING COMMISSION APPOINTMENTS
Date: 2-C/ 06"
Name R P
Address linq mo .4-ve
Phone Number W) Lgvo
1. What do you consider to be the major planning and development issue
Lake Elmo? Ma* 'a 64) Corn pre hens; ve
aire a curtof k7t1,1 sf. eau th. 17)
2. What do you see as the role and function of the Planning Commission?
ma,1U 666015 about all icculg hi'vu
en/yolk eep /11 in act. a if
mid then-- iskeg or fi
g the Ci
mt 0 vala(e
3. What experience and qualifications do you have that you feel will contribute to the Planni
Commission's work and which will enable you to provide a service in this regard?
e wo v k p-ee) pl.e cnr.L am4
fut t r• ckteS frof:6e
I have a expefriat(e 040 1;)?
4. How much time do you have, or are you willing to devote to Planning ComiWission activities?
J- In a bi/4. de,vale whaJoel- -/7)17,e.
ileateet tP be a siwni va lub/e,
o
hat property or development interest, either direct or indirect, do you have within Lake Elmo?
ittA paFt mr C owl 4-7)r. oq Pa
p co -kg a .1- 140 ta/X-e, Air-6 Li:WE-6m
Om 13 citric-6h tes dts fit
Please complete and return to the City, Office
60— both sma bus v c ail
/ 114.e.- Real E-74/11-6
tiqceWI (\a,nlvt keVt
tp (gatv
h.appw- iitq aii4DL SD 117 ,thhy, kuiyk
We -
aft ‘feCg d- g f
atUipe- 'pm n7/i7
Elmo
e Avenue North
Lake Elmo, Minnesota 55042
651.777.5510 Fax 777.9615
UCATION POR
Dec . 30/02
Date:
Le Royy J Ros s ow
Name
Address 11050 50t 11 St.
ISSION APPOINT MEWS'
Lake El rnO, Mn b5042
Phone Number Vi7) 6 FP
4.SV 6:i27
What. do you ,corisidet to In the 111.2jOr plositiing and development issues confrooting the City of
Lake no?
I-Iow and when t o expand t he pr oper use of t he oval I abl e unuse
2. What do you. see as the role and function of the Planning Cortiniission?
To meet the needs of the publ i c and help decide the various issues
as necess ary .
3, What eipezientt and 411n016.2.ticyris do you have. that you feel will cone to the PhnxMg
'Conuaission's work, met which will embte you to provide t •servicein tegard?
Old enough to know and under s t and No one can serve the needs and
requests of everyone
4. How anuch time do you have, or are you wilting to devote to Planning Cororoission activities?
WHAT every publ i c vol unt eer s houl d be able to under st and, al I the
t i me that is necessary
5. tproptzty .or4e,o)elopriveza interest, eithe;r d4ect
L E. r es i dent for 18 yrs. Ass oci ated i n area 35 yrs Owned land i n
Lake Elmo 33 yrs
Pletee complete and return to rite City °Mee
u have within Lake Etalo?
SeP:20: 2004 2:09PM
No5974
City ake Elmo
3800 Laverne Avenue North
Lake Elmo, Minnesota 55042
651.777,5510 Fax 777.9615
RECEIVED ...
2
901,1111F
LAKE
AkELMO
APPLICATION FOR PLANNING COMMISSION APPOINTMENTS
1. What do you c
Lake Elmo?
2. Wbat cia you see as the role and function of the lila
fi--..reot.t&A) X.Pit Her- 5i/0 t -1tree,
development issues confronting the City of
3. 'What etprince and qualifications doyoz have that you feel will contribute to the Planning
Coennussion'g work and which will ena rovide %service in this reaard?
-2- govr oeVaAaeorExv)4- z, • CO0 49 efle•420 e'O-Z 1 *IRS/ 0 E•Vrik-)
'406 apere-- 0.74, k 4S AO ant/4_ ea 4./...rnifea, eX/4/0"4 /,‘ 4e/4. 8.
5s-774.7:r.- ,e,,,is. ,a-v 41i,41, At,ve.) 4,,t- ,
4-lec' Recx/ -tbc,e4( A A'w5orreit. o lc 72544)./i/ i eiler pi.j14,01///v/ ,41067-4v,S1
4. How much time do you have, ot are you willing to devote to Planning Commission activities?
Wel(A-7- 4/0X- ./`-7 .710,re-e_c
5. What ptopetty or development interest, either direct or indirect, do you have within Lake Elmo?
4/44' Z- ire/ a tY0/104pliVe/t( 71 ->`-'fil 7-Ez as' '77 2- AMP
‘--6dae #k• f2c, th- 141§.7-
46/1/7Ly 4.04tlee- 6--ed cre_ecs.rra, #1/ P44-7-
5are-J t4 a- fg-r- Ca- deNee iv+
0
City of Lake Elmo
3800 'Laverne Avenue North
Lake Elmo, Minnesota 55042
651.777.5510 Fax 777.9615
RECEIVED
FEB 0 t 2195
" OW it
LAK E
EL M 0
APPLICATION FOR PLANNING COMMISSION APPOINTMENTS
Date:
Name IXEDP/M-4 LYZEI\I
Address CI WI A 12--r---01\1
Phone_ Numb Wyi-58 —5z1SQ J +3(.1) LW, (D
1, What do you consider to be the major planning and development issues confronting the City of
Lake Elmo?
ATTAN YnN-T
2, What do you see as the role and function of the Planning Commission?
3. What experience and qualifications do you have that you feel will contribute to the Planning
Commission's work and which will enable you to provide a service in this regard?
I
4. How much time do you have, or are you willing to devote to Planning Commission activities?
I)
5. What property or development interest, either direct or indirect, do you have within Lake Elrno?
Please complete and return to -the City Office
APPLICATION FOR
PLANNING COMMISSION APPOINTMENT
(QUESTIONNAIRE ATTACHMENT)
1.) The future development of Lake Elmo has been decided upon, in concept,
with the recent agreement reached with the Met Council. The challenge now is to
translate that intention into a feasible and acceptable Comprehensive Plan that
meets the negotiated requirements, but primarily satisfies and preserves the
existing character of the City. The present legacy of Lake Elmo is one of a
pioneer. It has not relied on formulas and regional pressures to define it's
community standards, and The City must continue to be unique and innovative
as we move ahead. We have seen, in neighboring communities, what results
when development occurs based on economic formulas, with little regard for the
residents who call it "home". The City must continue to be a leader and inventor
when it comes to developing new methods of blending growth and residential
spaces in a fashion that serves everyone's needs, and keeps Lake Elmo a
desirable place to live and work.
2.) The role and function of the Planning Commission is to investigate and
generate recommendations relating to growth and development within The City.
It is important that the Planning Commission receive input from the public, the
City staff, the City attorney, and other outside sources. The Planning
Commission should listen, debate, educate, and ultimately develop conclusions
that are presented to the City Council for action.
3.) I have been a resident,of Lake Elmo for the past 7 years. In the 1980's I was
employed with TKDA & Associates, and worked frequently with Larry Bohrer on
projects in Lake Elmo. I was very involved with the septic system upgrades in the
Old Village, and became familiar with The City's development philosophy. I was
also involved with development projects in other surrounding communities.
Recently I have been the chair of the Community Improvements Commission,
and have worked to upgrade the gas lines within the Cimarron neighborhood. I
am committed to remaining a resident of Lake Elmo, and wish to participate in
the planning process mandated by the Met Council.
4.) It is my understanding that the Commission meets bi-monthly. I would be
able to attend those meetings regularly. My time outside those scheduled
meetings would be limited to 5 to 10 hours per month.
5.) I own my home in the Cimarron neighborhood, and rent the land that it
occupies. My mother also owns a home in Cimarron, and similarly rents the
space.
Submitted by Deborah Lyzenga
01/24/2005 14:42 FAX 612 673 6733 cHURCHILL CAPITA
City of Lake Elmo
3800 Laverne Avenue North
Lake Elmo, Minnesota 55042
651.777.5510 Fax 777.9615
Z002 (o.
RECEIVES
,JAN 2 4 2017b
APPLICATION FOR PLANNING COMMISSION APPOINTMENTS
Date: 1/24(05
Name: Tam Kreimer
Address: 772 Jewel Avenue North
Phone Number; W) 612-673-6631 51-501-9794 CELL) 651-238-6738
L What do you consider to be the major planning and development issues confronting the
City of Lake Elmo?
The Metropolitan Council ruling and how Lake Elmo chooses to implement the required changes
are the major planning and development issues in the city. If Lake Elrno is forced to develop,
let's do it right and do everything we can to retain the character of the city.
2. What do you see as the role and function of the Planning Commission?
The Planning Commission should represent various areas of the city and various interests and
have the ability to assist in making decisions in the best interest of the city and its residents.
3. What experience and qualifications do you have that you feel will contribute to the
Planning Commission's work and which will enable you to provide a service in this
regard?
I grew up in Stillwater and have lived in Lake Elmo for over 6 years. My wife and I chose Lake
Elmo because of the character of the city and because we thought this would be a wonderful
place to raise our family. While my educational background is accounting and finance, I've
always been very interested in land development, housing, and city planning. I haven't missed a
"Parade of Homes" since I starting driving all over the Twin. Claes to see homes and
developments in 1986.
4. How much time do you have, or are you willing to devote to Planning Commission
activities?
1 arn willing to devote the time necessary to get the job done. I have active children and a
demanding wife and job, but 1 think most people have these or similar issues. My wife supports
my decision to apply for the Commission.
5. What property or development interest, either direct or indirect, do you have within
Lake Elmo?
1 am a homeowner in Stonegate.
Pit-ese complete and return to the City Office
City of Lake Elmo
3800 Laverne Avenue North
Lake Elmo, Minnesota 55042
651.777.5510 Fax 777.9615
Date: 1 /.21/ 03
Narne
Address
Phone Number W)
APPLICATION FOR PLANNING COMMISSION APPOINTMENTSRECIEIVEnnipm
41.1VJ
rre ,
4. Ho
f- oI-A 11r 5, r-e,a, ) i' n 7 Hi e-
+1) do r -e ar
5. What property or development interest,either direct o • indirect, do you have witbin Lak&Einio
/ q J1 6,0
1
-7 (
or ()tie -
CITY OF LAKE ELMO
City of
. What do you consider to be the major planning nd development issues co
Lake Elmo? 5-e-u..7 e, r ' " PI 1 "I'D b -e. Lt 6'
a.... K
.awtki 4...9.5 0 v.
role and function of the Planning Commission?
5 e- -fr. I) e c-) -Foi 6„,OUV1C Oh -Z-On r
3. What experience and qualifications do you have that you feel will contribute to the Planning
Commission's work and which will enable you to provide a service in this regard?
I; u a 5 t51,1 —he- ect- r-K 5 0, 0 KY 7 Yr, ; 5 5 Oil ..or 1 t- 4 5
re el t 4 1j
a .e.„/v ii . 1-11 e, .T. date... — 4c14<t-- EIPAZ) 1-k
uch time do You have, or are you willing to devote to Planning Commission activities?
+ o w n cc/ n
asv;
C. re.,
Please complete and ream to the City Office
RECEiVE0
3 Mit
City of Lake Elmo
3800 Laverne Avenue North
Lake Elmo, Minnesota 55042
651.777.5510 Fax 777.9615
APPLICATION FOR PLANNING COMMISSION APPOINTMENTS
Date: / 1 /
Name Tvdie F(rfe±
Address +577 Ave. NJ
Phone Number W) Dk,F5-07 H) lo5C-113q-
What do you consider to be the major planning and development issues confronting the, City of
Lake Elaw? "irtcra.i " o4 ifkke, E.( vim) LO\-i le ai +he ..urnie.
eyoupiA5 Keep fn u.{) tp(RA +lyres deveop OLU area,
Q. Loot *la* cAlves. reside struIce,s ,fac, ,fie5 +he
ocknt cvocv Aboa- oat a) -hi buieo a- Leiter Cat
2. What do you see as the role and function of the Planning Commission?
ToIcy IL in defazQ i ss u es ahwic Laea elm. rriaXe-
rcovvoiencia.-49-ns -Fp Cturic-W reled +Vox- (sGues
3. What experience and qualifications do you have that you feel will contribute to the Planning
Commission's work and which will enable you to provide a service in this regard?
bitsiAeSS - ctriet heuie- ben 'For 13 Years • can a- CP
AJ
W1 Goel( ecCuceLicd. r am a Vert.j per5tin hez,ve„, aloi See
patere, .issue_s , a, a +0 vve. rvvl opole-o m!,f
cen5reder a.) I v‘'e,WpoilniL Dr i'ssuestanitie, bf POS5Ible SOILA:fi'ed for ail '}nikived,
4. How much time do you have, or are you willing to devote to Planning Commission activities?
Frorn rnt6 tkneleArs-6.4.d-inai q-krd. are, 2 Tee-H.1%4J per rooyttA caid af -Hiem
s c.,1(50 some- .fime i'pobiued s-fradyiN is.ctes 9.a+660.(13 /410'1'M-1i-971
4N-f CD( 11 ke, tense •E'47111S s nicA scheckae. LA), I etuald
Iz devo-4e. -fifre PlaornAci 0_6mm'
5. What property or development interest, either direct or indirect, do you have within Lake Elmo?
haxe,& home- .iro
Please complete and return to the City Office
Lake Elmo
City Council
March 1, 2005
Agenda Section: CITY ENGINEER'S REPORT
Agenda Item: Approve Plans and Authorize Advertisement for Bids
Water Systems Interconnect Phase 11
B.
Background Information for March 1, 2005:
The City Engineer reported that plans and specs are complete on the second phase of the Water Systems
interconnect Project. This phase of the project installs 12-inch water main from the intersection of Tapestry
Drive and 45`h Street, to the existing public works building. This project vill allow us to disconnect from
the City of Oakdale's water system in the Lake Jane area.
The v Engineer recommends Council approval of the plans and authorizing the advertisement for bids.
Action Items:
Motion: . Second to adopt Resolution No. 2005-
020, A Resolution Approving Plans and Authorize Advertisement
for Bids, Water Systems Interconnect Phase TI, as verified by the
City Engineer in his memo dated February 24, 2005.
Attachments:,
Letter from Tom Prew dated February 24. 2005
Resolution 2005-020
Person responsible:
T.Prew
TKDA
ENGINEERS • ARCHITECTS • PLANNEit El C E: I v E
February 24, 2005
Honorable Mayor and City Council
City of Lake Elmo, Minnesota
Re: Approve Plans and Authorize Advertisement for Bids
Water Systems Interconnect Phase II
City of Lake Elmo, Minnesota
TKDA Commission No. 13186.000.003
Dear Mayor and City Council:
1500 Piper Jaffray Plaza
444 Cedar Street
Saint Paul, MN 55101-2140
(651) 292-4400
(651) 292-0083 Fax
www.tkda.com
Plans and Specifications are complete on the second phase of the Water Systems Interconnect
Project. This phase of the project installs 12-inch watermain from the intersection of Tapestry
Drive and 45th Street, to the existing public works building.
This project will allow us to disconnect from the City of Oakdale's water system in the Lake
Jane area.
We have specified that this project be performed by directional drilling. The boulevard area on
Lake Jane Trail is very congested, and this method will allow us to construct the pipe without
replacing all of Lake Jane Trail. We will be installing services along the watermain to provide
water to adjoining properties when they are ready to connect to it.
City Council Action Requested
Approve the enclosed Resolution approving the Plans and authorizing the Advertisement for,
Bids.
Sincerely,
Thomas Prew, P. E.
City Engineer
TDP:arw
Enclosure
An Employee Owned Company Promoting Affirmative Action and Equal Opportunity
CITY OF LAKE ELMO
WASHINGTON COUNTY, MINNESOTA
RESOLUTION NO. 2005-020
A RESOLUTION APPROVING PLANS AND SPECIFICATIONS AND
ORDERING ADVERTISMENT FOR BIDS
WATER SYSTEMS INTERCONNECT PHASE II
WHEREAS, the City Engineer has prepared plans and specifications for the Water
Systems Interconnect Phase II and has presented such plans and specifications to the
Council for approval.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF LAKE
ELMO, MINNESOTA:
Such plans and specifications, a copy of which is attached hereto and made a part
hereof, are hereby approved.
2. Th City Clerk shall prepare and cause to be inserted in the official paper and in the
Construction Bulletin an advertisement for bids upon the making of such
improvement under such approved plans and specifications. The advertisement
shall be published for two weeks, shall specify the work to be done, shall state that
bids will be opened and considered by the Council at the March Z5, 2005 Council
meeting, in the Council chambers of the City Hall, and that no bids will be
considered unless sealed and filed with the clerk and accompanied by a cash
deposit, cashier's check, bid bond, or certified check payable to the clerk for 5% of
the amount of such bid.
ADOPTED BY THE COUNCIL this 1st day of March, 2005.
Dean A. Johnston, Mayor
ATTEST:
Martin J. Rafferty, City Administrator
Lake Elmo
City Council
March 1, 2005
Agenda Section: Planning, Land Use & Zoning No. 9A
Agenda Item: Septic and Shoreland Setback Variance — 8784 Lake Jane Trail (Gibson)
Bac
ound Information for March 1, 2005:
On February 28 the Planning Commission will conduct a Public Hearing and adopt a recommendation
regarding this application to construct a new septic drainfield that encroaches a total of 75 square &feet into
the OHW setback from Lake Jane. Since there is no other on -site option, the encroachment is minimal, and
both the City Engineer and DNR reconunend approval we believe the Commission will conclude its work
on the application on February 28. We are sending the matter along to the Council in anticipation of that
Commission action so that this relatively minor issue can be concluded expeditiously.
Action items:
Motion to adopt the appropriate Resolution. (a draft consistent
with the February 28 Planning Commission recommendation will
be provided on March 1)
Attachments:
1. Planning Staff Report to Commission
2. City Engineers Memo
3. DNR Letter
4. Applicant's Documentation
Person responsible:
City Planner
Time Allocated:
LAKE ELMO PLANNING COMMISSION
STAFF REPORT
Date: February 25, 2005 for the meeting of February 28, 2005
Applicant: Robert Gibson
Location: 8784 Lake Jane Trail
Requested Action: Chapter 700 Variance for Septic Setback from OHW
Land Use Plan Guiding: SRD
Existing Zoning: R-1
Site History and Existing Conditions:
The 1.5 acre lot was platted well before present zoning, septic and Shoreland standards were in
place by the City. A 1350 square foot home and septic system were constructed on the lot in 1973.
City records reveal no Planning or Building applications/permits of significance to this request
since that time.
Discussion and Analysis:
The applicant has determined that a new septic drainfield is required for the property. The septic
designed has reviewed the lot and has determined that only one location is available on the lot for
a drainfield of the size required. This location places the new drainfield 65 feet from the OHW of
Lake Jane at the single closest point. Since the drainfield is proposed at an oblique a angle to the
OHW, only 75 square feet of the drainfield area will actually encroach on the OHW setback.
The City Engineer and DNR have both reviewed this application and recommend approval due to
the minimal degree of OHW encroachment proposed, and the lack of any alternative drainfield
sites on the lot.
Findings and Recommendations:
Variances to the standards of Chapter 700 (the City's septic ordinance) and Chapter 300
(Shoreland) are both processed in the same manner as zoning variances, with specified Findings
required by the Code.
In the terms of those Code -prescribed Findings Staff suggests the following regarding this
application:
1. The property can not be put to reasonable use without the granting of the variance
requested. The physical constraints of the lot mandate the proposed site as the only
location possible for a new drainfield,
2. The variance requested does result from physical circumstances found on this property.
While the physical constraints are not specifically unique to this property, the fact that
the lot design predates present City septic and Shoreland standards is a significant factor
supporting approval of the requested variance.
3. Granting of the variance will not change the essential character of the neighborhood.
Planning Commission Actions Requested:
Staff suggests that the foregoing Findings support a recommendation for approval of the requested
variance, based on those Findings.
Charles E. Dillerud, City Planner
Attachments:
1. Location Map
2. City Engineer's memo
DNR Comments
4. Applicant's Documentation
01.14.11......1..E.E111411/1
exeL am woloatmaaaai
Location Map
+Ow
loos
LAKE JANE
AWN MN /UV OF WATERS
MOM CTEDIMMINEEA 02.traP
3
4 4r.
4r, !
NC. 1
1
I
0601
,38
IMO
it 3
888
14,
it
R2ZW 321W P1OW
Vicinity Map
0 271
Scale in Feet
This develop Is tne relied of a compilation
and repro &igloo or land remain; they
appear in eselout YVaoldricion Gourley Oka.,
dreolna should be used lor refer BrILB
porpooris only, Wasildndtan county Is not
responsible ice any Inaccuracies.
Seamed WashInglon County Surveyor's Mica,
Plana (651) 430.5875
Pero,' data bssed on AS448 infiinnation
CITY OF EAST OAKDALE
570 KALMIA
LAKE ELMO MN 55042
SCHMIDT,JEAN M
8766 LAKE JANE TRL N
LAKE ELMO MN 55042
GIBSON,ROBERT F & DELORES M
8784 LAKE JANE TRL N
LAKE ELMO MN 55042
/:7 ✓ /i'1/7l//t'// 2OE, 4/
3555 Vl/4lpai /V'
V4DN4/a ,9T5, /v1> .a, //d
GOULD,ROBERT L & KATHLEEN E
8802 LAKE JANE TRL N
LAKE ELMO MN 55042
TKDA
ENGINEERS • ARCHiTCTS PLANNERS
MEMORANDUM
RECEIVED
Vtd 1 3 2005
1500 Piper Jaffray Plaza
444 Cedar Street
Saint Paul, MN 55101-2140
(651) 292-4400
(651) 292-0083 Fax
www,tkda.com
To: Chuck Dillerud Reference: 8784 Lake Jane Trail
Copies To: Septic System Variance Request
City of Lake Elmo, Minnesota
Comm. No. 13267.001
From: Thomas Prew, P. Routing:
Date: January 14, 2005
I have reviewed the revised variance request for the Gibson property at 8784 Lake Jane Trail and have the
following comments.
Lake Jane is a recreational development lake. The setback for a septic system is 75 feet from the OHW.
The applicant has submitted a revised design dated January 13, 2005. They have moved the location of the
mound such that the required variance is only about 75 square feet. This design would require the removal
of 3 very mature trees. This design appears the be the best design for this lot.
Due to the minimal nature of the variance request, and the lack of other available options on this lot, I
recommend approval of the variance request.
An Employee Owned Company Promoting Affirmative Action and Equal Opportunity
Kimberly Schaffel
From: Travis Germundson [travis,germundson@dnr.state.mn.us]
Sent: Friday, February 11, 2005 11:38 AM
To: Kimberly Schaffel
Subject: Preliminary Plat of Deer Glen
Kim,
I looked through the materials you sent and determined that the Parcels are not located
within a designated floodplain or shoreland area.
Therefore, I we have no administrative oversight nor comments to offer on this particular
plat.
If you need or would like the full size plats back I can drop them off.
.080/17* OA/
76'/ /.94-t's 7io/4.4#
4Adr
S444.1 I .4470irt
,,Nor SoFwe'Y
'VaFt-IFY Lor L41,14.5
t‘•-•
R.r
i?Oi.Ser,D44 LWP
4.4770,4I
2 2.oeS
RECEIVED
FE-31 7
N
TRet...s
At.4 1-/Aox re
00 Remopip
/)PPe tterf 7/PA/J
Ajetlkiwr we a
Aot ,
#94
2- ploVc.1411e [.7
A t...qm. Tk-e-ft
Af*tki4j
Pia ee,occt .Gt6uot 0(.1-4‘
Av tEt tieetle A
OA • u 41*
WAY
s..z
kl/t) ril.A 1•)o
UJ CLL.
1
41.•
X. 9 24
9-24,,ca
le:No YeAR.
ao
5c9
„
(0 °
tve4,1_,
ZliscatiAkezrg PiPt
Pt./44- kiC3L42fl4.ec.e›..,
r 4/Fr ro /PM oss T-
y Prio Ne.
TA).414. rVIR N 0 44 rip &'J't
—
9
92-;1.
ORPINfiRY 'Hat?,
E-NQ1 MAN< —
71-/E f/k2u,i-Jrz. .5 u4
4I•4 Srliktf-a. ZeFoR.5 Yewu
echtuar >40.2,1z. 1).0 (rior.1
Lake Elmo
city Council
March 1, 2005
Agenda Section: Planning, Land Use & Zoning
AgpdaItem: Comprehensive Plan Modifications - Policy
Background Information for March 1, 2005:
No. 9B
The Planning Commission will be (hopefully) completing their initial work on the Planning Policy
modifications to the Comprehensive Plan that are responsive to the Met Council Memo of Understanding at
its February 28 meeting. If so, we remain "on schedule". In anticipation of success on Monday, I have
attached the latest draft, along with my cover memo to the Commission explaining the changes from the
February 23 draft — minimal in number.
The Commission will address any additional guidance the Council may provide at its (the Commission's)
March 7 Workshop, and then begin work on the Land Use Plan modifications responsive to the Policy.
Action items:
Council guidance to the staff and Planning Commission regarding
modifications to the Planning Policy section of the Comprehensive
Plan.
Attachments: Time Allocated:
1, Cover memo to Commission and February 25 Draft Policy
MEMO
(February 25, 2005 for the Meeting of February 28, 2005)
To: Lake Elmo Planning Commission
From: Chuck
Subject: Comprehensive Plan — Policy Draft
We have attempted a quick turn from your Wednesday Workshop. I have made some
modifications to both the Planning Policy Draft based entirely on Kim's notes from the
Workshop. Since our Word "tracking" system was giving me trouble, I have had to resort
to an alternative draft mark-up process. The deleted text is just that — deleted, without the
marginal note. You will have to refer back to the earlier draft to see what is gone. New
text is bold, underlined, and italics (all three). As of 12:20 PM on Friday I have not
heard from any commissioners regarding other modifications.
Our calendar calls for presenting the Corrnnission-proposed draft of modified Planning
Policy foe City Council review and comment at the March 1 Council meeting. I am
hoping that the Commission agrees that we are far enough along on February 28 to do so.
If so, I will deliver the attached with any other modifications the Commission may wish
to the Council on Marchl .
CITY-WIDE PLANNING POLICY
Due to its proximity to Downtown St. Paul and desirable physical land characteristics, future
residential and commercial development in Lake Elmo is inevitable. Unless the pressure for
development is recognized, the ability of the City to accommodate future growth, while preserving
the rural character and natural environment, may be forfeited. The following general planning and
development policies are not intended to preclude growth and development within Lake Elmo, but
to limit and guide that growth and development in a manner that will allow reasonable growth to take
place, while preserving the character and features of Lake Elmo that make the City a unique and
desirable cotrununity:
I. Develop land use and infrastructure plans to accommodate household and
population forecasts of the 2030 Regional Development Framework.
2. Encourage the majority of the new households created in areas north of 10th
Street North, and outside of the Old Village Planning to be efficiently
developed in a rural context in the form of Open Space Development cluster
neighborhoods.
3. . Guide new community growth in keeping with the geographic assignments
and decennial household, population, and employment targets established by
the Memorandum of Agreement entered into by the City and the Metropolitan
Council in January , 2005.
4. Tirnit Metropolitan Urban Service Area (MUSA) expansion to the area that can
be served from the Regional Wastewater Interceptors specified; in the wastewater
volumes specified by the aforementioned Memorandum of Agreetnent., and staged
consistent with a City adopted development Staging Plan .
5. Adopt a MUSA expansion development staging plan/schedule that will comply
with at least the miniinum number of Regional Wastewater Residential
Equivalent Connections (REC's) specified for Lake Elmo by the 2030 Regional
Water Resources Plan, but that will also litnit total annual City household and
employment growth to a use .mix and scale that remains sustainable in the
context of providing municipal services/infrastructure and local government
fiscal responsibility.
Agricultural Preservation
In keeping with the general policies enumerated above, existing operating agricultural uses and
qualifying alternative uses that preserve the open space within the community shall be supported.
These uses shall be encouraged to continue operations, and to retain large land holdings that
contribute to operating efficiency.
In keeping with the general policies enumerated above, the City shall affirmatively establish and
pursue specific strategies and seek resources to assist existing agricultural uses in remaining a viable
alternative to urbanization for landowners, consistent with the concept of "a right to farm".
The provision of municipal infrastructure and services to areas of the City where operating
agriculture exists shall not be in a manner that results in an economic or operational disincentive to
continue agricultural use of the land.
Residential Development
All residential units should be designed, sited, and constructed to conserve energy in lighting, cooling,
and heating processes,
Allowable Residential Densities by land use classification are as follows:
RAD (Rural Agricultural/Diversified) — 1 Unit in 40 gross acres for areas zoned AG
(1999 Zoning District); and 4 Dwelling Units in 40 gross acres in areas zoned RR
(1999 Zoning District); or ?? Units per 40 gross acres in Open Space Development
projects only, regardless of zoning.
F U (Future Urbanized Development - Sewered) — 1 dwelling unit in gross acres
in areas designated on the Land Use Plan for future urbanization and wastewater
treatment by the Regional Wastewater System (MUSA). The FUDS classification
shall be limited to areas south of 10th Street and areas surrounding the Old Village in
accordance with the Old Village Plan,
NC (Neighborhood Conservation)
Density shall be limited to a maximum of 1 dwelling unit per acre and only where it
is demonstrated that a wastewater treatment strategy is available that is suitable to
protect the public health and environment, as determined by the City.
RE (Rural Estate) — 6 dwelling units per 20 gross acres, with no individual dwelling
unit on less than 2 1/2 acres. This classification relates to 1999 zoning district RE.
Areas of the City eligible for this classification shall be limited to those north of 10th
Street North excluding the areas within the Old Village Plan.
URD (Urban Residential) — Average Density of3,0 dwelling units per gross acre.
This classification is intended for the Old Village as designated by the Old Village
Plan and areas of the City south of 10th Street North serviced by, or planned for
service by, publicly owned central water and sewer. Eligible areas of the City shall
not be classified URD until the City Council has specifically approved the provision
of Regional wastewater service and public water supply to the area within 180 days
of the URD classification date.
The primary style of residential dwelling unit within. RAD, RE and NR land use classifications shall
be single family detached. In recognition of the City's policies regarding future housing resources
reflecting a balance of affordability and housing type, Life Cycle Housing and housing designed for
residents with physical challenges is specifically encouraged in URD classified areas and the Old
Village.
Residential neighborhood design shall result in developments with quality architectural detailing,
landscaping and street design that fosters the pedestrian, slows traffic, and provides adequate access
for roadway maintenance and emergency vehicles.
The Land Use Plan shall be based on natural features such as;
a. Soils, wetlands, woodlands, and severe slopes
b. Urbanization limitation strategies
2
c. Existing agriculture
d. Other factors
Within the designated RAD classifications, residential land development shall be prinaarily, as
opposed to exclusively, responsive the Open Space Development (OP) Section of the Zoning
Ordinance; and preserve 50% of the gross land area within such developments by means of
permanent open space conservation easements, and clustered dwelling unit groupings.
The Open Space Preservation District section of the Zoning Ordinance shall specify design
standards for residential development within the RAD classification.
Residential development shall be responsive to the Goals prescribed by the Housing Element of the
Lake Elmo Comprehensive Plan,
Non -Residential Development
Consumer retail land use will be planned and/or approved only to the extent that existing consumer
retail use within the City and consumer retail use in adjacent communities are clearly demonstrated to
not adequately provide retail goods and services for the residents of Lake Elmo.
While Lake Elrno is bordered on the north and south by Principal Arterial roadways, the City does
not agree with the concept that the traffic counts represented by those roadways is the basis for
non-residential land use at interchanges/intersections or in a service road "strip" arrangement. Non-
residential land use within the City should be local need driven, not traffic count driven.
Non-residential land use shall be focused in two geographic areas of the City: the 1-94 Corridor
(Principally Office/Research); and, as in -fill and renovation, in the Old Village. Limitation of non-
residential land use to those geographic areas will enhance the City policy of retaining the rural
character of the community, -while, in concert with existing and planned non-residential uses in
adjacent communities and existing non-residential within the City, the residents of the City will enjoy
reasonable access to employment opportunities, and required goods/services.
Consistent with Old Village policy, new linear non-residential development along State Highway 5
should not be allowed; and, the City should encourage existing non-residential uses along State
Highway 5 to adhere to Old Village policy regarding expansion and renovations.
All non-residential development shall be required to marntain high quality standards of site, structure
and landscape design. Uses within the Old Village shall comply with the design standards and
regulations adopted for that geographic area.
Alterations to the natural environment; or site layout, signage, lighting or structure architecture in
excess of Code requirements, to enhance the visibility of a non-residential use to vehicular traffic
shall be considered substantial evidence that the use is intended to serve other than City residents.
Non-residential uses in the 1-94 corridor shall be principally office/research in character. The term
office/research shall preclude uses that are primarily engaged in manufacturing, assembly,
warehousing, retail sales/service and hospitality except to the extent that such precluded uses directly
and demonstrably serve the primary office/research uses of the area, within Lake Elmo. Also
precluded is any use that introduces truck traffic except as such truck traffic is clearly incidental to a
specific office/research use.
Housing
It shall be the Policy of the City, by adopted plans, programs and development regulations to provide
for a variety of housing types for all people of all stages of the life cycle. It should also be the Policy
of the City to encourage retention and development of housing affordable to a broad range of
incomes while maintaining a fiscally responsible ratio of municipal services provided to real estate tax
revenue to support those municipal services, Examples of adherence to these housing policies
include:
1. Preservation the moderate cost housing alternatives represented by the Cimarron
Manufactured Housing neighborhood.
2. Affirmative City actions to address neighborhood design responsive to the unique
requirements of persons with physical disabilities, such as walkable access to public and
private goods, services and amenities.
3. Support for senior and age restricted housing initiatives within the Regional Sewered areas of
the Old Village and/or South of 10th Street North that demonstrate high standards of
design, materials, and resident amenities. Ease of resident access to goods and services
within the context the Non-residential Development Policies of this Plan should be an
important locational determinant in recognition of the reduced mobility of senior and age -
restricted residents.
4. Support of expanded opportunity for development of new housing resources affordable to
families of moderate income within the areas of the City planned for service by Regional
Wastewater Treatment. This may included housing density bonuses. but City financial
subsidy in support of those housing opportunities is not implied by this Policy.
It is equally important for the City to actively pursue retention of well -maintained existing housing
and neighborhoods. Adoption of and systematic enforcement of City codes that address housing and
neighborhood maintenance, together with timely rehabilitation and improvements to municipal
infrastructure will be important components of addressing this policy.
By zoning and other City codes the City should encourage housing development that respects the
natural environment of the community while striving to accommodate the need for a variety of
housing types and costs.
The City will support the availability of a full range of services and facilities for its residents in
proportion to the intensity of development within a geographic area of the City.
Environmental Protection
Encourage farmers to work closely with the Soil and Water Conservation District and utilize sound
soil erosion prevention practices, such as contour plowing, strip cropping, minimum tillage,
shelterbelts, and other similar practices.
Regulate the location and design of non -farm animal confinement areas to minimize pollution and
nuisance problems.
Require all residential developments to conform to the limitations presented by natural features,
including soils, drainage patterns, topography, and woodlands.
Require subdivisions to be designed to utilize the natural drainage system, including, but not limited
to ponds, wetlands and watercourses and groundwater recharge.
Adopt and enforce strict regulations regarding the design, location, and maintenance of on -site
sewage treattnent systems based on compliance with PCA Rule 7080.
4
Restrict development from areas containing unique or endangered forms of vegetation and/or
wildlife.
Strictly regulate development in floodplain, wetland and Shoreland areas in compliance with State
and Federal mandates.
Municipal Services
Provision of municipal services will remain proportionate to the intensity of development within
geographic areas of the City. Provision of municipal services will not be in a manner that drives
intensive development, but rather responsive to the intensity of development specified by the
Comprehensive Plan. Examples of actions that are responsive to this Policy include:
1, Design and acquire infrastructure and other City capital purchases to minimize future
operations and maintenance expense, particularly full time City staff,
2. Maximize the utilization of citizen volunteers where appropriate.
3. Maximize the benefits of technology in City operations and municipal services.
4. Emphasize preventative measures to avoid the occurrence of problems.
Transportation
The focus of motorized transportation planning and resulting infrastructure should be trips with
origins and/or destinations within the City, servicing Lake Elmo residents.
Vehicular trips not originating and/or ending within Lake Elmo should not be encouraged through
planning or infrastructure improvements by local, County, State or Federal Agencies,
Interstate 94 and State Highway 36 shall remain the primary vehicular corridors for traffic with
origins and/or destinations not in Lake Elmo.
The location of State Highway 5 in the center of the Old Village, coupled with the present and
forecasted volume of traffic on that roadway, presents numerous safety and urban design issues
which will require mitigation if the Old Village is to best serve as the center piece of the community.
The City, with the cooperation and assistance of the Minnesota Department of Transportation and
Washington County should continue to explore measures to reduce or eliminate the issues that are
caused bvState Highway 5 in the center of the Old Village.
The City shall investigate street segments that may benefit from traffic calming.
The City should support retention of the Expressway cross section of State Highway 36, with
signalization of key at -grade intersections. Improvement of the Highway 36 corridor to Parkway
standards should also be encouraged and supported.
The City should encourage, support and become advocates of public transit service to the City,
particularly commuter rail service to the St. Croix Valley area via the existing rail corridor, This
should include planning for one or more a transit hubs to serve HOV, bus and commuter rail
options at appropriate geographic locations.
The City should design, construct and maintain the minimum acceptable grid system of collector
streets. Where State Aid funds are expended for such construction, State Aid design standards should
be incorporated. Where State Aid funds are not used the collector streets should be constructed to a
paved section designed to minimize impervious surfacing and piped storm water conveyance.
While not located in Lake Elmo, the Lake Elmo Airport will continue to be a transportation facility
that will impact the City. The City should continue to vigorously oppose all initiatives to broaden the
operating capabilities of the Lake Elmo airport from the existing recreational aviation to corporate or
commercial aviation, by runway lengthening or other related improvements.
City policy and plans should recognize Lake Elmo Airport safety and noise zones based on
recreational aviation only.
1-94 Freeway Corridor Plannitie. Policy
The I-94 Corridor, extending from Inwood Avenue on the west to Manning Avenue on the east, and
generally defined at extending north to 10th Street North wiU, other than the limited -scale Old
Village, be the focal point of urbanized development within the City served by Regional Wastewater
Treatment through community build -out by 2030. Planning Policy specific to this geographic area
includes:
1. Preservation of the present Rural Character and living environment of the existing residential
neighborhoods south of the 10th Street — Stonegate, The Forest, and Midland Meadows.
Urban intensity development of land adjoining these neighborhoods must be so designed as
to preclude externalities of that urban development (such as through traffic, exterior lighting,
noise, and trespass) from negatively impacting the existing residential neighborhoods either
physically or financially. Any public utility extensions (water and sewer) to lands adjoining
these neighborhoods should not result in the City ordering of public water and sewer
extensions into these existing neighborhoods unless specifically requested to by 2/3 (two
thirds) majority of the homeowners.
2 The costs for extensions of Public water and sewer service shall be born exclusively
by those nmnetty owners that. as determined by the City. benefit from said
extensions and service.
All development/redevelopment shall be subject to a Development Staging Plan that either
regulates development geographically, or in terms of the number of Residential Equivalent
(REC) units permitted to be constructed annually — or both. The Staging Plan shall become
an Official element of the City Comprehensive Plan. All areas not served by Regional
Wastewater shall be planned and zoned at a density of 1 dwelling unit per 20 acres of land
until such point in time as the Staging Plan specifies development at a higher density can
take place.
4. Non-residential uses shall be limited to those specified by the Non-residential Use section of
this Planning Policy. The overall scale of non-residential use should be limited to
approximately 20% of the net developable land south of 10th Street (including presently
vacant land within Eagle Point Business Park, and Highpointe Health Campus). Non-
residential development should result in employment averaging 40 employees per acre
developed, and such employment should primarily be of a professional, technical and
management type.
5. Residential development shall be served by Regional wastewater treatment and shall be at a
average gross density of 3 dwelling units per acre, and may be of higher density depending
on the carrying capacity of the land and infrastructure. The incorporation of multiple
housing styles, types, and levels of affordability shall be encouraged, while avoiding
6
geographic concentrations of lower cost housing, housing styles and housing types.
Residential development may include senior and/or age -restricted housing as a self-
contained neighborhood that could include amenities, multiple care levels and other services
designed for those residents. A total of 3,700 REC's of Regional Wastewater Service shall be
reserved for residential development subject to the Development Staging Plan.
6. The Cimarron Manufactured Housing Neighborhood is found to be an important housing
resource of the City. It important to retain that resource. Not less than 500 REC's of
Regional Wastewater Service shall be reserved for use of the Cimarron neighborhood at such
time as the existing private wastewater system is determined to be in need of replacement or
major reconstruction.
7
NOTE: THIS IS TOTALLY NEW TEXT FOR THE OLD VILLAGE POLICY SECTION.
MUCH OF THIS IS TAKEN FROM THE PREVIOUS COMP PLAN WORD-FOR-
WORD. THERE NO LONGER WOULD BE A SEPARATE SECTION OF "OLD
VILLAGE PLANNING POLICY" IN THE COMP PLAN
2/25/05
OLD VILLAGE POLICY
Due primarily to its central location characteristics such as the library, the post office, the elementary
school and City administrative offices, the Village Area offers opportunities unique to the Lake Elmo
community. These opportunities are further enhanced by the historic residential and commercial
development pattern at a scale and density of a true rural center. rather than contemporary suburban
or exurban development patterns found elsewhere in the developing fringe of the Twin Cities region.
It shall be the Planning Policy of the City to acknowledge the opportunities of the central location
and historic development patterns presented by the Old Village Area, and incorporate those unique
characteristics into policy and plans for housing preservation, rehabilitation and development that
will be of benefit to both the Village Area and the entire Lake Elmo community. Examples of actions
responsive to this Policy would include:
1. Plans for new housing development adjacent to existing Village Area housing shall reflect
the character and scale of that existing development.
2. New housing within the Village Area shall be located so as to benefit from proximity to the
central location characteristics of the Village that have been identified.
3. New housing within the Village area shall be located and designed to reduce reliance on
vehicular movement within the Village Area to access public/private goods and services,
4. All development and redevelopment within the Old Village shall be responsive to the
adopted Old Village Plan.
5. Reservation of at least 1000 REC's of Regional Wastewater treatment capacity for service to
the Old Village area. A continuing reservation of at least 500 REC units shall be maintained
to provide Regional Wastewater Service to all existing residential and non-residential
properties within the Old Village now served by JESTS. The remaining REC's shall be made
available - consistent with the city-wide Development Staging Plan — for new development
within the Old Village, only if said new development is consistent with the Old Village Plan.
The City, by its policies and plans, shall support affordable and Senior Housing to be located
within the Village Area, responsive to the foregoing location/access housing policies.
Traffic volume and speed on Stillwater Boulevard (State Highway #5), traversing through the center
of the Village, is a safety problem; detracts from the Sense of unity between the north and south
portions of the Village; negatively impacts traffic circulation within the downtown portion of the
Village; and, seriously restricts pedestrian movements within the Village.
The Village Area appears to be one of the best locations for future mass transit facilities serving
Lake Elmo such as Park/Ride, The possibility of the rail corridor becoming a mass transit resource
for the community should be considered.
Convenient and safe pedestrian/bike circulation within a community not only reduces the air quality
degradation and accident risks of the vehicular alternative, but also strengthens the s ense of
community through resident interaction. Much of the Village, particularly south of Highway 5, has
historically developed at a density and in a pattern that encourages pedestrian/bike circulation.
Examples of actions responsive to this Policy would include:
1. Land use and public facility planning for the Village area should include options for a mass
transit hub that could serve bus as well as future commuter rail service or light rail.
2. Land use planning for the east Village area should recognize and address the impact of the
existing Lake Elmo Airport, The Metropolitan Airports Commission should be affirmatively
advised of Village land use plans that will preclude certain future operations and expansion
of the airport. It shall be the policy of the City to oppose any expansion of the Lake Elmo
Airport.
3. Safe and convenient Pedestrian/Bike circulation interconnected within the Village shall be a
primary component of all Village Plans. Pedestrian/Bike corridors shall be oriented and
located to emphasize access to the Village Central Business District, parks and other areas of
the Village where Public and Private goods, services and facilities are located.
4. The City. with the cooperation and assistance of the Minnesota Department of
Transportation and Washington County should continue to explore measures to reduce
or eliminate the issues that are caused by State Highway 5 in the center of the Old
Village,
(DRAFT FEBRUARY 25, 2005)
CITY-WIDE PLANNING POLICY
Due to its proximity to Downtown St. Paul and desirable physical land characteristics, future
residential and commercial development in Lake Elmo is inevitable. Unless the pressure for
development is recognized, the ability of the City to accommodate future growth, while preserving
the rural character and natural environment, may be forfeited. The following general planning and
development policies are not intended to preclude growth and development within Lake Elmo, but
to limit and guide that growth and development in a manner that will allow reasonable growth to take
place, while preserving the character and features of Lake Elmo that make the City a unique and
desirable community.
Develop land use and infrastructure plans to accommodate household and
population forecasts of the 2030 Regional Development Framework.
2. Encourage the majority of the new households created in areas north of 10th
Street North, and outside of the Old Village Planning to be efficiently
developed in a rural context in the form of Open Space Development cluster
neighborhoods.
3. . Guide new community growth in keeping with the geographic assignments
and decennial household, population, and employment targets established by
the Memorandum of Agreement entered into by the City and the Metropolitan
Council in January , 2005.
4. Limit Metropolitan Urban Service Area (MUSA) expansion to the area that can
be served from the Regional Wastewater Interceptors specified; in the wastewater
volumes specified by the aforementioned Memorandum of Agreement., and staged
consistent with a City adopted development Staging Plan
5. Adopt a MUSA expansion development staging plan/schedule that will comply
with at least the minimum number of Regional Wastewater Residential
Equivalent Connections (REC's) specified for Lake Elmo by the 2030 Regional
Water Resources Plan, but that will also limit total annual City household and
employment growth to a use mix and scale that remains sustainable in the
context of providing municipal services/infrastructure and local government
fiscal responsibility.
Urieukural Preservation
In keeping with the general policies enumerated above, existing operating agricultural uses and
qualifying alternative uses that preserve the open space within the community shall be supported.
These uses shall be encouraged to continue operations, and to retain large land holdings that
contribute to operating efficiency.
In keeping with the general policies enumerated above, the City shall affirmatively establish and
pursue specific strategies and seek resources to assist existing agricultural uses in remaining a viable
alternative to urbanization for landowners, consistent with the concept of "a right to farm".
The provision of municipal infrastructure and services to areas of the City where operating
agriculture exists shall not be in a manner that results in an economic or operational disincentive to
continue agricultural use of the land.
Residential Development
All residential units should be designed, sited, and constructed to conserve energy in lighting, cooling,
and heating processes.
Allowable Residential Densities by land use classification are as follows:
RAD (Rural Agricultural/Diversified) — 1 Unit in 40 gross acres for areas zoned AG
(1999 Zoning District); and 4 Dwelling Units in 40 gross acres in areas zoned RR
(1999 Zoning District); or ?? Units per 40 gross acres in Open Space Development
projects only, regardless of zoning.
F U (Future Urbanized Development - Sewered) — 1 dwelling unit in 20 gross acres
in areas designated on the Land Use Plan for future urbanization and wastewater
treatment by the Regional Wastewater System (MUSA). The FUDS classification
shall be limited to areas south of 10th Street and areas surrounding the Old Village in
accordance with the Old Village Plan.
NC (Neighborhood Conservation)
Density shall be limited to a maximum of 1 dwelling unit per acre and only where it
is demonstrated that a wastewater treatment strategy is available that is suitable to
protect the public health and environment, as determined by the City.
RE (Rural Estate) — 6 dwelling units per 20 gross acres, with no individual dwelling
unit on less than 2 1/2 acres. This classification relates to 1999 zoning district RE.
Areas of the City eligible for this classification shall be limited to those north of 10th
Street North excluding the areas within the Old Village Plan.
URD (Urban Residential) Average Density of 3.0 dwelling units per gross acre,
This classification is intended for the Old Village as designated by the Old Village
Plan and areas of the City south of 10th Street North serviced by, or planned for
service by, publicly owned central water and sewer. Eligible areas of the City shall
not be dassified URD until the City Council has specifically approved the provision
of Regional wastewater service and public water supply to the area within 180 days
of the URD classification date.
The primary style of residential dwelling unit within RAD, RE and NR land use classifications shall
be single family detached. In recognition of the City's policies regarding future housing resources
reflecting a balance of affordability and housing type, Life Cycle Housing and housing designed for
residents with physical challenges is specifically encouraged in URD classified areas and the Old
Village.
Residential neighborhood design shall result in developments with quality architectural detailing,
landscaping and street design that fosters the pedestrian, slows traffic, and provides adequate access
for roadway maintenance and emergency vehicles.
The Land Use Plan shall be based on natural features such as:
2
a, Soils, wetlands, woodlands, and severe slopes
b. Urbanization limitation strategies
c. Existing agriculture
d. Other factors
Within the designated RAD classifications, residential land development shall be primarily, as
opposed to exclusively, responsive the Open Space Development (OP) Section of the Zoning
Ordinance; and preserve 5O% of the gross land area within such developments by means of
permanent open space conservation easements, and clustered dwelling unit groupings.
The Open Space Preservation District section of the Zoning Ordinance shall specify- design
standards for residential development within the RAD classification.
Residential development shall be responsive to the Goals prescribed by the Housing Element of the
Lake Elmo Comprehensive Plan.
Non -Residential Development
Consumer retail land use will be planned and/or approved only to the extent that existing consumer
retail use within the City and consumer retail use in adjacent communities are clearly demonstrated to
not adequately provide retail goods and services for the residents of Lake Elmo.
While Lake Elmo is bordered on the north and south by Principal Arterial roadways, the City does
not agree with the concept that the traffic counts represented by those roadways is the basis for
non-residential land use at interchanges/intersections or in a service road "strip" arrangement. Non-
residential land use within the City should be local need driven, not traffic count driven.
Non-residential land use shall be focused in two geographic areas of the City: the 1-94 Corridor
(Principally Office/Research); and, as in -fill and renovation, in the Old Village. Limitation of non-
residential land use to those geographic, areas will enhance the City policy of retaining the rural
character of the community, while, in concert with existing and planned non-residential uses in
adjacent communities and existing non-residential within the City, the residents of the City will enjoy
reasonable access to employment opportunities, and requited goods/services.
Consistent with Old Village policy, new linear non-residential development along State Highway 5
should not be allowed; and, the City should encourage existing non-residential uses along State
Highway 5 to adhere to Old Village policy regarding expansion and renovations.
All non-residential development shall be required to maintain high quality standards of site, structure
and landscape design. Uses within the Old Village shall comply with the design standards and
regulations adopted for that geographic area.
Alterations to the natural environment; or site layout, signage, lighting or structure architecture in
excess of Code requirements, to enhance the visibility of a non-residential use to vehicular traffic
shall be considered substantial evidence that the use is intended to serve other than City residents.
Non-residential uses in the 1-94 corridor shall be principally office/research in character. The term
office/research shall preclude uses that are primarily engaged in manufacturing, assembly,
warehousing, retail sales/service and hospitality except to the extent that such precluded uses direcdy
and demonstrably serve the primary office/research uses of the area, within Lake Elmo. Also
precluded is any use that introduces truck traffic except as such truck traffic is clearly incidental to a
specific office/research use,
Housing
It shall be the Policy of the City, by adopted plans, programs and development regulations to provide
for a variety of housing types for all people of all stages of the life cycle. It should also be the Policy
of the City to encourage retention and development of housing affordable to a broad range of
incomes while maintaining a fiscally responsible ratio of municipal services provided to real estate tax
revenue to support those municipal services. Examples of adherence to these housing policies
include:
1. Preservation the moderate cost housing alternatives represented by the Cimarron
Manufactured Housing neighborhood.
2. Affirmative City actions to address neighborhood design responsive to the unique
requirements of persons with physical disabilities, such as walkable access to public and
private goods, services and amenities.
3. Support for senior arid age restricted housing initiatives within the Regional Sewered areas of
the Old Village and/or South of 10th Street North that demonstrate high standards of
design, materials, and resident amenities. Ease of resident access to goods and services
within the context the Non-residential Development Policies of this Plan should be an
important locational determinant in recognition of the reduced mobility of senior and age -
restricted residents.
4. Support of expanded opportunity for development of new housing resources affordable to
families of moderate income within the areas of the City planned for service by Regional
Wastewater Treatment. This may included housing density bonuses. but City financial
subsidy in support of those housing opportunities is not implied bv this Policy-.
It is equally important for the City to actively pursue retention of well -maintained existing housing
and neighborhoods. Adoption of and systematic enforcement of City codes that address housing and
neighborhood maintenance, together with timely rehabilitation and improvements to municipal
infrastructure will be important components of addressing this policy.
By zoning and other City codes the City should encourage housing development that respects the
natural environment of the corturiunity while striving to accommodate the need for a variety of
housing types and costs.
The City will support the availability of a full range of services and facilities for its residents in
proportion to the intensity of development within a geographic area of the City.
Environmental Protection
Encourage farmers to work closely with the Soil and Water Conservation District and utilize sound
soil erosion prevention practices, such as contour plowing, strip cropping, minimum tillage,
shelterbelts, and other similar practices.
Regulate the location and design of non -farm animal confinement areas to minimize pollution and
nuisance problems.
Require all residential developments to conform to the limitations presented by natural features,
including soils, drainage patterns, topography, and woodlands.
Require subdivisions to be designed to utilize the natural drainage system, including, but not limited
to ponds, wetlands and watercourses and groundwater recharge.
4
Adopt and enforce strict regulations regarding the design, location, and maintenance of on -site
sewage treatment systems based on compliance with PCA Rule 7080.
Restrict development from areas containing unique or endangered forms of vegetation and/or
wildlife.
Strictly regulate development in floodplain, wetland and Shoreland areas in compliance with State
and Federal mandates.
Municipal Services
Provision of municipal services will remain proportionate to the intensity of development within
geographic areas of the City. Provision of municipal services will not be in a manner that drives
intensive development, but rather responsive to the intensity of development specified by the
Comprehensive Plan. Exatnples of actions that are responsive to this Policy include:
1. Design and acquire infrastructure and other City capital purchases to minimize future
operations and maintenance expense, particularly full time City staff.
2. Maximize the utilization of citizen volunteers where appropriate.
3. Maximize the benefits of technology in City operations and municipal services.
4. Emphasize preventative measures to avoid the occurrence of problems.
Transportation
The focus of motorized transportation planning and resulting infrastructure should be trips with
origins and/or destinations within the City, servicing Lake Elmo residents.
Vehicular trips not originating and/or ending within Lake Elmo should not be encouraged through
planning or infrastructure improvements by local, County, State or Federal Agencies.
Interstate 94 and State Highway 36 shall remain the primary vehicular corridors for traffic with
origins and/or destinations not in Lake Elmo.
The location of State Highway 5 in the center of the Old Village, coupled with the present and
forecasted volume of traffic on that roadway, presents numerous safety and urban design issues
which will regnire mitigation if the Old Village is to best serve as the center piece of the community.
The City, with the cooperation and assistance of the Minnesota Department of Transportation and
Washington County should continue to explore measures to reduce or eliminate the issues that are
caused by State Highway 5 in the center of the Old Village.
The City shall investigate street segments that may benefit from traffic calming.
The City should support retention of the Expressway cross section of State Highway 36, with
signalizafion of key at -grade intersections. Improvement of the Highway 36 corridor to Parkway
standards should also be encouraged and supported.
The City should encourage, support and become advocates of public transit service to the City,
particularly commuter rail service to the St, Croix Valley area via the existing rail corridor. This
should include planning for one or more a transit hubs to serve HOV, bus and commuter rail
options at appropriate geographic locations,
The City should design, construct and maintain the minimum acceptable grid system of collector
streets, Where State Aid funds are expended for such construction, State Aid design standards should
be incorporated. Where State Aid funds are not used the collector streets should be constructed to a
paved section designed to minimize impervious surfacing and piped stotm water conveyance.
While not located in Lake Elmo, the Lake Elmo Airport will continue to be a transportation facility
that will impact the City. The City should continue to vigorously oppose all initiatives to broaden the
operating capabilities of the Lake Elmo airport from the existing recreational aviation to corporate or
commercial aviation, by runway lengthening or other related improvements.
City policy and plans should recognize Lake Elmo Airport safety and noise zones based on
recreational aviation only.
1-94 Freeway Corridor Planning Policy
The 1-94 Corridor, extending from Inwood Avenue on the west to Manning Avenue on the east, and
generally defined at extending north to 10th Street North will, other than the limited -scale Old
Village, be the focal point of urbanized development within the City served by Regional Wastewater
Treatment through community build -out by 2030. Planning Policy specific to this geographic area
includes:
1. Preservation of the present Rural Character arid living environment of the existing residential
neighborhoods south of the 10th Street — Stonegate, The Forest, and Midland Meadows.
Urban intensity development of land adjoining these neighborhoods must be so designed as
to preclude externalities of that urban development (such as through traffic, exterior lighting,
noise, and trespass) from negatively impacting the existing residential neighborhoods either
physically or financially. Any public utility extensions (water and sewer) to lands adjoining
these neighborhoods should not result in the City ordering of public water and sewer
extensions into these existing neighbothoods unless specifically requested to by 2/3 (two
thirds) majority of the homeowners.
2 The costs for extensions of Public water and sewer service shall be born exclusively
by those pronerty owners that. as determined by the City: benefit from said
extensions and service.
3. All development/redevelopment shall be subject to a Development Staging Plan that either
.regulates development geographically, or in terms of the number of Residential Equivalent
(REC) units permitted to be constructed annually — or both. The Staging Plan shall become
an Official element of the City Comprehensive Plan. All areas not served by Regional
Wastewater shall be planned and zoned at a density of 1 dwelling unit per 2) acres of land
until such point in time as the Staging Plan specifies development at a higher density can
take place.
4. Non-residential uses shall be limited to those specified by the Non-residential Use section of
this Planning Policy. The overall scale of non-residential use should be limited to
approximately 20% of the net developable land south of 10th Street (including presently
vacant land within Eagle Point Business Park, and Highpointe Health Campus). Non-
residential development should result in employment averaging 4;) employees per acre
developed, and such employment should primarily be of a professional, technical and
management type.
5. Residential development shall be served by Regional wastewater treatment and shall be at a
average gross density of 3 dwelling units per acre, and may be of higher density depending
6
on the carrying capacity of the land and infrastructure. The incorporation of multiple
housing styles, types, and levels of affordability shall be encouraged, while avoiding
geographic concentrations of lower cost housing, housing styles and housing types.
Residential development may include senior and/or age -restricted housing as a self-
contained neighborhood that could include amenities, multiple care levels and other services
designed for those residents. A total of 3,700 REC's of Regional Wastewater Service shall be
reserved for residential development subject to the Development Staging Plan.
6. The Cimarron Manufactured Housing Neighborhood is found to be an important housing
resource of the City. It important to retain that resource. Not less than 500 REC's of
Regional Wastewater Service shall be reserved for use of the Cimarron neighborhood at such
time as the existing private wastewater system is determined to be in need of replacement or
major reconstruction.
7