HomeMy WebLinkAbout02-08-2011 PacketCity of Lake Elmo
City Council Workshop
3800 Laverne Avenue North
Lake Elmo, MN 55042
February 8th, 2011
6:30 p.m. — 8:30 p.m. (?)
Agenda
Comprehensive Plan Update — Review of Draft Timeline and
Citizen and Stakeholder Participation and Organization Special
Event Permit
2. Special Event Permit Ordinance — City Council Review
3. Update on Discussions Regarding Location of the ECFC in Lake
Elmo
4. Adjourn
**A social gathering may or may not be held at the Lake Elmo Inn following
the meeting.**
MAYOR & COUNCIL ORKSHOP
DATE:
WORKSHOP
ITEM #:
DISCUSSION
2/08/2011
AGENDA ITEM: Comprehensive Plan Update — Review of Draft Timeline and Citizen and
Stakeholder Participation and Organization
SUBMITTED BY: Kyle Klatt, Planning Director
THROUGH: Bruce Messelt, City Administrato
REVIEWED BY: Kelli Matzek, City Planner
SUMMARY AND ACTION REOUESTED: The City Council is respectfully requested to
review and provide feedback on proposed timelines associated with future updates to the
Comprehensive Plan for the Village and 1-94 Corridor Planning Areas (the portions of Lake
Elmo that are planned for future sewered development).
BACKGROUND & STAFF REPORT: Staff envisions that the City's development of updates
to the Comprehensible Plan for each of the proposed sewered development areas will occur as
separate planning processes, but with some similarities in order to help staff better manage these
complex projects. Included for review by are three separate documents as follows:
• A general project outline/timeline for the 1-94 Corridor
A general project outline/timeline for the Village Area
• A graphical representation of the proposed timeline, with both project areas shown on the
same page.
Due to a lack of quorum present at its last meeting, the Planning Commission has yet to formally
review and comment on the proposed timelines. Staff would like to continue working on these
projects; and therefore is seeking general direction from the Council before proceeding with the
initial project tasks. In particular, Staff would like to begin pulling together the citizen
participation groups, including a larger "stakeholder" group and smaller work group.
Pease note that the latter portions of the Village planning timeline will need to be expanded upon
at some point in the future. This timeline will be further revised based on feedback from the
Planning Commission and Council and proposed work groups.
-- page 1 --
City Council Meeting Comp Plan Update Timeline
February 8th, 2011 Workshop Agenda Item #1
RECOMMENDATION: It is recommended that the City Council review the proposed
timelines and discuss any comments or suggested revisions at its meeting.
ATTACHMENTS:
1. 1-94 Area Draft Timeline/Process
2. Village Area Draft Timeline/Review Process
3. Graphical Timeline
SUGGESTED ORDER OF BUSINESS:
Introduction of Item
Report/Presentation ...,....................
Questions from Council to Staff
Public Input, if Appropriate ................„ ...
Council Discussion .............. . ......... ......
Council Direction, if Appropriate
City Administrator
............................... Planning Director
Mayor Facilitates
.. ,„., ..... „„„.., .......... Mayor Facilitates
.... ...............,... Mayor & City Council
...... „ ...... .............. Mayor Facilitates
-- page 2 --
A Draft Timeline/Process
JANUARY
Identify Stakeholders Group
Identify Technical Committee
Identify Work Group (subset of Stakeholders Group; 7-10 people)
FEBRUARY
First meeting ofStakeholders Group
Meeting One — Existing Conditions
Purpose: What is there now? What does the Comp Plan currently
say? What are the Met Council requirements? What is happening
in adjacent communities? What are the land uses adjacent to the
areas in developing Lake Elmo?
- Report back to Planning Commission, City Council
MARCH
Hold Open House
o Invite stakeholder group, commissioners (Planning, Parks, Environmental,
etc.), general public
o Seek input on Vision — If we can't all agree (at least in part) where we are
headed, getting there will never "end."
First meeting of Work Group
Meeting One — What is the Vision?
Purpose: Receive information received from open house. What is
the end goal for the Area South of 10th Street? A bustling
commercial node? Stable, safe neighborhoods? A regional draw
such as ? How does the city want to be seen from 1-94?
What is the community identity?
APRIL
- Report back to Planning Commission, City Council
o Get consensus on Vision for Area South of 10th Street
First meeting of Technical Committee
Purpose: What services need to be discussed? What do current
plans call for? What other plans are out there (school district,
Washington County, etc.)? Gather information.
• Schools
• Streets
• Sewer
• Storm Sewer/Surface Water
• Water
• Fire
MAY
II Police
• Parks
• Trails
Second meeting of Stakeholders Group
Meeting Two — Report on Work To Date
Purpose: Report on established Vision for South of 10th Street
Area. Report on work done by Technical Committee, City Staff.
Identify upcoming meetings, work, and options for more public
input.
Second meeting of Work Group
Meeting Two — Figuring out the Details — Commercial Focus
Purpose: Revisiting the existing land use map:
- Does residential housing along 1-94 coincide with the agreed
upon vision? Does it make sense? If the land continues to be
designated for residential along 1-94, what does the city want to do
with existing businesses?
- Does a corporate campus at the corner of Manning Avenue and I-
94 make sense? Is there a market?
Third meeting of Work Group
Meeting Three — Figuring out the Details — Residential Focus
Purpose: Revisiting the existing land use map:
- Does residential housing along I-94 coincide with the agreed
upon vision? Does it make sense? If the land continues to be
designated for residential along 1-94, what does the city want to do
with existing businesses?
- Do the property owners at the comer of Lake Elmo Avenue and
I Oth Street continue to want part of their properties guided for
sewer? Is it feasible? Where are their existing homes and septic
systems?
- Buffering existing neighborhoods (111-3 of Comp Plan identifies
requirements)
- Property guided for PF, but currently zoned R-3. Should that be
changed?
Report back to Planning Commission, City Council
o Review work done by Work Group, Technical Committee/City Staff
JUNE
Third meeting of Stakeholders Group
Meeting Three — Report on Work To Date
Purpose: Report on work done by Work Group - where land use
types should be located (generically residential and coirunercial).
Second meeting of Technical Committee
Purpose: Given the established vision and ideas of what land use
types should be where, do services need to be reevaluated? Are
there any red flags? Additional services needed? Where
appropriate?
• Schools
• Streets
• Sewer
• Storm Sewer/Surface Water
• Water
• Fire
• Police
• Parks
• Trails
JULY
- Fourth meeting of Work Group
Meeting Four — How to Implement — Creating a Future Land
Use Map
Purpose: Given the established vision, the additional services
needed (school, fire, police, etc.) and the ideas for appropriate
residential and commercial locations — create a Future Land Use
Map.
AUGUST
Fifth meeting of Work Group
Meeting Five — A More Detailed Future Land Use Map
Purpose: Revisit the Draft Future Land Use Map and give more
detailed review to what type of uses would be appropriate in which
commercial areas. What level of density would be more
appropriate for residentially guided properties.
SEPTEMBER
Hold Open House
o Invite stakeholder group, commissioners (Planning, Parks, Environmental,
etc.), general public
o Seek input on Detailed Future Land Use Map
Report back to Planning Commission, City Council
o Review work done by Work Group, Stakeholders Group, Technical
Committee/City Staff, Information from Open House
OCTOBER
- Sixth meeting of Work Group
Meeting Six — How Do We Get to the Vision? View Draft
Ordinance Language and Design Standards
Purpose: Revisit the Draft Future Land Use Map and give more
detailed review to what type of uses would be appropriate in which
commercial areas. What level of density would be more
appropriate for residentially guided properties.
Park Commission Meeting
o Review draft Future Land Use Map and More Detailed Plans
Planning Commission Meeting
o Review draft Future Land Use Map and More Detailed Plans
o Hold public hearing to amend the Comprehensive Plan
NOVEMBER
City Council Workshop
o Review draft Future Land Use Map and More Detailed Plans
City Council Meeting
o Approve Comprehensive Plan Amendment
Staff sends Comprehensive Plan Amendment to Metropolitan Council for approval.
DECEMBER
Village Area Comprehensive Plan Update
Draft Timeline/Review Process
Prepared By: Lake Elmo Planning Department
1/24/11
2011 Task/Meeting Summary
January Establish Stakeholder Group
• All potential stakeholders
Create Village Comprehensive Plan Update Work Group
• Including some members of the stakeholder group
Create Technical Review Committee
• Comprised of same members as recommended in the 1-94
review process
February
March
April
Stakeholder Meeting
• Planning Update - History of recent planning efforts
• Discuss overall Village housing unit count with update
regarding City Council density decision
• Review Planning Department density analysis
Work Group
• Meeting 1
• Review current plans and AUAR
• Discuss Civic/Institutional Plans and alternative
scenarios for public and semi-public uses
• Review transportation plans
• Discuss public realm (streets, parks, sidewalks, public
squares) and design options
• Storm Water Update
Planning Commission/Council Update
• Stakeholder feedback and comments
• Work group update
Open House #1
• Present options for civic and institutional "Community
Campus"
• General update concerning population and density
projections for the Village
• Sewer Project update
• Storm Water Planning discussion
Technical Committee
• Discuss Service needs in community
• Review current agency/departmental/governmental
May
June
July
planning efforts
Work Group
• Consider design standards and integration into the
Zoning Ordinance
• Review zoning district alternatives
• Identity preferred location for community campus
concept
• Review site design options for community campus
• Consider revised residential and open space plan with
new density projections.
• Establish preferred scale for Village area development
Planning Commission/Council Update
• Open House Review
• Review draft Land Use Plan update
Work Group
• Meeting 3
Technical Committee Meeting
Stakeholder Group
• Meeting 2
Planning Commission/Council Update
Work Group
• Meeting 4
August Work Group
• Meeting 5
Planning Commission/Council Update
September Open House #2
October
Technical Committee Meeting
• Review AUAR Update Document for submission to EQB
Work Group
• Meeting 6
Planning Commission/Council Update
• Review Draft Comprehensive Plan Update - with
revised Land Use Plan
November Work Group
• Meeting 7
December Stakeholder Group
• Meeting 3
2
Planning Commission/Council Update
Public Hearing - Planning Commission
Notes:
• Technical Committee meeting schedule will be timed to coincide with 1-94
Planning schedule
• Additional Work Group meetings will be called on an as -needed basis
January February March
Establish'
Stakeholders,
Technical, and
Work Groups
April May June July August September OctJanuary February
Ober November December
Stakeholders
Group- large 1st MIg 2nd Mtg
Work Group
1.94 (subset of 2nd and 3rd
slakeholderl tst Mtg MIg. 41h Mtg 5lh Mtg, 61h Mtg
Open House -
public -X '
Technical
Group -_ X
Commissions X
City Council X
Establish:
Stakeholders,
Technical, and
Work Groups
Stakeholders
Group - large
village Work Group
(include some
stakeholders)
Open House -
publJc
Technical
Group
Commissions
City Council
2nd MIg 3rd Mtg.
3rd klIg
2nd Mtg
4th MIg, 51h Mlg.
41h mig
6th Mtg. 7th Mtg
-
LAKE
ELMO
MAYOR 4c utvciL WORKSHOP
AGENDA ITEM:
SUBMITTED BY:
THROUGH:
REVIEWED BY:
DATE: 2/08/2011
WORKSHOP
ITEM #: 2
DISCUSSION
Special Event Permit Ordinance — City Council Review
Kyle Klatt, Planning Director
Bruce Messelt, City Administrato
David Snyder, City Attorney
Kelli Matzek, City Planner
SUMMARY AND ACTION REQUESTED: The City Council is respectfully requested to
consider and review a new ordinance to regulate special events within the City of Lake Elmo,
This ordinance is very similar to a document that was reviewed by the Planning Commission
more than a year ago, but never further refined or adopted by the City. A Special Event Permit is
intended to provide some regulation of temporary events on a case -by -case basis and is intended
to promote the orderly, compatible, and safe use of property for temporary special events and to
assure adequate provision of parking, traffic, sanitary facilities, utilities, public safety services,
and peace and tranquility of residential neighborhoods.
The proposed Ordinance 08-034 was presented to the Council last December, but was not acted
upon at that time so that the Council could spend more time reviewing the draft with Staff at a
workshop meeting.
BACKGROUND INFORMATION: This ordinance was first brought forward by Staff as a
follow-up to several requests for events within the City of Lake Elmo that would normally not be
allowed under the City's zoning regulations, The most significant of these events was a Rowing
Regatta on Lake Elmo that was ultimately permitted in the absence of any formal regulations
concerning such events (and also due to the fact that the event took place on a public water body
and within the regional park preserve). Staff has over the past several years, also received
requests for a "pet carnival" and other such events and promotions by local businesses.
One of the more significant changes to the proposed ordinance since the version previously
reviewed by Planning Commission has been the addition of a new category of special events for
Agricultural Sales Businesses. Specifically, the Ordinance now includes a provision that would
allow an Agricultural Sales Business that is conducted for a period of three months or less to be
permitted by a Special Event Permit. The ordinance would allow such a permit to be issued for
-- page 1 --
City Council Meeting Special Event Ordinance
February 8th, 2011 Workshop Agenda Item # 2
two consecutive years; otherwise, any agricultural sales businesses operating for a longer term
would need to obtain an Interim Use Permit in accordance with recent amendments to the City
Code,
The Agricultural Sales Provision is a direct result of recent discussions and action by the
Planning Commission and City Council regarding agricultural businesses. The proposed
ordinance would provide an alternate to a full interim use permit in cases where a grower or
importer would like to sell agricultural products for a limited time, As an example of how this
permit would be applied is a situation in which a grower needs to supplement the sales of their
produce grown on -site due to the loss of a crop due to bad weather or other unforeseen
circumstances.
The proposed ordinance does include several exemptions for events sponsored by a public entity,
events that take place in an athletic field, family gatherings, and other such activities,
STAFF REPORT: The City Attorney has noted that the City could try to define a threshold for
small events based on experience, such as by reference to an event that is known to bring in less
than 30 people but does not implicate public infrastructure, traffic, etc. In looking back at
previous events that were conducted in the City that would be considered a special event under
the proposed ordinance, Staff has been unable to identify any specific type of activity that would
seem to have met this threshold.
The Attorney has also suggested that the Planning Commission and City Council may want to
consider special events that have occurred in the past to determine if they can be used as a guide
concerning any problems that arose and how these issues may have been addressed. Some
typical problems include traffic back-ups, informal road closures, late night noise, minor
trespassing, insufficient restrooms, and other similar occurrences.
Staff has made other minor revisions to the ordinance based on comments from the Planning
Commissions, and all changes and revisions recommended by the Planning Commission are
included in the attached ordinance.
The Planning Commission unanimously recommended approval of the Special Event Ordinance
at its November 22, 2010 meeting.
ADDITIONAL INFORMATION: The model used for the draft ordinance was taken from the
City of North St. Paul. This ordinance was chosen as it was fairly broad in terms of its coverage,
while some other examples staff researched were very specific to certain types of events. This
broad and simple ordinance will be easier to administer as Lake Elmo currently has just a few
events to which the permit may pertain.
City History - In 2006 the Council approved an ordinance allowing Commercial Social Outdoor
Events as a conditional use in the agricultural zoning district, which it then repealed in April of
— page 2 --
City Council Meeting Special Event Ordinance
February 8th, 2011 Workshop Agenda Item # 2
2007. A Special Event Permit is different than the Commercial Social Outdoor Events in the
following ways:
1) A Special Event Permit would be required and reviewed for each event and would not
guarantee a future permit would be received by the applicant or property owner. A
Commercial Social Outdoor event was established as a Conditional Use Permit
(CUP) and would have run with the property in perpetuity.
2) The City Council would have the discretion to deny a Special Event Permit. If a CUP
was received and the conditions of a Commercial Social Outdoor Event were being
met, the City would have a difficult time revoking the permit.
3) A Special Event Permit would not necessarily be based on a zoning district. A CUP for a
Commercial Social Outdoor Event was allowed only in the Agricultural zoning
district.
4) Special Event Permit could be intended to regulate temporary, outdoor privately -
sponsored events open to the general public, held on public or privately -owned
property, and impacting city facilities or services. The draft ordinance provided
identifies specific gathering types that would not require a permit, such as a wedding.
The only application received by the City to implement the Commercial Social
Outdoor Event ordinance was to hold weddings on a property in the city.
Should the City Council adopt the propose ordinance as prepared by the Planning Commission,
the Council will need to determine the fees for this type of permit. Because the 2011 Fee
Schedule will be considered by the Council at its next meeting, Staff is recommending that the
fees for Special Events be addressed with other fees at the Council's subsequent meeting.
Part of the justification for requiring a Special Event Permit for certain events is to help ensure
that any potential public costs associated with the event are properly addressed. As noted in the
attached ordinance, the City may charge for any required clean-up from the event, and provisions
are included that require the applicant to provide adequate police, fire, and sanitary services
during the duration of the event.
PLANNING COMMISSION REPORT,: The Planning Commission conducted a public
hearing regarding the proposed Special Event Permit Ordinance at its November 8, 2010
meeting. No public comments were received at the meeting; however, the Commission tabled
taking action on the Ordinance and requested that Staff review the Ordinance with the City
Attorney before making its recommendation to the City Council, Staff reviewed the proposed
ordinance with the City Attorney and City Administrator in order to provide some clarity
concerning the intent of the ordinance, and based on these discussions, suggested that the
following modifications be made to the ordinance:
page 3 --
City Council Meeting Special Event Ordinance
February 8th, 2011 Workshop Agenda Item # 2
• That special events that last less than three consecutive days be permitted through an
administrative review process rather than requiring action by the City Council.
• That a special event permit be required for non-profit organizations in addition to other
property owners. The intent of the proposed ordinance is to ensure that larger events do
not create any problems that may negatively impact the public or result in costs that must
be born by the City. Whether an event is sponsored by a private business or non-profit
entity, requiring a special event permit can help the City reduce the potential for any
unforeseen costs or impacts. The Attorney has offered an opinion that private clubs
should not be regulated differently than a for -profit business.
• That the provisions related to exeeptions specifically state that only activities that have
been previously authorized by the City are exempt from the ordinance, and that if
expanded or enlarged, these events would need to secure a permit.
The Commission considered these changes, and ultimately recommended further modifications
to allow the City Administer to approve all Special Event Permits, with a provision that allows
the Administrator to refer permits to the Council as necessary. Staff has further clarified the
review requirements in the draft ordinance so that all denials must be made by the City Council,
RECOMMENDATION: Staff is recommending that the City Council review the proposed
Special Event Ordinance and direct Staff to make any changes prior to Council consideration of
the ordinance at a future meeting.
ATTACHMENTS
I. Ordinance 2008-034 — Special Event Permits
SUGGESTED ORDER OF BUSINESS:
Introduction of Item , ......... „.„. „ .... . , ,
..
Questions from Council to Staff ..... „„„„.
Public Input, if Appropriate .....
Discussion „ ....... ........ „ „ „.. „... „
Direction, if Appropriate
..... ...... City Administrator
..... ,.....,.,........, ........ Planning Director
......„,... ........... „Mayor Facilitates
..,.......,..... ...... ......,..,Mayor Facilitates
..... Mayor & City Council
Mayor Facilitates
-- page 4 --
Ordinanco 08-034 $.3ity Council Draft; 1"2/7/10,
CITY OF LAX ELMO
COUNTY OF WASHINGTON
STATE OF MINNESOTA
ORDINANCE NO. 08-034
AN ORDINANCE ADDING TO THE LAKE ELMO CITY CODE OF ORDINANCES BY
ADDING TO CHAPTER 110 OF THE BUSINESS REGULATIONS: BUSINESS
REGULATIONS TO PROMOTE THE ORDERLY, COMPATIBLE AND SAFE USE OF
PROPERTY FOR TEMPORARY SPECIAL EVENTS AND TO ASSURE ADEQUATE
PROVISION OF PARIUNG, TRAFFIC, SANITARY FACILITIES, UTILITIES, PEACE
AND TRANQUILITY OF RESIDENTIAL NEIGHBORHOODS AND SAFETY
SERVICES
SECTION 1. The City Council of the City of Lake Elmo hereby amends Title XI: Business
Regulations; Chapter 110 — General Licensing Provisions, by adding the following
language:
§ 110.070 SPECIAL EVENT PERMITS.
(A) Purpose and intent. The purpose of this Chapter is to promote the orderly, compatible
and safe use of property for temporary special events and to assure adequate provision of
parking, traffic, sanitary facilities, utilities, peace and tranquility of residential neighborhoods
and safety services.
(B) A Special Event shall include the following:
(1) Any temporary, privately -sponsored event, typically conducted outdoors, open to
the general public and held on public or privately owned property, where such event would not
otherwise be permitted under the City's zoning regulations.
(2) An Agricultural Sales Business as defined in Section 11.01 that is conducted for
less than three (3) months in any calendar year. A Special Event Permit for an Agricultural Sales
Business may be issued once per year and for no more than two consecutive years.
'(C) Exceptions: "Special Event" shall not apply to the following:
(1) Any permanent place of worship, stadium, athletic field, arena, theatre,
auditorium, or fairs conducted pursuant to Minn. Stats. Chapter 38.
(2) Special events or activities permitted or permitted by other State laws or
regulations of the City of Lake Elmo, including publicly -sponsored activities in the local park
system and any other lawfully established event for which the City Council has expressly
Ordinance 08-034 City Council Draft; 12/7/-10
granted approval prior to adoption of this ordinance, unless said event is expanded or enlarged,
in which case a Special Event Permit will be required.
(3) Family gatherings, including family reunions, graduation parties, baptisms,
confirmations, weddings, etc.
(4) Garage sales
(5) National Night -Out or Night -to -Unite established through the City of Lake Elmo.
(D) Permit Required
(1) No person on or after the effective date of this Chapter shall conduct or allow to
be conducted any special event as defined in this ordinance without first obtaining a Special
Event Permit.
(E) Requirements for Issuance of a Permit
(1) The following standards shall apply to all special events:
(a) Maximum Number of People, The permitee shall not sell tickets to nor
permit attendance at the permit location of more than the maximum number of people stated in
the special event permit.
(b) Sound Equipment. Sound producing equipment, including but not limited
to public address systems, radios, amplifiers, musical instruments and other recording and
playback devices, shall not be operated on the premises of the special event so as to be
unreasonably loud or be a nuisance or disturbance to the peace and tranquility of the citizens of
Lake Elmo,
(c) Sanitary Facilities, In accordance with Minnesota State Board of Health
regulations and standards and local specifications, adequate sanitary facilities must be provided
which are sufficient to accommodate the projected number of persons expected to attend the
event.
(d) Security. The peiinitee shall employ at his/her own expense such security
personnel as are necessary and sufficient to provide for the adequate security and protection of
the maximum number of persons in attendance at the special event and for the preservation of
order and protection of property in and around the event site. No permit shall be issued unless
Washington County Sheriffs Department is satisfied that such necessary and sufficient security
personnel will be provided by the permitee for the duration of the event.
(e) Food Service. The operator of the special event shall be responsible for
securing any permits, if necessary, from the Washington County Health Department for any food
services that are made available on the premises.
2
Ordinance 08-034 City Council Draft; 12/7/10
(f) Fire Protection. The permitee shall, at his/her own expense, take adequate
steps to insure fire protection as determined by the City of Lake Elmo Fire Chief
(g) Duration of Special Event. The permitee shall operate the special event
only on those days and during the hours specified on the permit.
(h) Cleanup Plan. The special event applicant is responsible for clean up of
the site upon completion of the special event, and shall specify the amount of time anticipated to
restore the site to its pre -event condition as part of an application. Any clean up or restoration
work required by the City may be charged to the applicant. Any City service that requires
overtime will be at the expense of the applicant.
(i) Waiver. The City Council, or City Administrator for those permits that
are subject to an administrative review and approval process, may grant a waiver from the
requirements of this Chapter in any particular case where the applicant can show that strict
compliance with this Chapter would cause exceptional and undue hardship by reason of the
nature of the special event or by reason of the fact that the circumstances make the requirement
of this Chapter unnecessary. Such waiver must be granted without detriment to the public
health, safety or welfare and without impairing the intent and purpose of these regulations.
(j) Insurance. Before the issuance of a permit, the permitee shall obtain
public liability insurance and property damage insurance with limits determined by the City
Administrator if reasonably determined necessary. Such insurance shall remain in full force and
effect in the specified amounts for the duration of the permit. Evidence of insurance shall
include an endorsement to the effect that the insurance company will notify the City Clerk in
writing at least ten (10) days before the expiration or cancellation of said insurance.
(k) Miscellaneous, Prior to the issuance of a permit, the City Council, or City
Administrator for those permits that are subject to an administrative review and approval
process, may impose any other conditions reasonably calculated to protect the health, safety and
welfare of persons, attendant or of the citizens of the City of Lake Elmo including, but not
limited to, restrictions on parking and vehicle access, lighting, litter and noise.
(2) In addition to the requirements listed above, the following shall also apply to a
Special Event Permit for an Agricultural Sales Business:
(a) All performance standards as specified in Section 154.110 for Agricultural
Sales Businesses. The City Council, or City Administrator for those permits that are subject to
an administrative review and approval process, may exempt the applicant from any of these
standards that are deemed unnecessary given the nature or duration of the event.
(F) Application Procedures.
(1) A written application for a Special Event Permit shall be filed on forms provided
by the City with the City Administrator not less than thirty (30) days before the date proposed for
holding the special event. The written application shall be signed by the person, persons, or
Ordinance 08-034 City Council Dipft; 12/7/10
parties conducting the event and the property owner, if different, and shall be accompanied by
the fee payable hereunder. Upon submission of an application for a Special Event Perrnit, City
staff will review the request and advise the applicant of the need for additional information, if
any.
(G) Fees
(1) The fee for a Special Event Permit shall be as established by the City Council.
(H) Granting a Permit
(1) Administrative Review and Approval. The City Administrator, or his/her
designee, shall review and determine whether or not a request for a special event and/or street
closing is acceptable. The City Administrator shall have the authority to issue Special Event
Permits for those events that meet the criteria of this Ordinance. In the event the City
Administrator determines the activity does not meet these criteria, such applications shall be
referred to the City Council for consideration.
(2) City Council Review and Approval. The City Administrator shall refer any
application for a Special Event Permit that may adversely affect the safety, health and welfare of
the citizens of Lake Elmo due to the size, location, or potential impacts of the event to the City
Council for final action.
(J) Denial of Permit
(1) The City Council shall have the right to deny the permit if, in the judgment of the
City Council, the granting of a permit would adversely affect the safety, health and welfare of the
citizens of Lake Elmo or if other criteria herein are not met. The applicant shall be notified of
such denial and may appear before the City Council to appeal such denial.
(K) Transferability
(1) No permit granted under this Chapter shall be transferred to any other person or
place without consent of the City Council, upon written application made therefore.
(L) Enforcement and Penalties
(1) The City Administrator and other such officers, employees, or agents as the City
Council or City Administrator may designate, shall enforce the provisions of this Chapter in
accordance with Section 10.99 of the City Code.
(2) The holding of a special event in violation of any provision of this Chapter shall
be deemed a public nuisance and may be abated as such.
(3) Any person violating any provision of this Chapter is guilty of a misdemeanor and
upon conviction shall be subject to the penalties set forth in Minnesota Statutes.
4
Ordinance 08-034 City Council Draft; 12/7/10
(M) Revocation of Permit
(1) The permit for a special event may be revoked by the City Council at any time if
any of the conditions necessary for the issuing of or contained in the permit are not complied
with or if any of the provisions of this Chapter are violated.
SECTION 2. Effective Date
This ordinance shall become effective immediately upon adoption and publication in the official
newspaper of the City of Lake Elmo,
SECTION 3. Adoption Date
This Ordinance No. 08-034 was adopted on this 7t1 day of December 2010, by a vote of
Ayes and Nays.
Mayor Dean A. Johnston
ATTEST:
Bruce Messelt
City Administrator
This Ordinance No 08-034 was published on the day of , 2010.
5
CITY OF
LAKE
ELMO
MAYOR & COUNCIL WORKSHOP
DATE:
WORKSHOP
ITEM #:
DISCUSSION
2/01/2011
AGENDA ITEM: Update on Discussions Regarding Location of the ECFC in Lake Elmo
SUBMITTED BY: Mayor & City Council
THROUGH: Bruce A. Messelt, City Administra
REVIEWED BY: Jack Griffin, City Engineer
Dave Snyder, City Attorney
Kyle Klatt, City Planner
Tom Bouthilet, Finance Director
SUMMARY AND ACTION REQUESTED,: The City Council is respectfully requested to
receive a brief update from Council Members Smith and Pearson, the City Administrator and
City Attorney regarding recent discussions relating to potential location of the Stillwater Area
School District's Early Childhood & Family Center in Lake Elmo,
BACKGROUND INFORMATION & STAFF REPORT: On February 1st, 2011, the Lake
Elmo City Council unanimously directed its staff to undertake the following actions with respect
to potential locating of the Stillwater Area Public Schools' Early Childhood Family Center
(ECFC) in Lake Elmo:
• Complete, if possible, a draft Joint Powers Agreement (JPA) with the School
District for location of the ECFC in Lake Elmo;
• Complete, if possible, a Purchase Option for approximately 16 acres of available
land for location of the ECFC via the JPA, as well as future public and civic
facilities; and
• Include members of the City Council, as feasible, in the efforts of the City in
order to provide an additional layer of transparency, attention and timeliness in
addressing the forthcoming issues.
In August 2010 and again on November 3rd, 2010, the City Council directed the City
Administrator actively seek to formulate a proposal to potentially locate the Stillwater Area
School District's Early Childhood & Family Center in Lake Elmo.
-- page 1 --
City Council Meeting
February 8th, 2010
Update on Discussions Regarding Location of the ECFC in Lake Elmo
Workshop Agenda Item # 3
Since that time, active conversation has taken place regarding this potential, leading to recent
efforts to craft the specific agreements for City and School District consideration, including a
very fruitful Wednesday staff -to -staff exchange. Tonight's presentation will serve as the
requested "check -in" with the City Council to ensure the efforts undertaken, to date, are on target
and consistent with previous Council direction to develop a viable location proposal.
RECOMMENDATION: It is respectfully recommended that the City Council receive a brief
presentation by Council Members Smith and Pearson, the City Administrator and City Attorney
regarding recent discussions and efforts relating to potential location of the Stillwater Area
School District's Early Childhood & Family Center in Lake Elmo.
ATTACHMENTS: Proposed Project Schedule (other materials will be handed out at
Tuesday's Workshop).
SUGGESTED ORDER OF BUSINESS:
Introduction of Item ....... ..... .„...„.........................„ ........ ..... City Administrator
Report/Presentation ..... ........ „............... Council/Staff
Questions from Council ..... ......„.„..........„ ..... ....„....................Mayor Facilitates
Public Input, if Appropriate ....... ..... ..........,...... ...... „... ....... ..„..Mayor Facilitates
Council Discussion/Direction .......... ..... „ ........... . ..... ........... Mayor Facilitates
-- page 2 --
Proposed Smhedu|e-DRAFT
City/School District Actions Regarding Lake E|mmECFE Site
Prepared by Lake Elmo Planning Department — 2/3/11
DATE . Planning/Zoning (Lake Elmo) | Lake Elmo City Council School District
Approval ofpurchase
option for 8rookmon3'"
Addition sites
Approve Joint Powers
Agreement
2/18 PubUcHeahngNntice—
Conmpnahenoive Plan
Amendment, Zoning Map
Amendment, Zoning Text
Amendment
2/24 Approve Joint Powers
Agreement
2/25 Submit financing plan toState
of Minnesota
2/28 Planning Commission Public
Hearing —Comprehensive Plan
and Zoning Amendments
3/1 Initiate Phase |
Environmental Study for
8rmV|(nlanxite
3/1 City Council Approval of
Comprehensive Plan
Amendment and related
actions
g/J Submit Comprehensive Plan
Amendment to Met Council
3/8 3/15 Execute purchase option
for 8puokman 3',
Addition sites
3/28 Planning Commission Site Plan
Review
|4/5 City Council Site Plan Review
5/31 Closing nnpurchase of
BnJoknlun3 Id Addition
sites
Site Plan Submission to City
I-94
Stakeholders
Group • large_
Work Group
(subset of
stakeholder)
Open House -
public
Technical
Group
Commissions
City Council
January February March April May June July August September October November December January February
Establish:
Stakeholders,
Technical, and
Work Groups
Establish:
Stakeholders,
Technical, and
Work Groups
lot Mtg.
2nt1 Mlg.
2nd and 3rd
Mtg.
3rd Mtg. 41h Mtg.
X
4th Mtg.
5th Mtg. 6th Mtg.
Stakeholders
Group - large 1st Mtq. 2nd Mtg. 3rd Mtg.
Village Work Group
(include some
stakeholders) 1st Mtg. 2nd Mtg. 3rd Mtg. 4th Mtg. 51h Mtg. 6th Mtg. 7th Mtg.
Open House - -
public X
Technical
X X X
Group
Commissions
X
City Council X X X