Loading...
HomeMy WebLinkAbout#06 - Well 5 Pumphouse Pay Request STAFF REPORT DATE: January 19, 2021 CONSENT AGENDA ITEM: Approve Pay Request No. 4 for the Well No. 5 Pumphouse Improvements SUBMITTED BY: Chad Isakson, Project Engineer REVIEWED BY: Kristina Handt, City Administrator Marty Powers, Public Works Director Jack Griffin, City Engineer ISSUE BEFORE COUNCIL: Should the City Council approve Pay Request No. 4 for the Well No. 5 Pumphouse Improvements? BACKGROUND: Total Mechanical Services, Inc. was awarded a construction contract on July 16, 2020 to complete the Well No. 5 Pumphouse Improvements. Work remains in progress with a substantial completion date of April 18, 2021 and final completion date of June 17, 2021. PROPOSAL DETAILS/ANALYSIS: Total Mechanical Services, Inc. has submitted Partial Pay Request No. 4 in the amount of $55,121.85. The request has been reviewed and payment is recommended in the amount requested. In accordance with the contract documents, the City has retained 5% of the total work completed. The amount retained is $24,380.40. FISCAL IMPACT: None. Partial payment is proposed in accordance with the Contract for the project. Payment remains within the authorized scope and budget. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Pay Request No. 4 for the Well No. 5 Pumphouse Improvements. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve Pay Request No. 4 to Total Mechanical Services, Inc. in the amount of $55,121.85 for the Well No. 5 Pumphouse Improvements”. ATTACHMENTS: 1. Partial Pay Estimate No. 4. PROJECT PAY FORM PARTIAL PAY ESTIMATE NO. PERIOD OF ESTIMATE TO PROJECT OWNER:CONTRACTOR: 1. Original Contract Amount 2. Net Change Order Sum 3. Revised Contract (1+2) 4. *Work Completed 5. *Stored Materials 6. Subtotal (4+5) 7. Retainage* 8. Previous Payments 9. Amount Due (6-7-8) *Detailed Breakdown Attached START DATE:ON SCHEDULE SUBSTANTIAL COMPLETION:X FINAL COMPLETION: ENGINEER'S CERTIFICATION:BOLTON AND MENK, Inc. DATE CONTRACTOR'S CERTIFICATION:CONTRACTOR DATE APPROVED BY OWNER:CITY OF LAKE ELMO, MINNESOTA DATE DATE No.Approval Date Amount $1,083,461.00 Additions Deductions $0.00 $487,608.00 $1,083,461.00 $487,608.00 $0.00 $408,105.75 $24,380.405.0% CONTRACT TIME TOTALS $0.00 $0.00 $55,121.85 NET CHANGE $0.00 CONTRACT CHANGE ORDER SUMMARY PAY ESTIMATE SUMMARY 4 12/31/202012/1/2020FROM PUMPHOUSE NO. 5 PROJECT NO. 2019.129 CITY OF LAKE ELMO 3880 LAVERNE AVENUE NORTH LAKE ELMO, MN 55042 ATTN: JACK GRIFFIN, CITY ENGINEER TOTAL MECHANICAL SERVICES, INC. 420 BROADWAY AVENUE SAINT PAUL PARK, MN 55071 ATTN: MARK DIESSNER 7/22/2020 6/17/2021 REVISED DAYS REMAINING 270 0 108 4/18/2021 ORIGINAL DAYS BY BY YES NO The undersigned Contractor certifies that to the best of their knowledge, information and belief the work covered by this payment estimate has been completed in accordance with the contract documents, that all amounts have been paid by the contractor for work for which previous payment estimates was issued and payments received from the owner, and that current payment shown herein is now due. The undersigned certifies that the work has been reviewed and to the best of their knowledge and belief, the quantities shown in this estimate are correct and the work has been performed in accordance with the contract documents. ENGINEER BY 1/7/21 FOCUS Engineering, inc.PROJECT PAYMENT FORM 1/8/21 PARTIAL PAY ESTIMATE NO.4 PUMPHOUSE NO. 5 CITY OF LAKE ELMO, MINNESOTA PROJECT NO. 2019.129 QUANTITY UNIT PRICE AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT 1 LS 1 $12,961.00 $12,961.00 0.04 $520.00 0.89 $11,500.00 2 LS 1 $50,000.00 $50,000.00 0.10 $5,000.00 0.80 $40,000.00 3 LS 1 $25,000.00 $25,000.00 1.00 $25,000.00 4 LS 1 $15,000.00 $15,000.00 0.00 $3.00 0.81 $12,108.00 5 LS 1 $100,000.00 $100,000.00 0.04 $4,000.00 0.89 $89,000.00 6 LS 1 $25,000.00 $25,000.00 0.32 $8,000.00 0.80 $20,000.00 7 LS 1 $150,000.00 $150,000.00 0.02 $3,500.00 1.00 $150,000.00 8 LS 1 $3,000.00 $3,000.00 0.83 $2,500.00 9 LS 1 $30,000.00 $30,000.00 0.90 $27,000.00 10 LS 1 $58,000.00 $58,000.00 0.52 $30,000.00 0.70 $40,500.00 11 LS 1 $32,000.00 $32,000.00 0.88 $28,000.00 12 LS 1 $14,000.00 $14,000.00 0.00 $0.00 13 LS 1 $3,000.00 $3,000.00 0.00 $0.00 14 LS 1 $55,000.00 $55,000.00 0.00 $0.00 15 LS 1 $500.00 $500.00 0.00 $0.00 16 LS 1 $170,000.00 $170,000.00 0.04 $7,000.00 0.16 $27,000.00 17 LS 1 $275,000.00 $275,000.00 0.05 $15,000.00 18 General Construction Allowance LS 1 $50,000.00 $50,000.00 19 LS 1 $15,000.00 $15,000.00 $1,083,461.00 $58,023.00 $487,608.00 TOTALS - BASE CONTRACT $1,083,461.00 $58,023.00 $487,608.00 DIVISION 1 - PUMPHOUSE NO. 5 General Conditions Mis Metals Carpentry Insulation and Roofing ITEM DESCRIPTION OF PAY ITEM UNIT CONTRACT THIS PERIOD TOTAL TO DATE Mobilization Bonds/Insurance Permit Sitework Masonry Concrete Doors and Windows Mechanical Painting Chemical Systems Computer Allowance Sprinkler Electrical Signs SUBTOTAL - DIVISION 1