Loading...
HomeMy WebLinkAbout#19 - 2020 Mill & Overlay Change Order STAFF REPORT DATE: January 5, 2021 CONSENT AGENDA ITEM: Approve Compensating Change Order No. 3 for the 2020 Mill and Overlay Project SUBMITTED BY: Cara Geheren, Project Engineer REVIEWED BY: Kristina Handt, City Administrator Marty Powers, Public Works Director Jack Griffin, City Engineer ISSUE BEFORE COUNCIL: Should the City Council approve Compensating Change Order No. 3 for the 2020 Mill and Overlay Project? BACKGROUND: Minnesota Paving and Materials was awarded a construction contract on June 2, 2020 to complete the 2020 Mill and Overlay Project. The contractor has completed the work in accordance with the contract, plans, and specifications. PROPOSAL DETAILS/ANALYSIS: Minnesota Paving and Materials has submitted a compensating change order to reconcile the estimated and actual quantities installed on the project. With approval of this change order the contract amount will be adjusted to reflect the actual quantities installed as a part of the project. FISCAL IMPACT: $325.16 decrease to the final construction contract amount. This compensating change order will decrease the final construction contract amount to $343,277.02. The original construction contract amount at the time of award was $299,960.18. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Compensating Change Order No. 3 for the 2020 Mill and Overlay Project. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve Compensating Change Order No. 3 for the 2020 Mill and Overlay Project, thereby decreasing the contract amount by $325.16”. ATTACHMENTS: 1. Compensating Change Order No. 3. CONTRACTCHANGEORDERFORM CHANGEORDERNO. DATE: TO: UNIT AmountofOriginalContract $ SumofAdditions/Deductionsapprovedtodate(CONo.1,CONo.2) $ ContractAmounttodate $ AmountofthisChangeOrder(ADD)(DEDUCT)(NOCHANGE)$ RevisedContractAmount $ TheContractPeriodforCompletionwillbe(UNCHANGED)(INCREASED)(DECREASED)days APPROVEDBYENGINEER:FOCUSENGINEERING APPROVEDBYCONTRACTOR DATE DATE APPROVEDBYOWNER:CITYOFLAKEELMO,MINNESOTA DATE DATE 0 ThisDocumentwillbecomeasupplementtotheContractandallprovisionswillapplyhereto.TheContractDocumentsare modifiedasfollowsuponexecutionofthisChangeOrder. BYENGINEER 299,960.18 43,642.00 343,602.18 (325.16) 343,277.02 INCREASE/(DECREASE) OMGMidwestDBAMNPaving&Materials 2020MILLANDOVERLAY PROJECTNO.2020.110 3 December15,2020 ITEM **Seeattacheditemization NETCONTRACTCHANGE ($325.16) CITYOFLAKEELMO,MINNESOTA BYBY CHANGEORDERDESCRIPTION/JUSTIFICATION: PertheprojectContractDocumentstheoriginalcontractamountandbasisofawardisestablishedusingtheestimated quantitiesforeachitemofworklistedinthebidscheduleandmultiplyingthembytheContractor’scorrespondingunitbid price.TheContractorispaidfortheactualfinalquantitiesinstalledontheprojectattheunitbidprices.  Atthecompletionoftheproject,acompensatingchangeorderispreparedtorevisetheestimatedquantitiesforeachwork itemlistedinthebidscheduletotheactualquantitiesinstalledandthecorrespondingContractAmountisrevisedaccordingly. Thiscompensatingchangeorderreflectsanetdecreasetothecontractamountby$325.16 Attachments(listdocumentssupportingchange):ItemizationofMaterials DESCRIPTIONOFPAYITEM QTY UNITPRICE FOCUSEngineering,inc.CHANGEORDERFORM Dan LoBello Digitally signed by Dan LoBello Date: 2020.12.15 16:05:13 -06'00'12.15.2020 CHANGEORDERNO. 3 2020MILLANDOVERLAY CITYOFLAKEELMO,MINNESOTA PROJECTNO.2020.110 QUANTITY UNITPRICE AMOUNT QUANTITY AMOUNT NETCHANGE AMOUNT 1 LS 1.00 $13,000.00 $13,000.00 1.00 $13,000.00 0.00 $0.00 2 LS 1.00 $6,300.00 $6,300.00 1.00 $6,300.00 0.00 $0.00 3 LF 50.00 $5.02 $251.00 280.00 $1,405.60 230.00 $1,154.60 4 EA 2.00 $245.78 $491.56 2.00 $491.56 0.00 $0.00 5 LF 364.00 $3.41 $1,241.24 0.00 $0.00 Ͳ364.00 Ͳ$1,241.24 6 SY 9,220.00 $1.45 $13,369.00 9,526.00 $13,812.70 306.00 $443.70 7 SY 13,840.00 $1.05 $14,532.00 14,076.00 $14,779.80 236.00 $247.80 8 SY 200.00 $3.00 $600.00 93.00 $279.00 Ͳ107.00 Ͳ$321.00 9 SY 10.00 $20.06 $200.60 0.00 $0.00 Ͳ10.00 Ͳ$200.60 10 LF 171.00 $8.15 $1,393.65 190.00 $1,548.50 19.00 $154.85 11 SY 9,225.00 $0.01 $92.25 9,526.00 $95.26 301.00 $3.01 12 TN 3,400.00 $61.85 $210,290.00 3,496.00 $216,227.60 96.00 $5,937.60 13 GAL 1,590.00 $0.01 $15.90 1,150.00 $11.50 Ͳ440.00 Ͳ$4.40 14 SY 200.00 $12.00 $2,400.00 103.00 $1,236.00 Ͳ97.00 Ͳ$1,164.00 15 SY 10.00 $30.10 $301.00 0.00 $0.00 Ͳ10.00 Ͳ$301.00 16 TN 390.00 $5.00 $1,950.00 39.77 $198.85 Ͳ350.23 Ͳ$1,751.15 17 EA 12.00 $184.38 $2,212.56 4.00 $737.52 Ͳ8.00 Ͳ$1,475.04 18 LF 167.00 $42.00 $7,014.00 186.00 $7,812.00 19.00 $798.00 19 EA 1.00 $12,050.00 $12,050.00 0.00 $0.00 Ͳ1.00 Ͳ$12,050.00 20 LF 220.00 $24.08 $5,297.60 232.00 $5,586.56 12.00 $288.96 21 CY 80.00 $42.43 $3,394.40 13.00 $551.59 Ͳ67.00 Ͳ$2,842.81 22 SY 740.00 $0.10 $74.00 2,310.00 $231.00 1,570.00 $157.00 23 LF 5,287.00 $0.22 $1,163.14 4,851.00 $1,067.22 Ͳ436.00 Ͳ$95.92 24 LF 10,574.00 $0.22 $2,326.28 10,058.00 $2,212.76 Ͳ516.00 Ͳ$113.52 $299,960.18 $287,585.02 Ͳ$12,375.16 TOTALSͲBASECONTRACT $299,960.18 $287,585.02 Ͳ$12,375.16 CHANGEORDERNO.1 19 LS Ͳ1.00 $12,050.00 Ͳ$12,050.00 0.00 $0.00 1.00 $12,050.00 CO1Ͳ2 ls 1.00 $45,150.00 $45,150.00 1.00 $45,150.00 0.00 $0.00 TOTALSͲCHANGEORDERNO.1 $33,100.00 $45,150.00 $12,050.00 CHANGEORDERNO.2 CO2Ͳ1 LS 1.00 $2,330.00 $2,330.00 1.00 $2,330.00 0.00 $0.00 CO2Ͳ2 LS 1.00 $2,180.00 $2,180.00 1.00 $2,180.00 0.00 $0.00 CO2Ͳ3 LF 1,856.00 $3.25 $6,032.00 1856.00 $6,032.00 0.00 $0.00 TOTALSͲCHANGEORDERNO.2 $10,542.00 $10,542.00 $0.00 TOTALSͲREVISEDCONTRACT $343,602.18 $343,277.02 Ͳ$325.16 ADJUSTVALVEBOX CONCRETECURBANDGUTTER(ALLTYPES) CORRECTFAILEDCULVERT DITCHGRADING TYPESP9.5BITUMINOUSWEARINGCOURSE(SPWEA330B) BITUMINOUSMATERIALFORTACKCOAT 2360BITUMINOUSWEARCOURSE,DRIVEWAYS INSTALLSALVAGEDBRICKPAVERS(DRIVEWAY) CLASS2AGGREGATESHOULDER ITEM DESCRIPTIONOFPAYITEM UNIT CONTRACT TOTALTODATE IMPORTANDPLACETOPSOIL(LV) SEEDING,FERTILIZERANDWOODFIBERBLANKET STRIPINGͲ4"YELLOWSTRIPING(STYLEVARIES) STRIPINGͲ4"WHITESTRIPING COMPENSATINGCHANGEORDER NO.3 MOBILIZATION TRAFFICCONTROL SILTFENCE INLETPROTECTION SAWCUTPAVEMENT(ALLTYPES) MILL2"OFEXIST.BITUMINOUSPAVEMENT,SHOULDERS MILL2.5"OFEXIST.BITUMINOUSPAVEMENT,DRIVELANES REMOVE&DISPOSEOFEXIST.BITUMINOUSPAVEMENT(DRIVEWAYS) SALVAGEBRICKPAVERS(DRIVEWAYS) REMOVE0.5"OFEX.BASEMATERIALANDRECOMPACT REMOVEANDDISPOSEOFEXISTINGCONCRETECURBANDGUTTER PATCHFAILEDSHOULDER GRADESHOULDERTODRAIN BASEBID CULVERTREPLACEMENT CORRECTFAILEDCULVERT REMOVEANDREPLACEVALVEBOXES