HomeMy WebLinkAbout#13 - Cimarron Grading PermitSTAFF REPORT DATE: 4/6/2021 Regular Agenda TO: Mayor and City Council ITEM: Cimarron Manufactured Home Community Grading Permit SUBMITTED BY: Ben Prchal, City Planner REVIEWED BY: Ken Roberts, Planning Director Jack Griffin, City Engineer SUMMARY AND ACTION REQUESTED: The City Council is being asked to consider a grading permit request from Kimley-Horn for the Cimarron Community Manufactured Home Park to remove sediment from their Rapid Infiltration Basins (RIBs). The applicant is proposing to excavate over 400 cubic yards of material, triggering the need for a public hearing, and resulting in the need for City Council approval. Furthermore the project also is within the shoreland area for Rose Lake and any movement of over 50 cubic yards of earth within the shoreland district requires a grading permit. Grading also is subject to meeting City standards for erosion control and the standards of the Valley Branch Watershed District. GENERAL INFORMATION Applicant: Kimley-Horn and Associates Inc. Property Owner: MHC Cimarron LLC, PO BOX 6115, Chicago Il, 60606. Location: Section 36 Township 029 Range 021 SW1/4-NE1/4 Request: Grading Permit Approval Grading Project Area: +/-3.5 acres Deadline for Action: Application Complete – 3/2/21 60 Day Deadline – 5/1/2021 Extension Letter Mailed – No 120 Day Deadline – NA Applicable Code: 151.017 Excavation and Grading Permits 150.270 Storm Water, Erosion, and Sediment Control 154.800 Shoreland Management Overlay District 154.103 Permits, Certificates and Licenses Article III – Environmental Performance Standards REQUEST DETAILS Kimley Horn is requesting a grading permit to excavate sediment and additional vegetative material that has accumulated within the Cimarron community Rapid Infiltration Basins (RIBs). The basins are designed to be a permeable basin which will treat and disperse wastewater. This basin acts as the final cleaning stage of the in the private wastewater cleaning process. With these basins acting as the final infiltration of water from the retention ponds adjacent to Rose Lake it is important that they stay “clear” of debris so they can operate to their best potential. The clogged basins has resulted in slow infiltration rates which has resulted in slower cycling of wastewater. To summarize the project, they will be removing 12 inches of material from the bottom of the north RIB and replace it with 12 inches of clean sand while simultaneously removing 12 inches of material form the south RIB and adding in 3.5 ft. of clean sand material. A clay liner will also be installed around the rim of the basins so that the water will properly permeate. PLANNING AND ZONING ISSUES VBWD Permit. A Valley Branch Watershed District permit will be required prior to any grading work being done. The grading permit will be conditioned on VBWD providing approval. Shoreland. With the grading taking place within the shoreland area of Rose Lake. The proposed project has been sent to the DNR for review. 2 Engineering Review. The engineering review for the Grading and Erosion Control Plan is very important as the majority of the project is related to engineering standards. The City Engineer has reviewed the project plans and their comments have been attached (Memo dated 3-29-2021). Public Comment. City Staff did receive some public comments from the neighboring property to the East. The neighbor is in favor of the correction if the plan is able to fix the issue of water seeping onto their land. However, if the maintenance of the RIBS does not fix the issue of seeping water they would like corrective action taken to connect the neighborhood to City Sewer. In response to this concern, the applicant has reached out to Staff to explain that the maintenance on the RIBs is intended to improve the situation. DRAFT CONDITIONS OF APPROVAL: Staff is recommending approval of the grading permit for Kimley-Horn to conduct grading activities within the RIB’s in the Cimarron Manufactured Home Community with the following conditions: 1. That a permit is obtained from the Valley Branch Watershed District. If a permit is not required a statement from the Watershed District stating that it does not meet the threshold to require a permit. 2. That a MPCA NPDES Permit are obtained and that all conditions of the permits are complied with. 3. That the conditions outlined in the City Engineer’s Memo dated 3-29-2021 be updated or incorporated prior to beginning work. 4. That site access to the property be limited to 10th Street North between Layton Ave. and Leeward Ave. 5. That vegetative and tree protective fencing be installed prior to grading and that the locations be staked and field inspected by the City prior to installation. 6. That construction hours be updated and limited to 7:00 AM to 7:00 PM Monday – Friday and 8:00 AM to 6:00 PM on Saturdays with no construction or grading activity on Sundays. DRAFT FINDINGS Staff is recommending the following findings with regards to the proposed grading project: 1. That the project is intended to maintain and improve the function of the Rapid Infiltration Basin(s) (RIBS) within the Cimarron Manufactured Home Park. 2. That the project will consist of excavation and grading of 2,655 cubic yards of material specifically to improve water mitigation within the RIBS. 3. That grading will be fully conducted on site with no off site impacts beyond normal maintenance activities. 4. That it is expected that the project will need to remove trees for implementation and completion of the project. 5. That the grading and erosion control plans will be updated and approved by the City Engineer so the operations on the site will comply with the City’s Storm Water, Erosion, and Sediment Control, and Tree Preservation ordinances and design standards. RECOMENDATION: Staff recommends that the City Council approve the grading permit with the conditions of approval as listed in the Staff report. Suggested motion: “Motion to approve Resolution 2021-035 which grants approval of the grading permit to remove sediment and repair the RIB(S) with the Cimarron Manufactured Home Park with conditions of approval as presented.” ATTACHMENTS: 1. Application Narrative 2. Application 3. Site Plan and Haul Route 4. Public Comment(s) 5. Resolution 2021-035 CITY OF LAKE ELMO WASHINGTON COUNTY STATE OF MINNESOTA RESOLUTION NO. 2021-035 A RESOLUTION APPROVING THE GRADING FOR THE RAPID INFILTRATION BASIN(S) WITHIN THE CIMARRON MANUFACTURED HOME COMMUNITY WHEREAS, Kimley-Horn (“Applicant”) has submitted an application to the City for a grading permit which is under review by the City but has not been approved; and WHEREAS, the Lake Elmo City Council held a public hearing on April 6, 2021 to consider the request for a grading permit; and WHEREAS, the Lake Elmo City Staff has recommended approval of the grading permit with conditions; and WHEREAS, the City Council reviewed the planning report and public comments regarding the proposed grading permit on April 6th, 2021; and NOW THEREFORE BE IT RESOLVED based upon the testimony elicited and information received, the City Council makes the following: FINDINGS 1. That the project is intended to maintain and improve the function of the Rapid Infiltration Basin(s) (RIBS) within the Cimarron Manufactured Home Park. 2. That the project will consist of excavation and grading of 2,655 cubic yards of material specifically to improve water mitigation within the RIBS. 3. That grading will be fully conducted on site with no off site impacts beyond normal maintenance activities. 4. That it is expected that the project will need to remove trees for implementation and completion of the project. 5. That the grading and erosion control plans will be updated and approved by the City Engineer so the operations on the site will comply with the City’s Storm Water, Erosion, and Sediment Control, and Tree Preservation ordinances and design standards. NOW, THEREFORE, BE IT RESOLVED, that based on the foregoing, the Lake Elmo City Council hereby approves the Applicants request for a grading permit for the RIBS at the Cimarron Manufactured Home Park with the following conditions: 1. That a permit is obtained from the Valley Branch Watershed District. If a permit is not required a statement from the Watershed District stating that it does not meet the threshold to require a permit. 2. That a MPCA NPDES Permit are obtained and that all conditions of the permits are complied with. 3. That the conditions outlined in the City Engineer’s Memo dated 3-29-2021 be updated or incorporated prior to beginning work. 4. That site access to the property be limited to 10th Street North between Layton Ave. and Leeward Ave. 5. That vegetative and tree protective fencing be installed prior to grading and that the locations be staked and field inspected by the City prior to installation. 6. That construction hours be updated and limited to 7:00 AM to 7:00 PM Monday – Friday and 8:00 AM to 6:00 PM on Saturdays with no construction or grading activity on Sundays. Passed and duly adopted this 6th day of April 2021, by the City Council of the City of Lake Elmo, Minnesota. ______________________________ Charles Cadenhead, Mayor ATTEST: _____________________________ Julie Johnson, City Clerk kimley-horn.com 767 Eustis Street, Suite 100, St Paul, MN 55114 651-393-6164 February 25, 2021 Mr. Ken Roberts Planning Director City of Lake Elmo 3880 Laverne Avenue North Lake Elmo, MN 55042 RE: Cimarron Park – RIB Rehab Grading Permit Mr. Roberts, Attached please find our Grading Permit submittal for the Rapid Infiltration Basin (RIB) Rehab project at Cimarron Park, 901 Lake Elmo Avenue North. Scope of work is to subcut 12” from the bottom of each RIB and replace with 12” of clean sand in the North RIB and 3.5’ of clean sand in the South RIB. Clay impermeable layers will be installed on the south ends of both RIBS to help with migrating water. Erosion control measures will be installed prior to start of construction and be removed after restoration and turf establishment. Rapid Infiltration basins are permeable basins, designed and operated to treat and disperse wastewater. The Cimarron RIB’s are the final cleaning stage of the wastewater treatment process. Water is pumped up from the settling ponds, adjacent Rose Lake, and drained into one of two RIB’s. Rapid infiltration of wastewater is based on a relatively high rate of infiltration into the soil followed by rapid percolation, either vertically or laterally away. The reason for this project is due to clogging that has occurred over years of settlement and weed/tree growth in the bottom of the RIB’s that has slowed infiltration rates. This project will improve the RIB percolation rates and disperse water quicker between cycles. The project is currently into the MPCA for review, so a Contractor and schedule hasn’t been developed yet. Once approved, a Contractor will be selected and hopefully be able to complete the work in April with a 3 to 4-week construction timeline, barring weather conditions. Work schedule would be Monday – Saturday, from 7am to 7pm. The attached PDF shows the haul route through the Park out to 10th Street. Once awarded the GC will have to provide us more info on where the fill will be coming from and his exact haul route to the site. Please let me know if you need anything else for review and approval of this permit. Sincerely, Alan Catchpool, P.E. Project Manager This document, together with the concepts and designs presented herein, as an instrument of service, is intended only for the specific purpose and client for which it was prepared. Reuse of and improper reliance on this document without written authorization and adaptation by Kimley-Horn and Associates, Inc. shall be without liability to Kimley-Horn and Associates, Inc.SHEET NUMBER 2018 KIMLEY-HORN AND ASSOCIATES, INC.767 EUSTIS STREET, SUITE 100, ST. PAUL, MN 55114PHONE: 651-645-4197WWW.KIMLEY-HORN.COMK:\TWC_LDEV\MHC Operating Limited Partnership\3 Design\CAD\PlanSheets\C0-COVER SHEET.dwg February 01, 2021 - 1:33pmBYREVISIONSNo.DATEPREPARED FORCOVER SHEETC000CIMARRON PARK RIBSREHABILITATIONMHC OPERATINGLIMITED PARTNERSHIPLAKE ELMOMNDATE:I HEREBY CERTIFY THAT THIS PLAN,SPECIFICATION OR REPORT WAS PREPARED BYME OR UNDER MY DIRECT SUPERVISION ANDTHAT I AM A DULY LICENSED PROFESSIONALENGINEER UNDER THE LAWS OF THE STATE OFMINNESOTA.MNLIC. NO.ALAN CATCHPOOL, P.E.02/01/202147969DATECHECKED BYSCALEDESIGNED BYDRAWN BYKHA PROJECT16010800002/01/2021AS SHOWNEISEISALCNORTH VICINITY N.T.S. SITE LAKE ELMO, WASHINGTON COUNTY, MN 1.CONTRACTOR SHALL CONFIRM THAT THE EXISTING CONDITIONS FOR THE SITE MATCH WHAT IS SHOWN ON THE DRAWINGS INCLUDED PRIOR TO CONSTRUCTION. 2.IF REPRODUCED, THE SCALES SHOWN ON THESE PLANS ARE BASED ON A 22x34 SHEET. 3.ALL NECESSARY INSPECTIONS AND/OR CERTIFICATIONS REQUIRED BY CODES AND/OR UTILITY SERVICES COMPANIES SHALL BE PERFORMED PRIOR TO ANNOUNCED BUILDING POSSESSION AND THE FINAL CONNECTION OF SERVICES. 4.ALL GENERAL CONTRACTOR WORK TO BE COMPLETED (EARTHWORK, FINAL UTILITIES, AND FINAL GRADING) BY THE MILESTONE DATE IN PROJECT DOCUMENTS. NOTES: GEOTECHNICAL ENGINEER TERRACON 13400 15TH AVE NORTH PLYMOTH, MN TELEPHONE: (763) 489-3100 CONTACT: JAKE WOTCZAK, P.E. PROJECT TEAM: SURVEYOR CORNERSTONE LAND SURVEYING, INC. 1970 NORTHWESTERN AVE, SUITE #200 STILLWATER, MN 55082 TELEPHONE: (651) 275-8969 CONTACT: DANIEL L. THURMES, R.L.S ENGINEER KIMLEY-HORN AND ASSOCIATES, INC. PREPARED BY: ALAN CATCHPOOL, P.E. 767 EUSTIS STREET, SUITE 100 ST. PAUL, MN 55114 TELEPHONE (651) 645-4197 OWNER / DEVELOPER MHC OPERATING LIMITED PARTNERSHIP 2 N RIVERSIDE PLZ, SUITE #800 CHICAGO, IL 60606 TELEPHONE: (312) 279-1400 CONTACT: ANDY BOSWELL CIMARRON PARK RIBS REHABILITATION FOR REHABILITATION PLANS Know what'sbelow. before you dig.Call 901 LAKE ELMO AVENUE NORTH DRAWING INDEX Sheet Number Sheet Title C000 COVER SHEET C100 GENERAL NOTES C300 EROSION AND SEDIMENT CONTROL PLAN C301 EROSION AND SEDIMENT CONTROL DETAILS C302 SWPPP C400 GRADING PLAN - RIB C401 CROSS SECTIONS - RIB This document, together with the concepts and designs presented herein, as an instrument of service, is intended only for the specific purpose and client for which it was prepared. Reuse of and improper reliance on this document without written authorization and adaptation by Kimley-Horn and Associates, Inc. shall be without liability to Kimley-Horn and Associates, Inc.SHEET NUMBER 2018 KIMLEY-HORN AND ASSOCIATES, INC.767 EUSTIS STREET, SUITE 100, ST. PAUL, MN 55114PHONE: 651-645-4197WWW.KIMLEY-HORN.COMK:\TWC_LDEV\MHC Operating Limited Partnership\3 Design\CAD\PlanSheets\C1-GENERAL NOTES.dwg February 01, 2021 - 1:33pmBYREVISIONSNo.DATEPREPARED FORGENERAL NOTESC100CIMARRON PARKRIBS REHABILITATIONMHC OPERATINGLIMITED PARTNERSHIPLAKE ELMOMNDATE:I HEREBY CERTIFY THAT THIS PLAN,SPECIFICATION OR REPORT WAS PREPARED BYME OR UNDER MY DIRECT SUPERVISION ANDTHAT I AM A DULY LICENSED PROFESSIONALENGINEER UNDER THE LAWS OF THE STATE OFMINNESOTA.MNLIC. NO.ALAN L. CATCHPOOL02/01/202147969DATECHECKED BYSCALEDESIGNED BYDRAWN BYKHA PROJECT16010800002/01/2021AS SHOWNEISEISALCGENERAL CONSTRUCTION NOTES 1.THE CONTRACTOR AND SUBCONTRACTORS SHALL OBTAIN A COPY OF THE MN DEPARTMENT OF TRANSPORTATION "STANDARD SPECIFICATIONS FOR CONSTRUCTION" (LATEST EDITION) AND BECOME FAMILIAR WITH THE CONTENTS PRIOR TO COMMENCING WORK, AND, UNLESS OTHERWISE NOTED, ALL WORK SHALL CONFORM AS APPLICABLE TO THESE STANDARDS AND SPECIFICATIONS. 2.THE CONTRACTOR SHALL BE RESPONSIBLE FOR FURNISHING ALL MATERIAL AND LABOR TO CONSTRUCT THE FACILITY AS SHOWN AND DESCRIBED IN THE CONSTRUCTION DOCUMENTS IN ACCORDANCE WITH THE APPROPRIATE APPROVING AUTHORITIES, SPECIFICATIONS AND REQUIREMENTS. CONTRACTOR SHALL CLEAR AND GRUB ALL AREAS UNLESS OTHERWISE INDICATED, REMOVING TREES, STUMPS, ROOTS, MUCK, EXISTING PAVEMENT AND ALL OTHER DELETERIOUS MATERIAL. 3.THE EXISTING SUBSURFACE UTILITY INFORMATION IN THIS PLAN IS QUALITY LEVEL "D" UNLESS OTHERWISE NOTED. THIS QUALITY LEVEL WAS DETERMINED ACCORDING TO THE GUIDELINES OF CI/ACSE 38/02, ENTITLED STANDARD GUIDELINES FOR THE COLLECTION AND DEPICTION OF SUBSURFACE QUALITY DATA BY THE FHA. EXISTING UTILITIES SHOWN ARE LOCATED ACCORDING TO THE INFORMATION AVAILABLE TO THE ENGINEER AT THE TIME OF THE TOPOGRAPHIC SURVEY AND HAVE NOT BEEN INDEPENDENTLY VERIFIED BY THE OWNER OR THE ENGINEER. GUARANTEE IS NOT MADE THAT ALL EXISTING UNDERGROUND UTILITIES ARE SHOWN OR THAT THE LOCATION OF THOSE SHOWN ARE ENTIRELY ACCURATE. FINDING THE ACTUAL LOCATION OF ANY EXISTING UTILITIES IS THE CONTRACTOR'S RESPONSIBILITY AND SHALL BE DONE BEFORE COMMENCING ANY WORK IN THE VICINITY. FURTHERMORE, THE CONTRACTOR SHALL BE FULLY RESPONSIBLE FOR ANY AND ALL DAMAGES DUE TO THE CONTRACTOR'S FAILURE TO EXACTLY LOCATE AND PRESERVE ANY AND ALL UNDERGROUND UTILITIES. THE OWNER OR ENGINEER WILL ASSUME NO LIABILITY FOR ANY DAMAGES SUSTAINED OR COST INCURRED BECAUSE OF THE OPERATIONS IN THE VICINITY OF EXISTING UTILITIES OR STRUCTURES, NOR FOR TEMPORARY BRACING AND SHORING OF SAME. IF IT IS NECESSARY TO SHORE, BRACE, SWING OR RELOCATE A UTILITY, THE UTILITY COMPANY OR DEPARTMENT AFFECTED SHALL BE CONTACTED AND THEIR PERMISSION OBTAINED REGARDING THE METHOD TO USE FOR SUCH WORK. 4.IT IS THE CONTRACTOR'S RESPONSIBILITY TO CONTACT THE VARIOUS UTILITY COMPANIES WHICH MAY HAVE BURIED OR AERIAL UTILITIES WITHIN OR NEAR THE CONSTRUCTION AREA BEFORE COMMENCING WORK. THE CONTRACTOR SHALL PROVIDE 48 HOURS MINIMUM NOTICE TO ALL UTILITY COMPANIES PRIOR TO BEGINNING CONSTRUCTION. 5.THE CONTRACTOR SHALL BE RESPONSIBLE FOR OBTAINING ALL REQUIRED CONSTRUCTION PERMITS AND BONDS IF REQUIRED PRIOR TO CONSTRUCTION. 6.THE CONTRACTOR SHALL HAVE AVAILABLE AT THE JOB SITE AT ALL TIMES ONE COPY OF THE CONSTRUCTION DOCUMENTS INCLUDING PLANS, SPECIFICATIONS, GEOTECHNICAL REPORT AND SPECIAL CONDITIONS AND COPIES OF ANY REQUIRED CONSTRUCTION PERMITS. 7.ANY DISCREPANCIES ON THE DRAWINGS SHALL BE IMMEDIATELY BROUGHT TO THE ATTENTION OF THE OWNER AND ENGINEER BEFORE COMMENCING WORK. NO FIELD CHANGES OR DEVIATIONS FROM DESIGN ARE TO BE MADE WITHOUT PRIOR APPROVAL OF THE OWNER AND NOTIFICATION TO THE ENGINEER. 8.ALL COPIES OF COMPACTION, CONCRETE AND OTHER REQUIRED TEST RESULTS ARE TO BE SENT TO THE OWNER DIRECTLY FROM THE TESTING AGENCY. 9.THE CONTRACTOR SHALL BE RESPONSIBLE FOR DOCUMENTING AND MAINTAINING AS-BUILT INFORMATION WHICH SHALL BE RECORDED AS CONSTRUCTION PROGRESSES OR AT THE COMPLETION OF APPROPRIATE CONSTRUCTION INTERVALS AND SHALL BE RESPONSIBLE FOR PROVIDING AS-BUILT DRAWINGS TO THE OWNER FOR THE PURPOSE OF CERTIFICATION TO JURISDICTIONAL AGENCIES AS REQUIRED. ALL AS-BUILT DATA SHALL BE COLLECTED BY A STATE OF MN PROFESSIONAL LAND SURVEYOR WHOSE SERVICES ARE ENGAGED BY THE CONTRACTOR. 10.ANY WELLS DISCOVERED ON SITE THAT WILL HAVE NO USE MUST BE PLUGGED BY A LICENSED WELL DRILLING CONTRACTOR IN A MANNER APPROVED BY ALL JURISDICTIONAL AGENCIES. CONTRACTOR SHALL BE RESPONSIBLE FOR OBTAINING ANY WELL ABANDONMENT PERMITS REQUIRED. 11.ANY WELL DISCOVERED DURING EARTH MOVING OR EXCAVATION SHALL BE REPORTED TO THE APPROPRIATE JURISDICTIONAL AGENCIES WITHIN 24 HOURS AFTER DISCOVERY IS MADE. 12.THE CONTRACTOR SHALL BE RESPONSIBLE FOR VERIFYING THAT THE PROPOSED IMPROVEMENTS SHOWN ON THE PLANS DO NOT CONFLICT WITH ANY KNOWN EXISTING OR OTHER PROPOSED IMPROVEMENTS. IF ANY CONFLICTS ARE DISCOVERED, THE CONTRACTOR SHALL NOTIFY THE OWNER PRIOR TO INSTALLATION OF ANY PORTION OF THE SITE WORK THAT WOULD BE AFFECTED. FAILURE TO NOTIFY OWNER OF AN IDENTIFIABLE CONFLICT PRIOR TO PROCEEDING WITH INSTALLATION RELIEVES OWNER OF ANY OBLIGATION TO PAY FOR A RELATED CHANGE ORDER. 13.SHOULD CONTRACTOR ENCOUNTER ANY DEBRIS LADEN SOIL, STRUCTURES NOT IDENTIFIED IN THE DOCUMENTS, OR OTHER SOURCE OF POTENTIAL CONTAMINATION, THEY SHALL IMMEDIATELY CONTACT THE ENGINEER AND OWNER. TYPICAL OWNER/ENGINEER OBSERVATIONS CONTRACTOR SHALL NOTIFY OWNER AND/OR ENGINEER 48 HOURS IN ADVANCE OF THE FOLLOWING ACTIVITIES: - PRE-CONSTRUCTION MEETING, SUBGRADE PREPARATION, BASE INSTALLATION ASPHALT INSTALLATION, UNDERGROUND PIPING AND UTILITIES INSTALLATION, INSTALLATION OF STRUCTURES, CHECK VALVES, HYDRANTS, METERS, ETC., SIDEWALK INSTALLATION, CONNECTIONS TO WATER AND SEWER MAINS, TESTS OF UTILITIES 3RD PARTY TEST REPORTS REQ'D TEST REPORTS REQUIRED FOR CLOSE OUT INCLUDE, BUT ARE NOT LIMITED TO: - DENSITY TEST REPORTS - BACTERIOLOGICAL TESTS OF WATER SYSTEM - PRESSURE TEST OF WATER/SEWER - LEAK TESTS ON SEWER SYSTEM AND GREASE TRAPS - ANY OTHER TESTING REQUIRED BY THE AGENCY/MUNICIPALITY WATER STORM SEWER & SANITARY SEWER NOTES 1.THE CONTRACTOR SHALL CONSTRUCT GRAVITY SEWER LATERALS, MANHOLES, GRAVITY SEWER LINES, AND DOMESTIC WATER AND FIRE PROTECTION SYSTEM AS SHOWN ON THESE PLANS. THE CONTRACTOR SHALL FURNISH ALL NECESSARY MATERIALS, EQUIPMENT, MACHINERY, TOOLS, MEANS OF TRANSPORTATION AND LABOR NECESSARY TO COMPLETE THE WORK IN FULL AND COMPLETE ACCORDANCE WITH THE SHOWN, DESCRIBED AND REASONABLY INTENDED REQUIREMENTS OF THE CONTRACT DOCUMENTS AND JURISDICTIONAL AGENCY REQUIREMENTS. IN THE EVENT THAT THE CONTRACT DOCUMENTS AND THE JURISDICTIONAL AGENCY REQUIREMENTS ARE NOT IN AGREEMENT, THE MOST STRINGENT SHALL GOVERN. 2.ALL EXISTING UNDERGROUND UTILITY LOCATIONS SHOWN ARE APPROXIMATE. THE CONTRACTOR SHALL COMPLY WITH ALL REQUIREMENTS FOR UTILITY LOCATION AND COORDINATION IN ACCORDANCE WITH THE NOTES CONTAINED IN THE GENERAL CONSTRUCTION SECTION OF THIS SHEET. 3.THE CONTRACTOR SHALL RESTORE ALL DISTURBED VEGETATION IN KIND, UNLESS SHOWN OTHERWISE. 4.DEFLECTION OF PIPE JOINTS AND CURVATURE OF PIPE SHALL NOT EXCEED THE MANUFACTURER'S SPECIFICATIONS. SECURELY CLOSE ALL OPEN ENDS OF PIPE AND FITTINGS WITH A WATERTIGHT PLUG WHEN WORK IS NOT IN PROGRESS. THE INTERIOR OF ALL PIPES SHALL BE CLEAN AND JOINT SURFACES WIPED CLEAN AND DRY AFTER THE PIPE HAS BEEN LOWERED INTO THE TRENCH. VALVES SHALL BE PLUMB AND LOCATED ACCORDING TO THE PLANS. 5.ALL PIPE AND FITTINGS SHALL BE CAREFULLY STORED FOLLOWING MANUFACTURER'S RECOMMENDATIONS. CARE SHALL BE TAKEN TO AVOID DAMAGE TO THE COATING OR LINING IN ANY D.I. PIPE FITTINGS. ANY PIPE OR FITTING WHICH IS DAMAGED OR WHICH HAS FLAWS OR IMPERFECTIONS WHICH, IN THE OPINION OF THE ENGINEER OR OWNER, RENDERS IT UNFIT FOR USE, SHALL NOT BE USED. ANY PIPE NOT SATISFACTORY FOR USE SHALL BE CLEARLY MARKED AND IMMEDIATELY REMOVED FROM THE JOB SITE, AND SHALL BE REPLACED AT THE CONTRACTOR'S EXPENSE. 6.WATER FOR FIRE FIGHTING SHALL BE MADE AVAILABLE FOR USE BY THE CONTRACTOR PRIOR TO COMBUSTIBLES BEING BROUGHT ON SITE. 7.ALL UTILITY AND STORM DRAIN TRENCHES LOCATED UNDER AREAS TO RECEIVE PAVING SHALL BE COMPLETELY BACK FILLED IN ACCORDANCE WITH THE GOVERNING JURISDICTIONAL AGENCY'S SPECIFICATIONS. IN THE EVENT THAT THE CONTRACT DOCUMENTS AND THE JURISDICTIONAL AGENCY REQUIREMENTS ARE NOT IN AGREEMENT, THE MOST STRINGENT SHALL GOVERN. 8.UNDERGROUND LINES SHALL BE SURVEYED BY A STATE OF MN PROFESSIONAL LAND SURVEYOR PRIOR TO BACK FILLING. 9.CONTRACTOR SHALL PERFORM, AT HIS OWN EXPENSE, ANY AND ALL TESTS REQUIRED BY THE SPECIFICATIONS AND/OR ANY AGENCY HAVING JURISDICTION. THESE TESTS MAY INCLUDE, BUT MAY NOT BE LIMITED TO, INFILTRATION AND EXFILTRATION, TELEVISION INSPECTION AND A MANDREL TEST ON GRAVITY SEWER. A COPY OF THE TEST RESULTS SHALL BE PROVIDED TO THE UTILITY PROVIDER, OWNER AND JURISDICTIONAL AGENCY AS REQUIRED. 10.CONTRACTOR SHALL PROVIDE FOR A MINIMUM HORIZONTAL CLEARANCE OF 10' AND A VERTICAL CLEARANCE OF 18" BETWEEN WATER AND SANITARY SEWER MANHOLES AND LINES. 11.IF ANY EXISTING STRUCTURES TO REMAIN ARE DAMAGED DURING CONSTRUCTION IT SHALL BE THE CONTRACTORS RESPONSIBILITY TO REPAIR AND/OR REPLACE THE EXISTING STRUCTURE AS NECESSARY TO RETURN IT TO EXISTING CONDITIONS OR BETTER. 12.ALL STORM PIPE ENTERING STRUCTURES SHALL BE GROUTED TO ASSURE CONNECTION AT STRUCTURE IS WATERTIGHT UNLESS OTHERWISE STATED BY CITY AND STATE DESIGN STANDARDS AND SPECIFICATIONS. 13.UNLESS OTHERWISE STATED IN CITY AND STATE DESIGN STANDARDS AND SPECIFICATIONS, ALL STORM SEWER MANHOLES IN PAVED AREAS SHALL BE FLUSH WITH PAVEMENT, AND SHALL HAVE TRAFFIC BEARING RING & COVERS. MANHOLES IN UNPAVED AREAS SHALL BE 6" ABOVE FINISH GRADE. LIDS SHALL BE LABELED "STORM SEWER". EXISTING CASTINGS AND STRUCTURES WITHIN PROJECT LIMITS SHALL BE ADJUSTED TO MEET THESE CONDITIONS AND THE PROPOSED FINISHED GRADE. 14.TOPOGRAPHIC INFORMATION IS TAKEN FROM A TOPOGRAPHIC SURVEY BY LAND SURVEYORS. IF THE CONTRACTOR DOES NOT ACCEPT EXISTING TOPOGRAPHY AS SHOWN ON THE PLANS, WITHOUT EXCEPTION, THEN THE CONTRACTOR SHALL SUPPLY, AT THEIR EXPENSE, A TOPOGRAPHIC SURVEY BY A REGISTERED LAND SURVEYOR TO THE OWNER FOR REVIEW. 15.CONSTRUCTION SHALL COMPLY WITH ALL APPLICABLE GOVERNING CODES AND BE CONSTRUCTED TO SAME. 16.ALL STORM STRUCTURES SHALL HAVE A SMOOTH UNIFORM POURED MORTAR FROM INVERT IN TO INVERT OUT. 17.ROOF DRAINS SHALL BE CONNECTED TO STORM SEWER BY PREFABRICATED WYES OR AT STORM STRUCTURES. ROOF DRAINS AND TRUCK WELL DRAIN SHALL RUN AT A MINIMUM 1% SLOPE, UNLESS NOTED OTHERWISE, AND TIE IN AT THE CENTERLINE OF THE STORM MAIN. 18.ALL ROOF AND SANITARY SEWER DRAINS SHALL BE INSULATED IF 7' OF COVER CANNOT BE PROVIDED. 19.THE CONTRACTOR SHALL PROTECT EXISTING UNDERGROUND UTILITIES AND APPURTENANCES THAT ARE TO REMAIN FROM DAMAGE DURING CONSTRUCTION OPERATIONS. 20.THE LOCATION OF EXISTING UTILITIES, STORM DRAINAGE STRUCTURES AND OTHER ABOVE AND BELOW-GRADE IMPROVEMENTS ARE APPROXIMATE AS SHOWN. IT IS THE CONTRACTOR'S RESPONSIBILITY TO DETERMINE THE EXACT LOCATION, SIZE AND INVERT ELEVATIONS OF EACH PRIOR TO THE START OF CONSTRUCTION. 21.A MINIMUM OF 5' SEPARATION IS REQUIRED BETWEEN UTILITIES AND TREES UNLESS A ROOT BARRIER IS UTILIZED. 22.GAS, PHONE AND ELECTRIC SERVICES SHOWN FOR INFORMATIONAL PURPOSES ONLY. DRY UTILITY COMPANIES MAY ALTER THE DESIGN LAYOUT DURING THEIR REVIEW. CONTRACTOR TO COORDINATE FINAL DESIGN AND INSTALLATION WITH UTILITY COMPANIES. 23.COORDINATE UTILITY INSTALLATION WITH IRRIGATION DESIGN AND INSTALLATION. 24.ALL DIMENSIONS ARE TO FLOW LINE OF CURB UNLESS OTHERWISE NOTED. PERIMETER WALL DIMENSIONS ARE TO INSIDE WALL FACE. REFERENCE ARCHITECTURAL PLANS FOR EXACT WALL WIDTH AND SPECIFICATIONS. 25.REFERENCE ARCHITECTURAL PLANS (BY OTHERS). FOR EXACT BUILDING DIMENSIONS, AND MATERIALS SPECIFICATIONS. 26.REFERENCE M.E.P. PLANS (BY OTHERS) FOR MECHANICAL EQUIPMENT DIMENSIONS AND SPECIFICATIONS. 27.CONTRACTOR SHALL REFERENCE STRUCTURAL PLANS (BY OTHERS) FOR MECHANICAL EQUIPMENT DIMENSIONS AND PAD PREPARATION SPECIFICATIONS. 28.CONTRACTOR SHALL REFERENCE M.E.P PLANS (BY OTHERS) FOR LIGHT POLE WIRING. GRADING AND DRAINAGE NOTES 1.GENERAL CONTRACTOR AND ALL SUBCONTRACTORS SHALL VERIFY THE SUITABILITY OF ALL EXISTING AND PROPOSED SITE CONDITIONS INCLUDING GRADES AND DIMENSIONS BEFORE START OF CONSTRUCTION. THE ENGINEER SHALL BE NOTIFIED IMMEDIATELY OF ANY DISCREPANCIES. 2.THE CONTRACTOR SHALL GRADE THE SITE TO THE ELEVATIONS INDICATED AND SHALL ADJUST BMP'S AS NECESSARY AND REGRADE WASHOUTS WHERE THEY OCCUR AFTER EVERY RAINFALL UNTIL A GRASS STAND IS WELL ESTABLISHED OR ADEQUATE STABILIZATION OCCURS. 3.CONTRACTOR SHALL ENSURE THERE IS POSITIVE DRAINAGE FROM THE PROPOSED BUILDINGS SO THAT SURFACE RUNOFF WILL DRAIN BY GRAVITY TO NEW OR EXISTING DRAINAGE OUTLETS. CONTRACTOR SHALL ENSURE NO PONDING OCCURS IN PAVED AREAS AND SHALL NOTIFY ENGINEER IF ANY GRADING DISCREPANCIES ARE FOUND IN THE EXISTING AND PROPOSED GRADES PRIOR TO PLACEMENT OF PAVEMENT OR UTILITIES. 4.CONTRACTOR SHALL PROTECT ALL MANHOLE COVERS, VALVE COVERS, VAULT LIDS, FIRE HYDRANTS, POWER POLES, GUY WIRES, AND TELEPHONE BOXES THAT ARE TO REMAIN IN PLACE AND UNDISTURBED DURING CONSTRUCTION. EXISTING CASTINGS AND STRUCTURES TO REMAIN SHALL BE ADJUSTED TO MATCH THE PROPOSED FINISHED GRADES. 5.BACKFILL FOR UTILITY LINES SHALL BE PLACED PER DETAILS, STANDARDS, AND SPECIFICATIONS SO THAT THE UTILITY WILL BE STABLE. WHERE UTILITY LINES CROSS THE PARKING LOT, THE TOP 6 INCHES SHALL BE COMPACTED SIMILARLY TO THE REMAINDER OF THE LOT. UTILITY DITCHES SHALL BE VISUALLY INSPECTED DURING THE EXCAVATION PROCESS TO ENSURE THAT UNDESIRABLE FILL IS NOT USED. 6.CONTRACTOR IS RESPONSIBLE FOR THE REMOVAL AND REPLACEMENT OF 4" OF TOPSOIL AT COMPLETION OF WORK. ALL UNPAVED AREAS IN EXISTING RIGHTS-OF-WAY DISTURBED BY CONSTRUCTION SHALL BE REGRADED AND SODDED. 7.AFTER PLACEMENT OF SUBGRADE AND PRIOR TO PLACEMENT OF PAVEMENT, CONTRACTOR SHALL TEST AND OBSERVE PAVEMENT AREAS FOR EVIDENCE OF PONDING. ALL AREAS SHALL ADEQUATELY DRAIN TOWARDS THE INTENDED STRUCTURE TO CONVEY STORM RUNOFF. CONTRACTOR SHALL IMMEDIATELY NOTIFY OWNER AND ENGINEER IF ANY DISCREPANCIES ARE DISCOVERED. 8.WHERE EXISTING PAVEMENT IS INDICATED TO BE REMOVED AND REPLACED, THE CONTRACTOR SHALL SAW CUT FULL DEPTH FOR A SMOOTH AND STRAIGHT JOINT AND REPLACE THE PAVEMENT WITH THE SAME TYPE AND DEPTH OF MATERIAL AS EXISTING OR AS INDICATED. 9.THE CONTRACTOR SHALL INSTALL PROTECTION OVER ALL DRAINAGE STRUCTURES FOR THE DURATION OF CONSTRUCTION AND UNTIL ACCEPTANCE OF THE PROJECT BY THE OWNER. ALL DRAINAGE STRUCTURES SHALL BE CLEANED OF DEBRIS AS REQUIRED DURING AND AT THE END OF CONSTRUCTION TO PROVIDE POSITIVE DRAINAGE FLOWS. 10.IF DEWATERING IS REQUIRED, THE CONTRACTOR SHALL OBTAIN ANY APPLICABLE REQUIRED PERMITS. THE CONTRACTOR IS TO COORDINATE WITH THE OWNER AND THE DESIGN ENGINEER PRIOR TO ANY EXCAVATION. 11.FIELD DENSITY TESTS SHALL BE TAKEN AT INTERVALS IN ACCORDANCE WITH THE LOCAL JURISDICTIONAL AGENCY OR TO MN/DOT STANDARDS. IN THE EVENT THAT THE CONTRACT DOCUMENTS AND THE JURISDICTIONAL AGENCY REQUIREMENTS ARE NOT IN AGREEMENT, THE MOST STRINGENT SHALL GOVERN. 12.ALL SLOPES AND AREAS DISTURBED BY CONSTRUCTION SHALL BE GRADED AS PER PLANS. THE AREAS SHALL THEN BE SODDED OR SEEDED AS SPECIFIED IN THE PLANS, FERTILIZED, MULCHED, WATERED AND MAINTAINED UNTIL HARDY GRASS GROWTH IS ESTABLISHED IN ALL AREAS. ANY AREAS DISTURBED FOR ANY REASON PRIOR TO FINAL ACCEPTANCE OF THE JOB SHALL BE CORRECTED BY THE CONTRACTOR AT NO ADDITIONAL COST TO THE OWNER. ALL EARTHEN AREAS WILL BE SODDED OR SEEDED AND MULCHED AS SHOWN ON THE LANDSCAPING PLAN. 13.THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE CONTROL OF DUST AND DIRT RISING AND SCATTERING IN THE AIR DURING CONSTRUCTION AND SHALL PROVIDE WATER SPRINKLING OR OTHER SUITABLE METHODS OF CONTROL. THE CONTRACTOR SHALL COMPLY WITH ALL GOVERNING REGULATIONS PERTAINING TO ENVIRONMENTAL PROTECTION. 14.SOD, WHERE CALLED FOR, MUST BE INSTALLED AND MAINTAINED ON EXPOSED SLOPES WITHIN 48 HOURS OF COMPLETING FINAL GRADING, AND AT ANY OTHER TIME AS NECESSARY, TO PREVENT EROSION, SEDIMENTATION OR TURBID DISCHARGES. 15.THE CONTRACTOR SHALL ENSURE THAT LANDSCAPE ISLAND PLANTING AREAS AND OTHER PLANTING AREAS ARE NOT COMPACTED AND DO NOT CONTAIN ROAD BASE MATERIALS. THE CONTRACTOR SHALL ALSO EXCAVATE AND REMOVE ALL UNDESIRABLE MATERIAL FROM ALL AREAS ON THE SITE TO BE PLANTED AND PROPERLY DISPOSED OF IN A LEGAL MANNER. 16.THE CONTRACTOR SHALL INSTALL ALL UNDERGROUND STORM WATER PIPING PER MANUFACTURER'S RECOMMENDATIONS AND MN/DOT SPECIFICATION. 17.ALL CONCRETE/ASPHALT SHALL BE INSTALLED PER GEOTECH REPORT, CITY OF LAKE ELMO AND MN/DOT SPECIFICATIONS. 18.SPOT ELEVATIONS ARE TO FLOWLINE OF CURB UNLESS OTHERWISE NOTED. 19.LIMITS OF CONSTRUCTION ARE TO THE PROPERTY LINE UNLESS OTHERWISE SPECIFIED ON THE PLAN. 20.IMMEDIATELY REPORT TO THE OWNER ANY DISCREPANCIES FOUND BETWEEN ACTUAL FIELD CONDITIONS AND CONSTRUCTION DOCUMENTS. 21.THE CONTRACTOR IS RESPONSIBLE FOR LOCATING AND PROTECTING EXISTING UTILITIES, AND SHALL REPAIR ALL DAMAGE TO EXISTING UTILITIES THAT OCCUR DURING CONSTRUCTION WITHOUT COMPENSATION. 22.BLEND NEW EARTHWORK SMOOTHLY TO TRANSITION BACK TO EXISTING GRADE. 23.ALL PROPOSED GRADES ONSITE SHALL BE 3:1 OR FLATTER UNLESS OTHERWISE INDICATED ON THE PLANS. ANY SLOPES STEEPER THAN 4:1 REQUIRE EROSION AND SEDIMENT CONTROL BLANKET. 24.ADHERE TO ALL TERMS AND CONDITIONS AS NECESSARY IN THE GENERAL N.P.D.E.S. PERMIT AND STORMWATER POLLUTION PREVENTION PLAN FOR STORMWATER DISCHARGE ASSOCIATED WITH CONSTRUCTION ACTIVITIES. 25.ADJUST AND/OR CUT EXISTING PAVEMENT AS NECESSARY TO ASSURE A SMOOTH FIT AND CONTINUOUS GRADE. 26.CONTRACTOR SHALL ENSURE MINIMUM GRADES ARE MET WITHIN PAVED AREAS, 1.2% FOR ASPHALT PAVING AND 0.6% FOR CONCRETE PAVING. EROSION CONTROL NOTES 1.THE STORM WATER POLLUTION PREVENTION PLAN ("SWPPP") IS COMPRISED OF THE EROSION CONTROL PLAN, THE STANDARD DETAILS, THE PLAN NARRATIVE, ATTACHMENTS INCLUDED IN THE SPECIFICATIONS OF THE SWPPP, PLUS THE PERMIT AND ALL SUBSEQUENT REPORTS AND RELATED DOCUMENTS. 2.ALL CONTRACTORS AND SUBCONTRACTORS INVOLVED WITH STORM WATER POLLUTION PREVENTION SHALL OBTAIN A COPY OF THE STORM WATER POLLUTION PREVENTION PLAN AND THE STATE OF MN NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM GENERAL PERMIT (NPDES PERMIT) AND BECOME FAMILIAR WITH THEIR CONTENTS. 3.BEST MANAGEMENT PRACTICES (BMP'S) AND CONTROLS SHALL CONFORM TO FEDERAL, STATE, OR LOCAL REQUIREMENTS OR MANUAL OF PRACTICE, AS APPLICABLE. THE CONTRACTOR SHALL IMPLEMENT ADDITIONAL CONTROLS AS DIRECTED BY THE PERMITTING AGENCY OR OWNER. 4.SITE ENTRY AND EXIT LOCATIONS SHALL BE MAINTAINED IN A CONDITION THAT WILL PREVENT THE TRACKING OR FLOWING OF SEDIMENT ONTO PUBLIC ROADWAYS. ALL SEDIMENT SPILLED, DROPPED, WASHED, OR TRACKED ON A PUBLIC ROADWAY MUST BE REMOVED IMMEDIATELY. WHEN WASHING IS REQUIRED TO REMOVE SEDIMENT PRIOR TO ENTRANCE ONTO A PUBLIC ROADWAY, IT SHALL BE DONE IN AN AREA STABILIZED WITH CRUSHED STONE WHICH DRAINS INTO AN APPROVED SEDIMENT BASIN. ALL FINES IMPOSED FOR DISCHARGING SEDIMENT ONTO PUBLIC AREAS SHALL BE PAID BY THE CONTRACTOR. 5.TEMPORARY SEEDING OR OTHER APPROVED METHODS OF STABILIZATION SHALL BE INITIATED WITHIN 7 DAYS OF THE LAST DISTURBANCE ON ANY AREA OF THE SITE. 6.THE CONTRACTOR SHALL MINIMIZE CLEARING TO THE MAXIMUM EXTENT PRACTICAL OR AS REQUIRED BY THE GENERAL PERMIT. 7.CONTRACTOR SHALL DENOTE ON PLAN THE TEMPORARY PARKING AND STORAGE AREA WHICH SHALL ALSO BE USED AS THE EQUIPMENT MAINTENANCE AND CLEANING AREA, EMPLOYEE PARKING AREA, AND AREA FOR LOCATING PORTABLE FACILITIES, OFFICE TRAILERS, AND TOILET FACILITIES. 8.ALL WASH WATER (CONCRETE TRUCKS, VEHICLE CLEANING, EQUIPMENT CLEANING, ETC.) SHALL BE DETAINED AND PROPERLY TREATED OR DISPOSED. 9.SUFFICIENT OIL AND GREASE ABSORBING MATERIALS AND FLOTATION BOOMS SHALL BE MAINTAINED ON SITE OR READILY AVAILABLE TO CONTAIN AND CLEAN-UP FUEL OR CHEMICAL SPILLS AND LEAKS. 10.THE CONTRACTOR SHALL BE RESPONSIBLE FOR DUST CONTROL ON SITE. THE USE OF MOTOR OILS AND OTHER PETROLEUM BASED OR TOXIC LIQUIDS FOR DUST SUPPRESSION OPERATIONS IS PROHIBITED. 11.RUBBISH, TRASH, GARBAGE, LITTER, OR OTHER SUCH MATERIALS SHALL BE DEPOSITED INTO SEALED CONTAINERS. MATERIALS SHALL BE PREVENTED FROM LEAVING THE PREMISES THROUGH THE ACTION OF WIND OR STORM WATER DISCHARGE INTO DRAINAGE DITCHES OR WATERS OF THE STATE. 12.ALL STORM WATER POLLUTION PREVENTION MEASURES PRESENTED ON THE PLAN SHALL BE INITIATED AS SOON AS IS PRACTICABLE. 13.ALL STAGING AREAS, STOCKPILES, SPOILS, ETC. SHALL BE LOCATED SUCH THAT THEY WILL NOT ADVERSELY AFFECT STORM WATER QUALITY. OTHERWISE, COVERING OR ENCIRCLING THESE AREAS WITH SOME PROTECTIVE MEASURE WILL BE NECESSARY. 14.CONTRACTOR SHALL BE RESPONSIBLE FOR RE-ESTABLISHING ANY EROSION CONTROL DEVICE WHICH THEY DISTURB. EACH CONTRACTOR SHALL NOTIFY THE OWNER'S REPRESENTATIVE OF ANY DEFICIENCIES IN THE ESTABLISHED EROSION CONTROL MEASURES THAT MAY LEAD TO UNAUTHORIZED DISCHARGE OR STORM WATER POLLUTION, SEDIMENTATION, OR OTHER POLLUTANTS. UNAUTHORIZED POLLUTANTS INCLUDE (BUT ARE NOT LIMITED TO) EXCESS CONCRETE DUMPING OR CONCRETE RESIDUE, PAINTS, SOLVENTS, GREASES, FUEL AND LUBRICANT OIL, PESTICIDES, AND ANY SOLID WASTE MATERIALS. 15.EROSION CONTROL DEVICES SHOWN ON THESE PLANS SHALL BE INSTALLED PRIOR TO THE START OF LAND-DISTURBING ACTIVITIES ON THE PROJECT. 16.ALL EROSION CONTROL DEVICES ARE TO BE INSTALLED IN ACCORDANCE WITH THE APPROVED PLANS AND SPECIFICATIONS FOR THIS PROJECT. CHANGES ARE TO BE APPROVED BEFORE CONSTRUCTION BY THE DESIGN ENGINEER AND THE CITY OF LAKE ELMO ENGINEERING DIVISION. 17.IF THE EROSION CONTROL PLAN AS APPROVED CANNOT CONTROL EROSION AND OFF-SITE SEDIMENTATION FROM THE PROJECT, THE EROSION CONTROL PLAN WILL HAVE TO BE REVISED AND/OR ADDITIONAL EROSION CONTROL DEVICES WILL BE REQUIRED ON SITE. ANY REVISIONS TO THE EROSION CONTROL PLAN MADE BY THE CONTRACTOR MUST BE APPROVED BY THE ENGINEER. EROSION CONTROL MAINTENANCE ALL MEASURES STATED ON THE EROSION AND SEDIMENT CONTROL PLAN, AND IN THE STORM WATER POLLUTION PREVENTION PLAN, SHALL BE MAINTAINED IN FULLY FUNCTIONAL CONDITION AS REQUIRED BY ALL JURISDICTIONS UNTIL NO LONGER REQUIRED FOR A COMPLETED PHASE OF WORK OR FINAL STABILIZATION OF THE SITE. ALL EROSION AND SEDIMENTATION CONTROL MEASURES SHALL BE CHECKED BY A CERTIFIED PERSON AT LEAST ONCE EVERY 7 CALENDAR DAYS AND WITHIN 24 HOURS OF THE END OF A 0.5" RAINFALL EVENT, AND CLEANED AND REPAIRED IN ACCORDANCE WITH THE FOLLOWING: INLET PROTECTION DEVICES AND BARRIERS SHALL BE REPAIRED OR REPLACED IF THEY SHOW SIGNS OF UNDERMINING, OR DETERIORATION. 1.ALL SEEDED AREAS SHALL BE CHECKED REGULARLY TO SEE THAT A GOOD STAND IS MAINTAINED. AREAS SHOULD BE FERTILIZED, WATERED AND RESEEDED AS NEEDED. FOR MAINTENANCE REQUIREMENTS REFER TO THE STANDARD SPECIFICATIONS. 2.SILT FENCES SHALL BE REPAIRED TO THEIR ORIGINAL CONDITIONS IF DAMAGED. SEDIMENT SHALL BE REMOVED FROM THE SILT FENCES WHEN IT REACHES ONE-THIRD THE HEIGHT OF THE SILT FENCE. 3.THE CONSTRUCTION ENTRANCE(S) SHALL BE MAINTAINED IN A CONDITION WHICH WILL PREVENT TRACKING OR FLOW OF MUD ONTO PUBLIC RIGHTS-OF-WAY. THIS MAY REQUIRE PERIODIC TOP DRESSING OF THE CONSTRUCTION ENTRANCES AS CONDITIONS DEMAND. 4.THE TEMPORARY PARKING AND STORAGE AREA SHALL BE KEPT IN GOOD CONDITION (SUITABLE FOR PARKING AND STORAGE). THIS MAY REQUIRE PERIODIC TOP DRESSING OF THE TEMPORARY PARKING AS CONDITIONS DEMAND. 5.ALL MAINTENANCE OPERATIONS SHALL BE DONE IN A TIMELY MANNER BUT IN NO CASE LATER THAN 2 CALENDAR DAYS FOLLOWING THE INSPECTION. PAVING AND STRIPING NOTES 1.ALL PAVING, CONSTRUCTION, MATERIALS, AND WORKMANSHIP WITHIN JURISDICTION'S RIGHT-OF-WAY SHALL BE IN ACCORDANCE WITH LOCAL OR COUNTY SPECIFICATIONS AND STANDARDS (LATEST EDITION) OR MN/DOT SPECIFICATIONS AND STANDARDS (LATEST EDITION) IF NOT COVERED BY LOCAL OR COUNTY REGULATIONS. 2.ALL SIGNS, PAVEMENT MARKINGS, AND OTHER TRAFFIC CONTROL DEVICES SHALL CONFORM TO MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES (M.U.T.C.D) AND CITY STANDARDS. 3.CONTRACTOR SHALL FURNISH ALL PAVEMENT MARKINGS FOR FIRE LANES, ROADWAY LANES, PARKING STALLS, ACCESSIBLE PARKING SYMBOLS, ACCESS AISLES, STOP BARS AND SIGNS, AND MISCELLANEOUS STRIPING WITHIN THE PARKING LOT AS SHOWN ON THE PLANS. 4.ALL EXPANSION JOINTS SHALL EXTEND THROUGH THE CURB. 5.THE MINIMUM LENGTH OF OFFSET JOINTS AT RADIUS POINTS SHALL BE 2 FEET. 6.ALL JOINTS, INCLUDING EXPANSION JOINTS WITH REMOVABLE TACK STRIPS, SHALL BE SEALED WITH JOINT SEALANT. 7.THE MATERIALS AND PROPERTIES OF ALL CONCRETE SHALL MEET THE APPLICABLE REQUIREMENTS IN THE A.C.I. (AMERICAN CONCRETE INSTITUTE) MANUAL OF CONCRETE PRACTICE. 8.CONTRACTOR SHALL APPLY A SECOND COATING OVER ALL PAVEMENT MARKINGS PRIOR TO ACCEPTANCE BY OWNER FOLLOWED BY A COAT OF GLASS BEADS AS APPLICABLE PER THE PROJECT DOCUMENTS. 9.ANY EXISTING PAVEMENT, CURBS AND/OR SIDEWALKS DAMAGED OR REMOVED WILL BE REPAIRED BY THE CONTRACTOR AT HIS EXPENSE TO THE SATISFACTION OF THE ENGINEER AND OWNER. 10.BEFORE PLACING PAVEMENT, CONTRACTOR SHALL VERIFY SUITABLE ACCESSIBLE ROUTES (PER A.D.A). GRADING FOR ALL SIDEWALKS AND ACCESSIBLE ROUTES INCLUDING CROSSING DRIVEWAYS SHALL CONFORM TO CURRENT ADA STATE/NATIONAL STANDARDS. IN NO CASE SHALL ACCESSIBLE RAMP SLOPES EXCEED 1 VERTICAL TO 12 HORIZONTAL. IN NO CASE SHALL SIDEWALK CROSS SLOPES EXCEED 2% . IN NO CASE SHALL LONGITUDINAL SIDEWALK SLOPES EXCEED 5%. IN NO CASE SHALL ACCESSIBLE PARKING STALLS OR AISLES EXCEED 2% (1.5% TARGET) IN ALL DIRECTIONS. SIDEWALK ACCESS TO EXTERNAL BUILDING DOORS AND GATES SHALL BE ADA COMPLIANT. CONTRACTOR SHALL NOTIFY ENGINEER IMMEDIATELY IF ADA CRITERIA CANNOT BE MET IN ANY LOCATION PRIOR TO PAVING. NO CONTRACTOR CHANGE ORDERS WILL BE ACCEPTED FOR A.D.A COMPLIANCE ISSUES. 11.MAXIMUM JOINT SPACING IS TWICE THE DEPTH OF THE CONCRETE PAVEMENT IN FEET. REFER TO GEOTECHNICAL REPORT NO. <XXXX> TERRACON PLYMOTH, MN DATED <MONTH, DAY, YEAR> 3:13:13:13:1 11:1 4 6 : 1 12:141:13:15:15:1 4:1 11:1 5:14:1 4 2 : 1 905905 910 910915915 904904 906 906 907 907 908 908 909 909 911911912912 913913914914916916917 917918918910 906 907 908 909 911 912910915915911912913914914916916910 915 915 911 912 913 913 914 914 916 916 910910915915911911912912912913913914914916916910 910910 915 915 906 906907 907908 908909 909911 911911 912 912 912913 913 914 914 910906907908909911912913910910 910 909 909 909908 908 SILT FENCE STOCKPILE EXCAVATED RIB MATERIAL HERE AND CAP WITH 12" TOPSOIL. INSTALL SILT FENCE AROUND ENTIRE PILE AFTER RESTORATION This document, together with the concepts and designs presented herein, as an instrument of service, is intended only for the specific purpose and client for which it was prepared. Reuse of and improper reliance on this document without written authorization and adaptation by Kimley-Horn and Associates, Inc. shall be without liability to Kimley-Horn and Associates, Inc.SHEET NUMBER 2018 KIMLEY-HORN AND ASSOCIATES, INC.767 EUSTIS STREET, SUITE 100, ST. PAUL, MN 55114PHONE: 651-645-4197WWW.KIMLEY-HORN.COMK:\TWC_LDEV\MHC Operating Limited Partnership\3 Design\CAD\PlanSheets\C3-EROS PH2 PLAN.dwg February 01, 2021 - 1:33pmBYREVISIONSNo.DATEPREPARED FOREROSION ANDSEDIMENTCONTROL PLANC300CIMARRON PARK RIBSREHABILITATIONMHC OPERATINGLIMITED PARTNERSHIPLAKE ELMOMNDATE:I HEREBY CERTIFY THAT THIS PLAN,SPECIFICATION OR REPORT WAS PREPARED BYME OR UNDER MY DIRECT SUPERVISION ANDTHAT I AM A DULY LICENSED PROFESSIONALENGINEER UNDER THE LAWS OF THE STATE OFMINNESOTA.MNLIC. NO.ALAN L. CATCHPOOL10/15/202047969DATECHECKED BYSCALEDESIGNED BYDRAWN BYKHA PROJECT16010800002/01/2021AS SHOWNEISEISALCEROSION CONTROL PLAN NOTES 1.ALL PERIMETER SILT FENCE AND ROCK CONSTRUCTION ENTRANCES SHALL BE INSTALLED PRIOR TO CONSTRUCTION. 2.THE CONTRACTOR SHALL CONSTRUCT DRAINAGE BASINS PRIOR TO SITE GRADING. 3.THE CONTRACTOR SHALL INSTALL CATCH BASIN EROSION CONTROL MEASURES. 4.WITHIN TWO WEEKS (14 DAYS) OF SITE GRADING, ALL DISTURBED AREAS SHALL BE STABILIZED WITH SEED, SOD, OR ROCK BASE. REFER TO LANDSCAPE PLANS FOR MATERIALS. 5.ALL EROSION CONTROL MEASURES SHALL BE INSTALLED AND MAINTAINED IN ACCORDANCE WITH CITY, STATE, AND WATERSHED DISTRICT PERMITS. 6.THE CONTRACTOR SHALL MAINTAIN ALL EROSION CONTROL MEASURES, INCLUDING THE REMOVAL OF SILT IN FRONT OF SILT FENCES DURING THE DURATION OF THE CONSTRUCTION. 7.ANY EXCESS SEDIMENT IN PROPOSED BASINS SHALL BE REMOVED BY THE CONTRACTOR. 8.REMOVAL ALL EROSION CONTROL MEASURES AFTER VEGETATION IS ESTABLISHED. 9.THE CONTRACTOR SHALL REMOVE ALL SOILS AND SEDIMENT TRACKED ONTO EXISTING STREETS AND PAVED AREAS AND SHALL SWEEP ADJACENT STREETS AS NECESSARY IN ACCORDANCE WITH CITY REQUIREMENTS. 10.IF BLOWING DUST BECOMES A NUISANCE, THE CONTRACTOR SHALL APPLY WATER FROM A TANK TRUCK TO ALL CONSTRUCTION AREAS. UPON IMPLEMENTATION AND INSTALLATION OF THE FOLLOWING AREAS: TRAILER, PARKING, LAYDOWN, PORTA-POTTY, WHEEL WASH, CONCRETE WASHOUT, FUEL AND MATERIAL STORAGE CONTAINERS, SOLID WASTE CONTAINERS, ETC., IMMEDIATELY DENOTE THEM ON THE SITE MAPS AND NOTE ANY CHANGES IN LOCATION AS THEY OCCUR THROUGHOUT THE CONSTRUCTION PROCESS. BMP AND EROSION CONTROL INSTALLATION SEQUENCE SHALL BE AS FOLLOWS: 1.INSTALL SILT FENCE. 2.TEMPORARILY SEED, THROUGHOUT CONSTRUCTION, DENUDED AREAS THAT WILL BE INACTIVE FOR 7 DAYS OR MORE. 3.COMPLETE GRADING AND INSTALLATION OF PERMANENT STABILIZATION OVER ALL AREAS. 4.OBTAIN CONCURRENCE WITH THE CIVIL ENGINEERING CONSULTANT THAT THE SITE HAS BEEN FULLY STABILIZED THEN: 1.REMOVE ALL REMAINING TEMPORARY EROSION ADN SEDIMENT CONTROL DEVICES 2.STABILIZE ANY AREAS DISTURBED BY THE REMOVAL OF BMPS. SEQUENCE OF CONSTRUCTION: NORTH SILT FENCE - PH I & II LEGENDLEGEND SILT FENCE - PH II EROSION CONTROL BLANKET - PH II PROPERTY SUMMARY CIMARRON PARK RIBS REHABILITATION EXISTING PERVIOUS AREA 3.08 AC EXISTING IMPERVIOUS AREA 0.00 AC PROPOSED PERVIOUS AREA 2.70 AC PROPOSED IMPERVIOUS AREA 0.38 AC TOTAL DISTURBED AREA 3.08 AC This document, together with the concepts and designs presented herein, as an instrument of service, is intended only for the specific purpose and client for which it was prepared. Reuse of and improper reliance on this document without written authorization and adaptation by Kimley-Horn and Associates, Inc. shall be without liability to Kimley-Horn and Associates, Inc.SHEET NUMBER 2018 KIMLEY-HORN AND ASSOCIATES, INC.767 EUSTIS STREET, SUITE 100, ST. PAUL, MN 55114PHONE: 651-645-4197WWW.KIMLEY-HORN.COMK:\TWC_LDEV\MHC Operating Limited Partnership\3 Design\CAD\PlanSheets\C3-EROS DETAILS.dwg February 01, 2021 - 1:33pmBYREVISIONSNo.DATEPREPARED FOREROSION ANDSEDIMENTCONTROL DETAILSC301CIMARRON PARK RIBSREHABILITATIONMHC OPERATINGLIMITED PARTNERSHIPLAKE ELMOMNDATECHECKED BYSCALEDESIGNED BYDRAWN BYKHA PROJECT16010800002/01/2021AS SHOWNEISEISALCSheet: 1File: ..\Library\Details\MNDOT_5-297.405-1853807-v3.pdfMissing or invalid reference This document, together with the concepts and designs presented herein, as an instrument of service, is intended only for the specific purpose and client for which it was prepared. Reuse of and improper reliance on this document without written authorization and adaptation by Kimley-Horn and Associates, Inc. shall be without liability to Kimley-Horn and Associates, Inc.SHEET NUMBER 2018 KIMLEY-HORN AND ASSOCIATES, INC.767 EUSTIS STREET, SUITE 100, ST. PAUL, MN 55114PHONE: 651-645-4197WWW.KIMLEY-HORN.COMK:\TWC_LDEV\MHC Operating Limited Partnership\3 Design\CAD\PlanSheets\C3-EROS DETAILS.dwg February 01, 2021 - 1:34pmBYREVISIONSNo.DATEPREPARED FORSWPPPC302CIMARRON PARK RIBSREHABILITATIONMHC OPERATINGLIMITED PARTNERSHIPLAKE ELMOMNDATE:I HEREBY CERTIFY THAT THIS PLAN,SPECIFICATION OR REPORT WAS PREPARED BYME OR UNDER MY DIRECT SUPERVISION ANDTHAT I AM A DULY LICENSED PROFESSIONALENGINEER UNDER THE LAWS OF THE STATE OFMINNESOTA.MNLIC. NO.ALAN L. CATCHPOOL02/01/202147969DATECHECKED BYSCALEDESIGNED BYDRAWN BYKHA PROJECT16010800002/01/2021AS SHOWNEISEISALCA.PROJECT OFFICE WALL SWPPP POSTINGS: THE FOLLOWING ITEMS MUST BE POSTED TOGETHER IN A SINGLE, ORGANIZED LOCATION ON A WALL INSIDE THE PROJECT OFFICE: 1) SWPPP SITE MAPS (ALL PHASES); 2) SWPPP DETAIL SHEETS; 3) MAP SHOWING LOCATION OF OFFSITE IMPORT OR EXPORT FACILITY; 4) REVISIONS TO DETAILS, SITE MAPS, OR SWPPP-RELATED RFIS; 5) SITE SWPPP BINDER; 6) SWCT PLACARD; 7) CURRENT OWNER STORMWATER COMPLIANCE TRAINING CERTIFICATES FOR SUPERINTENDENT(S) AND COMPLIANCE OFFICER(S); AND 8) CERTIFICATIONS AND/OR TRAINING CERTIFICATES REQUIRED TO PERFORM INSPECTIONS BY THE APPLICABLE CONSTRUCTION GENERAL PERMIT OR AUTHORITY HAVING JURISDICTION. B.PERMITTED PROJECT AREA: FOR PURPOSES OF THIS SWPPP AND ASSOCIATED STORMWATER PERMIT, 'PERMITTED PROJECT AREA' IS DEFINED AS ANY AND ALL AREAS WITHIN THE PROJECT LIMITS OF DISTURBANCE, AS SHOWN ON THE SWPPP SITE MAPS AND IDENTIFIED IN THE NOTICE OF INTENT TO THE AGENCY. ALL GROUND-DISTURBING AND CONSTRUCTION-RELATED ACTIVITIES (MATERIAL STORAGE, DUMPSTERS, PARKING AREAS, PROJECT OFFICE TRAILER, ETC.) MUST BE INCLUDED WITHIN THE PERMITTED PROJECT AREA LIMITS OF DISTURBANCE. ALL AREAS OUTSIDE THE PERMITTED PROJECT AREA (I.E., LIMITS OF DISTURBANCE) ACQUIRED FOR USE BY THE GC OR A SUBCONTRACTOR OF THE GC (BORROW SOURCES, DISPOSAL AREAS, ETC.) MUST BE MANAGED IN ACCORDANCE WITH THE NPDES PERMIT. THE CONTRACTOR IS REQUIRED TO LOCATE OFFICE TRAILERS AND MATERIAL STORAGE AREAS FOR THE PROJECT WITHIN THE LIMITS OF DISTURBANCE. THE CONTRACTOR MAY REQUEST USE OF OFF-SITE LOCATIONS FOR OFFICE TRAILERS OR NON-ERODIBLE MATERIAL STORAGE; HOWEVER, APPROVAL MUST BE OBTAINED FROM THE CONSTRUCTION MANAGER, AND THE CEC PRIOR TO THEIR USE. REQUESTS WILL BE REVIEWED ON A CASE BY CASE BASIS AND IF APPROVED, LIMITATIONS ON USE WILL BE PROVIDED BY THE CEC. C.SPECIAL PROJECT AREAS: THERE ARE NO SPECIAL PROJECTS, LOCATED BEYOND THE OWNER PERMITTED PROJECT AREA, REQUIRING INSPECTION AND MAINTENANCE ASSOCIATED WITH THIS CONSTRUCTION PROJECT. D.1 NON-STORMWATER DISCHARGES: THE GENERAL PERMIT FOR STORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITIES PROHIBITS MOST NON-STORMWATER DISCHARGES DURING THE CONSTRUCTION PHASE. ALLOWABLE NON-STORMWATER DISCHARGES THAT OCCUR DURING CONSTRUCTION ON THIS PROJECT, ARE INCLUDED IN THE SECTION PART IV.D. OF THE GENERAL PERMIT. BEST MANAGEMENT PRACTICES (BMPS) MUST BE IMPLEMENTED FOR THE GENERAL PERMIT ALLOWABLE DISCHARGES FOR THE DURATION OF THE PERMIT. THE TECHNIQUES DESCRIBED IN THIS SWPPP FOCUS ON PROVIDING CONTROL OF POLLUTANT DISCHARGES WITH PRACTICAL APPROACHES THAT UTILIZE READILY AVAILABLE EXPERTISE, MATERIAL, AND EQUIPMENT. NON-STORMWATER COMPONENTS OF SITE DISCHARGES MUST BE UNCONTAMINATED NON-TURBID WATER. ALL NON-STORMWATER DISCHARGES MUST BE ROUTED TO A STORMWATER CONTROL PRIOR TO DISCHARGE. WATER USED FOR CONSTRUCTION WHICH DISCHARGES FROM THE SITE MUST ORIGINATE FROM A PUBLIC WATER SUPPLY OR PRIVATE WELL APPROVED BY THE STATE HEALTH DEPARTMENT. WATER USED FOR CONSTRUCTION THAT DOES NOT ORIGINATE FROM AN APPROVED PUBLIC SUPPLY MUST NOT DISCHARGE FROM THE SITE; IT CAN BE RETAINED IN RETENTION PONDS UNTIL IT INFILTRATES OR EVAPORATES. WHEN NON-STORMWATER IS DISCHARGED FROM THE SITE, IT MUST BE DONE IN A MANNER SUCH THAT IT DOES NOT CAUSE EROSION OF THE SOIL DURING DISCHARGE. D.2 POWER WASHING: PROCESS WATER SUCH AS POWER WASHING WATER AND CONCRETE CUTTING EFFLUENT, AMONG OTHERS, MUST BE COLLECTED FOR TREATMENT AND DISPOSAL. IT MUST NOT BE FLUSHED INTO THE SITE STORM DRAIN SYSTEM OR DISCHARGED OFF-SITE. D.DISCHARGE POINTS: ALL DISCHARGE POINTS MUST BE INSPECTED TO DETERMINE WHETHER EROSION AND SEDIMENTATION CONTROL MEASURES ARE EFFECTIVE IN PREVENTING DISCHARGE OF SEDIMENT FROM THE SITE AND/OR IMPACTS TO RECEIVING WATERS. SEDIMENT ACCUMULATION DOWNGRADIENT OF DISCHARGE LOCATIONS SHALL BE REPORTED AS A SEDIMENT DISCHARGE AND THE POTENTIAL UPSTREAM CAUSE SHALL BE INVESTIGATED TO PREVENT FUTURE OCCURRENCE. CONTACT THE CM AND CEC TO DETERMINE APPROPRIATE ACTION FOR CLEANUP OF DISCHARGED SEDIMENT THAT MAY BE OUTSIDE OF THE LIMITS OF DISTURBANCE. SEE SAMPLING AND MONITORING OF EFFLUENT PLAN (IF APPLICABLE). E.CONTRACTOR SHALL UTILIZE TYPICAL CONSTRUCTION METHODS TO PROMOTE GROWTH IN RESTORING WITH TOPSOIL. F.LOCAL RAINFALL INTENSITIES WERE CONSIDERED WHEN DEVELOPING BMP'S. A.SUBCONTRACTOR SHALL IMPLEMENT BEST MANAGEMENT PRACTICES AS REQUIRED BY THIS STORM WATER POLLUTION PREVENTION PLAN. ADDITIONAL BEST MANAGEMENT PRACTICES SHALL BE IMPLEMENTED AS DICTATED BY CONDITIONS AT NO ADDITIONAL COST OF OWNER THROUGHOUT ALL PHASES OF CONSTRUCTION. B.BEST MANAGEMENT PRACTICES (BMP'S) AND CONTROLS SHALL CONFORM TO FEDERAL, STATE, OR LOCAL REQUIREMENTS OR MANUAL OF PRACTICE, AS APPLICABLE. CONTRACTOR SHALL IMPLEMENT ADDITIONAL CONTROLS AS DIRECTED BY PERMITTING AGENCY OR OWNER. C.SITE MAP MUST CLEARLY DELINEATE ALL STATE WATERS. PERMITS FOR ANY CONSTRUCTION ACTIVITY IMPACTING STATE WATERS OR REGULATED WETLANDS MUST BE MAINTAINED ON SITE AT ALL TIMES. D.SUBCONTRACTOR TO LIMIT DISTURBANCE OF SITE IN STRICT ACCORDANCE WITH SWPPP IMPLEMENTATION SEQUENCE, OR AS REQUIRED BY THE APPLICABLE GENERAL PERMIT. NO UNNECESSARY OR IMPROPERLY SEQUENCED CLEARING AND/OR GRADING SHALL BE PERMITTED. E.ALL DENUDED/BARE AREAS THAT WILL BE INACTIVE FOR 7 DAYS OR MORE, MUST BE STABILIZED IMMEDIATELY UPON COMPLETION OF MOST RECENT GRADING ACTIVITY, WITH THE USE OF FAST-GERMINATING ANNUAL GRASS/GRAIN VARIETIES, STRAW/HAY MULCH, WOOD CELLULOSE FIBERS, TACKIFIERS, NETTING AND/OR BLANKETS. COMPLETION MUST BE ACHIEVED WITHIN 7 DAYS. F.DISTURBED PORTIONS OF THE SITE WHERE CONSTRUCTION ACTIVITY HAS PERMANENTLY STOPPED SHALL BE PERMANENTLY STABILIZED AS SHOWN ON THE PLANS. THESE AREAS SHALL BE SEEDED, SODDED, AND/OR VEGETATED IMMEDIATELY, AND COMPLETED NO LATER THAN 7 DAYS AFTER THE LAST CONSTRUCTION ACTIVITY OCCURRING IN THESE AREAS. REFER TO THE GRADING PLAN AND/OR LANDSCAPE PLAN. G.SLOPES SHALL BE LEFT IN A ROUGHENED CONDITION DURING THE GRADING PHASE TO REDUCE RUNOFF VELOCITIES AND EROSION. TEMPORARY AND/OR PERMANENT STABILIZATION SHALL BE APPLIED PER REQUIREMENTS IN THESE E&S CONTROL NOTES. H.DUE TO THE GRADE CHANGES DURING THE DEVELOPMENT OF THE PROJECT, THE CONTRACTOR SHALL BE RESPONSIBLE FOR ADJUSTING THE EROSION AND SEDIMENT CONTROL MEASURES (SILT FENCES, ETC.) TO PREVENT EROSION AND POLLUTANT DISCHARGE OFF-SITE. I.ALL MEASURES STATED ON THIS SITE MAP, AND IN THE STORM WATER POLLUTION PREVENTION PLAN, SHALL BE MAINTAINED IN FULLY FUNCTIONAL CONDITION UNTIL NO LONGER REQUIRED FOR A COMPLETED PHASE OF WORK OR FINAL STABILIZATION OF THE SITE. ALL EROSION AND SEDIMENTATION CONTROL MEASURES SHALL BE CHECKED BY A QUALIFIED PERSON IN ACCORDANCE WITH THE CONTRACT DOCUMENTS OR THE APPLICABLE PERMIT, WHICHEVER IS MORE STRINGENT, AND REPAIRED IN ACCORDANCE WITH THE SITE PLANS. J.STORM WATER POLLUTANT CONTROL MEASURES INSTALLED DURING CONSTRUCTION, THAT WILL ALSO PROVIDE STORM WATER MANAGEMENT AFTER CONSTRUCTION, ARE INCLUDED IN THE CONTRACT DOCUMENTS. THE SITE-SPECIFIC POST CONSTRUCTION STORM WATER OPERATION AND MAINTENANCE (O&M) MANUAL IS INCLUDED IN THE CONTRACT DOCUMENTS. K.ALL PERMANENT CONTROLS AND SYSTEMS MUST BE INSTALLED AND FUNCTIONING AS DESIGNED AND FREE OF ACCUMULATED SEDIMENT AND DEBRIS DURING FINAL PROJECT INSPECTION AND APPROVAL. L.SILT FENCE OR FABRIC PLACED UNDER THE GRATE IS NOT AN APPROVED FORM OF INLET PROTECTION. ANY HAZARDOUS OR POTENTIALLY HAZARDOUS MATERIAL THAT IS BROUGHT ONTO THE CONSTRUCTION SITE SHALL BE HANDLED PROPERLY TO REDUCE THE POTENTIAL FOR STORMWATER POLLUTION. ALL MATERIALS USED ON THIS CONSTRUCTION SITE SHALL BE PROPERLY STORED, HANDLED, DISPENSED AND DISPOSED OF FOLLOWING ALL APPLICABLE LABEL DIRECTIONS. FLAMMABLE AND COMBUSTIBLE LIQUIDS SHALL BE STORED AND HANDLED ACCORDING TO APPLICABLE REGULATIONS, AND, AT A MINIMUM, ACCORDING TO 29 CFR 1926.152. ONLY APPROVED CONTAINERS AND PORTABLE TANKS SHALL BE USED FOR STORAGE AND HANDLING OF FLAMMABLE AND COMBUSTIBLE LIQUIDS. MATERIAL SAFETY DATA SHEETS (MSDS) INFORMATION SHALL BE KEPT ON SITE FOR ANY AND ALL APPLICABLE MATERIALS. HOWEVER, MSDS MAY ALSO BE ACCESSED VIA TELEPHONE OR OTHER ELECTRONIC MEANS OR APPARATUS. IN THE EVENT OF AN ACCIDENTAL SPILL, IMMEDIATE ACTION SHALL BE TAKEN BY THE SUBCONTRACTOR TO CONTAIN AND REMOVE THE SPILLED MATERIAL. THE SPILL SHALL BE REPORTED TO THE APPROPRIATE AGENCIES IN THE REQUIRED TIME FRAMES. AS REQUIRED UNDER THE PROVISIONS OF THE CLEAN WATER ACT, ANY SPILL OR DISCHARGE ENTERING WATERS OF THE UNITED STATES SHALL BE PROPERLY REPORTED. ALL HAZARDOUS MATERIALS, INCLUDING CONTAMINATED SOIL AND LIQUID CONCRETE WASTE, SHALL BE DISPOSED OF BY THE SUBCONTRACTOR IN THE MANNER SPECIFIED BY FEDERAL, STATE AND LOCAL REGULATIONS AND BY THE MANUFACTURER OF SUCH PRODUCTS. THE SUBCONTRACTOR SHALL PREPARE A WRITTEN RECORD OF ANY SPILL AND ASSOCIATED CLEAN-UP ACTIVITIES OF PETROLEUM PRODUCTS OR HAZARDOUS MATERIALS IN EXCESS OF 1 GALLON OR REPORTABLE QUANTITIES, WHICHEVER IS LESS, ON THE DAY OF THE SPILL. THE SUBCONTRACTOR SHALL PROVIDE NOTICE TO OWNER, VIA THE ONLINE CRITICAL INCIDENT REPORT, IMMEDIATELY UPON IDENTIFICATION OF ANY SPILL. SPILL REPORT FORMS ARE AVAILABLE IN THE ONLINE SWPPP REPORTING SYSTEM PROVIDED BY THE OWNER. COPIES OF SPILL CRITICAL INCIDENT REPORTS SHALL BE PRINTED AND MAINTAINED IN THE JOBSITE BINDER. ANY SPILLS OF PETROLEUM PRODUCTS OR HAZARDOUS MATERIALS IN EXCESS OF REPORTABLE QUANTITIES AS DEFINED BY EPA OR THE STATE OR LOCAL AGENCY REGULATIONS, SHALL BE IMMEDIATELY REPORTED TO THE EPA NATIONAL RESPONSE CENTER (1-800-424-8802) AND THE MINNESOTA DEPARTMENT OF NATURAL RESOURCES (1-800-943-0003) THE STATE REQUIRES REPORTING WHEN: ·THERE IS AN IMPACT TO HUMAN HEALTH ·THERE IS AN IMPACT TO THE ENVIRONMENT ·THERE IS A FIRE, EXPLOSION, OR SAFETY HAZARD ·A SPILL IS NOT IMMEDIATELY CLEANED UP ·THE SPILL WAS MORE THAN THE REPORTABLE QUANTITY OF 1 GALLON OF A PETROLEUM PRODUCT THE REPORT SHOULD BE FILED WITH THE STATE OF MINNESOTA. ALL REPORTS SHOULD BE FILED WITHIN 24 HOURS OF A SPILL OCCURRING. THE REPORTABLE QUANTITY FOR HAZARDOUS MATERIALS CAN BE FOUND IN 40 CFR 302 AND THE US EPA WEBSITE: HTTP://WWW.EPA.GOV/SUPERFUND/POLICY/RELEASE/RG TO MINIMIZE THE POTENTIAL FOR A SPILL OF PETROLEUM PRODUCT OR HAZARDOUS MATERIALS TO COME IN CONTACT WITH STORMWATER, THE FOLLOWING STEPS SHALL BE IMPLEMENTED: 1)ALL MATERIALS WITH HAZARDOUS PROPERTIES, SUCH AS PESTICIDES, PETROLEUM PRODUCTS, FERTILIZERS, SOAPS, DETERGENTS, CONSTRUCTION CHEMICALS, ACIDS, BASES, PAINTS, PAINT SOLVENTS, ADDITIVES FOR SOIL STABILIZATION, CONCRETE, CURING COMPOUNDS AND ADDITIVES, ETC., SHALL BE STORED IN A SECURE LOCATION, UNDER COVER AND IN APPROPRIATE, TIGHTLY SEALED CONTAINERS WHEN NOT IN USE. 2)THE MINIMUM PRACTICAL QUANTITY OF ALL SUCH MATERIALS SHALL BE KEPT ON THE JOB SITE AND SCHEDULED FOR DELIVERY AS CLOSE TO TIME OF USE AS PRACTICAL. 3)A SPILL CONTROL AND CONTAINMENT KIT (CONTAINING FOR EXAMPLE, ABSORBENT MATERIAL SUCH AS KITTY LITTER OR SAWDUST, ACID, BASE, NEUTRALIZING AGENT, BROOMS, DUST PANS, MOPS, RAGS, GLOVES, GOGGLES, PLASTIC AND METAL TRASH CONTAINERS, ETC.) SHALL BE PROVIDED AT THE CONSTRUCTION SITE AND ITS LOCATION(S) SHALL BE IDENTIFIED WITH LEGIBLE SIGNAGE AND SHOWN ON SITE MAPS. a.THE SPILL CONTROL AND CONTAINMENT KIT SUPPLIES SHALL BE OF SUFFICIENT QUANTITIES AND APPROPRIATE CONTENT TO CONTAIN A SPILL FROM THE LARGEST ANTICIPATED PIECE OF EQUIPMENT AND FROM THE LARGEST ANTICIPATED QUANTITIES OF PRODUCTS STORED ON THE SITE AT ANY GIVEN TIME. b.CONTENTS SHALL BE INSPECTED DAILY DURING THE DAILY STORMWATER INSPECTION. 4)ALL PRODUCTS SHALL BE STORED IN AND USED FROM THE ORIGINAL CONTAINER WITH THE ORIGINAL PRODUCT LABEL. CONTAINERS MUST BE STORED IN A MANNER TO PROTECT THEM FROM THE ELEMENTS AND INCIDENTAL DAMAGE. 5)ALL PRODUCTS SHALL BE USED IN STRICT COMPLIANCE WITH INSTRUCTIONS ON THE PRODUCT LABEL. 6)THE DISPOSAL OF EXCESS OR USED PRODUCTS SHALL BE IN STRICT COMPLIANCE WITH INSTRUCTIONS ON THE PRODUCT LABEL AND REGULATIONS. GENERAL NOTES EROSION AND SEDIMENT CONTROL NOTES HAZARDOUS MATERIAL MANAGEMENT & SPILL REPORTING SWPPP DESIGNER: ALAN CATCHPOOL, P.E. 767 EUSTIS STREET, SUITE 100 ST. PAUL, MN 55114 CERTIFICATION EXPIRES 2021 SIGNATURE: SILT FENCE 1580 L.F. BMP QUANTITY TABLE UPON IMPLEMENTATION AND INSTALLATION OF THE FOLLOWING AREAS: TRAILER, PARKING, LAYDOWN, PORTA-POTTY, WHEEL WASH, CONCRETE WASHOUT, FUEL AND MATERIAL STORAGE CONTAINERS, SOLID WASTE CONTAINERS, ETC., IMMEDIATELY DENOTE THEM ON THE SITE MAPS AND NOTE ANY CHANGES IN LOCATION AS THEY OCCUR THROUGHOUT THE CONSTRUCTION PROCESS. BMP AND EROSION CONTROL INSTALLATION SEQUENCE SHALL BE AS FOLLOWS: 1.TEMPORARILY SEED, THROUGHOUT CONSTRUCTION, DENUDED AREAS THAT WILL BE INACTIVE FOR 7 DAYS OR MORE. 2.INSTALL UTILITIES, UNDERDRAINS, STORM SEWERS, UNDERGROUND SYSTEM, CURBS AND GUTTERS. 3.INSTALL APPROPRIATE INLET PROTECTION AT ALL STORM SEWER STRUCTURES AS EACH INLET STRUCTURE IS INSTALLED. 4.PERMANENTLY STABILIZE AREAS TO BE VEGETATED AS THEY ARE BROUGHT TO FINAL GRADE. 5.PREPARE SITE FOR PAVING. 6.PAVE SITE AND INSTALL STRIPING. 7.INSTALL APPROPRIATE INLET PROTECTION DEVICES FOR PAVED AREAS AS WORK PROGRESSES. 8.COMPLETE GRADING AND INSTALLATION OF PERMANENT STABILIZATION OVER ALL AREAS. 9.OBTAIN CONCURRENCE WITH THE CIVIL ENGINEERING CONSULTANT THAT THE SITE HAS BEEN FULLY STABILIZED THEN: 1.REMOVE ALL REMAINING TEMPORARY EROSION ADN SEDIMENT CONTROL DEVICES 2.STABILIZE ANY AREAS DISTURBED BY THE REMOVAL OF BMPS. THE GC MUST UPDATE THE SWPPP, INCLUDING THE JOBSITE BINDER AND SITE MAPS, TO REFLECT THE PROGRESS OF CONSTRUCTION ACTIVITIES AND GENERAL CHANGES TO THE PROJECT SITE. UPDATES SHALL BE MADE DAILY TO TRACK PROGRESS WHEN ANY OF THE FOLLOWING ACTIVITIES OCCUR: BMP INSTALLATION, MODIFICATION OR REMOVAL, CONSTRUCTION ACTIVITIES (E.G., PAVING, STORM SEWER INSTALLATION, FOOTING INSTALLATION, ETC.), CLEARING, GRUBBING OR GRADING, OR TEMPORARY OR PERMANENT STABILIZATION. IMPORTANT: THE GENERAL CONTRACTOR MUST SUBMIT A REQUEST FOR INFORMATION (RFI) TO THE CEC AND OBTAIN WRITTEN CEC APPROVAL BEFORE DOING ANY OF THE FOLLOWING: 1.MODIFYING EROSION OR SEDIMENT CONTROL BMPS (SUBSTITUTIONS ARE TYPICALLY ONLY APPROVED IF SPECIFIED MATERIALS ARE NOT AVAILABLE OR THERE IS A VALID REASON THE SPECIFIED BMP WILL NOT WORK) 2.ADDING/DELETING EROSION OR SEDIMENT CONTROL BMPS; 3.MODIFYING THE SWPPP IMPLEMENTATION SEQUENCE; OR 4.PERFORMING ANY ACTIONS OR IN ANY MANNER THAT IS CONTRARY TO THE SWPPP. THE CONTRACTOR MAY MODIFY OR ADD ADDITIONAL BMPS, WITHOUT CEC APPROVAL, IN AN EMERGENCY SITUATION TO PREVENT SEDIMENT DISCHARGE OR PROTECT WATER QUALITY; HOWEVER, GC MUST NOTIFY THE CEC AS SOON AS PRACTICAL AS TO THEIR ACTIONS TO DISCUSS THE NEED FOR ADDITIONAL OR SUPPLEMENTAL MEASURES AND TO OBTAIN THE REQUIRED APPROVALS. THE CONTRACTOR IS ULTIMATELY RESPONSIBLE TO ENSURE COMPLIANCE WITH THE PERMIT AND PROTECTION OF DOWNSTREAM WATER QUALITY. AMENDING THE SWPPP DOES NOT MEAN THAT IT HAS TO BE REPRINTED. IT IS ACCEPTABLE TO ADD ADDENDA, SKETCHES, NEW SECTIONS, DETAILS, AND/OR REVISED DRAWINGS THAT HAVE THE CEC NAME IN PRINT, ARE STAMPED, SIGNED, DATED, AND ARE ACCOMPANIED BY WRITTEN COPY OF THE ASSOCIATED RFI AND ITS RESPONSE FROM CEC. ENGINEERED ITEMS MUST BE SIGNED AND STAMPED BY THE CEC OF RECORD FOR THE PROJECT. PROJECT DESCRIPTION 1.ALL MEASURES STATED ON THE EROSION AND SEDIMENT CONTROL PLAN AND IN THE STORM WATER POLLUTION PREVENTION PLAN, SHALL BE MAINTAINED IN FULLY FUNCTIONAL CONDITION UNTIL FINAL STABILIZATION OF THE SITE. ALL EROSION SEDIMENTATION CONTROL MEASURES SHALL BE CHECKED BY A QUALIFIED PERSON AT LEAST ONCE EVERY SEVEN CALENDAR DAYS, AND WITHIN 24 HOURS AT THE END OF A RAINFALL EVENT AND SHOULD BE CLEANED AND REPAIRED IN ACCORDANCE WITH THE FOLLOWING 1.1.INLET PROTECTION AND BARRIERS SHALL BE REPAIRED OR REPLACED IF THEY SHOW SIGNS OF UNERMINING OR SHALL BE REPLACED IF THEY SHOW SIGNS OF DETERIORATION 1.2.ALL SEEDED AREAS SHALL BE CHECKED REGULARLY TO SEE THAT A GOOD STAND IS MAINTAINED. AREAS SHOULD BE FERTILIZED AND RESEEDED AS NEEDED 1.3.SILT FENCES AND BRIO-ROLL SHALL BE REPAIRED TO THEIR ORIGINAL CONDITION IF DAMAGED. SEDIMENT SHALL BE REMOVED FROM THE SILT FENCES WHEN IT REACHES ONE-THIRD TO ONE-HALF HEIGHT OF THE FENCE. 1.4.THE CONSTRUCTION ENTRANCES SHALL BE MAINTAINED IN A CONDITION WHICH WILL PREVENT TRACKING OR FLOW OF MUD ONTO PUBLIC RIGHTS OF WAY. 1.5.THE TEMPORARY PARKING AND STORAGE AREA SHALL BE KEPT IN GOOD CONDITION (SUITABLE FOR PARKING AND STORAGE). THIS MAY REQUIRE PERIODIC TOP DRESSING OF THE TEMPORARY PARKING AREA AS CONDITIONS DEMAND. SEQUENCE OF CONSTRUCTION SWPPP UPDATES AND AMMENDMENTS MAINTEANANCE 1.THIS PROJECT CONSISTS OF THE EXCAVATION OF RIB MATERIAL AND THE FOLLOWING RESTORATION. 905 910 910915915904 906 906 907 907 908 908 909 9 0 9 911 911912912913913914914916916917 917918918910 910915 906 906907 907908 908909 909911 911912912 913 914 916 910910 915915 911911 912912 913913 914914 916 908909910909 910906907908909911912912905910 910 904904906 906907 907908 908 909 909 911 911912 912910909 9109093:14:14:1 3:1 4:1 3:111:1 54 : 1 3:1 3:1 3:13:1 15:13:1 4:1 4:1 42 : 1 4 6 : 1 3:1 CONTRACTOR SHALL REMOVE VEGETATION, ROOT ZONES, AND CONTAMINATED SOIL FROM BOTTOM OF POND PER DIRECTION OF ENGINEER AND FIELD GEO-TECHNICAL ENGINEER. MATERIAL FROM BOTTOM OF RIBS SYSTEMS SHALL BE DISPOSED OF IN ACCORDANCE WITH MPCA REQUIREMENTS AND LOCAL JURISDICTIONAL REQUIREMENTS. ONCE CONTAMINATED MATERIAL IS REMOVED, BOTTOM OF RIB SHALL BE SCARIFIED TO DEPTH OF 12 INCHES. CONTRACTOR SHALL PLACE WASHED SAND MEETING MNDOT 3149 FINE FILTER AGGREGATE WITH 3-5% PASSING THE 200 SIEVE, TO THE ELEVATIONS SHOWN ON THE CROSS SECTIONS. CONTRACTOR SHALL KEEP ONE CELL OPERATIONAL AT ALL TIMES. IF WATER NEEDS TO BE TRANSFERRED TO RESTORED RIB, A FRAC TANK SHALL BE USED TO ALLOW FINES AND DEBRIS TO SETTLE OUT.910915909911912913914FIELD LOCATE EXISTING SANITARY SEWER PIPE FROM SEEPAGE PONDS, DO NOT DAMAGE/DISTURB FIELD VERIFY IF EXISTING PIPE EXISTS. IF FOUND, CAP BOTH ENDS. 12' CLAY CAP OR IMPERMEABLE HDPE 40MIL LINER 12' CLAY CAP OR IMPERMEABLE HDPE 40MIL LINER A A B B C C D D29:127:19:1 4:15:1 This document, together with the concepts and designs presented herein, as an instrument of service, is intended only for the specific purpose and client for which it was prepared. Reuse of and improper reliance on this document without written authorization and adaptation by Kimley-Horn and Associates, Inc. shall be without liability to Kimley-Horn and Associates, Inc.SHEET NUMBER 2018 KIMLEY-HORN AND ASSOCIATES, INC.767 EUSTIS STREET, SUITE 100, ST. PAUL, MN 55114PHONE: 651-645-4197WWW.KIMLEY-HORN.COMK:\TWC_LDEV\MHC Operating Limited Partnership\3 Design\CAD\PlanSheets\C5-GRADING PLAN RIB.dwg February 01, 2021 - 1:34pm©BYREVISIONSNo.DATEPREPARED FORGRADING PLAN -RIBC400CIMARRON PARKRIBS REHABILITATIONMHC OPERATINGLIMITED PARTNERSHIPLAKE ELMOMNDATE:I HEREBY CERTIFY THAT THIS PLAN,SPECIFICATION OR REPORT WAS PREPARED BYME OR UNDER MY DIRECT SUPERVISION ANDTHAT I AM A DULY LICENSED PROFESSIONALENGINEER UNDER THE LAWS OF THE STATE OFMINNESOTA.MNLIC. NO.ALAN L. CATCHPOOL02/01/202147969DATECHECKED BYSCALEDESIGNED BYDRAWN BYKHA PROJECT16010800002/01/2021AS SHOWNEISEISALCGRADING PLAN NOTES 1.ALL WORK SHALL BE PERFORMED IN ACCORDANCE WITH THE CITY OF LAKE ELMO, SPECIFICATIONS AND BUILDING PERMIT REQUIREMENTS. 2.CONTRACTOR TO CALL GOPHER STATE CALL ONE @ <1-800-252-1166> AT LEAST TWO WORKING DAYS PRIOR TO EXCAVATION/CONSTRUCTION FOR UTILITY LOCATIONS. 3.CONTRACTOR TO FIELD VERIFY THE LOCATIONS AND ELEVATIONS OR EXISTING UTILITIES AND TOPOGRAPHIC FEATURES PRIOR TO THE START OF SITE GRADING. THE CONTRACTOR SHALL IMMEDIATELY NOTIFY THE PROJECT ENGINEER OF ANY DISCREPANCIES OR VARIATIONS. 4.SUBGRADE EXCAVATION SHALL BE BACKFILLED IMMEDIATELY AFTER EXCAVATION TO HELP OFFSET ANY STABILITY PROBLEMS DUE TO WATER SEEPAGE OR STEEP SLOPES. WHEN PLACING NEW SURFACE MATERIAL ADJACENT TO EXISTING PAVEMENT, THE EXCAVATION SHALL BE BACKFILLED PROMPTLY TO AVOID UNDERMINING OF EXISTING PAVEMENT. 5.CONTRACTOR SHALL BE RESPONSIBLE FOR ALL HORIZONTAL AND VERTICAL CONTROL. 6.GRADES SHOWN ARE FINISHED GRADES. CONTRACTOR SHALL ROUGH GRADE TO SUBGRADE ELEVATION AND LEAVE STREET READY FOR SUBBASE. 7.ALL EXCESS MATERIAL, BITUMINOUS SURFACING, CONCRETE ITEMS, ANY ABANDONED UTILITY ITEMS, AND OTHER UNSTABLE MATERIALS SHALL BECOME THE PROPERTY OF THE CONTRACTOR AND SHALL BE DISPOSED OF OFF THE CONSTRUCTION SITE. 8.UPON COMPLETION OF EXCAVATION AND FILLING, CONTRACTOR SHALL RESTORE ALL DISTURBED AREAS ON SITE. ALL DISTURBED AREAS SHALL BE RE-VEGETATED WITH A MINIMUM OF 4" OF TOPSOIL COVERED BY EROSION CONTROL FABRIC AND SEED. PROPERTY LINE EXISTING CONTOUR PROPOSED CONTOUR925 LEGEND 0.00%PROPOSED ADA SLOPE NORTH CONTRACTOR SHALL INSTALL A 12" CLAY CAP OR IMPERMEABLE HDPE 40MIL LINER, FROM THE BOTTOM OF THE POND TO THE TOP OF THE RIB RIB REHABILITATION NOTES 1.IN THE EVENT THAT THE SEDIMENT IS INTRODUCED INTO THE RIB DURING OR IMMEDIATELY FOLLOWING EXCAVATION, REMOVE SEDIMENT PRIOR TO INITIATING THE NEXT STEP IN THE BASIN CONSTRUCTION PROCESS. 2.IF DEWATERING IS REQUIRED, ALL WATER MUST BE ROUTED TO ONE OF THE RIB BASINS THAT IS TO REMAIN ONLINE DURING CONSTRUCTION THROUGH A SETTLING TANK SYSTEM. 3.REMOVE VEGETATION AND SEDIMENT IN THE BOTTOM OF THE RIB BASIN TO A DEPTH WHERE CLEAN SUB-BASE IS DETERMINED BY THE FIELD ENGINEER. 4.ONLY LOW IMPACT CONSTRUCTION EQUIPMENT SHALL BE ALLOWED IN THE RIB BASIN BOTTOM AREA BEFORE OR AFTER IT IS CONSTRUCTED. ONLY SPECIFIED EQUIPMENT WILL BE ALLOWED INSIDE OF ORANGE CONSTRUCTION FENCE FOR THE SOLE PURPOSE OF CONSTRUCTING THE RIB. 5.ALL EXCAVATED MATERIAL SHALL BE STOCK PILED IN THE DESIGNATED LOCATION ON SITE. THE MATERIAL WILL NEED TO BE SLOPED TO DRAIN AND COVERED IN ACCORDANCE WITH MPCA SPECIFICATIONS. 6.ALL CLAY MATERIAL SHALL MEET THE REQUIREMENTS OF THE MPCA POND LINER WITH POROSITY OF 10-8. 7.ALL RIB AREAS SHALL BE PROTECTED DURING CONSTRUCTION OPERATIONS. Offset A'-A' 904 905 910 915 920 904 905 910 915 920 Offset B'-B' 904 905 910 915 920 904 905 910 915 920 Offset C'-C' 904 905 910 915 904 905 910 915 Offset D'-D' 904 905 910 915 904 905 910 915 EXISTING GRADE FINISH GRADE/ TOP OF SAND (ELEV: 908.00) EXCAVATION LIMIT/ BOTTOM OF SAND (ELEV: 904.50) EXISTING GRADE PR. SAND FILL 3:13 : 1 EXISTING GRADE FINISH GRADE/ TOP OF SAND (ELEV: 908.00) EXCAVATION LIMIT/ BOTTOM OF SAND (ELEV: 904.50) EXISTING GRADE PR. SAND FILL 3:13 : 1 EXISTING GRADE FINISH GRADE/ TOP OF SAND (ELEV: 910.00) EXCAVATION LIMIT/ BOTTOM OF SAND (ELEV: 909.00) EXISTING GRADE PR. SAND FILL 3:13: 1 EXISTING GRADE FINISH GRADE/ TOP OF SAND (ELEV: 910.00) EXCAVATION LIMIT/ BOTTOM OF SAND (ELEV: 909.00) EXISTING GRADE PR. SAND FILL 3:13 : 1 EXISTING GRADE EXISTING GRADE EXISTING GRADE EXISTING GRADE BERM WORK WITH CAPPING REPAIR SE CORNER OF BERM This document, together with the concepts and designs presented herein, as an instrument of service, is intended only for the specific purpose and client for which it was prepared. Reuse of and improper reliance on this document without written authorization and adaptation by Kimley-Horn and Associates, Inc. shall be without liability to Kimley-Horn and Associates, Inc.SHEET NUMBER 2018 KIMLEY-HORN AND ASSOCIATES, INC.767 EUSTIS STREET, SUITE 100, ST. PAUL, MN 55114PHONE: 651-645-4197WWW.KIMLEY-HORN.COMK:\TWC_LDEV\MHC Operating Limited Partnership\3 Design\CAD\PlanSheets\C5-GRADING PLAN RIB SECTIONS.dwg February 01, 2021 - 1:35pm©BYREVISIONSNo.DATEPREPARED FORCROSS SECTIONS -RIBC401CIMARRON PARK RIBSREHABILITATIONMHC OPERATINGLIMITED PARTNERSHIPLAKE ELMOMNDATE:I HEREBY CERTIFY THAT THIS PLAN,SPECIFICATION OR REPORT WAS PREPARED BYME OR UNDER MY DIRECT SUPERVISION ANDTHAT I AM A DULY LICENSED PROFESSIONALENGINEER UNDER THE LAWS OF THE STATE OFMINNESOTA.MNLIC. NO.ALAN L. CATCHPOOL02/01/202147969DATECHECKED BYSCALEDESIGNED BYDRAWN BYKHA PROJECT16010800002/01/2021AS SHOWNEISEISALC PARCEL 1PARCEL 2PARCEL 2PARCEL 3PARCEL 410TH STREET NORTHLAKE ELMO AVENUE NORTH ΔSEE SHEET 4 OF 4 SHEETSFOR TOPOGRAPHIC DETAILSSEE SHEET 2 OF 4 SHEETSFOR TOPOGRAPHIC DETAILSSEE SHEET 3 OF 4 SHEETSFOR TOPOGRAPHIC DETAILSPID#3602921210001CONTACT:KIMLEY-HORNAlan Catchpool, PE767 Eustis StreetSuite 100St. Paul, MN 55114651-393-6164www.kimley-horn.comKH19004SURVKH04TOPOGRAPHICMAPCOUNTY/CITY:REVISIONS:PROJECT LOCATION:LAND SURVEYING, INC.CORNERSTONESuite #2001970 Northwestern AveStillwater, MN 55082Phone 651.275.8969Fax 651.275.8976dan@cssurvey.netDATEREVISIONPROJECT NO.FILE NAME901LEGAL DESCRIPTION:LAKE ELMO AVE. N.1. BEARINGS ARE BASED ON COORDINATES SUPPLIED BY THE WASHINGTONCOUNTY SURVEYORS OFFICE.2. UNDERGROUND UTILITIES SHOWN NOT SHOWN OR LOCATED.3. CONTOURS SHOWN WERE OBTAINED FROM THE MN DNR MnTOPO WEBSITEAND HAVE NOT BEEN FIELD VERIFIED. ELEVATIONS SHOWN WITHIN DETAILEDTOPOGRAPHIC AREAS BASED ON FIELD MEASUREMENTS.4.BOUNDARY LINES SHOWN ARE APPROXIMATE IN NATURE AND ARE FORREFERENCE ONLY. NO FIELD WORK HAS BEEN PERFORMED TO VERIFY THEBOUNDARY LOCATION.5.CERTAIN MOBILE HOME LOCATIONS, ROAD LOCATIONS, AND OTHERIMPROVEMENTS SHOWN ARE APPROXIMATE IN NATURE AND DIGITIZED FROMAVAILABLE AERIAL PHOTOGRAPHY. NO FIELD WORK HAS BEEN DONE TOVERIFY ANY IMPROVEMENT LOCATIONS.6.OTHER ROAD SURFACES EXIST WITHIN THE MOBILE HOME PARK THAT ARENOT SHOWN. MAIN MOBILE HOME PARK ROAD SHOWN FOR REFERENCE ONLYAND WAS DIGITIZED FROM AVAILABLE AERIAL PHOTOGRAPHY.SURVEY NOTES:CITY OF LAKE ELMOWASHINGTONCOUNTYThe following legal description was provided by the owner and appears to match available tax records.PARCEL 1:The South Half of the Southwest Quarter of the Northwest Quarter of Section 36, Township 29 North,Range 21 West of the Fourth Principal Meridian, Washington County, Minnesota.PARCEL 2:The Southwest Quarter of the Northeast Quarter, the Southeast Quarter of the Northwest Quarter, and theNorth Half of the Southwest Quarter of the Northwest Quarter of Section 36, Township 29 North, Range21 West of the Fourth Principal Meridian, Washington County, Minnesota.PARCEL 3:The North Half of the Northeast Quarter of Section 36, Township 29 North, Range 21 West of the FourthPrincipal Meridian, Washington County, Minnesota, except the East 1633.58 feet thereof, and except theWest 10 rods thereof.PARCEL 4:The North Half of the Northwest Quarter and the West 10 rods of the Northwest Quarter of the NortheastQuarter of Section 36, Township 29 North, Range 21 West of the Fourth Principal Meridian, WashingtonCounty, Minnesota, except that part of the Northwest Quarter of Section 36, Township 29, Range 21,described as follows:Commencing at the northwest corner of said Northwest Quarter; thence on an assumed bearing ofSouth, along the west line of said Northwest Quarter, a distance of 290.50 feet; thence North 89degrees 46 minutes 00 seconds East a distance of 60 feet; thence on a bearing of North along a lineparallel with the West line of said Northwest Quarter, a distance of 20.5 feet to the actual point ofbeginning; thence continuing northerly on said parallel line, 60.00 feet; thence North 44 degrees 52minutes 55 seconds East, a distance of 212.57 feet to its intersection with a line parallel with and60.00 feet south of the north line of said Northwest Quarter; thence North 89 degrees 46 minutes 00seconds East along said parallel line 80.50 feet; thence on a bearing of South, 195.00 feet; thencesouthwesterly on a tangential curve concave to the northwest, 23.60 feet, radius of said curve being15.06 feet; thence South 89 degrees 46 minutes 00 seconds West, a distance of 215.50 feet to thepoint of beginning.PID#3602921120001PID#3602921230002PID#360292123000107-22-19PRELIMINARY ISSUE08-05-19ADDITIONAL ROADS09-16-20ADDITIONAL TOPO10-13-20ADDITIONAL TOPO11-27-20POND TOPO INFOCERTIFICATION:I hereby certify that this plan was prepared byme, or under my direct supervision, and that I ama duly Licensed Land Surveyor under the laws ofthe state of Minnesota.Daniel L. Thurmes Registration Number: 25718Date:__________________-NO TITLE WORK PROVIDED FOR THE BENEFIT OF THIS MAP.-EXISTING COUNTY MAPPING AND PREVIOUS SURVEYS INDICATE THERE AREMULTIPLE EASEMENTS AFFECTING THE SUBJECT PROPERTY. CERTAINEASEMENTS OF INTEREST ARE SHOWN ON THE SURVEY. IT IS ASSUMED TITLEWORK WILL BE PROVIDED IN THE FUTURE THAT LIST SAID EASEMENTS.-EASEMENTS OF WHICH WE ARE UNAWARE MAY EXIST-HIGHWAY EASEMENT DIMENSIONS SHOWN ON THIS MAP WERE OBTAINEDFROM AVAILABLE COUNTY MAPPING.TITLE NOTES:CIMARRONLAKE ELMO, MN0NORTH150300PARK EXPANSIONPID#3602921240001PID#3602921130001PRELIM INARYSHEET 1 OF 4BENCHMARKS:ELEVATIONS BASED ON INFORMATION AS SHOWN ON THE MNDOT GEODETICWEBSITE. SURVEY DISK NYBECK MN163 WITH AN ELEVATION OF 941.54 WASUSED TO ESTABLISH VERTICAL CONTROL FOR THIS SURVEY (NAVD 88)SEE SHEETS 2,3 AND 4 OF 4 SHEETS FOR SYMBOLLEGEND AND MONITORING WELL INFORMATION PALMER DRIVEPID#3602921210001CONTACT:KIMLEY-HORNAlan Catchpool, PE767 Eustis StreetSuite 100St. Paul, MN 55114651-393-6164www.kimley-horn.comKH19004SURVKH04TOPOGRAPHICMAPCOUNTY/CITY:REVISIONS:PROJECT LOCATION:LAND SURVEYING, INC.CORNERSTONESuite #2001970 Northwestern AveStillwater, MN 55082Phone 651.275.8969Fax 651.275.8976dan@cssurvey.netDATEREVISIONPROJECT NO.FILE NAME901LAKE ELMO AVE. N.CITY OF LAKE ELMOWASHINGTONCOUNTYPID#3602921120001PID#3602921230002PID#360292123000107-22-19PRELIMINARY ISSUE08-05-19ADDITIONAL ROADS09-16-20ADDITIONAL TOPO10-13-20ADDITIONAL TOPO11-27-20POND TOPO INFOCERTIFICATION:I hereby certify that this plan was prepared byme, or under my direct supervision, and that I ama duly Licensed Land Surveyor under the laws ofthe state of Minnesota.Daniel L. Thurmes Registration Number: 25718Date:__________________CIMARRONLAKE ELMO, MN0NORTH3060PARK EXPANSIONPID#3602921240001PID#3602921130001PRELIM INARY PALMER DRIVE CULVERT DETAILSHEET 4 OF 4LEGEND:UNDERGROUND ELECTRICUNDERGROUND CABLE TVUNDERGROUND FIBER OPTICUNDERGROUND TELEPHONEOVERHEAD UTILITYUNDERGROUND GASSANITARY SEWERSTORM SEWERWATERMAINFENCECURB [TYPICAL]CONTOURSFOUND MONUMENTSET 1/2" IRON PIPEMARKED RLS NO. 25718CABLE TV PEDESTALAIR CONDITIONERELECTRIC MANHOLEELECTRIC METERELECTRIC PEDESTALELECTRIC TRANSFORMERLIGHT POLEGUY WIREPOWER POLEGAS MANHOLEGAS METERTELEPHONE MANHOLETELEPHONE PEDESTALSANITARY CLEANOUTSANITARY MANHOLECATCH BASINSTORM DRAINFLARED END SECTIONSTORM MANHOLEFIRE DEPT. CONNECTIONHYDRANTCURB STOPWATER WELLWATER MANHOLEWATER METERPOST INDICATOR VALVEWATER VALVEBOLLARDFLAG POLEMAIL BOXTRAFFIC SIGNUNKNOWN MANHOLESOIL BORINGSPOT ELEVATIONTRAFFIC SIGNALCONIFEROUS TREEDECIDUOUS TREEBENCHMARKS:ELEVATIONS BASED ON INFORMATION AS SHOWN ON THE MNDOT GEODETICWEBSITE. SURVEY DISK NYBECK MN163 WITH AN ELEVATION OF 941.54 WASUSED TO ESTABLISH VERTICAL CONTROL FOR THIS SURVEY (NAVD 88)DESCRIPTIONNORTHINGEASTINGELEVATIONGW-001178494.98490715.81919.57GW-002179054.42490502.76883.51GW-003179346.06490011.69884.63GW-004178522.71490184.04882.73GW-005177765.16491086.14913.29GW-006177904.4490760.23916.33GW-007177607.04490767.33914.21GW-008177578.24490355.02920.26GW-009178294.92490649.62918.94MONTORING WELLSELEVATIONS SHOWN ON THE ABOVE TABLE ARE MEASUREDTO THE TOP OF THE MONITORING WELL COVER 1000 ft N➤➤N © 2021 Google © 2021 Google © 2021 Google March 29, 2021 City of Lake Elmo Lake Elmo City Hall 3800 Laverne Ave. N. Lake Elmo, MN 55042 Dear City of Lake Elmo, We are the Screaton family.Since 1989,we have owned and farmed the 40-acre parcel directly to the east of the Rapid Infiltration Basins (“RIBs”).The RIBs are located within twenty feet of our parcel.Starting in 2017,wastewater from the RIBs has leaked onto our land,which makes farming the parcel very difficult and impedes future development.In 2017,we notified Cimarron about the leak.Cimarron later told us they had contacted the relevant authorities and were working to fix it. We want a permanent solution to this problem and are satisfied if the Kimley-Horn plan fixes it. However,if the leak persists,we want a commitment that Cimarron will hook up to the sewer as outlined in the 2040 Lake Elmo Comprehensive Plan,Chapter 9, Wastewater: The 2020 Staging Plan includes the extension of a second trunk sewer from the MCES Cottage Grove Ravine Meter Station to serve the portions of the Southeast Planning MUSA from Lake Elmo Avenue to Manning Avenue.In addition to serving new development in this area,service will be extended to the existing Cimarron manufactured home park consisting of approximately 510 units.Cimarron owns and operates a private sewer collection and wastewater treatment system.A new lift station will likely be required to connect to the City sanitary sewer system.This service area also includes the future connection to the existing Oakland Junior High School to replace an existing on-site wastewater facility. Page 320, 9-3. The existing units in the Cimarron manufactured home park will be served by regional sewer between 2030 and 2040 unless environmental threats require a more immediate connection. Page 324, 9-7. (emphasis added). We are concerned this wastewater leak could qualify as an environmental threat warranting a more immediate connection. Attached is a picture showing the proximity of our land to the RIBs. Thank you for the opportunity to provide comment. Sincerely, The Screaton Family