HomeMy WebLinkAbout2022-075CITY OF LAKE ELMO
WASHINGTON COUNTY
STATE OF MINNESOTA
RESOLUTION 2022-075
A RESOLUTION APPROVING A CONDITIONAL USE PERMIT FOR THE
CONSTRUCTION OF A CHAPEL WITH CONDITIONS AT 8249
DEMONTREVILLE TRAIL NORTH
WHEREAS, the City of Lake Elmo is a municipal corporation organized and existing
under the laws of the State of Minnesota; and
WHEREAS, Carmelite Hermitage of the Blessed Virgin Mary (the "Applicant") has
submitted an application to the City of Lake Elmo (the "City") for a Conditional Use Permit for
the construction of a chapel on the property located at 8249 Demontreville Trail North (PID#
0902921120002) (the "Property"); and
WHEREAS, the Lake Elmo Planning Commission held a public hearing on said matter
on July 11, 2022; and
WHEREAS, the Lake Elmo Planning Commission has submitted its report and
recommendation to the City Council as part of a Staff Memorandum dated August 3, 2022; and
WHEREAS, the City Council considered said matter at its August 3, 2022 meeting; and
NOW, THEREFORE, based on the testimony elicited and information received, the
City Council makes the following:
FINDINGS
1) That the procedures for obtaining said Conditional Use Permit are found in the Lake
Elmo Zoning Ordinance, Section 105.12.290.
2) That all the submission requirements of said Section 105.12.290 have been met by the
Applicant.
3) That the proposed Conditional Use Permit is for the construction of a Chapel.
4) The proposed use will not be detrimental to or endanger the public health, safety, comfort,
convenience or general welfare of the neighborhood or the city. The proposed use should
not be detrimental or in any way endanger the public health, safety, comfort.
5) The use or development conforms to the City of Lake Elmo Comprehensive Plan. The
proposed use conforms to the Comprehensive Plan.
6) The use or development is compatible with the existing neighborhood. The proposed use
is permitted in the Public Facilities zoning district subject to a CUR
7) The proposed use meets all specific development standards for such use listed in the
Zoning Code. The proposed use must meet the provisions ofArticle XVI — Public and
Semi -Public Districts.
8) If the proposed use is in a flood plain management or shoreland area, the proposed use
meets all the specific standards for such use listed in Article XIX (Shoreland
Management) and Title I00 (Flood Plain Management). The proposed use must meet the
Shoreland Regulations.
9) The proposed use will be designed, constructed, operated, and maintained so as to be
compatible in appearance with the existing or intended character of the general vicinity
and will not change the essential character of that area. The proposed use will be
compatible in appearance with the existing character of the general vicinity and will not
change the essential character of the area.
I0) The proposed use will not be hazardous or create a nuisance as defined under this
Chapter to existing or future neighboring structures. The proposed chapel is to be set bath
form the public right of way and from adjacent land owners and so should not create a
nuisance to existing or future neighboring structures.
I I)The proposed use will be served adequately by essential public facilities and services,
including streets, police and fire protection, drainage structures, refuse disposal, water
and sewer systems and schools or will be served adequately by such facilities and
services provided by the persons or agencies responsible for the establishment of the
proposeduse. Theproposed chapel will be adequately served hypublic services orfacifides
and served by facihtiesprovided by the applicant
12)The proposed use will not create excessive additional requirements at public cost for
public facilities and services and will not be detrimental to the economic welfare of the
community. The proposed use should not create excessive additional requirements at
public cost.
13)The proposed use will not involve uses, activities, processes, materials, equipment, and
conditions of operation that will be detrimental to any persons, property, or the general
welfare because of excessive production of traffic, noise, smoke, fumes, glare, or odors.
The proposed use should not be detrimental to persons, property, or the general public
welfare.
14) Vehicular approaches to the property, where present, will not create traffic congestion or
interfere with traffic on surrounding public thoroughfares. With the new direct access
(Res 2021-092) the proposed use should not create traffic congestion. The chapel will mainly
be used by members and intermidentguests.
15)The proposed use will not result in the destruction, loss, or damage of a natural or scenic
feature of major importance. The proposed use should not impact natural or scenic
features.
16)That, in accordance with City Code Section 105.12.290, the construction of a chapel shall be
permissible under the Conditions 1-5 as provided in the decision below, and incorporated
herein:
DECISION
NOW, THEREFORE, BE IT FURTHER RESOLVED, and based upon the
information received and the above Findings, that the City Council of the City of Lake Elmo
hereby approves the request by Carmelite Hermitage of the Blessed Virgin Mary for a
Conditional Use Permit for the construction of a chapel on the property located at 8249
Demontreville Trail North, and grants the same, subject to the following conditions of approval:
1) The applicant must obtain all other necessary City, State, and other governing body
permits and approvals before the commencement of any construction activity on the
site. These include, but not limited to, a Valley Branch Watershed District permit,
approval of revised plans by the City Engineer, a building permit, and an on -site
wastewater (septic) permit.
2) No construction by begin until all items and changes outlined by the City Engineer in
the memorandum addressing the Carmelite Chapel Conditional Use Permit and Site
Improvements dated June 20t", 2022 are addressed to the satisfaction of the City
Engineer.
3) No construction may begin until all items outlined by the Fire Chief in his memo dated
June 22nd 2022 are addressed to the satisfaction of the Fire Chief.
4) No construction may begin until the applicant has provided written documentation
demonstrating adequate wastewater management facilities exist or are proposed to serve
the proposed chapel. This should include either a Washington County inspection
compliance report for the existing on -site wastewater system or a wastewater
management plan and permit approved by Washington County to serve the proposed
chapel.
5) If the applicant or owner has not taken action toward starting the chapel or if substantial
construction of the chapel has not taken place within 12 months of the City's approval
of conditional use permit, the CUP approval shall become void. The applicant or owner
may request City Council approval of a time extension to start or implement the
conditional use permit.
Passed and duly adopted this 3rd day of August, 2022 by the City Council of the City of
Lake Elmo, Minnesota.
Milyor Charles Cadenhead
ATTEST:
gJul*hn o , City Clerk