HomeMy WebLinkAbout2023-021CITY OF LAKE ELMO
WASHINGTON COUNTY
STATE OF MINNESOTA
RESOLUTION 2023-021
A RESOLUTION APPROVING A CONDITIONAL USE PERMIT FOR THE
CONSTRUCTION AND OPERATION OF A SOLAR FARM ON THE PROPERTY
LOCATED AT 10755 50TH STREET NORTH
WHEREAS, the City of Lake Elmo is a municipal corporation organized and existing
under the laws of the State of Minnesota; and
WHEREAS, CEF Lake Elmo Community Solar, LLC (the "Applicant") has submitted an
application to the City of Lake Elmo (the "City") for a Conditional Use Permit for the construction
and operation of a solar farm on the property located at 10755 50th Street North (PID#
11.029.21.11.0003) (the "Property"); and
WHEREAS, the Lake Elmo Planning Commission held a public hearing on said matter
on November 22, 2021; and
WHEREAS, the Lake Elmo Planning Commission has submitted its report and
recommendation to the City Council as part of a Staff Memorandum dated March 15, 2022; and
WHEREAS, the City Council considered said matter at its April 5th, 2022 meeting and
voted to deny the conditional use permit request; and
WHEREAS, the Applicant has since revised its landscaping plans to address screening
concerns that were the basis for the City Council's denial of the conditional use permit; and
WHEREAS, pursuant to Minnesota Statutes Sections 462.3595, subdivision 2 and
462.357, subdivision 3, the City Council held a public hearing on March 21, 2023, to consider the
proposed conditional use permit with revised plans; and
NOW, THEREFORE, based on the testimony elicited and information received, the City
Council makes the following:
FINDINGS
1) That the procedures for obtaining said Conditional Use Permit are found in the Lake Elmo
Zoning Ordinance, Section 105.12.290.
2) That all the submission requirements of said Section 105.12.290 have been met by the
Applicant.
LA515-114-860632.v2
3) That the proposed Conditional Use Permit is for the construction and operation of a solar
farm on the property located at 10755 50th Street North.
4) The proposed use will not be detrimental to or endanger the public health, safety, comfort,
convenience or general welfare of the neighborhood or the city. The proposed use will not
be detrimental or in any way endanger the public health, safety, comfort. Conditions
intended to mitigate any potential impact have been included in the CUP, and include
items such as screening, setbacks, and stormwater management.
5) The use or development conforms to the City of Lake Elmo Comprehensive Plan. Chapter
3 of the Comprehensive Plan notes the City has incorporated standards into its zoning
ordinances regarding siting of structures and buildings to support access to solar
resources. Given the City's dominant residential landscape pattern, options for private
property owners including individual homeowners and homeowners' associations to
capitalize on solar energy are supported by the City's adopted ordinances and official
controls.
6) The use or development is compatible with the existing neighborhood. The proposed use
is permitted in the Rural Residential District subject to a CUP. With conditions, the use
is compatible with the existing neighborhood.
7) The proposed use meets all specific development standards for such use listed in Article 7
of this Chapter. The proposed use will meet the specific development standards for a solar
facility with specific conditions.
8) If the proposed use is in a flood plain management or shoreland area, the proposed use
meets all the specific standards for such use listed in Chapter 150, § 150.250 through
150.257 (Shoreland Regulations) and Chapter 152 (Flood Plain Management). The
property is located outside the 0.2% annual chance floodplain and shoreland area.
9) The proposed use will be designed, constructed, operated and maintained so as to be
compatible in appearance with the existing or intended character of the general vicinity and
will not change the essential character of that area. The proposed use will be compatible
in appearance with the existing and intended character of the general vicinity and will
not change the essential character of the area.
10) The proposed use will not be hazardous or create a nuisance as defined under this Chapter
to existing or future neighboring structures. The proposed use will not be hazardous or
create a nuisance. To help ensure this, City staff is recommending conditions for
screening and decommissioning.
11) The proposed use will be served adequately by essential public facilities and services,
including streets, police and fire protection, drainage structures, refuse disposal, water and
sewer systems and schools or will be served adequately by such facilities and services
provided by the persons or agencies responsible for the establishment of the proposed use.
LA515-114-860632.v2
No wastewater or City water facilities are needed to serve this site. The site is otherwise
adequately served by existing City services.
12) The proposed use will not create excessive additional requirements at public cost for public
facilities and services and will not be detrimental to the economic welfare of the
community. The proposed use will not create excessive additional requirements at public
cost.
13) The proposed use will not involve uses, activities, processes, materials, equipment and
conditions of operation that will be detrimental to any persons, property or the general
welfare because of excessive production of traffic, noise, smoke, fumes, glare or odors.
The proposed use will generate 1-3 trips per year on the site.
14) Vehicular approaches to the property, where present, will not create traffic congestion or
interfere with traffic on surrounding public thoroughfares. The proposed use will not
create traffic congestion or interfere with traffic on surrounding public streets.
15) The proposed use will not result in the destruction, loss or damage of a natural or scenic
feature of major importance. The proposed use will not impact a natural or scenic feature.
16) That, in accordance with City Code Section 105.12.290, the Applicant's proposed use of
the Property as a solar farm shall be permissible under the Conditions 1-9 as provided in
the decision below, and incorporated herein:
DECISION
NOW, THEREFORE, BE IT FURTHER RESOLVED, and based upon the information
received and the above Findings, that the City Council of the City of Lake Elmo hereby approves
the request by CEF Lake Elmo Community Solar, LLC for a Conditional Use Permit for the
construction and operation of a solar farm on the property located at 10755 50th Street North, and
grants the same, subject to the following conditions of approval:
Prior to issuance of City permits for the project:
1) Stormwater Management: A stormwater management plan meeting all State, Watershed
District and City rules is required and a permit must be obtained from the Valley Branch
Watershed District. These required details must be included:
a. Soil borings will be required for infiltration basins;
b. If adjacent properties are impacted by stormwater discharge, written permission
from those property owners is required;
c. The storm water facilities must remain privately owned and maintained; and
d. A Stormwater Maintenance and Easement Agreement in the City's standard form
is required.
LA515-114-860632.v2
2) The Applicant must provide to the City Engineer a statement from a qualified engineer
certifying the foundation and design of the solar panels, racking and support is within
accepted professional standards, given local soil and climate conditions.
3) A revised landscape plan should be submitted to address the Landscape Architects memo
dated March 13th 2023 and address reduced tree spacing.
4) Tree plantings must be 9ft. at the time of planting.
5) The Applicant must provide an approved interconnection agreement with Xcel.
6) The Applicant must provide to the Fire Department details about the proposed gate to
ensure it is in compliance with the Fire Code.
7) The Applicant must provide a letter of credit in the amount of $120,652 for
decommissioning the site. The letter of credit must be in good standing at all times and
issued by a bank determined by the City to be solvent and creditworthy. The letter of credit
shall be in a form approved by the City. In the event the letter of credit is not renewed or
is cancelled, the City may revoke the conditional use permit.
8) The Applicant must obtain all other necessary City, State, and other governing body
permits prior to the commencement of any construction activity on the parcel including but
not limited to an approved stormwater management plan, utility plans, grading plan, and
building permits.
General:
8) The Applicant must install a Fire Department lock box for emergency access to the site at
an approved location and provide keys for emergency access into the property and any
controls necessary for emergency use or shut down.
9) The modules and equipment on the site must be removed within 90 days after the site is no
longer operational or has not operated continuously for 12 months. In the event that it is
not removed by that time, the City has permission to enter the property to remove the
modules and equipment and recover its costs from the letter of credit. In the event that the
letter of credit is insufficient to cover the City's costs, the City shall certify the costs against
the property and collect the costs with the property taxes.
Passed and duly adopted this 4th day of April 2023 by the City Council of the City of Lake
Elmo, Minnesota.
Charles Cadenhead, Mayor
ATTEST:
LA515-114-860632.v2
Julie Johnso 9
ty Clerk
LA515-114-860632.v2