HomeMy WebLinkAbout#15 - 2021 Seal Coat and Striping STAFF REPORT
DATE: July 6, 2021
CONSENT
AGENDA ITEM: Accept Quotes and Award Contracts for the 2021 Seal Coat Project and 2021
Striping Project
SUBMITTED BY: Jack Griffin, City Engineer
REVIEWED BY: Kristina Handt, City Administrator
Marty Powers, Public Works Director Mike Rusenovich, Project Engineer
ISSUE BEFORE COUNCIL: Should the City Council accept quotes and award a construction contract
for the 2021 Seal Coat Project and the 2021 Striping Project?
BACKGROUND: In accordance with the city’s annual street maintenance program, certain streets have been scheduled to be seal coated in 2021. See attached Location Map. Streets that have existing pavement markings must be restriped after the seal coat work is complete. The street maintenance work programmed in 2021 was reviewed jointly by Public Works and Engineering to confirm the work to be completed. PROPOSAL DETAILS/ANALYSIS: Quotes for seal coating were solicited from 4 qualified contractors
and 3 quotes were received on June 23, 2021. Asphalt Surface Technologies Corporation submitted the lowest quote of $78,438.00. Quotes for striping were solicited from two qualified contractors. Two quotes were received on June 24, 2021. Sir Lines-A-Lot LLC submitted the lowest quote of $5,379.00. See
attached tabulations for a breakdown of the quotes received. The seal coat work is required to be completed by October 5, 2021 and the striping work by October 15, 2021. FISCAL IMPACT: Total contract to be authorized for the seal coat work is $78,438.00, and the total contract to be authorized for the striping contract is $5,379.00. The project costs are funded through the City’s annual street maintenance budget. RECOMMENDATION: Staff is recommending that the City Council consider, as part of the Consent Agenda, accepting the quotes and awarding a construction contract to Asphalt Surface Technologies Corporation in the amount of $78,438.00 for the 2021 Seal Coat Project and a construction contract to Sir Lines-A-Lot, LLC in the amount of $5,379.00 for the 2021 Striping Project. If removed from the consent agenda, the recommended motion for this action is as follows: “Move to accept the quotes and award a Construction Contract to Asphalt Surface Technologies Corporation in the amount of $78,438.00 for the 2021 Seal Coat Project and a Construction Contract
to Sir Lines-A-Lot, LLC in the amount of $5,379.00 for the 2021 Striping Project.” ATTACHMENTS: 1. Tabulation of Seal Coat Quotes.
2. Tabulation of Striping Quotes. 3. 2021 Seal Coat Project Construction Contract. 4. 2021 Striping Project Construction Contract.
TABULATION OF QUOTES2021 SEAL COAT PROJECTCITY OF LAKE ELMO, MINNESOTAPROJECT NO. 2021.108 QUOTES RECEIVED BY: JUNE 23, AT END OF DAYITEM UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTALNO. DESCRIPTION QUANTITY UNIT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT1BITUMINOUS SEAL COAT WITH 1/8" DRESSER TRAP ROCK AND CRS-2P EMULSIFIED ASPHALT65,300 SY $1.18 $77,054.00 $1.149 $75,029.70 $1.30 $84,890.002PROTECT EXISTING PREFORMED THERMOPLASTIC PAVEMENT MARKING (TURN ARROW)22 EA $30.00 $660.00 $125.00$2,750.00 $120.00 $2,640.003PROTECT EXISTING PREFORMED THERMOPLASTIC PAVEMENT MARKING (12” WIDE CROSSWALK STRIPING)724 LF $1.00 $724.00 $5.00$3,620.00 $5.00 $3,620.00TOTAL$78,438.00 $81,399.70 $91,150.00 $0.00 Asphalt Surface Technologies DID NOT SUBMIT Fahrner Asphalt Sealers Allied Blacktop Company Pearson Bros. Project No. 2021.108Tabulation of Quotes for 2021 Seal Coat ProjectPage 1
TABULATION OF QUOTES2021 STRIPING PROJECTCITY OF LAKE ELMO, MINNESOTAPROJECT NO. 2021.108 QUOTES RECEIVED BY: JUNE 25, AT 10:00 AMITEM UNIT TOTAL UNIT TOTALNO. DESCRIPTION QUANTITY UNIT PRICE AMOUNT PRICE AMOUNT14" SOLID LINE - WHITE EPOXY7,731 LF $0.28 $2,164.68 $0.45 $3,478.9524" SOLID LINE - YELLOW EPOXY5,315 LF $0.28 $1,488.20 $0.45 $2,391.7534" DOUBLE SOLID LINE - YELLOW EPOXY2,252 LF $0.56 $1,261.12 $0.90 $2,026.80424" SOLID LINE - WHITE EPOXY STOP BARS30 LF $12.00 $360.00 $9.00 $270.005PAVEMENT MESSAGE TURN ARROWS - WHITE EPOXY1 EA $105.00 $105.00 $120.00 $120.00TOTAL $5,379.00 $8,287.50 Sir Lines-A-Lot LLC AAA Striping Service Co. Project No. 2021.108 Tabulation of Quotes for 2021 Striping ProjectPage 1
Table of Contents for 2021 Seal Coat Project May, 2021
CITY OF LAKE ELMO, MINNESOTA
2021 SEAL COAT PROJECT
PROJECT NO. 2021.108
TABLE OF CONTENTS
TITLE PAGES
Cover & Table of Contents 1
Construction Contract 2
Quote Proposal 1
Location Map 1
Street List 1
Specifications
0410 Responsible Contractor Verification 1
1100 Summary of Work 2
3212 Seal Coating 1
Project No. 2021.108 General Conditions for 2021 Seal Coat Project Page 1 of 2
State of Minnesota
Washington County
CONSTRUCTION CONTRACT FOR THE
2021 SEAL COAT PROJECT
LAKE ELMO, MINNESOTA
This Contract, made this _______ day of __________ 2021, by the City of Lake Elmo, Minnesota (herinafter called the “Owner”) and
___Asphalt Surface Technologies Corporation___ (hereinafter called the “Contractor”).
WITNESSETH that the parties hereto agree as follows:
The Contractor shall provide all labor, services, materials, equipment and machinery, transportation, tools, fuel, power, light, heat,
telephone, water, sanitary facilities, temporary facilities, and all other facilities and incidentals, including profit and overhead,
necessary for the performance, testing, start-up, and completion of the work as described herein:
IN WITNESS WHEREOF, the parties hereto have executed this contract as of the date first above written.
(Contractor) (City of Lake Elmo)
DESCRIPTION OF WORK: The Contractor shall place signage, sweep clean, and seal coat the streets shown on the attached
Location Map dated November, 2020 for Lake Elmo. The work shall be completed per the applicable MnDOT Standard
Specifications for Construction (2018 Edition) and in accordance with the specifications and special provisions outlined within this
Construction Contract. The Contractor shall provide all necessary traffic control in accordance with the MMUTCD.
Bituminous material shall be MnDOT 2356, CRS-2P Emulsified Asphalt. Cover aggregate material shall be 1/8 inch Dresser Trap
Rock, or approved equal.
All work shall be in accordance with MnDOT “Standard Specifications for Construction”, Section 2356. In addition, the following
requirements shall apply: Cleaning and sweeping of the streets prior to the seal coating shall be done by the Contractor. Pavement
markings shall be tabbed prior to seal coating. Existing preformed thermoplastic pavement markings shall be protected before seal
coating. Following the seal coating process, the Contractor shall remove the preformed pavement marking protection. Sweeping
the excess seal coat aggregate from the streets and picking it up after seal coating will be done by the Contractor. Excess aggregate
shall be swept up no sooner than five (5) days after the seal coat application, depending on the breaking and curing of the asphalt,
as determined by the Engineer. 5 days following the seal coat, the contractor shall perform an initial sweep of the project area to
remove surplus aggregate unless otherwise directed by the Engineer. 30 days following the initial sweeping, the Contractor shall
sweep off the remaining surplus aggregate over the project area. All surplus aggregate shall be swept up by the Contractor as
determined by the Engineer. Multiple pick-up sweeps may be required if excess seal coat aggregate remains on the street, as
determined by the Engineer. Excess seal coat aggregate resulting from street sweeping shall be disposed of by the Contractor.
Cleaning and sweeping shall be considered incidental to the unit prices shown on the Quote Form. The Contractor shall be
responsible for signing or otherwise preventing the parking of vehicles on the street the day of seal coating. Any areas which
cannot be sealed due to parked vehicles shall be touched up by the Contractor after the vehicle can be moved. No additional
compensation will be given.
The bituminous seal coating material application rates shall be:
A. Emulsified Asphalt to be applied at 0.24-0.26 gallons per square yard.
B. 1/8 inch Dresser Trap Rock, or approved equal to be applied at 20-23 pounds per square yard.
C. Application rates may be varied by the Engineer in the field as different surface conditions are encountered.
D. Load tickets from the refinery and weight tickets shall be furnished to the Engineer
All seal coat work shall carry a one-year warranty period against any loss of adhesion.
The Contractor will be paid per Square Yard for work completed in accordance with the Construction Contract.
All work shall be completed within the specified time frame and under the terms and conditions provided within this Construction
Contract, and in accordance with the “General Conditions” shown in this contract. The contractor shall complete the proposed
work by OCTOBER 5, 2021.
The Owner will make payment for the whole contract upon acceptance by the Owner of all work required hereunder and in
compliance with all the terms and conditions of this contract.
TOTAL AMOUNT (INSERT FROM QUOTE FORM): ____$78,438.00______
Project No. 2021.108 General Conditions for 2021 Seal Coat Project Page 2 of 2
GENERAL CONDITIONS
I. CHANGES IN WORK. - The Owner may at any time, make changes in the drawings and specifications, within the general scope thereof. If
such changes cause an increase or decrease in the amount due under this contract or in the time required for its performance, an
equitable adjustment will be made, and this contract will be modified accordingly by a “Contract Change Order”. No charge for any extra
work or material will be allowed unless the same has been ordered on such contract change order by the Owner and the price therefore
stated in the order.
II. INSPECTION OF WORK. - All materials and workmanship will be subject to inspection, examination, and test, by the Owner, who will have
the right to reject defective material and workmanship or require its correction.
III. COMPLETION OF WORK. - If the Contractor refuses or fails to complete the work within the time specified in this contract, or any
extension thereof, the Owner may terminate the Contractor’s rights to proceed. In such event the Owner may take over the work and
prosecute the same to completion by contract or otherwise, and the Contractor will be liable for any excess cost occasioned the Owner
thereby; and the Owner may take possession of and utilize in completing the work such materials and equipment as may be on the site of
the work and necessary therefore. If the Owner does not terminate the right of the Contract to proceed, the Contractor will continue the
work, in which event, actual damages for delay will be impossible to determine, and in lieu thereof, the Contractor may be required to
pay to the Owner the sum of $100 as liquidated damages for each calendar day of delay, and the Contractor will be liable for the amount
thereof: Provided, however, that the right of the Contractor to proceed will not be terminated because of delays in the completion of the
completion of the work due to unforeseeable causes beyond the Contractor’s control and without Contractor’s fault or negligence.
IV. RELEASES. - Prior to final payment, the Contractor will submit evidence that all payrolls, material bills, and other indebtedness connected
with the work have been paid as required by the Owner.
V. OBLIGATION TO DISCHARGE LIENS. - Acceptance by the Owner of the completed work performed by the Contractor and payment
therefore by the Owner will not relieve the Contractor of obligation to the Owner (which obligation is hereby acknowledged) to discharge
any and all liens for the benefit of subcontractors, laborers, material-person, or any other persons performing labor upon the work or
furnishing material or machinery for the work covered by this contract, which have attached to or may subsequently attach to the
property, or interest of the Owner.
VI. NOTICES AND APPROVAL IN WRITING. - Any notice, consent, or other act to be given or done hereunder will be valid only if in writing.
VII. CLEANING UP. - The Contractor shall keep the premises free from accumulation of waste material and rubbish and at the completion of
the work shall remove from the premises all rubbish, implements and surplus materials.
VIII. WARRANTY. - Contractor warrants and guarantees that title to all work, materials, and equipment covered by any Application for
Payment, whether incorporated in the Project or not, will pass to Owner no later than the time of payment free and clear of all Liens. If
within one year after completion of the work, any work is found to be defective, Contractor shall promptly, without cost to the Owner,
correct such defective work as approved by the Owner.
IX. INDEMNIFICATION. - Contractor shall defend and indemnify the city against claims brought or actions filed against the city or any of its
officers, employees or agents for property damage, bodily injury or death to third persons, arising out of or relating to contractors work
under the contract.
X. WORKERS’ COMPENSATION INSURANCE. - Contractor shall provide a certificate of insurance showing evidence of workers’ compensation
coverage or provide evidence of qualification as a self-insurer of workers’ compensation.
XI. LIABILITY INSURANCE REQUIREMENTS. – A certificate of insurance acceptable to the City shall be filed with the City prior to the
commencement of the work. The certificate and the required insurance policies shall contain a provision that the coverage afforded
under the contract will not be canceled or allowed to expire until at least 30 days prior written notice has been given to the city.
Contractor shall maintain commercial general liability (CGL) insurance with a limit of not less than $1,000,000 each occurrence and an
aggregate limit of not less than $2,000,000. The CGL insurance shall cover liability arising from premises, operations, independent
contractors, subcontractors, products-completed operations, personal injury and advertising injury, and contractually-assumed liability.
The City and FOCUS Engineering, Inc. shall be named as an additional insured under the CGL. Contractor shall maintain automobile
liability insurance, and if necessary, umbrella liability insurance with a limit of not less than $1,000,000 each accident and an aggregate
limit of not less than $2,000,000. The insurance shall cover liability arising out of any auto, including owned, hired, and non-owned autos.
36
10th
60th
5th
HudsonKeats Lake Elmo50th
15th Inwood34th
20th
27th
53rd
55th
Jane
Lake Jane
Jamaca57th
59th
Hill
47th
7th
31st
51st
43rd
39th Demontreville45th
38th
ManningStillwater
24th26th
42nd
Island58th9th
30th
32ndKimbro
21st
Jade6thIvoryHill
t
o
p
IsleOls
o
n
L
a
k
e
8thJulep
12th
Jewel
44th
56th
Iris22nd
37th
36th
35th LaverneJuniperAnnikaJasmineJamley LegionLily
Klondike16th
Upper 33Rd
ImperialLinden3rdKirkwood 33rd
Deer PondHytrail
IrvingHidden Bay4thJerome14thJune28th VillageTapestryJasper
Eagle Point
Jonquil
Wildflower
LaytonPrivateKelvinIronwoodHighlandsJaneroLe
e
w
a
r
d
Cimarron10th StreetKindr
e
d
JamesIrishPrairievie
wJack Pine49th
JayLower 31st
Marquess
IrvinLilacMonarchLower 8th LisbonBirch Bark40thLavender
KraftLampertBlazingstarWhistling Valley
Junco Little Bluestem
11thLady Slipper5t
h
S
t
r
e
e
t
Windbreak
Sunfish Lake Park InboundIvywoodInnsdale3rd Street Marquess TrailLang
l
y
JunoLan
s
i
n
g
JulianneUpper 30th
6th
S
t
r
e
e
t
Lisbon AvenueIrwinSunflower
41st
WB I9
4
T
o
I
n
w
o
o
d
A
v
e
N
Upper 7t
h
Queen
Upper 9th 57th StreetUpper 42Nd
27
t
h
S
t
r
e
e
t
15th Stree
t
Cherrywood
WB I94 To Keats
A
v
e
N
44th Street
41st Street
Jas
m
i
n
e
A
v
e
n
u
e
59th Street
HummingbirdJero
m
e
A
v
e
n
u
e
Keats Ave N To
W
B
I
9
4
Manning Ave N To W
B
I
9
4
Hill Trail
30th Street33rd Street24t
h
S
t
r
e
e
t
20th Street58th StreetLegion Lane
Lark
s
p
u
r
Demontreville Trail
HummingbordAccess21st
Laverne57th Street32nd ManningIrish35th
34th LilyLilac
55th
Jamaca
35th
Laverne56th
Stillwater36
Lake ElmoLanglyLaytonLilac33rd Lily10th StreetMan
n
i
n
g
6th StreetIsle21st
9th
57th
36th
Kirkwood
53rd
Linde
n
Whistling ValleyManning
50th
5th
33rd
Highlands
59th
6th Street
Innsda
le
Ir
o
nw
o
o
d
Linden
Legion Lane
LindenPrivate
Julep28th VillageLilac
IvyInnsdaleLower 8th
31st
57th
Lisbon
9th
39thKeats55th56th36
IsleJulepIrvin55th
Manning32nd
Laverne37thKelv
in
ManningLegion9th
Ivy
34th
LaytonLindenJade5thHudson
36th
39th
DOWNSLAKE
LAKE ELMOREGIONALPARK RESERVE
LAKE ELMO
LAKE JANE
SUNFISH LAKE
OLSONLAKE
LAKE DEMONTREVILLE
CLEARLAKE
HORSESHOELAKE
ROSELAKE
REIDPARK
VFWPARK
LIONS PARK
TANA RIDGEPARK
City of Woodbury
STONEGATEPARK
KRAMERLAKE
GOOSELAKEARMSTRONGLAKE
RIDGEPARK
KEATS AVE NEAGLE POINTLAKE
TABLYNPARK
HEIGHTSPARK
LAKE JANEHILLS PARK
PEBBLEPARK
City of Oakdale
West LakelandTownship
Baytown Township
City ofOak ParkHeights
City of GrantCity ofPine Springs
DEMONTREVILLEWILDLIFE PARK
DEMONTREVILLEPARK
KLEISPARK CARRIAGESTATIONPARK
SUNFISH LAKEPARK
City ofOak ParkHeights
StillwaterTownship
HOMESTEDPARK
7
HERITAGEPARK
VERONICAPOND
GOETSCHEL'SPOND
City ofAfton
TablynPark
Eagle PointCreek Estates
Lake ElmoHeights
Torre Pines
Farms ofLake Elmo
Parkview Estates
WildflowersShores
HuppertAdd
BeautCrest Estates FriedrichHghts
Kenridge Add
Prairie RidgeOffice Park
Eagle PointBusiness Park
Stonegate
Hammes CountryVista
Whistling Valley
MidlandMeadows
DavidNelson Est
TheHomestead
TartanMeadows
The Forest
Schwartz-Martinco Add
PackardPark
EdenPark
HeritageFarm
LonesomePine Add
DownsLake Est
MyronEllman
Elmo View
Cty AudPlat No. 8
Lake Elmo Park
Brookman Add
Sunfish Ponds
Hamlet OnSunfish Lake
ParkMeadows
Tapestry AtCharlottes' Grove
Berschen's Shores
DawcinAcres
LakeJaneHighlands
TealPass Est
Fox FireEstates
Meyer'sPineridgeKrausesAdd
Springborn'sGreen Acres
Arabian Hills
JudithMaryManor
Lake Elmo Vista
Rolling Hills Est
Prairie Hamlet
HiddenMeadowsOf Lake Elmo
Jesse'sHideaway
DiscoverCrossing
Arvold'sAcres
St. Croix'sSanctuary
TamarackFarm Est
CarriageStation
TanaRidgeJohn M DayFarm Add
The Fields ofSt. Croix2nd Add
The Fieldsof St. Croix
BluestemAt The Fieldsof St. Croix
BurrwoodEstBergmannAdd
DemontrevilleHighlands Add
Lane's DemontrevilleCountry ClubDemontrevilleHighlands Add
Olson Lake Add
Oace AcresAdd
LakeJaneHills
Lake JaneManor No. 1
ThreeLakesFarm Add
Bordners Garner
Farmettes
Royal Golf Club
Southwind
Hunters Crossing
HammesEstates
Savona
Boulder Ponds
Inwood
Lakewood Crossing2nd Addition
Easton Village
Wildflower
Cimarron
Legacy At Northstar
Village Preserve
ST. CROIX SANCTUARY PARK
EDENPARK
PILOTPARK
HAMMESPARK
GOOSE LAKEPARK
F
Map Date: November 2020010.5 Miles
Created By: Planning Department
Street SegmentFrom To DevelopmentLength Width CDS Area (SF) Area (SY)39TH ST N * MN TH 5 (STILLWATER BLVD) LAVERNE AVE N MSAS 1,589.00 28 0 44,492.00 4,943.5639TH ST N * CSAH 17 (LAKE ELMO AVE) LAVERNE AVE N MSAS 845.00 28 0 23,660.00 2,628.89JAMLEY AVE N 28TH ST N 31ST ST N 2016 Street Imp Addendum 1 1,820.00 20 0 36,400.00 4,044.44HIGHLANDS TRL N HILLTOP AVE N DEMONTREVILLE TRL N 2016 Street Imp Addendum 1 1,350.00 32 0 43,200.00 4,800.007TH ST N 5TH ST N JAY AVE N Savona 1st - 3rd 913.00 23 0 20,999.00 2,333.227TH ST N JAY AVE N JUNIPER CT N Savona 1st - 3rd 266.00 23 0 6,118.00 679.787TH ST N JUNIPER CT N JAMES AVE N Savona 1st - 3rd 991.00 23 0 22,793.00 2,532.56JAY AVE N (EAST) 7TH ST N 5TH ST N Savona 1st - 3rd 318.00 16 0 5,088.00 565.33JAY AVE N (WEST) 7TH ST N 5TH ST N Savona 1st - 3rd 341.00 16 0 5,456.00 606.22JUNIPER AVE N NORTH LIMITS 7TH ST N Savona 1st - 3rd 388.00 23 0 8,924.00 991.56JUNIPER CT N 7TH ST N CUL-DE-SAC Savona 1st - 3rd 433.00 23 0 9,959.00 1,106.56JUNIPER CT N CUL-DE-SAC CUL-DE-SAC Savona 1st - 3rd 222.00 19 0 4,218.00 468.675TH ST N (WHEN SOUTH SIDE WIDER) (North) * KEATS AVE (CSAH 19) NORTH SIDE WIDER Savona 1st - 3rd 326.00 15 0 4,890.00 543.335TH ST N (WHEN SOUTH SIDE WIDER) (South) * KEATS AVE (CSAH 19) NORTH SIDE WIDER Savona 1st - 3rd 326.00 24 0 7,824.00 869.335TH ST N (WHEN NORTH SIDE WIDER) (North) * SOUTH SIDE WIDER 7TH ST Savona 1st - 3rd 220.00 24 0 5,280.00 586.675TH ST N (WHEN NORTH SIDE WIDER) (South) * SOUTH SIDE WIDER 7TH ST Savona 1st - 3rd 220.00 15 0 3,300.00 366.675TH ST N (WHEN SOUTH SIDE WIDER) (North) * 7TH ST N NORTH SIDE WIDER Savona 1st - 3rd 401.00 15 0 6,015.00 668.335TH ST N (WHEN SOUTH SIDE WIDER) (South) * 7TH ST N NORTH SIDE WIDER Savona 1st - 3rd 401.00 24 0 9,624.00 1,069.335TH ST N (WHEN NORTH SIDE WIDER) (North) * SOUTH SIDE WIDER JAY AVE N Savona 1st - 3rd 403.00 36 0 14,508.00 1,612.005TH ST N (WHEN NORTH SIDE WIDER) (South) * SOUTH SIDE WIDER JAY AVE N Savona 1st - 3rd 403.00 15 0 6,045.00 671.675TH ST N (WHEN SOUTH SIDE WIDER) (North) * JAY AVE N NORTH SIDE WIDER Savona 1st - 3rd 420.00 15 0 6,300.00 700.005TH ST N (WHEN SOUTH SIDE WIDER) (South) * JAY AVE N NORTH SIDE WIDER Savona 1st - 3rd 420.00 36 0 15,120.00 1,680.005TH ST N (WHEN NORTH SIDE WIDER) (North) * SOUTH SIDE WIDER JUNCO RD N Savona 1st - 3rd 248.00 24 0 5,952.00 661.335TH ST N (WHEN NORTH SIDE WIDER) (South) * SOUTH SIDE WIDER JUNCO RD N Savona 1st - 3rd 248.00 15 0 3,720.00 413.335TH ST N * JUNCO RD N WEST END 3RD ADD Savona 1st - 3rd 941.00 51 0 47,991.00 5,332.33JAMES AVE N NORTH LIMITS 7TH ST N Savona 1st - 3rd 189.00 23 0 4,347.00 483.00JAMES AVE N 7TH ST N JUNCO RD N Savona 1st - 3rd 308.00 23 0 7,084.00 787.11JAMES AVE N JUNCO RD N WEST LIMITS Savona 1st - 3rd 341.00 23 0 7,843.00 871.44JUNCO RD N JAMES AVE N 5TH ST N Savona 1st - 3rd 922.00 23 0 21,206.00 2,356.22JUNCO RD N JUNCO RD N JUNCO RD N Savona 1st - 3rd 260.00 23 0 5,980.00 664.446TH ST LN N JAMES AVE N WEST END 3RD ADD Savona 1st - 3rd 814.00 23 0 18,722.00 2,080.225TH ST LN N 5TH ST N SPLIT Savona 1st - 3rd 1,347.00 23 0 30,981.00 3,442.335TH ST LN N SPLIT 5TH ST N Savona 1st - 3rd 170.00 32 0 5,440.00 604.4440TH ST N LADY SLIPPER RD N WILDFLOWER DR N Village Preserve 1st - 2nd 406.00 24 0 9,744.00 1,082.6741ST ST N (North) LAKE ELMO AVE (CSAH 17) LADY SLIPPER RD N Village Preserve 1st - 2nd 219.00 14 0 3,066.00 340.6741ST ST N (South) LAKE ELMO AVE (CSAH 17) LADY SLIPPER RD N Village Preserve 1st - 2nd 219.00 14 0 3,066.00 340.6741ST ST CIR N LADY SLIPPER RD N CUL-DE-SAC Village Preserve 1st - 2nd 406.00 23 45 15,699.73 1,744.41LADY SLIPPER CT N LADY SLIPPER RD N CUL-DE-SAC Village Preserve 1st - 2nd 124.00 23 45 9,213.73 1,023.75LADY SLIPPER RD N 41ST ST N LADY SLIPPER CT N Village Preserve 1st - 2nd 366.00 24 0 8,784.00 976.00LADY SLIPPER RD N 41ST ST N 40TH ST N Village Preserve 1st - 2nd 1,002.00 24 0 24,048.00 2,672.00UPPER 42ND ST N LADY SLIPPER CT N LAVERNE CIR N Village Preserve 1st - 2nd 720.00 23 0 16,560.00 1,840.00LAVERNE CIR N UPPER 42ND ST N CUL-DE-SAC Village Preserve 1st - 2nd 77.00 23 45 8,132.73 903.64LAVERENE AVE N LAVERNE CIR N 40TH ST N Village Preserve 1st - 2nd 865.00 23 0 19,895.00 2,210.56TOTALS 587,690.00 65,300.00* Tab pavement markings on indicated streets prior to seal coating. (Incidental)2021 SEAL COAT PROJECT - LAKE ELMO
CITY OF LAKE ELMO, MN | PROJECT NO. 2020.108 SUMMARY OF WORK 1100-1
SECTION 1100 – SUMMARY OF WORK
GENERAL REQUIREMENTS
1. WORK COVERED BY CONTRACT DOCUMENTS: Under this Section of the Specifications the work contemplated
consists of furnishing all labor, materials, skills, equipment, and facilities required for a complete seal coat
treatment for the designated streets provided for within these Plans and Specifications. The work shall
include:
A. Place signs indicating “No Parking–Seal Coating Tomorrow” or similar language. Notification must be
provided at least 24-hours but not more than 36-hours in advance of work.
B. Place signs indicating “Loose Gravel” on each street to be seal coated (locations to be approved by the
Engineer). All signs shall be installed prior to the commencement of seal coating operations. The
Contractor shall remove said signs within 48 hours of completing all sweeping of excess aggregate.
C. Sweep the streets clean and free of debris before the bituminous application. Streets must be free from
any standing water before the bituminous application.
D. Place sand or felt over gate valves and manholes before placing bituminous material on streets. The sand
or felt will be supplied by the Contractor.
E. Delineate existing pavement markings along all streets (pavement markers to be approved by the
Engineer). Place protection for existing preformed thermoplastic pavement markings as directed by
engineer.
F. Place the bituminous material.
G. Place the cover aggregate.
H. Roll the surface with pneumatic tired rollers.
I. Remove protection of preformed thermoplastic pavement markings.
J. Pick up sweep and properly dispose of the excess cover aggregate and general cleanup. Excess aggregate
shall be swept up no sooner than five (5) days after the seal coat application, depending on the breaking
and curing of the asphalt, as determined by the Engineer. 5 days following the seal coat, the contractor
shall perform an initial sweep of the project area to remove surplus aggregate unless otherwise directed
by the Engineer. 30 days following the initial sweeping, the Contractor shall sweep off the remaining
surplus aggregate over the project area. All surplus aggregate shall be swept up by the Contractor as
determined by the Engineer. All required sweeping events shall be considered incidental to the Contract
with no additional compensation. The surplus aggregate swept from the streets shall be the responsibility
of the Contractor.
2. TRAFFIC CONTROL: The Contractor shall be responsible for signing or otherwise preventing the parking of
vehicles on the street the day of seal coating. Any areas which cannot be sealed due to parked vehicles shall
be touched up by the Contractor after the vehicle can be moved. No additional compensation will be given.
The Contractor shall provide all necessary traffic control in accordance with the Minnesota Manual on Uniform
Traffic Control Devices (MMUTCD). All signage must be removed within 48-hours of completing the work. All
traffic control and mobilization is incidental to the Contract.
3. SEQUENCE OF WORK: All work must be completed in accordance with Section 3.02 and 3.03 of the
Agreement and according to each milestone listed herein. Once the Contractor initiates the placement of
CITY OF LAKE ELMO, MN | PROJECT NO. 2020.108 SUMMARY OF WORK 1100-2
bituminous material on any street for the project the work must proceed diligently without interruption until
all aggregate has been placed and rolled for all streets scheduled for seal coating, except for interruptions to
work operations due to contract working hours and/or weather conditions. The Contractor must begin
sweeping of excess aggregate on the fifth day following the final placement of the aggregate, unless otherwise
approved by the Engineer. Once sweeping operations begin, the sweeping work must proceed diligently
without interruption until all excess aggregate has been removed for all streets on the project, except for
interruptions to work operations due to contract working hours and/or weather conditions.
4. WORK UNDER OTHER CONTRACTS: The City may choose to perform minor repairs or seal individual cracks
prior to seal coating. The Contractor must obtain approval from the City prior to seal coating any street
segment.
5. WORK LOCATION: The streets to be seal coated are listed in the Appendix.
6. CONTRACTOR USE OF PREMISES: The Contractor’s operations shall be confined to the areas covered in the
right-of-way and easements granted to the Owner. Any procedures by the Contractor of any sort beyond the
limits indicated shall be the sole responsibility of the Contractor who shall save the Owner harmless from any
claim for damages due to trespassing.
7. MEASUREMENT AND PAYMENT: Seal coating shall be measured and paid by the Square Yard of the actual
area covered with bituminous material and cover aggregate and shall cover all costs associated with a
complete project as specified herein (including delineation of any existing striping and additional pick-up
sweep events necessary as determined by the Engineer).
8. WARRANTY: In accordance with the Section 13.07 of the Supplementary Conditions, all seal coat work shall
carry a one-year warranty period against any loss of adhesion.
CITY OF LAKE ELMO, MN | PROJECT NO. 2021.108 SEAL COATING 3212-1
SECTION 3212 – SEAL COATING
SCOPE
Under this Section shall be included the furnishing of all material, equipment, labor and skills necessary to
construct a bituminous seal coat.
GENERAL REQUIREMENTS
1. BASIS OF PAYMENT: Measurement and Payment shall be by the square yard, complete in place and paid for
the price in the BID PROPOSAL.
PRODUCTS
1. BITUMINOUS MATERIAL: The material shall be Mn/DOT 2356, CRS-2P Emulsified Asphalt. Bituminous material
shall be measured by gallon volume of material at 60 degrees F from manifest collected with each load
received at the site on the day the material is actually placed.
2. COVER AGGREGATE: The material shall be 1/8 inch Dresser Trap Rock, or approved equal. Aggregate shall be
delivered by Ton on the basis of weight tickets received at the site on the day the material is actually placed to
check application rate.
EXECUTION
1. GENERAL: All work shall be in accordance with Mn/DOT “Standard Specifications for Construction”, Section
2356. In addition, the following requirements shall apply.
2. STREET SWEEPING: Cleaning and sweeping of the streets prior to the seal coating shall be done by the
Contractor. Sweeping the excess seal coat aggregate from the streets and picking it up after seal coating will
be done by the Contractor. Multiple pick-up sweeps may be required if excess seal coat aggregate remains on
the street, as determined by the Engineer. Excess seal coat aggregate resulting from street sweeping shall be
disposed of by the Contractor. Cleaning and sweeping shall be considered incidental to the unit prices shown
in the Bid Proposal.
3. TRAFFIC CONTROL: The Contractor shall be responsible for signing or otherwise preventing the parking of
vehicles on the street the day of seal coating. Any areas which cannot be sealed due to parked vehicles shall
be touched up by the Contractor after the vehicle can be moved. No additional compensation will be given.
4. APPLICATION RATES: The bituminous seal coating material application rates shall be:
A. Emulsified Asphalt to be applied at 0.24-0.26 gallons per square yard.
B. 1/8 inch Dresser Trap Rock, or approved equal to be applied at 20-23 pounds per square yard.
C. Application rates may be varied by the Engineer in the field as different surface conditions are
encountered.
D. Load tickets from the refinery and weight tickets shall be furnished to the Engineer.
Table of Contents for 2021 Striping Project June, 2021
CITY OF LAKE ELMO, MINNESOTA
2021 STRIPING PROJECT
PROJECT NO. 2021.108
TABLE OF CONTENTS
TITLE PAGES
Cover & Table of Contents 1
Construction Contract 2
Quote Form 1
Location Map 1
Street List & Striping Tabulation 1
Record Striping Plans
39th Street N 1
5th Street N 3
Specifications: 3217 Pavement Markings 3
Project No. 2021.108 General Conditions for 2021 Striping Project Page 1 of 2
State of Minnesota
Washington County
CONSTRUCTION CONTRACT FOR THE
2021 STRIPINGPROJECT
LAKE ELMO, MINNESOTA
This Contract, made this ________ day of ___________ 2021, by the City of Lake Elmo, Minnesota (herinafter called the “Owner”)
and ___Sir Lines-A-Lot LLC____ (hereinafter called the “Contractor”).
WITNESSETH that the parties hereto agree as follows:
The Contractor shall provide all labor, services, materials, equipment and machinery, transportation, tools, fuel, power, light, heat,
telephone, water, sanitary facilities, temporary facilities, and all other facilities and incidentals, including profit and overhead,
necessary for the performance, testing, start-up, and completion of the work as described herein:
IN WITNESS WHEREOF, the parties hereto have executed this contract as of the date first above written.
(Contractor) (City of Lake Elmo)
DESCRIPTION OF WORK: The Contractor shall place epoxy pavement markings for the City of Lake Elmo on the streets shown
on the attached Location Map, dated November, 2020, and in accordance with the attached Street List and Striping Tabulation
form dated June, 2021. All pavement markings shall be Epoxy Resin with Drop-on Glass Beads. The Contractor shall provide all
necessary traffic control in accordance with the MMUTCD.
All work shall be in accordance with City of Lake Elmo Specifications, Section 3217 Pavement Markings and applicable MnDOT
“Standard Specifications for Construction (2018 Edition)”.
Placement of epoxy materials shall be permitted only on a clean, dry pavement surface and air and pavement temperatures must be
at least 50 degrees F. Markings shall not be applied when the wind or other conditions cause a film of dust to be deposited on the
pavement surface before the material can be applied. Permanent pavement markings shall not be placed over temporary tape
markings.
All pavement markings not conforming to the requirements of the Contract shall be removed and replaced or otherwise repaired to
the satisfaction of the Engineer. Removal of unacceptable work shall be accomplished with suitable blasting or grinding equipment
unless other means are authorized by the Engineer.
The Contractor will be paid per Linear Foot for line markings and Per Each for symbols and turn arrows completed in accordance
with the Construction Contract.
All work shall be completed within the specified time frame and under the terms and conditions provided within this Construction
Contract, and in accordance with the “General Conditions” shown in this contract. The contractor shall complete the proposed
work by OCTOBER 15, 2020.
The Owner will make payment for the whole contract upon acceptance by the Owner of all work required hereunder and in
compliance with all the terms and conditions of this contract.
TOTAL AMOUNT (INSERT FROM QUOTE FORM): _______$5,379.00______
Project No. 2021.108 General Conditions for 2021 Striping Project Page 2 of 2
GENERAL CONDITIONS
I. CHANGES IN WORK. - The Owner may at any time, make changes in the drawings and specifications, within the general scope thereof. If
such changes cause an increase or decrease in the amount due under this contract or in the time required for its performance, an
equitable adjustment will be made, and this contract will be modified accordingly by a “Contract Change Order”. No charge for any extra
work or material will be allowed unless the same has been ordered on such contract change order by the Owner and the price therefore
stated in the order.
II. INSPECTION OF WORK. - All materials and workmanship will be subject to inspection, examination, and test, by the Owner, who will have
the right to reject defective material and workmanship or require its correction.
III. COMPLETION OF WORK. - If the Contractor refuses or fails to complete the work within the time specified in this contract, or any
extension thereof, the Owner may terminate the Contractor’s rights to proceed. In such event the Owner may take over the work and
prosecute the same to completion by contract or otherwise, and the Contractor will be liable for any excess cost occasioned the Owner
thereby; and the Owner may take possession of and utilize in completing the work such materials and equipment as may be on the site of
the work and necessary therefore. If the Owner does not terminate the right of the Contract to proceed, the Contractor will continue the
work, in which event, actual damages for delay will be impossible to determine, and in lieu thereof, the Contractor may be required to
pay to the Owner the sum of $100 as liquidated damages for each calendar day of delay, and the Contractor will be liable for the amount
thereof: Provided, however, that the right of the Contractor to proceed will not be terminated because of delays in the completion of the
completion of the work due to unforeseeable causes beyond the Contractor’s control and without Contractor’s fault or negligence.
IV. RELEASES. - Prior to final payment, the Contractor will submit evidence that all payrolls, material bills, and other indebtedness connected
with the work have been paid as required by the Owner.
V. OBLIGATION TO DISCHARGE LIENS. - Acceptance by the Owner of the completed work performed by the Contractor and payment
therefore by the Owner will not relieve the Contractor of obligation to the Owner (which obligation is hereby acknowledged) to discharge
any and all liens for the benefit of subcontractors, laborers, material-person, or any other persons performing labor upon the work or
furnishing material or machinery for the work covered by this contract, which have attached to or may subsequently attach to the
property, or interest of the Owner.
VI. NOTICES AND APPROVAL IN WRITING. - Any notice, consent, or other act to be given or done hereunder will be valid only if in writing.
VII. CLEANING UP. - The Contractor shall keep the premises free from accumulation of waste material and rubbish and at the completion of
the work shall remove from the premises all rubbish, implements and surplus materials.
VIII. WARRANTY. - Contractor warrants and guarantees that title to all work, materials, and equipment covered by any Application for
Payment, whether incorporated in the Project or not, will pass to Owner no later than the time of payment free and clear of all Liens. If
within one year after completion of the work, any work is found to be defective, Contractor shall promptly, without cost to the Owner,
correct such defective work as approved by the Owner.
IX. INDEMNIFICATION. - Contractor shall defend and indemnify the city against claims brought or actions filed against the city or any of its
officers, employees or agents for property damage, bodily injury or death to third persons, arising out of or relating to contractors work
under the contract.
X. WORKERS’ COMPENSATION INSURANCE. - Contractor shall provide a certificate of insurance showing evidence of workers’ compensation
coverage or provide evidence of qualification as a self-insurer of workers’ compensation.
XI. LIABILITY INSURANCE REQUIREMENTS. – A certificate of insurance acceptable to the City shall be filed with the City prior to the
commencement of the work. The certificate and the required insurance policies shall contain a provision that the coverage afforded
under the contract will not be canceled or allowed to expire until at least 30 days prior written notice has been given to the city.
Contractor shall maintain commercial general liability (CGL) insurance with a limit of not less than $1,000,000 each occurrence and an
aggregate limit of not less than $2,000,000. The CGL insurance shall cover liability arising from premises, operations, independent
contractors, subcontractors, products-completed operations, personal injury and advertising injury, and contractually-assumed liability.
The City and FOCUS Engineering, Inc. shall be named as an additional insured under the CGL. Contractor shall maintain automobile
liability insurance, and if necessary, umbrella liability insurance with a limit of not less than $1,000,000 each accident and an aggregate
limit of not less than $2,000,000. The insurance shall cover liability arising out of any auto, including owned, hired, and non-owned autos.
36
10th
60th
5th
HudsonKeats Lake Elmo50th
15th Inwood34th
20th
27th
53rd
55th
Jane
Lake Jane
Jamaca57th
59th
Hill
47th
7th
31st
51st
43rd
39th Demontreville45th
38th
ManningStillwater
24th26th
42nd
Island58th9th
30th
32ndKimbro
21st
Jade6thIvoryHill
t
o
p
IsleOls
o
n
L
a
k
e
8thJulep
12th
Jewel
44th
56th
Iris22nd
37th
36th
35th LaverneJuniperAnnikaJasmineJamley LegionLily
Klondike16th
Upper 33Rd
ImperialLinden3rdKirkwood 33rd
Deer PondHytrail
IrvingHidden Bay4thJerome14thJune28th VillageTapestryJasper
Eagle Point
Jonquil
Wildflower
LaytonPrivateKelvinIronwoodHighlandsJaneroLe
e
w
a
r
d
Cimarron10th StreetKindr
e
d
JamesIrishPrairievie
wJack Pine49th
JayLower 31st
Marquess
IrvinLilacMonarchLower 8th LisbonBirch Bark40thLavender
KraftLampertBlazingstarWhistling Valley
Junco Little Bluestem
11thLady Slipper5t
h
S
t
r
e
e
t
Windbreak
Sunfish Lake Park InboundIvywoodInnsdale3rd Street Marquess TrailLang
l
y
JunoLan
s
i
n
g
JulianneUpper 30th
6th
S
t
r
e
e
t
Lisbon AvenueIrwinSunflower
41st
WB I9
4
T
o
I
n
w
o
o
d
A
v
e
N
Upper 7t
h
Queen
Upper 9th 57th StreetUpper 42Nd
27
t
h
S
t
r
e
e
t
15th Stree
t
Cherrywood
WB I94 To Keats
A
v
e
N
44th Street
41st Street
Jas
m
i
n
e
A
v
e
n
u
e
59th Street
HummingbirdJero
m
e
A
v
e
n
u
e
Keats Ave N To
W
B
I
9
4
Manning Ave N To W
B
I
9
4
Hill Trail
30th Street33rd Street24t
h
S
t
r
e
e
t
20th Street58th StreetLegion Lane
Lark
s
p
u
r
Demontreville Trail
HummingbordAccess21st
Laverne57th Street32nd ManningIrish35th
34th LilyLilac
55th
Jamaca
35th
Laverne56th
Stillwater36
Lake ElmoLanglyLaytonLilac33rd Lily10th StreetMan
n
i
n
g
6th StreetIsle21st
9th
57th
36th
Kirkwood
53rd
Linde
n
Whistling ValleyManning
50th
5th
33rd
Highlands
59th
6th Street
Innsda
le
Ir
o
nw
o
o
d
Linden
Legion Lane
LindenPrivate
Julep28th VillageLilac
IvyInnsdaleLower 8th
31st
57th
Lisbon
9th
39thKeats55th56th36
IsleJulepIrvin55th
Manning32nd
Laverne37thKelv
in
ManningLegion9th
Ivy
34th
LaytonLindenJade5thHudson
36th
39th
DOWNSLAKE
LAKE ELMOREGIONALPARK RESERVE
LAKE ELMO
LAKE JANE
SUNFISH LAKE
OLSONLAKE
LAKE DEMONTREVILLE
CLEARLAKE
HORSESHOELAKE
ROSELAKE
REIDPARK
VFWPARK
LIONS PARK
TANA RIDGEPARK
City of Woodbury
STONEGATEPARK
KRAMERLAKE
GOOSELAKEARMSTRONGLAKE
RIDGEPARK
KEATS AVE NEAGLE POINTLAKE
TABLYNPARK
HEIGHTSPARK
LAKE JANEHILLS PARK
PEBBLEPARK
City of Oakdale
West LakelandTownship
Baytown Township
City ofOak ParkHeights
City of GrantCity ofPine Springs
DEMONTREVILLEWILDLIFE PARK
DEMONTREVILLEPARK
KLEISPARK CARRIAGESTATIONPARK
SUNFISH LAKEPARK
City ofOak ParkHeights
StillwaterTownship
HOMESTEDPARK
7
HERITAGEPARK
VERONICAPOND
GOETSCHEL'SPOND
City ofAfton
TablynPark
Eagle PointCreek Estates
Lake ElmoHeights
Torre Pines
Farms ofLake Elmo
Parkview Estates
WildflowersShores
HuppertAdd
BeautCrest Estates FriedrichHghts
Kenridge Add
Prairie RidgeOffice Park
Eagle PointBusiness Park
Stonegate
Hammes CountryVista
Whistling Valley
MidlandMeadows
DavidNelson Est
TheHomestead
TartanMeadows
The Forest
Schwartz-Martinco Add
PackardPark
EdenPark
HeritageFarm
LonesomePine Add
DownsLake Est
MyronEllman
Elmo View
Cty AudPlat No. 8
Lake Elmo Park
Brookman Add
Sunfish Ponds
Hamlet OnSunfish Lake
ParkMeadows
Tapestry AtCharlottes' Grove
Berschen's Shores
DawcinAcres
LakeJaneHighlands
TealPass Est
Fox FireEstates
Meyer'sPineridgeKrausesAdd
Springborn'sGreen Acres
Arabian Hills
JudithMaryManor
Lake Elmo Vista
Rolling Hills Est
Prairie Hamlet
HiddenMeadowsOf Lake Elmo
Jesse'sHideaway
DiscoverCrossing
Arvold'sAcres
St. Croix'sSanctuary
TamarackFarm Est
CarriageStation
TanaRidgeJohn M DayFarm Add
The Fields ofSt. Croix2nd Add
The Fieldsof St. Croix
BluestemAt The Fieldsof St. Croix
BurrwoodEstBergmannAdd
DemontrevilleHighlands Add
Lane's DemontrevilleCountry ClubDemontrevilleHighlands Add
Olson Lake Add
Oace AcresAdd
LakeJaneHills
Lake JaneManor No. 1
ThreeLakesFarm Add
Bordners Garner
Farmettes
Royal Golf Club
Southwind
Hunters Crossing
HammesEstates
Savona
Boulder Ponds
Inwood
Lakewood Crossing2nd Addition
Easton Village
Wildflower
Cimarron
Legacy At Northstar
Village Preserve
ST. CROIX SANCTUARY PARK
EDENPARK
PILOTPARK
HAMMESPARK
GOOSE LAKEPARK
F
Map Date: November 2020010.5 Miles
Created By: Planning Department
CITY OF LAKE ELMO, MINNESOTA2020 STRIPING PROJECTPROJECT NO. 2020.108Street FROM: TO:Length (LF)Single White (LF)Single Yellow (LF)Double Yellow (LF)Stop Bar (LF)Turn Arrows (EA)Notes5th St N Keats (CSAH 19) Julia Ave N 2959 7646 5315 30 Provide 24" White Stop Bar at CSAH 19 Intersection39th St NLake Elmo Ave (CSAH 17)Stillwater Blvd (CSAH 15)2434 85 2252 1Sum (LF): 5,393 7,731 5,315 2,252 30 1STREET LIST AND STRIPING TABULATION
LakeElmoAvenue/CSAH1739th Street
LaverneAvenue113433880
4" DOUBLE SOLID YELLOW LINE,EPOXY LaytonAvenueOHUOHUOHUOHUOHUO
H
U
O
H
UStil lw aterBoulevard/TH510390
11465
3 9 th Stre e t4" DOUBLE SOLID YELLOW LINE, EPOXY
4" SOLID WHITE LINE, EPOXY
RIGHT TURN ARROW, TAPE 12'(30x30)R3-7RLIC. NO.
DESIGNED
DRAWN
CHECKED
JRR
MRW
MRW LAKE ELMO, MINNESOTA
39TH STREET NORTH:
MICHAEL R. WARNER
44693 3/26/2015
SHEETDATEBYREV.
DATELIC. NO.
I HEREBY CERTIFY THAT THIS PLAN, SPECIFICATION, OR REPORT WAS PREPARED
BY ME OR UNDER MY DIRECT SUPERVISION AND THAT I AM A DULY LICENSEDPROFESSIONAL ENGINEER UNDER THE LAWS OF THE STATE OF MINNESOTA.
DESIGNED
DRAWN
CHECKED Bolton & Menk, Inc. 2015, All Rights Reservedc
H:\LKELMN\N15108307\C3D\108307C901.dwg 9/8/2015 2:19:10 PM
WILLMAR, MN CHASKA, MN RAMSEY, MN MAPLEWOOD, MNMANKATO, MN FAIRMONT, MN SLEEPY EYE, MN BURNSVILLE, MN
BAXTER, MN ROCHESTER, MN AMES, IA SPENCER, IA
STREET AND SANITARY SEWER IMPROVEMENTSSIGNING AND STRIPING
C9.01FEETSCALE
0 10050
HORZ.RECORD PLAN 1015CONTRACTOR: GEISLINGER & SONS, INC.CITY PROJECT NO: 2014.131COMPLETION DATE: AUGUST 2015
2020 Striping Project 3217‐1 Revision date: APRIL 2019
SECTION 3217 – PAVEMENT MARKINGS
SCOPE:
This Work shall consist of furnishing and applying pavement markings for control and guidance of traffic in
accordance with these Specifications and at locations shown in the Plans, or as directed by the Engineer.
PRODUCTS:
1.EPOXY RESIN. Epoxy resin for pavement markings shall meet the requirements of MnDOT Standard
Specifications for Construction, 2018 Edition.
2.DROP‐ON GLASS BEADS: Drop‐On Glass Beads for pavement markings shall meet the requirements of
MnDOT Standard Specifications for Construction, 2018 Edition.
3.PREFORMED THERMOPLASTIC PAVEMENT MARKING SYMBOLS: Reflective thermoplastic markings shall
meet the requirements of MnDOT Standard Specifications for Construction, 2018 Edition (Section 3356)
and does not require the preheating of the pavement surface.
EXECUTION:
1.PAVEMENT MARKINGS:
A.All Pavement Marking, except pavement marking symbols, shall be Epoxy Resin with Drop‐on Glass
Beads.
B.All Pavement Marking Symbols shall be ground in and comply with MnDOT approved products.
2.TRAFFIC CONTROLS: The Contractor shall provide Traffic Control for the pavement marking operations in
conformance with the Minnesota Manual of Uniform Traffic Control Devices. Suitable warning signs shall
be placed near the beginning of the worksite and well ahead of the worksite for alerting approaching
traffic from both directions. Small markers shall be placed along newly marked lines to control traffic and
prevent damage to newly marked surfaces. Pavement marking equipment shall be identified with large
warning signs indicating slow‐moving equipment in operation.
3.SURFACE PREPARATION: All surfaces to be marked shall be thoroughly cleaned immediately prior to an
application of pavement marking. Dust, dirt, and other granular surface deposits shall be removed by
sweeping, blowing with compressed air, rinsing with water, or a combination of these methods as
required. Rubber deposits, surface laitance, existing paint markings, and other coatings adhering to the
pavement shall be completely removed with scrapers, wire brushes, sandblasting, approved chemicals, or
mechanical abrasion as directed. Where oil or grease is present, affected areas shall be scrubbed with
several applications of trisodium phosphate solution or other approved detergent or degreaser, and
rinsed thoroughly after each application. After cleaning, oil‐soaked areas shall be sealed with cut shellac
to prevent bleeding. Pavement surfaces shall be allowed to dry when water is used for cleaning. Surfaces
shall be recleaned when work has been stopped due to rain.
A.Cleaning Existing Pavement Markings. In general, markings shall not be placed over existing
pavement marking patterns. Existing pavement markings shall be removed that are in good
condition but interfere or conflict with the newly applied markings. Deteriorated or obscured
markings that are not misleading or confusing or interfere with the adhesion of the new marking
material do not require removal. New preformed and thermoplastic pavement markings shall not
be applied over existing preformed or thermoplastic markings. Whenever grinding, scraping,
sandblasting, or other operations are performed, the Work must be conducted in such a manner
2020 Striping Project 3217‐2 Revision date: APRIL 2019
that the finished pavement surface is not damaged or left in a pattern that is misleading or
confusing.
B.When surface preparation operations are completed, the pavement surface shall be blown‐off with
compressed air to remove residue resulting from the cleaning work.
4.APPLICATION: Pavement markings shall be placed in accordance with the details shown in the Plans and
as directed by the Engineer. The Contractor shall place spotting at appropriate points to provide
horizontal control for striping, and determine necessary starting and cutoff points. The Contractor must
request Engineer review and approval prior to proceeding with striping operations. Material shall not be
applied over a longitudinal joint.
A.Epoxy. The epoxy material application shall immediately follow the pavement cleaning and shall be
applied in accordance with MnDOT specifications. When epoxy pavement is applied to a MnDOT
2360 SUPERPAVE wearing course surface, the epoxy pavement marking wet film thicknesses shall be
increased from a 15 mil to a 20 mil minimum wet film thickness.
Placement of epoxy materials shall be permitted only on a clean, dry pavement surface and air and
pavement temperatures must be at least 50 degrees F. Markings shall not be applied when the wind
or other conditions cause a film of dust to be deposited on the pavement surface before the
material can be applied. Permanent pavement markings shall not be placed over temporary tape
markings.
B.Glass Beads. Glass beads shall be applied immediately after application of the epoxy resin line to
provide an immediate no‐track system. For 20 mil applications, glass beads shall be applied at a rate
of at least 25 LB/GAL.
C.Preformed Thermoplastic Pavement Marking Symbols. Material shall be installed following the
ground in method. Installation shall be in accordance with manufacturer recommendations.
D.Tolerances. A tolerance of ¼‐inch under or ¼‐inch over the specified width will be allowed for
striping provided the variation is gradual and does not detract from the general appearance. Broken
line segments may vary up to ½‐foot from the specified lengths provided the over and under
variations are reasonably compensatory. Alignment deviations from the specified lane widths shall
not exceed 1‐inch. Establishment of application tolerances shall not relieve the Contractor of their
responsibility to comply closely with the planned dimensions.
5.PROTECTION OF PAVEMENT MARKINGS: The Contractor shall furnish and install all necessary warning
and directional signs and devices in order to maintain traffic while pavement markings are being applied
in the presence of traffic, and to protect uncured markings as needed until traffic can cross markings
without damaging markings. When necessary, a pilot car and flaggers shall be used to provide adequate
control and direction of traffic. Warning signs and barricades shall be placed only where marking
operations are in progress, shall be relocated as often as necessary, and shall not be left in place over
night. Unless approved by the Engineer, traffic shall be allowed to keep moving at all times and the
striping equipment shall be operated in a manner that will not make it necessary for traffic to cross
uncured markings.
6.CLEANING: Waste materials shall be removed or destroyed at the end of each work day. Upon completion
of the Work, all containers and debris shall be removed from the site. Epoxy spots upon adjacent surfaces
shall be carefully removed by approved procedures which will not damage the surfaces and the entire job
shall be left clean and acceptable to the City.
7.CERTIFICATION: The Contractor shall furnish a certified report on the quality of materials shipped to the
Project. This report shall not be interpreted as a basis for final acceptance. When required, all emptied
containers shall be returned to the epoxy material storage area or made available for checking by the
2020 Striping Project 3217‐3 Revision date: APRIL 2019
Engineer. The Contractor shall make accurate accounting of the epoxy materials used in the Work.
8.CORRECTION OF DEFECTS: All pavement markings not conforming to the requirements of the Contract
shall be removed and replaced or otherwise repaired to the satisfaction of the Engineer. Removal of
unacceptable work shall be accomplished with suitable blasting or grinding equipment unless other
means are authorized by the Engineer.
If the Engineer requires removal and replacement, the Contractor shall remove, by an approved process,
at least 90% of the deficient line, with no excessive scarring of the existing pavement. The removal width
shall be one inch wider all around the nominal width of the pavement marking to be removed.
END OF SECTION