HomeMy WebLinkAbout#09 - Hamlet Sanitary Sewer Extension Pay Request STAFF REPORT DATE: September 7, 2021 CONSENT AGENDA ITEM: Accept Improvements and Approve Pay Request No. 4 (Final) for the Hamlet on Sunfish Lake Sanitary Sewer Extension SUBMITTED BY: Mark Scholle, Project Engineer REVIEWED BY: Kristina Handt, City Administrator Marty Powers, Public Works Director Jack Griffin, City Engineer ISSUE BEFORE COUNCIL: Should the City Council accept the improvements and approve Pay Request No. 4 (Final) for the Hamlet on Sunfish Lake Sanitary Sewer Extension? BACKGROUND: A-1 Excavating, Inc. was awarded a construction contract on July 7, 2020 to complete the Hamlet on Sunfish Lake Sanitary Sewer Extension. The contractor has completed the work in accordance with the contract, plans, and specifications, including all punch list items. PROPOSAL DETAILS/ANALYSIS: A-1 Excavating, Inc., has submitted Partial Pay Request No. 4 (Final) in the amount of $7,760.15. The Project Engineer has prepared a Certificate of Completion indicating that all work is completed, including all punch list items, and is recommending the acceptance of the improvements and release of final retainage. Project acceptance will initiate the one-year warranty period for the improvements. The one-year warranty will begin on September 7, 2021 and will extend through September 7, 2022. FISCAL IMPACT: The final total construction cost is $140,953.10. This is 16% under the original contract amount of $167,247.00, and remains within the overall project budget. RECOMMENDATION: Staff is recommending that the City Council, as part of the Consent Agenda, accept the improvements and approve Pay Request No. 4 (Final) for the Hamlet on Sunfish Lake Sanitary Sewer Extension. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to accept the Hamlet on Sunfish Lake Sanitary Sewer Extension and approve Pay Request No. 4 (Final) to A-1 Excavating, Inc. in the amount of $7,760.15”. ATTACHMENTS: 1. Partial Pay Estimate No. 4 (Final). 2. Certificate of Completion. CITY OF LAKE ELMO, MN HAMLET ON SUNFISH LAKE SANITARY SEWER EXTENSION PROJECT NO. 2018.128 CERTIFICATE OF COMPLETION DATE OF ISSUANCE: SEPTEMBER 7, 2021 OWNER: CITY OF LAKE ELMO, MN CONTRACTOR: A-1 EXCAVATING, INC PROJECT NAME: HAMLET ON SUNFISH LAKE SANITARY SEWER EXTENSION PROJECT NO.: 2018.128 This Certification of Completion applies to all work under the Contract Documents This Certification of Completion applies to the following specified parts of the Contract Documents I do hereby certify that the work to which this Certificate applies has been constructed in accordance with the Contract dated July 14, 2020. The above-mentioned improvement is hereby declared to be complete and acceptance of this work is recommended. DATE OF COMPLETION: SEPTEMBER 7, 2021 Mark Scholle Reg. No. 40483 FOCUS Engineering, Inc. THE WARRANTY PERIOD BEGINS September 7, 2021 AND ENDS September 7, 2022 8-31-21