HomeMy WebLinkAbout#12 - Section 16 Sanitary Sewer Extension STAFF REPORT
DATE: September 7, 2021
CONSENT
AGENDA ITEM: Order the Improvements and Preparation of Plans and Specifications for
the Section 16 Sanitary Sewer Extension
SUBMITTED BY: Jack Griffin, City Engineer REVIEWED BY: Kristina Handt, City Administrator Marty Powers, Public Works Director Chad Isakson, Assistant City Engineer
ISSUE BEFORE COUNCIL: Should the City Council order the Improvements and preparation of Plans
and Specifications for the Section 16 Sanitary Sewer Extension? BACKGROUND: The City of Lake Elmo has been working with Oakdale to establish a sanitary sewer connection to Oakdale to serve the 180 acres located along Ideal Avenue and County State Aid Highway 14 (CSAH 14). Amongst these efforts the city has approved a Comprehensive Plan Amendment to allow for sewered development, is in the process of negotiating and establishing an ongoing sanitary sewer use agreement with the City of Oakdale, and has entered into a purchase agreement with NorthPoint Development, LLC to develop the approximately 75 acres located at Ideal Avenue, South of CSAH 14. At the August 17, 2021 council meeting the city approved the Cooperative Agreement with Oakdale for the reconstruction of the Oakdale lift station (Lift Station 6) located at the intersection of Ideal Avenue and Stillwater Boulevard
PROPOSAL DETAILS/ANALYSIS: Staff met with the Oakdale City Engineer and SEH, Inc. to develop a coordinated work scope, project schedule and engineering fees to extend sanitary sewer from the
reconstructed Lift Station 6 to the intersection of Ideal Avenue (CSAH 13) and 31st Street North. A sewer stub will be left along the east boulevard of Ideal Avenue for connection by the developer.
In order to secure a sanitary sewer connection with the City of Oakdale by the fall of 2022, and to support
the proposed development schedule, the design for this work should be initiated at this time with a project schedule as attached. The proposed schedule allows for the sanitary sewer design and construction to be coordinated with the Oakdale lift station project, and to receive contractor bids for construction in 2022.
FISCAL IMPACT: Not to exceed $74,600 for SEH, Inc. Task Order 19.
If authorized, FOCUS Engineering and SEH, Inc. will prepare the plans and specifications. The design phase of the improvements for SEH is in the amount of $58,700. The city will also require geotechnical services for the design of the improvements, estimated to be +/-$12,000.
RECOMMENDATION: Staff is recommending that the City Council approve, as part of the consent
agenda, a Resolution Ordering the Improvement and preparation of Plans and Specifications for the Section
16 Sanitary Sewer Extension. If removed from the consent agenda, the recommended motion for this action
is as follows:
“Move to approve Resolution No. 2021-095, Ordering the Improvement and preparation of Plans and Specifications for the Section 16 Infrastructure Improvements, including the approval of Task Order
19 for SEH, Inc. in the not to exceed amount of $74,600.”
ATTACHMENTS: 1. Resolution Ordering the Improvement and Preparation of Plans and Specifications.
2. Section 16 Sanitary Sewer Extension – Location Map. 3. Section 16 Sanitary Sewer Extension – Project Schedule.
4. Task Order 19 for SEH, Inc. for the Sanitary Sewer Extension.
CITY OF LAKE ELMO
WASHINGTON COUNTY STATE OF MINNESOTA
RESOLUTION NO. 2021-095
A RESOLUTION ORDERING THE IMPROVEMENT AND
PREPARATION OF PLANS AND SPECIFICATIONS THE SECTION 16 INFRASTRUCTURE IMPROVEMENTS
WHEREAS, the City of Lake Elmo has requested, by mutual agreement with Oakdale, to add future sanitary sewer flows from 180-acres of undeveloped land (“Property”) in Lake Elmo near Ideal Avenue and County Road 14, which is proposed to be developed with industrial, commercial, and residential uses; and WHEREAS, Lake Elmo has approved a Comprehensive Plan Amendment to allow for sewered development and is in the process of negotiating and establishing an ongoing sanitary sewer use
agreement with the City of Oakdale; and WHEREAS, the sewage from the Property would flow to Oakdale’s existing Lift Station 6
located at Ideal Avenue and Stillwater Boulevard, which will be reconstructed and relocated as a separate project with Oakdale as the lead agency with Lake Elmo cost participation; and WHEREAS, the City has entered into a purchase agreement with NorthPoint Development, LLC to develop the approximately 75 acres located at Ideal Avenue, South of CSAH 14; and WHEREAS, as part of the purchase agreement, Lake Elmo is obligated to extend the sanitary sewer from the reconstructed Lift Station 6 to the intersection of Ideal Avenue (CSAH 13) and 31st Street. NOW, THEREFORE, BE IT RESOLVED, 1. Such improvement is hereby ordered as proposed in the council resolution adopted this 7th day of September, 2021.
2. The city engineer is hereby designated as the engineer for making this improvement. The engineer, and his consultants, shall oversee the preparation of the Plans and Specifications for the
making of such improvement. 3. The city engineer shall retain the services of a SEH, Inc., in the amount not to exceed $74,600, to
assist, where needed, to prepare Plans and Specifications for the making of such improvement and to assist the city engineer during the construction phase of the improvement as requested. ADOPTED BY THE LAKE ELMO CITY COUNCIL ON THE SEVENTH DAY OF SEPTEMBER, 2021. CITY OF LAKE ELMO
By: __________________________ (Seal) Charles Cadenhead
ATTEST: Mayor ________________________________ Julie Johnson, City Clerk
34th27thJamaca31st38thStillwater26thIris37th36th35thJamleyImperial28thJonquilPrivateIronwoodJanero
InnsIrwin27th Str
e
et
Irish35th34th33rdInnsdale
Ironwo
o
d 28thInnsdaleIsle37thLAKE ELMOREGIONALPARK RESERVETABLYNPARKHEIGHTSPARKCity of OakdaleSUNFISH LAKEPARKTablynParkEagle PointCreek EstatesLake ElmoHeightsFarms ofLake ElmoWildflowersShoresHuppertAddBeautCrest EstatesFriedrichHghtsKenridge AddPrairie RidgeOffice ParkFarmettesNew Lift Station completed asseparateproject byOakdaleSection 16 Sanitary SewerExtension, from LS to 31st StreetIrisEaCreWildflowersShoresaaeeeeIIrisIris33ssrss Sewer Service AreaSTILLWATER BLVD (CSAH 14)IDEAL AVENUEUP RAILROAD
PROJECT SCHEDULE
CITY OF LAKE ELMO
SECTION 16 INFRASTRUCTURE IMPROVEMENTS
PROJECT NO. 2021.116
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
SEPTEMBER 7, 2021 Council orders preparation of preparation of Plans and Specfications.
MARCH 1, 2022 Council approves Plans and Specifications and orders Advertisement for Bids.
MARCH 30, 2022 Project Bid Date: Receive contractor bids.
APRIL 19, 2022 Council accepts Bids and awards Contract.
MAY 30, 2022 Conduct Pre‐Construction Meeting and issue Notice to Proceed.
OCTOBER 7, 2022 Substantial Completion.
NOVEMBER 18, 2022 Final Completion.
TASK ORDER No. 19 – SECTION 16 SANITARY SEWER EXTENSION Page 1 of 4
TASK ORDER No. 19
CITY OF LAKE ELMO, MINNESOTA – SHORT ELLIOTT HENDRICKSON, INC.
PROFESSIONAL CONSULTING SERVICES AGREEMENT
In accordance with ARTICLE 1 of the Master AGREEMENT between the City of Lake Elmo (“CITY”) and
Short Elliott Hendrickson, Inc. (SEH) (“CONSULTANT”), dated August 13, 2014 (“AGREEMENT”), the
ENGINEER agrees to provide Professional Consulting Support Services as follows:
SECTION 16 SANITARY SEWER EXTENSION
PROJECT OVERVIEW: The City of Lake Elmo requires professional design and construction phase
engineering services for the Section 16 Sanitary Sewer Extension. The City of Lake Elmo has been
working with Oakdale to establish a sanitary sewer connection to Oakdale to serve the 180 acres
located along Ideal Avenue and County State Aid Highway 14 (CSAH 14). This project will extend
sanitary sewer along the east side of Ideal Avenue (CSAH 13) from Oakdale's reconstructed Lift
Station 6, located at the intersection of Stillwater Boulevard (CSAH 6) and Helmo Avenue/Ideal
Avenue, to the intersection of Ideal Avenue (CSAH 13) and 31st Street North. A sewer stub will be left
along the east boulevard of Ideal Avenue for connection by a future development project. The
sanitary sewer extension work will include cased roadway crossings at Helmo Avenue and Stillwater
Boulevard (CSAH 6).
The services outlined in this task order are intended to assist the city to complete the final design,
including the preparation of plans and specifications and contract documents, bidding phase services,
and construction phase support services as detailed in this Task Order.
SERVICES TO BE PROVIDED BY ENGINEER: SEH, Inc. shall provide the following Professional
Engineering Services:
1. Project Management throughout the course of the work for preparation of design documents
and construction phase services including submittal of a weekly progress memo and job to
date budget form.
2. Preparation of Plans and Specifications, and Contract Documents.
Project kick‐off meeting with city staff.
Work with city staff to develop critical success criteria for the project, obtain project
information and formalize the budget and schedule.
Identify small utility conflicts related to the proposed design to the City’s Project
Manager. The city will coordinate necessary relocation efforts with the respective
small utility company as needed.
Prepare preliminary pipe route layout and review with city to confirm location of
sanitary sewer along the corridor.
Prepare geotechnical evaluation services work plan and solicit proposals for inclusion
into the project plans and specifications for the sanitary sewer installation.
TASK ORDER No. 19 – SECTION 16 SANITARY SEWER EXTENSION Page 2 of 4
Provide 60% plans and specifications to city for review, including design criteria and
assumptions memorandum.
Provide 90% plans and specifications to city for review, including updated design
criteria and assumptions memorandum.
Revise and final plans and specifications based on city comments.
Prepare opinion of probable cost based on final plans.
Identify permits required to complete the proposed work. The design shall incorporate
measures to meet compliance requirements for all permits necessary.
Prepare and submit any necessary permit applications for approval.
DELIVERABLES:
Plans in electronic format (PDF) and hard copy format (2 full size and 4 half size).
Specifications in electronic format and hard copy format (3 copies for the city and the
appropriate number for contracts and required permits).
Opinion of Total Probable Project Costs.
Design Memorandum summarizing final design assumptions and performance criteria
incorporated into the project design.
Identification of easements needed for the construction of the project. Easements
shall be placed on the final plans.
Completed project permit applications ready for signature by city representative.
3. Bidding Phase Services for each bid package.
Submit “Advertisement for Bids” to Stillwater Gazette and Quest CDN.
Distribute plans and specifications as requested by bidders.
Maintain plan‐holder list.
Respond to bidders’ questions and issue addenda as necessary.
Tabulate bid in electronic format.
Prepare contract award recommendation letter.
4. Construction Phase Services.
Assist the city to prepare for the preconstruction meeting and attend meeting.
Provide technical and construction administration support throughout the project as
requested by the City’s Project Manager (assume 40 hours from the design engineer of
record).
Coordinate and provide construction staking.
Provide review of shop drawings and make recommendations regarding acceptability
of submittals.
Prepare and submit record drawings in electronic format (AutoCAD and PDF) and hard
copy format (1 full size and 2 half‐size) based upon staking information and
information provided by the contractor and city.
TASK ORDER No. 19 – SECTION 16 SANITARY SEWER EXTENSION Page 3 of 4
Prepare and submit the utility as‐built survey data as GIS Shape Files, including
relevant asset information (such as date of install, material type, size, structure type).
5. City Responsibilities. The city (or its consultants) will provide the following:
Retain geotechnical investigation services based on recommended scope of services
and provide copy of geotechnical report as completed for the project area.
Coordination with the public and conduct public meetings.
Presentation(s) to the City Council.
Easement negotiations and acquisition, if needed.
Review of 60% and 90% plans and specifications.
Coordination with small utility companies if conflicts are identified.
Construction Administration of the Contract.
Construction Observation.
Retain Material and Compaction testing services based on recommended scope.
One year warranty inspections.
Preparation of Feasibility Report, if any, including assessment calculations, assessment
role and conduct Final Assessment Hearing.
TIMES FOR RENDERING SERVICES: CONSULTANT shall perform its services and provide deliverables
in accordance with the following schedule:
1. September 7, 2021 Council orders preparation of Plans and Specifications.
2. March 1, 2022 Council approves Plans and Specifications; Authorizes Ad for Bids.
3. March 30, 2022 Receive contractor bids.
4. April 19, 2022 Council accepts bids and awards contract.
5. May 30, 2022 Conduct Pre‐Construction Meeting and issue Notice to Proceed.
6. October 7, 2022 Substantial Completion.
7. November 18, 2022 Final Completion.
CITY’S REPRESENTATIVE AND CONTRACT ADMINISTRATION: The CITY’s representative with respect
to services rendered by CONSULTANT under this TASK ORDER shall be the City Engineer. Project
correspondence must be addressed to:
Jack Griffin, P.E., City Engineer
City of Lake Elmo
3800 Laverne Avenue North
Lake Elmo, MN 55042
651.300.4264
Email: Jack.griffin@focusengineeringinc.com
TASK ORDER No. 19 – SECTION 16 SANITARY SEWER EXTENSION Page 4 of 4
COMPENSATION: Compensation to CONSULTANT shall be based on the hourly billing rates for each
staff as assigned and provided in the CONSULTANT’S Proposal and Fee Estimate for the work. Invoices
shall be submitted once each month and should be sent to the attention of the City Engineer.
Compensation to CONSULTANT for Project Management, the Preparation of Plans and Specifications,
Contract Documents, and Bidding Phase Services shall be on an hourly rate basis in a not to exceed
amount of $58,700.00.
Compensation to the CONSULTANT for the Construction Phase Services shall be on an hourly rate
basis in a not to exceed amount of $15,900.00.
ADDITIONAL SERVICES: If authorized by the City, CONSULTANT shall furnish or obtain from others
Additional Services which are not considered under this Task Order. Such services shall be
compensated for on an Hourly Rate basis in an amount approved by the City prior to any services
being started or as otherwise mutually agreed. The City is not obligated to compensate CONSULTANT
for services completed outside the approved scope of work which are completed prior to
CONSULTANT submitting a written request to the City, and receiving written approval of the City.
ATTACHMENTS: This agreement supersedes and replaces all previous understandings, agreements
or contracts, written or verbal, between CONSULTANT and City, regarding the Section 16 Sanitary
Sewer Extension. The following documents are attached for reference:
1. ENGINEER’s Proposal and Fee Estimate dated August 23, 2021.
APPROVAL AND ACCEPTANCE: Approval and Acceptance of this Task Order, including the
attachment(s) listed above, shall incorporate this document as part of the AGREEMENT.
CONSULTANT is authorized to begin performance of services upon receipt of a copy of this Task Order
signed by CITY.
The Effective Date of this Task Order is September 7, 2021.
SHORT ELLIOTT HENDRICKSON, INC. CITY OF LAKE ELMO, MINNESOTA
By _________________________________ By _______________________________ __
(Authorized Principal of the Firm) City Administrator
Engineers | Architects | Planners | Scientists
Short Elliott Hendrickson Inc., 3535 Vadnais Center Drive, St. Paul, MN 55110-3507
SEH is 100% employee-owned | sehinc.com | 651.490.2000 | 800.325.2055 | 888.908.8166 fax
August 23, 2021 RE: City of Lake Elmo Section 16 Sanitary Sewer Extension (Ideal Avenue from Stillwater Boulevard to 31st Street) Proposal for Design & Construction Administration Services SEH No. LAKMO 162405 Jack Griffin, P.E.
City Engineer City of Lake Elmo 3880 Laverne Avenue North, Suite 100
Lake Elmo, MN 55042 Dear Mr. Griffin: Short Elliott Hendrickson Inc. (SEH®) is pleased to submit this proposal for design services, preparation of bidding documents, permitting and construction administration assistance for the Ideal Avenue sanitary sewer extension from Stillwater Boulevard to 31st Street. The proposed project consists of approximately 700 feet of new sanitary sewer connecting to the City of Oakdale Lift Station at Stillwater Boulevard and Ideal Avenue and extending north along Ideal Avenue to 31st Street. These improvements are planned to be constructed in 2022 to provide service to proposed development. We propose the following team to assist the City of Lake Elmo (City) with this project: Todd Blank – Project Manager, Joe Meemken – Project Engineer, Jeff Thene – Lead Technician, and Luke
Thompson – Geotechnical Engineer. If authorized to proceed, we will begin work promptly. We propose to furnish the scope of services as described in City Task Order 19, and as listed in the
attached work task and hour breakdown, on an hourly basis plus reimbursable expenses for an estimated maximum fee of $74,600. Project challenges include boring casing pipe under the County roads, avoiding/minimizing wetland impacts, and potential water main, gas main and fiber optic conflicts
along the proposed alignment. Additional assumptions relating to our understanding of the desired scope of services are included at the bottom of the work task breakdown. Payment for any additional services shall be based on the actual time required to perform the services and the billable rates for the employees engaged directly on the project, plus actual reimbursable expenses. All services will be provided in accordance with the Master Agreement between SEH and the City of Lake Elmo and will be invoiced monthly.
Jack Griffin, PE August 23, 2021
Page 2 We appreciate the opportunity to assist the City with this project! If this proposal is acceptable, please
sign below and return a copy for our records. If you need any further information or wish to review this together, please contact me at 651.490.2017.
Sincerely,
Todd M. Blank, PE Principal/Project Manager Accepted this _______ day of _______________, 2021
CITY OF LAKE ELMO, MINNESOTA
By ____________________________________
s:\ko\l\lakmo\common\rfps\cr13 san sew extension\cr13 san sew proposal_08-23-2021.docx
City of Lake Elmo - Proposal for Inwood Avenue Sanitary Sewer Extension (Oakdale Lift Station No. 6 - 31st Street)
SHORT ELLIOTT HENDRICKSON: PROJECT WORK PLAN PROJECT NAME: Inwood Ave (CR13) Sanitary Sewer Extension (Oakdale LS No. 6 - 31st Street)
PROJECT NUMBER: CLIENT: CITY OF LAKE ELMO CLIENT CONTACT: Jack Griffin
PROJECT MANAGER: Todd Blank
TOTAL HOURS 544 56 20 150 98 51 50 10 44 16 29 6 14HOURLY BILLING RATE $183.00 $162.00 $136.00 $116.00 $144.00 $136.00 $136.00 $117.00 $81.00 $93.00 $136.00 $136.00TOTAL LABOR COST $72,621 $1,994 $74,600 $10,248.00 $3,240.00 $20,400.00 $11,368.00 $7,344.00 $6,800.00 $1,360.00 $5,148.00 $1,296.00 $2,697.00 $816.00 $1,904.00% OF TOTAL COST 13.7%4.3%27.3%15.2%9.8%9.1%1.8%6.9%1.7%3.6%1.1%2.6%
Task DESCRIPTION OF TASK Todd Blank Scott Haupt Joe Meemken Mike LaDoux Jeff Thene Rebecca Beduhn Chad Jorgenson Greg Tvedt Survey Assistant
Anjie Hanson/Lynn Howe Emily Jennings Luke Thompson
Project Mgr.QA/QC Project Engineer Staff Engineer Lead Tech Sr. Wetland Scientist Sr. Traffic Engineer Survey Crew Chief Survey Assistant Admin.Water Resources Engineer Geotechnical Engineer
1 PROJECT MANAGEMENT $4,717.00 $4,700
Project mgmt thoughout including monthly progress & budget updates $3,112.00 $3,112.00 12 4 4
Internal Kick-off and progress meetings $957.00 $957.00 3 3
QA/QC $648.00 $648.00 4
2 PREPARATION OF PLANS AND SPECIFICATIONS $50,798.00 $941.00 $51,700
Project Kick-off meeting $638.00 $39.00 $677.00 2 2
Develop critical success criteria, obtain project info, budget and schedule $638.00 $638.00 2 2
Site visit to review existing conditions & obtain site photos $910.00 $39.00 $949.00 2 4
Review record plan data $743.00 $743.00 1 2 2
Coordination with private utilities, conduct one private utility meeting $2,030.00 $39.00 $2,069.00 2 8 4
Coordination with Washington County $1,454.00 $1,454.00 2 8
Delineate existing weltands east side CR 13, prepare report, review with VBWD $3,361.00 $3,361.00 1 2 20 2
Topographic Survey $1,960.00 $476.00 $2,436.00 2 12 4
Prepare Base Map $1,008.00 $1,008.00 4 4
Evaluate existing Oakdale sanitary sewer & evaluate capacity $1,271.00 $1,271.00 1 8
Set Sanitary Sewer Alignment $743.00 $743.00 1 2 2
Preliminary Sanitary Sewer Design $1,303.00 $1,303.00 1 4 4
Finalize Sanitary Sewer Design $1,247.00 $1,247.00 1 4 2 2
Prepare geotechnical scope of services for City to solicit proposals $796.00 $796.00 1 1 4
Mark & survey boring locations, review geotechnical recommendations $1,521.00 $98.00 $1,619.00 1 2 2 6
Prepare Construction Documents
Title sheet $484.00 $484.00 1 3
General Notes and Tabulations $368.00 $368.00 1 2
Details $736.00 $736.00 2 4
Sanitary Sewer Plan and Profiles $1,240.00 $1,240.00 4 6
Erosion Control and SWPPP $1,240.00 $1,240.00 2 6 2
Prepare Detour/Traffic Control Plan & Tabulations $4,447.00 $4,447.00 1 6 18 10
Constructability Review $848.00 $848.00 4 2
Design Summary Memoranda $1,276.00 $1,276.00 4 4
Project Specifications $4,512.00 $4,512.00 4 16 4 4 2
Identify small utility conflicts and communicate them to the city $1,248.00 $1,248.00 6 3
VBWD & USCOE Wetland Permitting $5,906.00 $5,906.00 2 4 30 4 4
Identify, prepare and submit permit applications (MPCA, Wash Co)$1,008.00 $250.00 $1,258.00 4 4
60% plans with utility layout. Design criteria and assumptions memo $1,646.00 $1,646.00 2 6 4
90% plans with updated design criterian and assumptions memo $1,646.00 $1,646.00 2 6 4
Revised final plans and specs $1,795.00 $1,795.00 1 4 6 4
Opinion of probable costs based on final plans $2,775.00 $2,775.00 1 8 8 4
3 BIDDING SERVICES $2,296.00 $2,300
Submit ad for bids to Stillwater Gazette and Quest CDN $186.00 $186.00 2
Maintain planholders list $93.00 $93.00 1
Respond to bidders questions and issue addenda as necessary $1,096.00 $1,096.00 2 4 2
Attend virtual bid opening $276.00 $276.00 1 1
Tabulate bids & downloaded submitted information in electronic format $369.00 $369.00 1 2
Prepare contract award recommendation letter $276.00 $276.00 1 1
4 CONSTRUCTION ADMINISTRATION SERVICES $14,810.00 $1,053.00 $15,900
Prepare contract documents & construction plans $186.00 $186.00 2
Attend preconstruction meeting $638.00 $45.00 $683.00 2 2
Shop Drawing review $576.00 $576.00 4
Technical and construction admin support - 40 hours assumed $5,600.00 $5,600.00 20 20
Coordinate and provide construction staking $3,780.00 $1,008.00 $4,788.00 24 12
Record drawings based on staking info and info from contractor and city $2,400.00 $2,400.00 4 16
Utility as-built survey data as GIS shape files $1,630.00 $1,630.00 8 6
- -
Total:$74,600
Assumptions:1. Proposal assumes topographic survey only needed from roadway centerline to edge of right-of-way (half the corridor width).2. Valley Branch Watershed District's stormwater management requirements are not anticipated to be triggered, therefore no VBWD coordination/permitting time for stormwater management is included.3. No wetland mitigation costs are included in the proposal.4. Proposed construction is within County ROW, so no easement preparation or acquistion is included in the proposal.
Expenses
TotalLabor Total Task Total