HomeMy WebLinkAbout#20 - 38th -39th St Change Order 1DATE: December 7, 2021 CONSENT AGENDA ITEM: Approve Change Order No. 1 for the 38th-39th Street Neighborhood Street and Utility Improvements SUBMITTED BY: Chad Isakson, Project Engineer REVIEWED BY: Kristina Handt, City Administrator Marty Powers, Public Works Director Jack Griffin, City Engineer ISSUE BEFORE COUNCIL: Should the City Council approve Change Order No. 1 for the 38th-39th Street Neighborhood Street and Utility Improvements? BACKGROUND: A-1 Excavating was awarded a construction contract on June 1, 2021 to complete the 38th-39th Street Neighborhood Street and Utility Improvements. The work is substantially complete with a final completion date of July 22, 2022. PROPOSAL DETAILS/ANALYSIS: A change order has been prepared and has been signed by A-1 Excavating, Inc. to address work that was not included in the contract and has been ordered to be completed by the city. The changes are itemized below: • Extend a roadway culvert by 8-feet on 39th Street North to improve side slop stability and safety. • Install a 40-foot driveway culvert at 8370 39th Street North not included in the original design. • Install a 30-foot driveway culvert at 3948 Innsdale Avenue not included in the original design. FISCAL IMPACT: This change order will increase the construction contract with A-1 Excavating in the amount of $8,011.50 bringing the revised construction contract to $2,884,419.50. The total project costs remain within the approved budget and contingencies. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Change Order No. 1 for the 38th-39th Street Neighborhood Street and Utility Improvements. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve Change Order No. 1 for the 38th-39th Street Neighborhood Street and Utility Improvements, thereby increasing the contract amount by $8,011.50.” ATTACHMENTS: 1. Change Order No. 1.