HomeMy WebLinkAbout#22 - Water Tower 3 Accept Bids and Award ContractDATE: January 18, 2022 REGULAR AGENDA ITEM: Accept Bids and Award Contract for Water Tower No. 3 SUBMITTED BY: Jack Griffin, City Engineer REVIEWED BY: Kristina Handt, City Administrator Marty Powers, Public Works Director Chad Isakson, Assistant City Engineer ISSUE BEFORE COUNCIL: Should the City Council accept bids and award a contract for Water Tower No. 3? BACKGROUND: In accordance with the City’s Capital Improvement Plan, a new water tower is planned for construction in 2022/2023 to support growth and development within the low-pressure zone areas of the city and to provide overall storage capacity for the city’s water supply system. The project includes a 1.0 million gallon composite elevated storage tank, similar in design and construction to the Inwood Water Storage Tank constructed in 2014. The welded steel storage tank will be elevated roughly 100 feet high by placing it on a large diameter reinforced concrete support tower. The tank overflow elevation will be set at the 1085 elevation as identified in the city’s comprehensive water plan. The foundation design and construction will require over excavation by approximately 10 feet with import of granular fill materials due to the existing fill materials that were found on the site during geotechnical investigations. The project includes site and utility improvements, electrical and control improvements, and pressure reducing valve control station modifications necessary for a complete and functioning water storage tank. To integrate the tank communications and operations with the city’s SCADA system, modifications are included for the pressure reducing valve located on Lake Elmo Avenue and the UPRR. Site work includes grading, restoration with seeding, access roadway with turnaround, and minor tree planting (five trees) to be placed for screening. The bid package also includes the painting of 2 City logos on the tank. The tank color and logo orientation can be determined after bids are received. The project is planned to start construction in 2022 and be online at the end of 2023. On November 16, 2021, the City Council approved the plans and specifications for Water Tower No. 3 and authorized staff to advertise the project for bids. The Project was advertised on QuestCDN.com and in the Stillwater Gazette in accordance with the Minnesota Competitive Bidding requirements. PROPOSAL DETAILS/ANALYSIS: Bids were received and opened electronically on January 11, 2022. The City received 3 bids for this project, with Phoenix Fabricators & Erectors, LLC providing the lowest bid in the amount of $3,493,000. Contractor references for Phoenix Fabricators & Erectors, LLC were reviewed by the City’s engineering consultant for the project and a letter recommending the award of the project is attached as part of this agenda item. The City Engineer and his consultant are therefore recommending that the Council award the contract to the lowest responsible bidder, Phoenix Fabricators & Erectors, LLC as outlined in the attached letter. FISCAL IMPACT: Approval of this resolution commits the council to enter into a construction contract for Water Tower No. 3. Entering into a construction contract for this portion of the project has a total post-bid estimated project cost of $3,910,000. The project will be funded through the Water Enterprise Fund. This project is a part of the Water Tower No. 3 Capital Improvement Project which has a total post-bid estimated project cost of $4,550,000 (vs. CIP Budget of $4,110,000). RECOMMENDATION: Staff is recommending that the City Council approve a resolution accepting bids and awarding a contract to Phoenix Fabricators & Erectors, LLC in the low bid amount of $3,493,000 for Water Tower No. 3. The recommended motion for this action is as follows: “Move to approve Resolution No. 2022–012 accepting bids and awarding a contract to Phoenix Fabricators & Erectors, LLC in the amount of $3,493,000 for Water Tower No. 3.” ATTACHMENTS: 1. Resolution Accepting Bids and Awarding a Contract for Water Tower No. 3. 2. Letter of Award Recommendation and Tabulation of Bids. 3. Project Schedule. CITY OF LAKE ELMO WASHINGTON COUNTY STATE OF MINNESOTA RESOLUTION NO. 2022-012 A RESOLUTION ACCEPTING BIDS AND AWARDING A CONTRACT FOR WATER TOWER NO. 3 WHEREAS, pursuant to an advertisement for bids for Water Tower No. 3, bids were received, opened, and tabulated according to law, and bids were received complying with the advertisement; and WHEREAS, bids were tabulated, checked and summarized to verify that all requirements of the submittal were met; and WHEREAS, the project engineer reviewed the bids and has provided a letter recommending the award of the contract to the lowest responsible bidder, Phoenix Fabricators & Erectors, LLC, for the bid amount of $3,493,000.00. NOW, THEREFORE, BE IT RESOLVED, 1. That the Mayor and City Clerk are hereby authorized and directed to enter into a Contract in the accordance with the above ordered Project, in the amount of the Contractor’s lowest responsible bid, and according to the plans and specifications thereof approved by the City Council. 2. The City Clerk is hereby authorized and directed to return forthwith to all bidders the deposits made with their bids, except that the deposits of the successful bidder and the next two lowest bidders shall be retained until a contract has been signed. ADOPTED BY THE LAKE ELMO CITY COUNCIL ON THE EIGHTEENTH DAY OF JANUARY, 2022. CITY OF LAKE ELMO By: __________________________ Charles Cadenhead (Seal) Mayor ATTEST: ________________________________ Julie Johnson City Clerk Engineers | Architects | Planners | Scientists Short Elliott Hendrickson Inc., 3535 Vadnais Center Drive, St. Paul, MN 55110-3507 651.490.2000 | 800.325.2055 | 888.908.8166 fax | sehinc.com SEH is 100% employee-owned | Affirmative Action–Equal Opportunity Employer January 12, 2022 RE: Lake Elmo, Minnesota Water Tower No. 3 2020.118 SEH No. LAKMO 161368 14.00 Mr. Jack Griffin City Engineer City of Lake Elmo 3880 Laverne Avenue North, Suite 100 Lake Elmo, MN 55042 Dear Mr. Griffin: On January 11, 2022, bids were received for the Water Tower No. 3 project. The attached Tabulation of Bids shows the bids received from all bids submitted. Three (3) bids were received for the project. The bids ranged from $3,493,000.00 to $4,382,000.00. The low bid was submitted by Phoenix Fabricators & Erectors, LLC of Avon, IN. Based on our experience and review, it is our opinion that Phoenix Fabricators & Erectors, LLC has the required equipment and expertise to perform the work as outlined in the contract specifications. We, therefore, recommend award of the project in the low bid amount of $3,493,000.00. We hope this analysis of the bids is adequate for your needs. If you have any questions regarding this information, please contact me. Sincerely, Chad T. Katzenberger, PE Project Manager (Lic. MN) mrb Attachment x:\ko\l\lakmo\161368\1-genl\14-corr\2022.01.12 l city recommend award.docx TABULATION OF BIDS123Water Tower No. 3Engineer's EstimatePhoenix Fabricators & Erectors, LLCLandmark Structures Caldwell Tanks, Inc.Lake Elmo, Minnesota182 South CR 900 East 1665 Harmond Road 4000 Tower RoadSEH No.: LAKMO 161368Avon, IN 46123 Fort Worth, TX 76177 Louisville, KY 40219Bid Date: 2:00 p.m., Tuesday, January 11, 2022Item No. Item UnitEst. Quantity Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total Price1 SITE GRADING LS 1.00 $20,000.00 $20,000.00 $18,000.00 $18,000.00 $47,000.00 $47,000.00 $30,000.00 $30,000.002 ROCK CONSTRUCTION ENTRANCE EACH 1.00 200.00 200.00 3,400.00 3,400.00 4,000.004,000.00 3,500.00 3,500.003 TRAFFIC CONTROL LS 1.00 5,000.00 5,000.00 12,000.00 12,000.00 5,000.00 5,000.00 5,000.00 5,000.004 SUBGRADE EXCAVATION CY 175.00 19.00 3,325.00 14.00 2,450.00 25.00 4,375.00 25.00 4,375.005 GEOTEXTILE FABRIC TYPE V SY 200.00 4.00 800.00 17.50 3,500.00 4.00 800.00 5.00 1,000.006 ORGANIC TOPSOIL BORROW CY 175.00 40.00 7,000.00 35.00 6,125.00 60.0010,500.00 35.00 6,125.007 SELECT GRANULAR BORROW CY 200.00 30.00 6,000.00 29.00 5,800.00 40.008,000.00 35.00 7,000.008 AGGREGATE BASE CLASS 1 (MODIFIED) - CY 8.00 24.00 192.00 45.00 360.00 55.00 440.00 100.00 800.009 AGGREGATE BASE, CLASS 6 (CV) (P) CY 375.00 18.00 6,750.00 65.00 24,375.00 36.00 13,500.00 40.00 15,000.0010 TYPE SP 9.5 WEARING CORUSE MIX (3,C) TON 80.00120.00 9,600.00 130.00 10,400.00135.00 10,800.00 170.00 13,600.0011 BIT. MATERIAL FOR TACK COAT GAL 35.00 3.00 105.00 30.00 1,050.00 10.00 350.00 25.00 875.0012 5" CONCRETE SIDEWALK SF202.00 11.00 2,222.00 20.00 4,040.00 15.00 3,030.00 15.00 3,030.0013 8" CONCRETE DRIVEWAY SF 240.00 11.00 2,640.00 45.00 10,800.00 20.00 4,800.00 16.00 3,840.0014 CONNECT TO EXISTING WATER MAIN EACH 1.00 3,500.00 3,500.00 1,900.00 1,900.00 4,000.00 4,000.00 5,000.00 5,000.0015 6" DIP WATER MAIN PIPE, CL. 52 (POLY ENCASED) LF 17.00 90.00 1,530.00 55.00 935.00 80.00 1,360.00 70.00 1,190.0016 16" DIP WATER MAIN PIPE, CL. 52 (POLY ENCASED) LF 78.00 120.00 9,360.00 140.00 10,920.00 200.00 15,600.00 110.00 8,580.0017 6" GATE VALVE & BOX EACH 1.00 2,500.00 2,500.00 2,500.00 2,500.00 2,600.002,600.00 3,000.00 3,000.0018 HYDRANT EACH 1.00 6,000.00 6,000.00 6,000.00 6,000.00 6,200.00 6,200.00 6,500.00 6,500.0019 DUCTILE IRON FITTINGS, LB650.00 12.00 7,800.00 9.00 5,850.00 5.00 3,250.00 9.00 5,850.0020 4' X 4' CATCH BASIN WITH GRATING EACH 1.00 4,200.00 4,200.00 4,500.00 4,500.00 6,000.00 6,000.00 8,500.00 8,500.0021 1.5" CLEAR ROCK (WRAPPED IN TYPE 1 CY 16.00 72.00 1,152.00 85.00 1,360.00 90.00 1,440.00 50.00 800.0022 18" RCP STORM SEWER PIPE, CL. V LF 100.0076.00 7,600.00 110.00 11,000.0093.00 9,300.00 70.00 7,000.0023 18" RCP APRON W/ TRASH GUARD EACH 1.00 2,300.00 2,300.00 2,500.00 2,500.00 2,200.00 2,200.00 2,500.00 2,500.0024 15" CAS PIPE CULVERT LF 73.00 60.00 4,380.00 55.00 4,015.00 75.00 5,475.00 50.00 3,650.0025 15" CAS PIPE APRON W/ TRASH GUARD EACH 2.00 600.00 1,200.00 450.00 900.001,250.00 2,500.00 450.00 900.0026 HAND PLACED RIP RAP, CL. III CY 20.00 120.00 2,400.00 125.00 2,500.00 104.00 2,080.00 150.00 3,000.0027 GEOTEXTILE FABRIC TYPE IV SY 74.00 6.00 444.00 4.50 333.00 10.00 740.00 10.00 740.0028 GEOTEXTILE FABRIC TYPE V SY 400.00 6.00 2,400.00 4.50 1,800.004.00 1,600.00 2.00 800.0029 SILT FENCE, TYPE HI LF 300.00 4.00 1,200.00 6.00 1,800.00 2.00 600.00 5.00 1,500.0030 SEDIMENT CONTROL LOG TYPE WOOD FIBER LF 40.00 4.00 160.00 7.00 280.00 8.00 320.00 10.00 400.0031 TEMPORARY SEEDING (MIX 22-112 WITH TYPE 1 ACRE 0.502,000.00 1,000.00 5,000.00 2,500.001,600.00 800.00 5,000.00 2,500.0032 SEEDING (MIX 25-141 WITH FERTILIZER & ACRE 0.506,000.00 3,000.00 9,000.00 4,500.001,000.00 500.00 10,000.00 5,000.0033 CONIFEROUS TREE 8' HT B&B TREE 12.00 1,350.00 16,200.00 550.00 6,600.00 1,200.00 14,400.00 500.00 6,000.0034 LOAM TOPSOIL BORROW CY 28.00 40.00 1,120.00 55.00 1,540.00 60.00 1,680.00 33.00 924.0035 MULCH MATERIAL TYPE 6 CY 27.50 40.00 1,100.00 46.00 1,265.00 64.001,760.00 100.00 2,750.0036 1 MG COMPOSITE ELEVATED WATER STORAGE LS 1.00 3,345,000.00 3,345,000.00 3,091,202.00 3,091,202.00 3,524,000.00 3,524,000.00 3,942,771.00 3,942,771.0037 SCADA AND NEW RTU AT NEW TOWER, AND LS 1.0035,000.00 35,000.00 44,000.00 44,000.0040,000.00 40,000.00 45,000.00 45,000.0038 PRV STATION VALVE MODIFICATIONS AND LS 1.00 75,000.00 75,000.00 100,000.00 100,000.00 63,000.00 63,000.00 128,000.00 128,000.0039 FURNISH ASN INSTALL COMPLETE GAS LS 1.00 43,000.00 43,000.00 80,000.00 80,000.00 50,000.00 50,000.00 95,000.00 95,000.00$3,642,380.00$3,493,000.00 $3,874,000.00 $4,382,000.00TOTAL BID PRICE$3,642,380.00 $3,874,000.00 $4,382,000.00$3,493,000.00Short Elliott Hendrickson Inc.Page 1 of 1 PROJECT SCHEDULE  CITY OF LAKE ELMO    WATER TOWER NO. 3  PROJECT NO. 2020.118  FOCUS ENGINEERING, inc.  Cara Geheren, P.E.  651.300.4261  Jack Griffin, P.E.               651.300.4264  Ryan Stempski, P.E. 651.300.4267  Chad Isakson, P.E. 651.300.4283                  JUNE 9, 2021 Authorize Geotechincal Invesitgation Services.    JUNE 22, 2021 Preliminary Design Scoping meeting with Public Works.    JULY 6, 2021    Approve Purchase Option Agreement for Elevated Storage Tank No. 3.    JULY 6, 2021 Authorize Plans and Specifications for Elevated Storage Tank No. 3.      *Review preliminary design recommendations (tower style, materials and site plan)    JULY 9, 2021    Receive Preliminary Borings/Soil Classsifications.    JULY 23, 2021    Receive Geotechnical Services Evaluation Report.    NOVEMBER 16, 2021  Approve Plans and Specifications for Elevated Storage Tank No. 3.    JANUARY 11, 2022  Receive Contractor Bids.    JANUARY 18, 2022  Accept Bids and Award Contract.    FEBRUARY 8, 2022  Conduct Pre‐construction meeting and issue Notice to Proceed.    2022 CONSTRUCTION  Foundation and Concrete Shaft Construction, On Ground Tank Fabrication,  preliminary Site Work.     2023 CONSTRUCTION On Ground Tank Painting, Raising Tank, Roof Assembly and Final Painting,  Electical‐Controls and Final Site Work.    OCTOBER 13, 2023  Substantial Completion (water tower online and operational).    NOVEMBER 17, 2023  Final Completion (punch list and final paperwork).