HomeMy WebLinkAbout#15 - Whistling Valley Pay Req 6 STAFF REPORT DATE: October 18, 2022 CONSENT AGENDA ITEM: Approve Pay Request No. 6 for the Whistling Valley Street and Utility Improvements SUBMITTED BY: Mark Scholle, Project Engineer REVIEWED BY: Kristina Handt, City Administrator Marty Powers, Public Works Director Jack Griffin, City Engineer ISSUE BEFORE COUNCIL: Should the City Council approve Pay Request No. 6 for the Whistling Valley Street and Utility Improvements? BACKGROUND: Jacon, LLC was awarded a construction contract on January 4, 2022 to complete the Whistling Valley Street and Utility Improvements. Work remains in progress with a substantial completion date of October 14, 2022 and final completion date of November 25, 2022. PROPOSAL DETAILS/ANALYSIS: Jacon, LLC has submitted Partial Pay Request No. 6 in the amount of $164,734.93. The request has been reviewed and payment is recommended in the amount requested. In accordance with the contract documents, the City has retained 5% of the total work completed. The amount retained is $101,745.20. FISCAL IMPACT: None. Partial payment is proposed in accordance with the Contract for the project. Payment remains within the authorized scope and budget. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Pay Request No. 6 for the Whistling Valley Street and Utility Improvements. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve Pay Request No. 6 to Jacon, LLC in the amount of $164,734.93 for the Whistling Valley Street and Utility Improvements”. ATTACHMENTS: 1. Partial Pay Estimate No. 6. PROJECT PAY FORM PARTIAL PAY ESTIMATE NO. PERIOD OF ESTIMATE TO PROJECT OWNER: CONTRACTOR: 1. Original Contract Amount 2. Net Change Order Sum 3. Revised Contract (1+2) 4. *Work Completed 5. *Stored Materials 6. Subtotal (4+5) 7. Retainage* 8. Previous Payments 9. Amount Due (6-7-8) *Detailed Breakdown Attached START DATE:ON SCHEDULE SUBSTANTIAL COMPLETION:X FINAL COMPLETION: ENGINEER'S CERTIFICATION: FOCUS Engineering, inc. DATE CONTRACTOR'S CERTIFICATION: CONTRACTOR DATE APPROVED BY OWNER:CITY OF LAKE ELMO, MINNESOTA DATE DATE BY BY YES NO The undersigned Contractor certifies that to the best of their knowledge, information and belief the work covered by this payment estimate has been completed in accordance with the contract documents, that all amounts have been paid by the contractor for work for which previous payment estimates was issued and payments received from the owner, and that current payment shown herein is now due. The undersigned certifies that the work has been reviewed and to the best of their knowledge and belief, the quantities shown in this estimate are correct and the work has been performed in accordance with the contract documents. ENGINEER BY 4/18/2022 11/25/2022 REVISED DAYS REMAINING 221 0 56 10/14/2022 ORIGINAL DAYS CONTRACT CHANGE ORDER SUMMARY PAY ESTIMATE SUMMARY 6 9/30/20229/1/2022FROM WHISTLING VALLEY UTILITY AND STREET IMPROVEMENTS PROJECT NO. 2020.123 CITY OF LAKE ELMO 3800 LAVERNE AVENUE NORTH LAKE ELMO, MN 55042 ATTN: JACK GRIFFIN, CITY ENGINEER JACON, LLC 3900 LABORE ROAD VADNAIS HEIGHTS, MN 55110 ATTN: DWIGHT JOHNSON CONTRACT TIME TOTALS $173,260.35 $0.00 $164,734.93 NET CHANGE $173,260.35 $101,745.285.0% $1,768,425.33 CO-3 7/19/2022 $2,802.29 $0.00 CO-4 9/2/2022 $12,432.00 $2,034,905.54 CO-1 3/15/2022 $141,959.85 $2,443,866.80 CO-2 6/7/2022 $16,066.21 $2,034,905.54 No.Approval Date Amount $2,270,606.45 Additions Deductions $173,260.35 FOCUS Engineering, inc.PROJECT PAYMENT FORM gg, 10/10/22 Dwight Johnson Digitally signed by Dwight JohnsonDN: C=US, E=dwight@jaconco.com, O=Jacon LLC, OU=Project Manager, CN=Dwight JohnsonReason: I have reviewed this documentDate: 2022.10.12 09:21:31-05'00' PARTIAL PAY ESTIMATE NO. 6 WHISTLING VALLEY UTILITY AND STREET IMPROVEMENTS CITY OF LAKE ELMO, MINNESOTA PROJECT NO. 2020.123 QUANTITY UNIT PRICE AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT 1 LUMP SUM 1 $122,784.30 $122,784.30 0.00 $0.00 1.00 $122,784.30 2 ACRE 1 $12,012.90 $12,012.90 0.00 $0.00 0.11 $1,321.42 3 LIN FT 4679 $5.43 $25,406.97 0.00 $0.00 4,823.00 $26,188.89 4 SQ YD 13 $31.05 $403.65 0.00 $0.00 0.00 $0.00 5 SQ YD 30 $10.35 $310.50 0.00 $0.00 22.00 $227.70 6 SQ YD 34 $190.00 $6,460.00 34.00 $6,460.00 34.00 $6,460.00 7 LIN FT 670 $5.00 $3,350.00 34.00 $170.00 670.00 $3,350.00 8 SQ YD 55 $35.00 $1,925.00 0.00 $0.00 50.00 $1,750.00 9 SQ YD 23218 $5.00 $116,090.00 0.00 $0.00 23,218.00 $116,090.00 10 SQ YD 200 $10.35 $2,070.00 56.00 $579.60 200.00 $2,070.00 11 EACH 19 $45.00 $855.00 0.00 $0.00 0.00 $0.00 12 EACH 37 $341.89 $12,649.93 0.00 $0.00 10.00 $3,418.90 13 EACH 46 $200.00 $9,200.00 0.00 $0.00 46.00 $9,200.00 14 EACH 18 $150.00 $2,700.00 0.00 $0.00 28.00 $4,200.00 15 EACH 12 $50.00 $600.00 0.00 $0.00 12.00 $600.00 16 CU YD 10448 $0.79 $8,253.92 0.00 $0.00 693.00 $547.47 17 SQ FT 824 $7.32 $6,031.68 0.00 $0.00 0.00 $0.00 18 CU YD 4890 $31.20 $152,568.00 400.00 $12,480.00 5,165.00 $161,148.00 19 CU YD 3869 $20.30 $78,540.70 400.00 $8,120.00 3,939.00 $79,961.70 20 HOUR 40 $120.00 $4,800.00 0.00 $0.00 29.00 $3,480.00 21 TON 2210 $90.00 $198,900.00 0.00 $0.00 838.00 $75,420.00 22 TON 2945 $83.00 $244,435.00 53.37 $4,429.71 1,141.37 $94,733.71 23 TON 200 $156.00 $31,200.00 7.03 $1,096.68 55.03 $8,584.68 24 GAL 1628 $2.00 $3,256.00 0.00 $0.00 600.00 $1,200.00 25 LIN FT 1458 $14.00 $20,412.00 1,164.00 $16,296.00 1,458.00 $20,412.00 26 EACH 14 $250.00 $3,500.00 11.00 $2,750.00 14.00 $3,500.00 27 LIN FT 55 $21.00 $1,155.00 0.00 $0.00 40.00 $840.00 28 EACH 1 $420.00 $420.00 0.00 $0.00 1.00 $420.00 29 EACH 1 $12,300.00 $12,300.00 0.00 $0.00 0.00 $0.00 30 EACH 2 $1,500.00 $3,000.00 2.00 $3,000.00 2.00 $3,000.00 31 EACH 18 $675.00 $12,150.00 0.00 $0.00 19.00 $12,825.00 32 EACH 14 $500.00 $7,000.00 11.00 $5,500.00 14.00 $7,000.00 33 EACH 2 $4,025.00 $8,050.00 0.00 $0.00 2.00 $8,050.00 34 EACH 12 $7,500.00 $90,000.00 0.00 $0.00 12.00 $90,000.00 35 EACH 71 $770.00 $54,670.00 0.00 $0.00 44.00 $33,880.00 36 EACH 37 $485.00 $17,945.00 0.00 $0.00 37.00 $17,945.00 37 EACH 37 $550.00 $20,350.00 0.00 $0.00 37.00 $20,350.00 38 LIN FT 1189 $36.60 $43,517.40 0.00 $0.00 1,212.00 $44,359.20 39 EACH 11 $3,283.15 $36,114.65 0.00 $0.00 11.00 $36,114.65 40 LIN FT 112 $116.70 $13,070.40 0.00 $0.00 85.00 $9,919.50 41 LIN FT 816 $81.00 $66,096.00 0.00 $0.00 485.00 $39,285.00 42 LIN FT 6691 $71.25 $476,733.75 0.00 $0.00 6,993.00 $498,251.25 43 SQ YD 56 $34.00 $1,904.00 0.00 $0.00 23.60 $802.40 44 LB 3040 $6.83 $20,763.20 0.00 $0.00 3,026.00 $20,667.58 45 LIN FT 3849 $30.36 $116,855.64 255.00 $7,741.80 4,889.00 $148,430.04 46 LIN FT 1310 $30.80 $40,348.00 0.00 $0.00 1,665.00 $51,282.00 47 LIN FT 5284 $13.86 $73,236.24 0.00 $0.00 4,311.00 $59,750.46 48 SQ YD 13 $110.00 $1,430.00 13.00 $1,430.00 13.00 $1,430.00 49 EACH 19 $2,079.00 $39,501.00 9.00 $18,711.00 19.00 $39,501.00 50 LUMP SUM 1 $6,500.00 $6,500.00 0.00 $0.00 0.85 $5,525.00 51 SQ FT 63.31 $130.00 $8,230.30 0.00 $0.00 0.00 $0.00 52 EACH 10 $340.00 $3,400.00 0.00 $0.00 0.00 $0.00 53 LIN FT 1000 $3.00 $3,000.00 0.00 $0.00 0.00 $0.00 54 EACH 34 $220.00 $7,480.00 0.00 $0.00 17.00 $3,740.00 55 CU YD 678 $40.25 $27,289.50 0.00 $0.00 531.00 $21,372.75 56 SQ YD 6401 $11.67 $74,699.67 0.00 $0.00 4,332.00 $50,554.44 57 ACRE 0.5 $4,500.00 $2,250.00 0.00 $0.00 0.00 $0.00 58 SQ YD 2505 $2.60 $6,513.00 0.00 $0.00 0.00 $0.00 59 CY YD 50 $149.50 $7,475.00 0.00 $0.00 58.00 $8,671.00 60 EACH 2 $1,750.00 $3,500.00 0.00 $0.00 1.00 $1,750.00 61 LIN FT 12301 $3.00 $36,903.00 0.00 $0.00 7,080.00 $21,240.00 $2,412,566.30 $88,764.79 $2,003,605.04 ADJUST CASTING ADJUST CATCH BASIN REMOVE CASTING GEOTEXTILE FABRIC, TYPE V GEOGRID MOBILIZATION** REMOVE BITUMINOUS WALK REMOVE SIGN SALVAGE AND REINSTALL MAIL BOX ASSEMBLY** CLEARING AND GRUBBING** REMOVE CONCRETE CURB AND GUTTER REMOVE CONCRETE DRIVEWAY PAVEMENT REMOVE BITUMINOUS DRIVEWAY PAVEMENT SALVAGE AND REINSTALL DRIVEWAY PAVERS SAWING PAVEMENT (FULL DEPTH) REMOVE SEWER PIPE (STORM) REMOVE BITUMINOUS PAVEMENT (P)** ITEM DESCRIPTION OF PAY ITEM UNIT CONTRACT THIS PERIOD TOTAL TO DATE TYPE SP 9.5 WEARING COURSE MIX (2,B) (DRIVEWAYS & TRAIL) BITUMINOUS MATERIAL FOR TACK COAT 4" PVC SCHEDULE 40 PERF PE PIPE DRAIN W/ BACKFILL AND WRAP DRAINTILE CLEANOUT 12" HDPE STORM SEWER PIPE AGGREGATE BASE CL 6 (CV)(P)** COMMON EXCAVATION (P)** STREET SWEEPING TYPE SP 9.5 WEARING COURSE MIX (2,C) TYPE SP 12.5 WEARING COURSE MIXTURE (2,C) 12" FLARED END SECTION 6" CONCRETE HEADWALL CONCRETE FLUME FURNISH AND INSTALL CASTING ASSEMBLY R-3067-V CONNECT DRAINTILE TO EXISTING STORM STRUCTURE CONNECT TO EXISTING WATERMAIN HYDRANT AND GATE VALVE ASSEMBLY 10" HDPE TO 8" DIP TRANSITION FITTING 1.5" CURB STOP & BOX 1.5" CORPORATION STOP 1.5" TYPE K COPPER PIPE 8" GATE VALVE AND BOX 6" WATERMAIN DUCTILE IRON CL 52 8" WATERMAIN DUCTILE IRON CL 52 10" HDPE DR 11 WATERMAIN (DIRECTIONAL DRILLING) W/ 4700 LB TRACER WIRE** 4" INSULATION DUCTILE IRON FITTINGS CONCRETE CURB AND GUTTER DESIGN D412 CONCRETE CURB AND GUTTER DESIGN B618 24" CONCRETE RIBBON CURB 6" CONCRETE DRIVEWAY PAVEMENT INSTALL CONCRETE PEDESTRIAN RAMP TRAFFIC CONTROL SIGN PANELS TYPE C SIGN PANELS TYPE SPECIAL (STREET NAME SIGN) SILT FENCE PREASSEMBLED STORM DRAIN INLET PROTECTION COMMON TOPSOIL BORROW PULVERIZED (LV) SODDING TYPE MINERAL** SEEDING (SEED MIXTURE TYPE 25-141) EROSION CONTROL BLANKETS CATEGORY 3N CLASS 3 RIP-RAP WITH GEOTEXTILE FABRIC TEMPORARY ROCK CONSTRUCTION ENTRANCE SEDIMENT CONTROL LOG QUANTITY UNIT PRICE AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT ITEM DESCRIPTION OF PAY ITEM UNIT CONTRACT THIS PERIOD TOTAL TO DATE NOTE: ** PREVAILING WAGE COSTS INCLUDED IN UNIT PRICE PER CHANGE ORDER NO.1 Orig. Contract Amount $2,270,606.45 CO-1 $141,959.85 TOTALS - BASE CONTRACT $2,412,566.30 $88,764.79 $2,003,605.04 CO2-1 LS 1 $16,066.21 $16,066.21 0.00 $0.00 1.00 $16,066.21 $16,066.21 $0.00 $16,066.21 CO3-1 LS 1 $368.00 $368.00 0.00 $0.00 1.00 $368.00 CO3-2 LF 53 $45.93 $2,434.29 0.00 $0.00 53.00 $2,434.29 $2,802.29 $0.00 $2,802.29 CO4-1 EA 12 $1,036.00 $12,432.00 12.00 $12,432.00 12.00 $12,432.00 $12,432.00 $12,432.00 $12,432.00 TOTALS - REVISED CONTRACT $2,443,866.80 $101,196.79 $2,034,905.54 SUBTOTAL - CHANGE ORDER NO. 2 ADD TRACER WIRE FOR ALL PROJECT SERVICES AND HYDRANTS CHANGE ORDER NO. 3 SALVAGE OF EXISTING BASE MATERIAL SUBTOTAL - CHANGE ORDER NO. 3 CONCRETE VALLEY GUTTER CHANGE ORDER NO. 4 HYDRANT SPLASH PAD SUBTOTAL - CHANGE ORDER NO. 4 CHANGE ORDER NO. 2 See note above and Change Order-1 for detail