Loading...
HomeMy WebLinkAbout#28 - 2023 Street Improvements STAFF REPORT DATE: October 18, 2022 REGULAR AGENDA ITEM: Approve Resolution Receiving Feasibility Report and Calling Hearing on Improvement for the 2023 Street Improvements SUBMITTED BY: Jack Griffin, City Engineer REVIEWED BY: Kristina Handt, City Administrator Marty Powers, Public Works Director Chad Isakson, Assistant City Engineer ISSUE BEFORE COUNCIL: Should the City Council accept the Feasibility Report and call a public hearing for the 2023 Street Improvements to be held at the November 15, 2022 Council meeting? BACKGROUND: On September 6, 2022, the City Council authorized the preparation of a feasibility report for the 2023 Street Improvements. The public streets selected for improvement in 2023 are in accordance with the city’s Street Capital Improvement Program which provides for the long-term planning and management of street and transportation infrastructure throughout the city. PROPOSAL DETAILS/ANALYSIS: A Feasibility Report has been prepared to address street and drainage improvements programmed for construction in 2023. The report serves to identify the necessary improvements, the estimated project costs, and to consider the assessment of a portion of the project costs to properties adjacent to and benefitting from the improvements. The proposed project includes street and drainage improvements within the Fields of St. Croix 2nd Addition and in Tana Ridge, consisting of approximately 12,300 feet (2.3 miles) of local streets as detailed below: Fields of St. Croix 2nd Addition • Little Bluestem Trail, from Stillwater Way to Little Bluestem Lane. • Little Bluestem Trail One-Way Pair, from Little Bluestem Lane to 44th Street. • Little Bluestem Circle, from Little Bluestem Trail to west end cul-de-sac. • Little Bluestem Court, from Little Bluestem Trail to east end cul-de-sac. • Little Bluestem Lane, from 44th Street to Little Bluestem Trail. • 44th Street North, from Lily Avenue to east end cul-de-sac. • 44th Street Lane North. • Lily Avenue North, including both North and South Loops. Tana Ridge • Lily Avenue North, from 50th Street North to south end cul-de-sac. The proposed improvements include the reconstruction or full depth reclamation of the street pavement section, with new bituminous pavement and new concrete curb and gutter. The existing bituminous curb will be replaced with new concrete curb and gutter to improve drainage, improve the construction quality, and provide edge control to protect and extend the service life of the new bituminous surface. From a preliminary design perspective, it appears that no street widening or geometric changes will be needed in either neighborhood, allowing the improvements to maintain the existing grading, drainage, and curb line conditions, with minimal or no change. However, by maintaining the existing street widths to reduce property impacts and lower project costs, it is recommended that “No Parking” signage be installed as part of the Project to implement the No Parking Designation plans as presented in the feasibility report. As part of the street improvements, it is recommended that the storm sewer/drainage system and existing public watermain system be inspected and that deficiencies or needed repairs be incorporated into the project. Therefore, the scope of this Report includes the restoration of the existing street drainage system, including either repair or replacement of existing drainage pipe and structures, and storm sewer casting replacement. Drainage improvements are limited to the necessary improvements to meet watershed rules and to prevent water from standing on or along the new street pavements, and are not intended to resolve pre-existing private property drainage issues. Minor repairs and/or upgrades to the public watermain system are also recommended in both subdivisions. The Fields of St. Croix subdivision was also constructed with an extensive trail network consisting of on-road public trails and off-road private trails. There is approximately 4,400 feet of 8-ft. wide bituminous trails located within the public right-of-way, separated from the street with a 4-ft. grassed boulevard. These trails were rated by Public Works in 2021 as good condition and were fog sealed in 2022. Therefore, there are no trail improvements incorporated as part of this Project. The Report includes an estimate of total project costs for each neighborhood and is further detailed by infrastructure component, including the street and drainage improvements, and water system repairs/upgrades. The estimates include construction costs, engineering, geotechnical investigations, legal, and administration costs directly associated with project implementation. A small allowance is included for potential easement review and potential acquisition and a 10% contingency is included to address changing market conditions until contractor bids can be received to firm up the construction costs. The proposed street and drainage improvements would be partially assessed against the benefitting properties consistent with the city’s Special Assessment Policy. Street and drainage improvements are assessed at a rate of 30% of the total project costs for residential properties using a unit method. Residential properties are considered to provide an equal demand on street use and are therefore assessed on a per unit basis, including “flag” lots located on private streets. The remaining 70% of the project costs are paid through the city general fund. Residential properties with direct access to the street, vacant lots, and lots with direct access from a private street are included as benefitting properties. Each property is assessed one unit unless the property has the ability to be subdivided using the current underlying land use and zoning regulations. Assessments for street and drainage improvements will be levied over a 15-year period. All assessments are be charged an interest rate of 1% over the bond rate for the project. There are 56 single family residential properties, 14 townhome properties, and 1 city Park located along the public streets in the Fields of St. Croix 2nd Addition. There are 20 residential properties and 1 city Park located along the public streets in Tana Ridge. For the higher cost reconstruction improvement, the unit assessment is $12,900 for the Fields of St. Croix 2nd Addition and $17,100 for Tana Ridge. For a full depth reclamation improvement, if determined to be a feasible alternative, the unit assessment is $8,000 for the Fields of St. Croix 2nd Addition and $11,400 for Tana Ridge. The preliminary assessment rolls detailing each benefitting property’s proposed assessment amount are included in the Appendix of this report. In addition to the recommended improvements, the estimated project costs and the proposed assessments, this report addresses the project schedule, permitting requirements and the easement and right-of-way acquisition needed to implement the improvements. FISCAL IMPACT: The total estimated project cost is $3,100,000 for the Fields of St. Croix 2nd Addition, and $1,223,000 for Tana Ridge. These costs assume a full pavement section reconstruction improvement. If it is determined that full depth reclamation is feasible, the total estimated project cost is $1,930,000 for the Fields of St. Croix 2nd Addition, and $825,000 for Tana Ridge. The estimated project costs and breakdown are detailed below: FIELDS OF ST. CROIX 2ND ADDITION: Total Estimated Project Cost $3,100,000 • Full Pavement Section Reconstruction with Storm Sewer Repair/Replacement $3,045,000 *Full Depth Reclamation (if feasible): $1,875,000 • Water System Repairs/Upgrades $ 55,000 TANA RIDGE: Total Estimated Project Cost $1,223,000 • Full Pavement Section Reconstruction with Storm Sewer Repair/Replacement $1,196,000 *Full Depth Reclamation (if feasible): $798,000 • Water System Repairs/Upgrades $ 27,000 For the street and drainage improvements, $915,900 ($568,000 for Reclaim) would be paid through special assessment from Fields of St. Croix 2nd Addition, 359,100 ($239,400 for Reclaim) would be paid through special assessment from Tana Ridge, with the remaining $2,966,000 ($1,865,600 for Reclaim) paid through the general fund. The total estimated cost for the water system repair/upgrades is $82,000 and would be paid through the water enterprise fund. RECOMMENDATION: Staff is recommending that the City Council approve a Resolution, receiving the Feasibility Report and calling a public hearing for the 2023 Street Improvements. The recommended motion for this action is as follows: “Move to approve Resolution No. 2022-098, receiving the Feasibility Report and Calling a Public Hearing for the 2023 Street Improvements.” ATTACHMENTS: 1. Resolution Receiving Report and Calling for Hearing on Improvements. 2. Notice of Hearing on Improvement. 3. 2023 Street Improvements – Location Map. 4. 2023 Street Improvements – Project Schedule. Feasibility Report (available for review at City Hall). CITY OF LAKE ELMO WASHINGTON COUNTY STATE OF MINNESOTA RESOLUTION NO. 2022-098 A RESOLUTION RECEIVING A FEASIBILITY REPORT FOR THE 2023 STREET IMPROVEMENTS AND CALLING HEARING ON IMPROVEMENT WHEREAS, pursuant to City Council authorization, adopted on September 6, 2022, a feasibility report has been prepared by FOCUS Engineering, Inc. for the 2023 Street Improvements; and WHEREAS, the feasibility report recommends that benefitting properties be assessed all or a portion of the cost of the improvements pursuant to the city’s Special Assessment Policy and Minnesota Statutes, Chapter 429; and WHEREAS, the feasibility report provides information regarding whether the proposed improvement is necessary, cost-effective, and feasible; whether it should best be made as proposed or in connection with some other improvement; the estimated cost of the improvements as recommended; and a description of the methodology used to calculate individual assessments for affected parcels. NOW, THEREFORE, BE IT RESOLVED, 1. That the City Council will consider the improvements in accordance with the report and the assessments of the abutting properties for all or a portion of the cost of the improvements pursuant to Minnesota Statues, Chapter 429 at an estimated total project street and drainage improvement cost of $3,045,000 for the Fields of St. Croix 2nd Addition and $1,196,000 for Tana Ridge. 2. A public hearing shall be held on such proposed improvements on the 15th day of November, 2022 in the council chambers of City Hall, at or approximately after 7:00 P.M. and the clerk shall give mailed and published notice of such hearing and improvement as required by law. ADOPTED BY THE LAKE ELMO CITY COUNCIL ON THE EIGHTEENTH DAY OF OCTOBER, 2022. CITY OF LAKE ELMO By: __________________________ Charles Cadenhead (Seal) Mayor ATTEST: ________________________________ Julie Johnson City Clerk CITY OF LAKE ELMO NOTICE OF HEARING ON IMPROVEMENT 2023 STREET IMPROVEMENTS Notice is hereby given that the City Council of Lake Elmo will conduct a public hearing on Tuesday, November 15, 2022, at or approximately after 7:00 PM to consider the making of the following improvements, pursuant to Minnesota Statutes, Sections 429.011 to 429.111: Street and drainage improvements along the public streets within the Fields of St. Croix 2nd Addition and in Tana Ridge, consisting of the reconstruction or full depth reclamation of the street pavement section, with new bituminous pavement and new concrete curb and gutter. As part of the improvements the project will incorporate the restoration of the existing drainage system along the streets and right-of-way, including repair and/or replacement of existing drainage pipe and structures. The improvements may also include repairs and/or upgrades to the public watermain system in both subdivisions. The project includes approximately 12,300 feet (2.3 miles) of public streets including the following segments: Fields of St. Croix 2nd Addition • Little Bluestem Trail, from Stillwater Way to Little Bluestem Lane. • Little Bluestem Trail One-Way Pair, from Little Bluestem Lane to 44th Street. • Little Bluestem Circle, from Little Bluestem Trail to west end cul-de-sac. • Little Bluestem Court, from Little Bluestem Trail to east end cul-de-sac. • Little Bluestem Lane, from 44th Street to Little Bluestem Trail. • 44th Street North, from Lily Avenue to east end cul-de-sac. • 44th Street Lane North. • Lily Avenue North, including both North and South Loops. Tana Ridge • Lily Avenue North, from 50th Street North to south end cul-de-sac. The area proposed to be assessed for these improvements include properties abutting or properties that gain direct driveway access from the above referenced streets. The estimated total cost for the street and drainage improvements is $3,045,000 for the Fields of St. Croix 2nd Addition and $1,196,000 for Tana Ridge. The estimated total cost for the Water System Repair/Upgrades is $55,000 in the Fields of St. Croix 2nd Addition and $27,000 in Tana Ridge. A reasonable estimate of the impact of the assessment will be available at the hearing. Such persons as desiring to be heard with reference to the proposed improvements will be heard during this meeting. DATED: October 18, 2022 BY ORDER OF THE LAKE ELMO CITY COUNCIL Charles Cadenhead, Mayor (Published in the Stillwater Gazette on October 21, 2022 and October 28, 2022) CITY OF LAKE ELMO NOTICE OF HEARING ON IMPROVEMENT 2023 STREET IMPROVEMENTS Notice is hereby given that the City Council of Lake Elmo will conduct a public hearing on Tuesday, November 15, 2022, at or approximately after 7:00 PM to consider the making of the following improvements, pursuant to Minnesota Statutes, Sections 429.011 to 429.111: Street and drainage improvements along the public streets within the Fields of St. Croix 2nd Addition and in Tana Ridge, consisting of the reconstruction or full depth reclamation of the street pavement section, with new bituminous pavement and new concrete curb and gutter. As part of the improvements the project will incorporate the restoration of the existing drainage system along the streets and right-of-way, including repair and/or replacement of existing drainage pipe and structures. The improvements may also include repairs and/or upgrades to the public watermain system in both subdivisions. The project includes approximately 12,300 feet (2.3 miles) of public streets including the following segments: Fields of St. Croix 2nd Addition  Little Bluestem Trail, from Stillwater Way to Little Bluestem Lane.  Little Bluestem Trail One-Way Pair, from Little Bluestem Lane to 44th Street.  Little Bluestem Circle, from Little Bluestem Trail to west end cul-de-sac.  Little Bluestem Court, from Little Bluestem Trail to east end cul-de-sac.  Little Bluestem Lane, from 44th Street to Little Bluestem Trail.  44th Street North, from Lily Avenue to east end cul-de-sac.  44th Street Lane North.  Lily Avenue North, including both North and South Loops. Tana Ridge  Lily Avenue North, from 50th Street North to south end cul-de-sac. The area proposed to be assessed for these improvements include properties abutting or properties that gain direct driveway access from the above referenced streets. The estimated total cost for the street and drainage improvements is $3,045,000 for the Fields of St. Croix 2nd Addition and $1,196,000 for Tana Ridge. The estimated total cost for the Water System Repair/Upgrades is $55,000 in the Fields of St. Croix 2nd Addition and $27,000 in Tana Ridge. A reasonable estimate of the impact of the assessment will be available at the hearing. Such persons as desiring to be heard with reference to the proposed improvements will be heard during this meeting. DATED: October 18, 2022 BY ORDER OF THE LAKE ELMO CITY COUNCIL Charles Cadenhead, Mayor (Published in the Stillwater Gazette on October 21, 2022 and October 28, 2022) FIGURE NO. 1 LOCATION MAP 2023 STREET IMPROVEMENTS CITY OFLAKE ELMO TANA RIDGE LEGEND PROJECT NO. 2022.123 OCTOBER, 2022 FIELDS OF ST. CROIX 2ND ADDITION TANA RIDGE FIELDS OF ST. CROIX 2ND ADDITION PROJECT SCHEDULE  CITY OF LAKE ELMO    2023 STREET IMPROVEMENTS  PROJECT NO. 2022.123  FOCUS ENGINEERING, inc.  Cara Geheren, P.E.   651.300.4261  Jack Griffin, P.E.                651.300.4264  Ryan Stempski, P.E.  651.300.4267  Chad Isakson, P.E.  651.300.4283                  SEPTEMBER 6, 2022  Council orders preparation of Feasibility Report.      OCTOBER 18, 2022  Presentation  of  Feasibility  Report.  Council  accepts  Report  and  calls  for  Improvement Hearing.       TBD  Neighborhood informational meeting.      NOVEMBER 15, 2022  Public Improvement Hearing. Council Orders the Improvement (4/5th Vote)  and preparation of Plans and Specfications.      MARCH 7, 2023  Council approves Plans and Specifications and orders Advertisement for Bids.      APRIL 6, 2023      Project Bid Date: Receive contractor bids.      APRIL 18, 2023  Council accepts Bids and awards Contract.       MAY 29, 2023    Conduct Pre‐Construction Meeting and issue Notice to Proceed.   OCTOBER 6, 2023    Substantial Completion.   NOVEMBER 17, 2023    Final Completion.      *Final Assessment Hearing Schedule TBD