HomeMy WebLinkAbout#28 - 2024 Collector Street Imrprovement Preliminary Design STAFF REPORT
DATE: August 15, 2023
REGULAR
AGENDA ITEM: Authorize Preliminary Design Engineering Services for the 2024 Collector Street Improvement Projects SUBMITTED BY: Jack Griffin, City Engineer REVIEWED BY: Kristina Handt, City Administrator Marty Powers, Public Works Director Chad Isakson, Assistant City Engineer
ISSUE BEFORE COUNCIL: Should the City Council authorize preliminary design engineering services for the 2024 Collector Street Improvement projects?
BACKGROUND: The City has developed a 10-year Street Capital Improvement Program which provides long-term planning and management of street and transportation infrastructure throughout the city. The CIP Program consists of a 10-year overview of scheduled capital street projects to address the City’s goals for
maintaining public street infrastructure to an acceptable level of service. PROPOSAL DETAILS/ANALYSIS: Several collector streets in the City have been identified for
improvement in 2024 as outlined below:
• Hudson Boulevard Improvements – Segment A, extending from Inwood Avenue to the east property line of 9242 Hudson Boulevard (“Project”). The Project includes pavement rehabilitation, drainage improvements, and urbanizing the north side of Hudson Boulevard with a new bituminous trail. The Project will coordinate the design and construction with the segments of Hudson Boulevard to be
improved through the Amira and Hendrix development projects.
• 15th Street North Improvements, extending from Inwood Avenue North to the Oakdale City limits (“Project”). The Project includes pavement rehabilitation and related drainage improvements for the roadway segment.
• 30th Street North Gap Segment Improvements. The Project extends from the eastern edge of Lisbon Avenue North to approximately 475-feet east of Village Parkway (“Project”). The Project includes pavement rehabilitation, curb & gutter replacement, shared-use path resurfacing and related drainage improvements for the roadway segment, tying into the recent improvements at each project termini.
In order to ready each of these Projects for construction in 2024, engineering has prepared a work plan and task order, and has requested a fee estimate from KLJ, Inc. for preliminary design engineering support services. The three projects are being combined together for economies of scale and implementation
efficiencies. The preliminary design work will result in detailed recommendations for the proposed improvement project for each street segment, including proposed pavement rehabilitation, curb and gutter improvements, street widths, turn lanes, lane configuration, pedestrian pathways, and stormwater management. The scope of the preliminary design work includes topographic survey, field condition assessment reviews, identification of small utility conflicts, evaluation of existing and required right-of-way and easements, review of geotechnical evaluations obtained by the City, and coordination with as-built
plans and approved plans for adjacent street segments.
FISCAL IMPACT: $80,300 for preliminary design engineering support services; including $45,900 for
the Hudson Boulevard Improvements – Segment A, $16,200 for the 15th Street North Improvements, and $18,200 for the 30th Street North Gap Segment Improvements. The projects are being funded through improvement bonds, the general tax levy and potentially a portion through municipal state aid funds.
RECOMMENDATION: Staff is recommending that the City Council authorize KLJ, Inc. to provide preliminary design engineering services for the 2024 Collector Street Improvement Projects as outlined in the attached Task Orders (#6, #7 and #8). The recommended motion for this action is as follows:
“Move to authorize KLJ, Inc. to provide preliminary design engineering services for the 2024 Collector Street Improvement Projects as outlined in the attached Task Orders, including Task Order No. 6, Task Order No. 7, and Task Order No.8, in the amount not to exceed $80,300.” ATTACHMENTS: 1. Project Location Map. 2. KLJ, Inc. Task Order No. 6 – Hudson Boulevard Improvements – Segment A. 3. KLJ, Inc. Task Order No. 6 – 15th Street North Improvements. 4. KLJ, Inc. Task Order No. 6 – 30th Street North Gap Segment Improvements.
10th5thHudsonKeatsLake Elmo15thInwood34th20th27thJamaca7th31st38thManningStillwater24th26thIsland9th30th32nd21stJade6th
Ivory8th12thJewelIris22nd37th36th35thLaverneJuniperAnnikaJasmineJamleyLegionKlondike16thUpper 33RdImperial3rd33rdIrving4th14thJune28thVillageEagle PointJonquilLaytonPrivateKelvin
IronwoodJanero Leeward Cimarron10th StreetJamesJayLower 31stLower 8thLisbon
KraftLampertWhistling ValleyJunco11th5th Stre
e
tSunfish Lake Park InboundIvywoodInnsda3rd StreetLangly
JunoLansingJulianneUpper 30th6th StreetLisbon AvenueIrwinWB I94 To Inwood Ave NUpper 7thQueenUpper 9th27th St
r
e
e
t 15th StreetWB I94 To Keats Ave NJasmi
n
e
A
ve
n
ue Keats Ave N To WB I94Manning Ave N To WB I9430th Street
33rd Street24th Street20th StreetLegion Lane21stLaverne32ndIrish35th34th35thLaverneLanglyLaytonLilac33rd10th Street6th Street21st9th36thWhistling Valley5th33rd6th StreetInnsdale
Ironwoo
d LindenLegion LaneLindenPrivateJulep28thVillageIvyInnsdaleLower 8th31stLisbon9thIsleManning32ndLaverne37thManningLegion9th34thLaytonJade5thHudson36thDOWNSLAKELAKE ELMOREGIONALPARK RESERVELAKE ELMOSUNFISH LAKEHORSESHOELAKEROSELAKEREIDPARKVFWPARKLIONS PARKCity of WoodburySTONEGATEPARKKRAMERLAKEGOOSELAKEARMSTRONGLAKERIDGEPARKKEATS AVE NEAGLE POINTLAKETABLYNPARKHEIGHTSPARKCity of OakdaleWest LakelandTownshipSUNFISH LAKEPARKHOMESTEDPARKHERITAGEPARKCity ofAftonTablynParkEagle PointCreek EstatesLake ElmoHeightsTorre PinesFarms ofLake ElmoParkview EstatesWildflowersShoresHuppertAddBeautCrest EstatesFriedrichHghtsKenridge AddPrairie RidgeOffice ParkEagle PointBusiness ParkStonegateHammes CountryVistaWhistling ValleyMidlandMeadowsDavidNelson EstTheHomesteadTartanMeadowsThe ForestSchwartz-Martinco AddPackardParkEdenParkHeritageFarmLonesomePine AddDownsLake EstMyronEllmanElmo ViewCty AudPlat No. 8Lake Elmo ParkHamlet OnSunfish LakeParkMeadowsBordners GarnerFarmettesRoyal Golf Club SouthwindHunters CrossingHammesEstatesSavonaBoulder PondsInwoodLakewood Crossing2nd AdditionEaston VillageCimarronEDENPARKPILOTPARKHAMMESPARKGOOSE LAKEPARKI-94
TASK ORDER No. 6 – HUDSON BOULEVARD IMPROVEMENTS ‐SEGMENT A Page 1 of 3
TASK ORDER No. 6
CITY OF LAKE ELMO, MINNESOTA – KLJ
PROFESSIONAL ENGINEERING SERVICES AGREEMENT
In accordance with ARTICLE 1 of the Master AGREEMENT between the City of Lake Elmo (“CITY”) and
Kadrmas, Lee & Jackson, Inc. (KLJ) (“ENGINEER”), dated February 20, 2018 (“AGREEMENT”), the
ENGINEER agrees to provide Professional Engineering Support Services as follows:
HUDSON BOULEVARD IMPROVEMENTS – SEGMENT A
PROJECT OVERVIEW: The CITY requires preliminary design engineering services for the Hudson
Boulevard Improvements – Segment A, extending from Inwood Avenue to the east property line of
9242 Hudson Boulevard (“Project”). The Project includes pavement rehabilitation and related drainage
improvements for the roadway segments that have not yet been recently improved or is planned for
improvement by the Amira Subdivision or Hendrix Subdivision.
SERVICES TO BE PROVIDED BY ENGINEER: KLJ shall provide the following Professional Engineering
Services:
PRELIMINARY DESIGN SERVICES
1. Project management throughout the course of work for preparation of preliminary design
documents including a monthly PMT meeting, and submittal of a weekly progress memo and
job to date budget form.
2. Project kick‐off meeting with city staff.
3. Work with city staff to develop critical success criteria for the project, obtain project
information and formalize the budget and schedule.
4. Review Hudson Boulevard Improvement Plans prepared for the Amira and Hendrix
subdivisions to coordinate project design transitions.
5. Site visit to review existing conditions, perform existing curb review for full or spot
replacement, and perform existing pavement review to define project limits.
6. Review existing roadway drainage and storm sewer systems, perform unconfined visual
observations, and make recommendations regarding additional storm sewer televising.
7. Survey: Coordinate Gopher State One Call utility locates and perform topographic survey of
existing conditions within project limits for the purposes of preparing design documents.
8. Right of way verification: Review title work and verify right‐of‐way for all properties impacted
by the proposed improvements.
9. Review Geotechnical Evaluation Report findings and recommendations obtained by the CITY.
10. Prepare preliminary design including recommendations on street widths, turn lanes, lane
configuration, pedestrian improvements, and stormwater management.
11. Identify right of way and easement needs to construct the proposed infrastructure.
12. Identify small utility conflicts related to the proposed preliminary design.
TASK ORDER No. 6 – HUDSON BOULEVARD IMPROVEMENTS ‐SEGMENT A Page 2 of 3
13. Prepare opinion of probable cost based on the preliminary design layout.
14. Identify permits required to complete the proposed work. The design shall incorporate
measures to meet compliance requirements for all permits necessary.
DRONE FOOTAGE SERVICES
1. Record aerial footage of the project site.
DELIVERABLES:
1. Exhibits displaying recommended infrastructure.
2. Opinion of Total Probable Project Costs.
3. Design Memorandum summarizing final design assumptions and performance criteria
incorporated into the project design.
4. Identification of easements needed for the construction of the project.
5. Drone video (.mp4).
CITIES RESPONSIBILITIES: The City (or its consultants) will provide the following:
Coordination with the public and conduct public meetings.
Presentation(s) to the City Council.
Easement negotiations and acquisition, if needed.
Hire geotechnical firm for geotechnical investigation.
TIMES FOR RENDERING SERVICES: CONSULTANT shall perform its services and provide deliverables in
accordance with the following schedule:
1. August 15, 2023 –Engineering Services Authorized.
2. All Task Order Services shall be substantially completed by September 22, 2023.
CITY’S REPRESENTATIVE AND CONTRACT ADMINISTRATION: The CITY’s representative with respect
to services rendered by ENGINEER under this TASK ORDER shall be the City Engineer. Project
correspondence must be addressed to:
Jack Griffin, P.E., City Engineer
City of Lake Elmo
3880 Laverne Avenue North
Lake Elmo, MN 55042
651.300.4264
Email: Jack.griffin@focusengineeringinc.com
COMPENSATION: Compensation to ENGINEER shall be on an hourly rate basis using the hourly billing
rates provided in the ENGINEER’s Proposal for the work. Invoices shall be submitted once each month
and should be sent to the attention of the City Engineer.
TASK ORDER No. 6 – HUDSON BOULEVARD IMPROVEMENTS ‐SEGMENT A Page 3 of 3
Compensation to ENGINEER for Project Management, Survey and Preliminary Design Services for the
Project shall be on an hourly rate basis in a not to exceed amount of $43,800.
Compensation to ENGINEER for Drone Footage Services for the Project shall be on an hourly rate basis
in a not to exceed amount of $2,100.
Payment for Services shall be in accordance with ARTICLE 3.2 of the Master AGREEMENT.
ADDITIONAL SERVICES: If authorized by the City, ENGINEER shall furnish or obtain from others
Additional Services which are not considered under this Task Order. Such services shall be compensated
for on an Hourly Rate basis in an amount approved by the City prior to any services being started or as
otherwise mutually agreed. The City is not obligated to compensate ENGINEER for services completed
outside the approved scope of work which are completed prior to ENGINEER submitting a written
request to the City, and receiving written approval of the City.
ATTACHMENTS: This agreement supersedes and replaces all previous understandings, agreements or
contracts, written or verbal, between ENGINEER and City, regarding the Project. The following
documents are attached for reference:
1. ENGINEER’s 2023 Rate Sheet.
APPROVAL AND ACCEPTANCE: Approval and Acceptance of this Task Order, including the
attachment(s) listed above, shall incorporate this document as part of the AGREEMENT. ENGINEER is
authorized to begin performance of services upon receipt of a copy of this Task Order signed by CITY.
The Effective Date of this Task Order is AUGUST 16, 2023.
KLJ CITY OF LAKE ELMO, MINNESOTA
By _________________________________ By _________________________________
(Authorized Principal of the Firm) City Administrator
STANDARD RATE
$89
$100
$122
$75
$97
$110
$128
$160
$79
$97
$125
$161
$92
$132
$143
$171
$86
$104
$125
$82
$153
$207
$186
$282
$100
$189
$71
$97
$136
$204
Special Equipment/Software
Subsistence (Per Diem) – Lodging
Subsistence (Per Diem) – Meals
Misc. Project Related Expenses
Sub-Contracts
KLJ 2023 RATE SHEET
Time and Half for Overtime Included in Hourly Rate
REIMBURSABLE EXPENSES (IF APPLICABLE)
ATV, UTV, Snowmobile Included in Hourly Rate Per Project Basis
Survey Equipment Included in Hourly Rate Actual Cost
CAD and GIS Work Station Included in Hourly Rate $45/Day per
Employee
Postage and Routing Printing Cost Included in Hourly Rate Cost plus 15%
Mileage Included in Hourly Rate Cost plus 15%
Senior Project Manager $277 Project Assistant I
Government Relations Specialist I $125 Project Assistant II
Government Relations Specialist II $129
Contract Administrator $112 Public Engagement/Gov't Relations Mgr
Senior Public Engagment Strategist
Senior Designer $179 2 Person Survey Crew
Associate Project Manager $186 Project Controls Specialist I
Project Manager $225 Project Controls Specialist II
Principal Planner $197 Professional Land Surveyor
Associate Designer $110 Principal Land Surveyor
Designer $128 1 Person Survey Crew
Associate Planner $97 Crew Chief
Planner $140 Senior Crew Chief
Senior Planner $171 Land Surveyor in Training
Engineer $172 ROW Professional
Senior Engineer $229 Senior ROW Professional
Principal Engineer $276 Survey Technician
Engineer in Training I $110 Engineering Technician IV
Engineer in Training II $125 Associate ROW
Associate Engineer $135 ROW Agent
Environmental Planner IV $189 Engineering Technician I
Paleontologist $128 Engineering Technician II
Paleontologist Technician $86 Engineering Technician III
Environmental Planner I $93 GIS Analyst II
Environmental Planner II $100 GIS Analyst III
Environmental Planner III $143 GIS Analyst IV
Archaeologist III $122 CAD Technician III
Archaeologist IV $160 GIS Technician
Environmental Technician $93 GIS Analyst I
2023 KLJ Hourly Rates – Municipal
KLJ STAFF TYPE STANDARD
RATE
KLJ STAFF TYPE
Archaeologist Technician $86 CAD Technician I
Archaeologist II $104 CAD Technician II
KLJ 2023 Rate Sheet
TASK ORDER No. 7 – 15TH STREET NORTH IMPROVEMENTS Page 1 of 3
TASK ORDER No. 7
CITY OF LAKE ELMO, MINNESOTA – KLJ
PROFESSIONAL ENGINEERING SERVICES AGREEMENT
In accordance with ARTICLE 1 of the Master AGREEMENT between the City of Lake Elmo (“CITY”) and
Kadrmas, Lee & Jackson, Inc. (KLJ) (“ENGINEER”), dated February 20, 2018 (“AGREEMENT”), the
ENGINEER agrees to provide Professional Engineering Support Services as follows:
15TH STREET NORTH IMPROVEMENTS
PROJECT OVERVIEW: The CITY requires preliminary design engineering services for improvements
along 15th Street North, extending from Inwood Avenue North to the Oakdale City limits (“Project”).
The Project includes pavement rehabilitation and related drainage improvements for the roadway
segment.
SERVICES TO BE PROVIDED BY ENGINEER: KLJ shall provide the following Professional Engineering
Services:
PRELIMINARY DESIGN SERVICES
1. Project management throughout the course of work for preparation of preliminary design
documents including a monthly PMT meeting, and submittal of a weekly progress memo and
job to date budget form.
2. Project kick‐off meeting with city staff.
3. Work with city staff to develop critical success criteria for the project, obtain project
information and formalize the budget and schedule.
4. Site visit to review existing conditions and perform existing pavement conditions review.
5. Coordinate Gopher State One Call utility locates and perform topographic survey of existing
conditions within project limits for the purposes of preparing design documents.
6. Right of way verification: Review corridor right‐of‐way and easement information available on
GIS. Project work is not anticipated to extend beyond the existing roadway inslope. Right‐of‐
way verification and title work is not included in work scope.
7. Review Geotechnical Evaluation Report findings and recommendations obtained by the CITY.
8. Prepare preliminary design including recommendations on street widths, turn lanes, lane
configuration, and stormwater management.
9. Perform a feasibility review to construct pedestrian facilities along the north side of 15th
Street North through the project limits.
10. Identify right of way and easement needs to construct the proposed infrastructure. Any right
of way or easement needs will require title work verification to be performed in the final
design phase.
11. Identify small utility conflicts related to the proposed preliminary design.
12. Prepare opinion of probable cost based on the preliminary design layout.
TASK ORDER No. 7 – 15TH STREET NORTH IMPROVEMENTS Page 2 of 3
13. Identify permits required to complete the proposed work. The design shall incorporate
measures to meet compliance requirements for all permits necessary.
DELIVERABLES:
1. Exhibits displaying recommended infrastructure.
2. Opinion of Total Probable Project Costs.
3. Design Memorandum summarizing final design assumptions and performance criteria
incorporated into the project design.
4. Identification of easements needed for the construction of the project.
CITIES RESPONSIBILITIES: The City (or its consultants) will provide the following:
Coordination with the public and conduct public meetings.
Presentation(s) to the City Council.
Easement negotiations and acquisition, if needed.
Hire geotechnical firm for geotechnical investigation.
TIMES FOR RENDERING SERVICES: CONSULTANT shall perform its services and provide deliverables in
accordance with the following schedule:
1. August 15, 2023 –Engineering Services Authorized.
2. All Task Order Services shall be substantially completed by September 22, 2023.
CITY’S REPRESENTATIVE AND CONTRACT ADMINISTRATION: The CITY’s representative with respect
to services rendered by ENGINEER under this TASK ORDER shall be the City Engineer. Project
correspondence must be addressed to:
Jack Griffin, P.E., City Engineer
City of Lake Elmo
3880 Laverne Avenue North
Lake Elmo, MN 55042
651.300.4264
Email: Jack.griffin@focusengineeringinc.com
COMPENSATION: Compensation to ENGINEER shall be on an hourly rate basis using the hourly billing
rates provided in the ENGINEER’s Proposal for the work. Invoices shall be submitted once each month
and should be sent to the attention of the City Engineer.
Compensation to ENGINEER for Project Management, Survey and Preliminary Design Services for the
Project shall be on an hourly rate basis in a not to exceed amount of $16,200.00.
Payment for Services shall be in accordance with ARTICLE 3.2 of the Master AGREEMENT.
TASK ORDER No. 7 – 15TH STREET NORTH IMPROVEMENTS Page 3 of 3
ADDITIONAL SERVICES: If authorized by the City, ENGINEER shall furnish or obtain from others
Additional Services which are not considered under this Task Order. Such services shall be compensated
for on an Hourly Rate basis in an amount approved by the City prior to any services being started or as
otherwise mutually agreed. The City is not obligated to compensate ENGINEER for services completed
outside the approved scope of work which are completed prior to ENGINEER submitting a written
request to the City, and receiving written approval of the City.
ATTACHMENTS: This agreement supersedes and replaces all previous understandings, agreements or
contracts, written or verbal, between ENGINEER and City, regarding the Project. The following
documents are attached for reference:
1. ENGINEER’s 2023 Rate Sheet.
APPROVAL AND ACCEPTANCE: Approval and Acceptance of this Task Order, including the
attachment(s) listed above, shall incorporate this document as part of the AGREEMENT. ENGINEER is
authorized to begin performance of services upon receipt of a copy of this Task Order signed by CITY.
The Effective Date of this Task Order is AUGUST 16, 2023.
KLJ CITY OF LAKE ELMO, MINNESOTA
By _________________________________ By _________________________________
(Authorized Principal of the Firm) City Administrator
STANDARD RATE
$89
$100
$122
$75
$97
$110
$128
$160
$79
$97
$125
$161
$92
$132
$143
$171
$86
$104
$125
$82
$153
$207
$186
$282
$100
$189
$71
$97
$136
$204
Special Equipment/Software
Subsistence (Per Diem) – Lodging
Subsistence (Per Diem) – Meals
Misc. Project Related Expenses
Sub-Contracts
KLJ 2023 RATE SHEET
Time and Half for Overtime Included in Hourly Rate
REIMBURSABLE EXPENSES (IF APPLICABLE)
ATV, UTV, Snowmobile Included in Hourly Rate Per Project Basis
Survey Equipment Included in Hourly Rate Actual Cost
CAD and GIS Work Station Included in Hourly Rate $45/Day per
Employee
Postage and Routing Printing Cost Included in Hourly Rate Cost plus 15%
Mileage Included in Hourly Rate Cost plus 15%
Senior Project Manager $277 Project Assistant I
Government Relations Specialist I $125 Project Assistant II
Government Relations Specialist II $129
Contract Administrator $112 Public Engagement/Gov't Relations Mgr
Senior Public Engagment Strategist
Senior Designer $179 2 Person Survey Crew
Associate Project Manager $186 Project Controls Specialist I
Project Manager $225 Project Controls Specialist II
Principal Planner $197 Professional Land Surveyor
Associate Designer $110 Principal Land Surveyor
Designer $128 1 Person Survey Crew
Associate Planner $97 Crew Chief
Planner $140 Senior Crew Chief
Senior Planner $171 Land Surveyor in Training
Engineer $172 ROW Professional
Senior Engineer $229 Senior ROW Professional
Principal Engineer $276 Survey Technician
Engineer in Training I $110 Engineering Technician IV
Engineer in Training II $125 Associate ROW
Associate Engineer $135 ROW Agent
Environmental Planner IV $189 Engineering Technician I
Paleontologist $128 Engineering Technician II
Paleontologist Technician $86 Engineering Technician III
Environmental Planner I $93 GIS Analyst II
Environmental Planner II $100 GIS Analyst III
Environmental Planner III $143 GIS Analyst IV
Archaeologist III $122 CAD Technician III
Archaeologist IV $160 GIS Technician
Environmental Technician $93 GIS Analyst I
2023 KLJ Hourly Rates – Municipal
KLJ STAFF TYPE STANDARD
RATE
KLJ STAFF TYPE
Archaeologist Technician $86 CAD Technician I
Archaeologist II $104 CAD Technician II
KLJ 2023 Rate Sheet
TASK ORDER No. 8 – 30TH STREET NORTH GAP SEGMENT IMPROVEMENTS Page 1 of 3
TASK ORDER No. 8
CITY OF LAKE ELMO, MINNESOTA – KLJ
PROFESSIONAL ENGINEERING SERVICES AGREEMENT
In accordance with ARTICLE 1 of the Master AGREEMENT between the City of Lake Elmo (“CITY”) and
Kadrmas, Lee & Jackson, Inc. (KLJ) (“ENGINEER”), dated February 20, 2018 (“AGREEMENT”), the
ENGINEER agrees to provide Professional Engineering Support Services as follows:
30TH STREET NORTH GAP SEGEMENT IMPROVEMENTS
PROJECT OVERVIEW: The CITY requires preliminary design engineering services for improvements
along 30th Street North to address an unimproved gap segment. The improvements extend from the
eastern edge of Lisbon Avenue North to approximately 475‐feet east of Village Parkway (“Project”).
The Project includes pavement rehabilitation, curb & gutter replacement, shared‐use path resurfacing
and related drainage improvements for the roadway segment, tying into the recent improvements at
the project termini.
SERVICES TO BE PROVIDED BY ENGINEER: KLJ shall provide the following Professional Engineering
Services:
SURVEY
1. Coordinate Gopher State One Call utility locates and perform topographic survey of existing
conditions within project limits for the purposes of preparing design documents.
PRELIMINARY DESIGN SERVICES
1. Project management throughout the course of work for preparation of preliminary design
documents including a monthly PMT meeting, and submittal of a weekly progress memo and
job to date budget form.
2. Project kick‐off meeting with city staff.
3. Work with city staff to develop critical success criteria for the project, obtain project
information and formalize the budget and schedule.
4. Site visit to review existing conditions, perform existing curb review for full or spot
replacement, and perform existing pavement conditions review to define project limits.
5. Right of way verification: Review corridor right‐of‐way and easement information available on
GIS. Project work is not anticipated to extend beyond the existing roadway inslope. Right‐of‐
way verification and title work is not included in work scope.
6. Review Geotechnical Evaluation Report findings and recommendations obtained by the CITY.
7. Prepare preliminary design including recommendations on street widths, turn lanes, lane
configuration, pedestrian improvements, and stormwater management.
TASK ORDER No. 8 – 30TH STREET NORTH GAP SEGMENT IMPROVEMENTS Page 2 of 3
8. Identify right of way and easement needs to construct the proposed infrastructure. Any right
of way or easement needs will require title work verification to be performed in the final
design phase.
9. Identify small utility conflicts related to the proposed preliminary design.
10. Prepare opinion of probable cost based on the preliminary design layout.
11. Identify permits required to complete the proposed work. The design shall incorporate
measures to meet compliance requirements for all permits necessary.
DELIVERABLES:
1. Exhibits displaying recommended infrastructure.
2. Opinion of Total Probable Project Costs.
3. Design Memorandum summarizing final design assumptions and performance criteria
incorporated into the project design.
4. Identification of easements needed for the construction of the project.
CITIES RESPONSIBILITIES: The City (or its consultants) will provide the following:
Coordination with the public and conduct public meetings.
Presentation(s) to the City Council.
Easement negotiations and acquisition, if needed.
Hire geotechnical firm for geotechnical investigation.
TIMES FOR RENDERING SERVICES: CONSULTANT shall perform its services and provide deliverables in
accordance with the following schedule:
1. August 15, 2023 –Engineering Services Authorized.
2. All Task Order Services shall be substantially completed by September 22, 2023.
CITY’S REPRESENTATIVE AND CONTRACT ADMINISTRATION: The CITY’s representative with respect
to services rendered by ENGINEER under this TASK ORDER shall be the City Engineer. Project
correspondence must be addressed to:
Jack Griffin, P.E., City Engineer
City of Lake Elmo
3880 Laverne Avenue North
Lake Elmo, MN 55042
651.300.4264
Email: Jack.griffin@focusengineeringinc.com
COMPENSATION: Compensation to ENGINEER shall be on an hourly rate basis using the hourly billing
rates provided in the ENGINEER’s Proposal for the work. Invoices shall be submitted once each month
and should be sent to the attention of the City Engineer.
TASK ORDER No. 8 – 30TH STREET NORTH GAP SEGMENT IMPROVEMENTS Page 3 of 3
Compensation to ENGINEER for Project Management, Survey and Preliminary Design Services for the
Project shall be on an hourly rate basis in a not to exceed amount of $18,200.00.
Payment for Services shall be in accordance with ARTICLE 3.2 of the Master AGREEMENT.
ADDITIONAL SERVICES: If authorized by the City, ENGINEER shall furnish or obtain from others
Additional Services which are not considered under this Task Order. Such services shall be compensated
for on an Hourly Rate basis in an amount approved by the City prior to any services being started or as
otherwise mutually agreed. The City is not obligated to compensate ENGINEER for services completed
outside the approved scope of work which are completed prior to ENGINEER submitting a written
request to the City, and receiving written approval of the City.
ATTACHMENTS: This agreement supersedes and replaces all previous understandings, agreements or
contracts, written or verbal, between ENGINEER and City, regarding the Project. The following
documents are attached for reference:
1. ENGINEER’s 2023 Rate Sheet.
APPROVAL AND ACCEPTANCE: Approval and Acceptance of this Task Order, including the
attachment(s) listed above, shall incorporate this document as part of the AGREEMENT. ENGINEER is
authorized to begin performance of services upon receipt of a copy of this Task Order signed by CITY.
The Effective Date of this Task Order is AUGUST 16, 2023.
KLJ CITY OF LAKE ELMO, MINNESOTA
By _________________________________ By _________________________________
(Authorized Principal of the Firm) City Administrator
STANDARD RATE
$89
$100
$122
$75
$97
$110
$128
$160
$79
$97
$125
$161
$92
$132
$143
$171
$86
$104
$125
$82
$153
$207
$186
$282
$100
$189
$71
$97
$136
$204
Special Equipment/Software
Subsistence (Per Diem) – Lodging
Subsistence (Per Diem) – Meals
Misc. Project Related Expenses
Sub-Contracts
KLJ 2023 RATE SHEET
Time and Half for Overtime Included in Hourly Rate
REIMBURSABLE EXPENSES (IF APPLICABLE)
ATV, UTV, Snowmobile Included in Hourly Rate Per Project Basis
Survey Equipment Included in Hourly Rate Actual Cost
CAD and GIS Work Station Included in Hourly Rate $45/Day per
Employee
Postage and Routing Printing Cost Included in Hourly Rate Cost plus 15%
Mileage Included in Hourly Rate Cost plus 15%
Senior Project Manager $277 Project Assistant I
Government Relations Specialist I $125 Project Assistant II
Government Relations Specialist II $129
Contract Administrator $112 Public Engagement/Gov't Relations Mgr
Senior Public Engagment Strategist
Senior Designer $179 2 Person Survey Crew
Associate Project Manager $186 Project Controls Specialist I
Project Manager $225 Project Controls Specialist II
Principal Planner $197 Professional Land Surveyor
Associate Designer $110 Principal Land Surveyor
Designer $128 1 Person Survey Crew
Associate Planner $97 Crew Chief
Planner $140 Senior Crew Chief
Senior Planner $171 Land Surveyor in Training
Engineer $172 ROW Professional
Senior Engineer $229 Senior ROW Professional
Principal Engineer $276 Survey Technician
Engineer in Training I $110 Engineering Technician IV
Engineer in Training II $125 Associate ROW
Associate Engineer $135 ROW Agent
Environmental Planner IV $189 Engineering Technician I
Paleontologist $128 Engineering Technician II
Paleontologist Technician $86 Engineering Technician III
Environmental Planner I $93 GIS Analyst II
Environmental Planner II $100 GIS Analyst III
Environmental Planner III $143 GIS Analyst IV
Archaeologist III $122 CAD Technician III
Archaeologist IV $160 GIS Technician
Environmental Technician $93 GIS Analyst I
2023 KLJ Hourly Rates – Municipal
KLJ STAFF TYPE STANDARD
RATE
KLJ STAFF TYPE
Archaeologist Technician $86 CAD Technician I
Archaeologist II $104 CAD Technician II
KLJ 2023 Rate Sheet