HomeMy WebLinkAbout#06 - MPCA Grant Agreement STAFF REPORT
DATE: October 3, 2023
CONSENT
AGENDA ITEM: Approve MPCA Grant Agreement, and Order Preparation of Feasibility Report, and the Preparation of Plans and Specifications for the Stillwater Boulevard (CSAH 14) Trunk Watermain Improvements SUBMITTED BY: Kristina Handt, City Administrator
REVIEWED BY: Jack Griffin, City Engineer Marty Powers, Public Works Director Chad Isakson, Assistant City Engineer
ISSUE BEFORE COUNCIL: Should the City Council approve the Grant Agreement with the MPCA, and order the Preparation of Feasibility Report, and the Preparation of Plans and Specifications for the
Stillwater Boulevard (CSAH 14) Trunk Watermain Improvements?
BACKGROUND: In accordance with the City’s Capital Improvement Plan, the extension of a trunk watermain has been identified for construction in 2024, extending along Stillwater Boulevard (CSAH 14)
from approximately 885 feet east of Jamaca Avenue to approximately 1,530 feet west of Lake Elmo Avenue, and connecting the existing Jamaca Avenue trunk watermain to the watermain network in the Village area (see attached Project Exhibit). The project will construct a critical trunk water transmission line that completes a primary watermain loop within the intermediate pressure zone, and provides a secondary transmission main to ensure a continued
water supply under conditions of a trunk watermain repair/break. The trunk watermain improvement is also needed to meet the growing water supply delivery demands for the newly connected neighborhoods outside of the City growth areas, and was identified as an important water system improvement in the Clean Drinking Water Supply Plan (CDWSP) recently completed for the 3M Settlement Funds. Along the watermain extension, municipal water will be made available to 10 additional existing residential properties, 2 of which have private well advisories. PROPOSAL DETAILS/ANALYSIS: To ready the Project for construction in 2024, staff prepared and
submitted a 3M Settlement Priority 1 Drinking Water Grant application. The grant was recently approved by the 3M Settlement Fund Co-Trustees and the MPCA prepared the Grant Agreement for the Project.
The Grant Agreement provides funding for the majority of the total estimated project costs including
construction of the public watermain improvements, private water service connection costs and City connection/WAC fees for the 2 properties with exiting well advisories, private well abandonment costs for the 2 properties with existing well advisories, and engineering costs to implement the Project. It is
recommended that the installation of private water services be constructed as part of the Project for the remaining 8 existing properties without well advisories, however these costs are not grant eligible.
In order to initiate the improvement, the Council must approve the MPCA Grant Agreement and order the preparation of a Feasibility Report as required by the statutory process for public improvements that are specially assessed. The Feasibility Report will advise on the scope of recommended improvements; provide estimated project costs; identify easement and right-of-way, permits and other requirements of other local agencies needed to implement the improvements; recommend whether the improvements should be best made as proposed or in connection with some other improvement; and advise if the improvements are necessary, cost effective, and feasible. The report will also provide a proposed preliminary assessment roll for each of the benefitting properties based upon the City’s Special Assessment Policy for Local Improvements.
In addition to the authorization of the Feasibility Report, the Council is asked to authorize the preparation of Plans and Specifications. This will allow the design work to commence immediately, including the acquisition of the topographic survey and field reviews prior to winter ground conditions.
FISCAL IMPACT: The Project will be substantially funded through the MPCA Grant in the amount of $3,140,000. Additional Project funding may include special assessments and water enterprise funding. The
Grant is set to expire on December 31, 2025.
RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, the Grant Agreement with the MPCA for the Stillwater Boulevard (CSAH 14) Trunk Watermain Improvements. If removed from the Consent Agenda, the recommended motion for this action is as follows: “Move to approve the Grant Agreement with the MPCA for the
Stillwater Boulevard (CSAH 14) Trunk Watermain Improvements.” Staff is also recommending that the City Council approve, as part of the Consent Agenda, a Resolution Ordering the preparation of a Feasibility Report and ordering the preparation of Plans and Specifications for the Stillwater Boulevard (CSAH 14) Trunk Watermain Improvements. If removed from the Consent
Agenda, the recommended motion for this action is as follows “Move to approve Resolution No. 2023-097, Ordering preparation of a Feasibility Report and Preparation of Plans and Specifications for the
Stillwater Boulevard (CSAH 14) Trunk Watermain Improvements.”
Staff is further recommending that the City Council award, as part of the Consent Agenda, a Professional Engineering Design and Construction Support Services Contract for the Stillwater Boulevard (CSAH 14) Trunk Watermain Improvements. Staff is recommending SEH, Inc. be awarded the contract in accordance with the attached Task Order No. 25. If removed from the Consent Agenda, the recommended motion for this action is as follows:
“Move to approve a Professional Engineering Design and Construction Support Services Contract to SEH, Inc in the not to exceed amount of $267,400 for the Stillwater Boulevard (CSAH 14) Trunk Watermain Improvements.” ATTACHMENTS: 1. Project Location Map/Exhibit. 2. MPCA Grant Agreement PRO20230004.
3. Resolution Ordering the Preparation of a Feasibility Report and the Preparation of Plans and Specifications for the Stillwater Boulevard (CSAH 14) Trunk Watermain Improvements. 4. SEH, Inc. Task Order #25 – Stillwater Boulevard (CSAH 14) Trunk Watermain Improvements.
>>>>>>>>||||||||||||||||||Feet06001200EXISTING STORM SEWEREX. WATER MAINLEGENDEX. HYDRANT|>>EXISTING STORM STRUCTURECITY OF LAKE ELMO,STILLWATER BOULEVARD CONNECTING WATERMAINPROJECT NO. 2023.113 JUNE, 2023FIGURE NO. 1PROPOSED IMPROVEMENTSMINNESOTADIRECTIONAL DRILL 14"HDPE DR11 WATERMAINALONG NORTH SIDE OFSTILLWATER BLVD(CSAH 14)12" DIP WATERMAIN(BY OTHERS)DIRECTIONAL DRILL 14"HDPE DR11 WATERMAINALONG SOUTH SIDE OFSTILLWATER BLVD(CSAH 14)DIRECTIONAL DRILL 14"HDPE DR11 WATERMAINALONG NORTH SIDE OFSTILLWATER LANECONNECT TO EX. 12" DIPWATERMAIN AT 9524STILLWATER BLVD NREMOVE APPROX. 1400LF OF EX. 4" DIPWATERMAIN ANDREPLACE WITH NEW 12"DIP WATERMAIN -REPLACE HYDRANTS /VALVES AS NECESSARYCONNECT TO EX. 12" DIPWATERMAIN AT 9434STILLWATER BLVD NPROPOSED WATER MAINPROPOSED HYDRANT|PROPOSED VALVEEX. VALVEPROPOSED WATER SERVICECONNECT TO EX 4" DIP WATERMAINEAST OF SERVICE CONNECTION TO9186 JAMACA CT N.EX. 4" DIP WATERMAIN WEST OF NEWCONNECTION TO REMAIN IN PLACE.
Grant Agreement
State of Minnesota
Doc Type: Contract/Grant
SWIFT Contract Number:
Agency Interest ID: 90810
Activity ID: PRO20230004
This Grant Agreement is between the state of Minnesota, acting through its Commissioner of the
Minnesota Pollution Control Agency, 520 Lafayette Road North, St. Paul, MN 55155‐4194 (“MPCA” or
“State”), and City of Lake Elmo, a Minnesota municipal corporation, 3880 Laverne Avenue North, Lake
Elmo, MN 55042 ("Grantee" or "Contractor" or “City”).
Recitals
1. Under Minn. Stat. § 116.03, subd. 2, the State is empowered to enter into this grant.
2. The City is authorized to enter into this grant under Minn. Stat. § 412.211.
3. The State and City are in need of the City of Lake Elmo Stillwater Boulevard Trunk Watermain
project, as part of the Conceptual Drinking Water Supply Plan (Conceptual Plan), to address
Perfluoroalkyl Substances (PFAS) impacts to drinking water supplies in the East Metro area.
4. Grantee will comply with required grants management policies and procedures set forth through
Minn. Stat. § 16B.97, subd. 4(a)(1).
5. The Grantee represents that it is duly qualified and agrees to perform all services described in this
grant agreement to the satisfaction of the State. Pursuant to Minn. Stat. § 16B.98, subd. 1, the
Grantee agrees to minimize administrative costs as a condition of this grant.
Grant Agreement
1. Term of Grant Agreement
1.1 Effective date: September 20, 2023, Per Minn. Stat.§16B.98, Subd. 5, the Grantee must not
begin work until this grant contract is fully executed and the State's Authorized
Representative has notified the Grantee that work may commence. Per Minn.Stat.§16B.98
Subd. 7, no payments will be made to the Grantee until this grant contract is fully executed.
1.2 Expiration date: December 31, 2025, or until all obligations have been satisfactorily fulfilled,
whichever occurs first.
1.3 Survival of terms. The following clauses survive the expiration or cancellation of this grant
agreement: Indemnification; State Audits; Government Data Practices and Intellectual
Property; Publicity and Endorsement; Governing Law, Jurisdiction, and Venue; and Data
Disclosure.
2. Grantee’s Duties
The grantee will plan, design and construct the trunk water transmission line along Stillwater
Boulevard in the City of Lake Elmo (extending 885 feet east of Jamaca Ave to approximately 1,530
feet west of Lake Elmo Avenue). This project also includes the connection of two homes with well
advisories along the watermain extension to municipal water. The neighboring eight homes may be
eligible for municipal water connection in the future if new sampling data results in a well advisory.
3. Time
The Grantee must comply with all the time requirements described in this grant agreement. In the
performance of this grant agreement, time is of the essence.
4. Consideration and Payment
4.1 Consideration. The State will pay for all services performed by the Grantee under this grant
agreement as follows:
(a) Compensation. The MPCA will reimburse the Grantee according to approved invoices
relating to the duties listed in Clause 2. The MPCA will review the expense documentation
submitted by the Grantee for the costs and will reimburse the Grantee for reasonable and
necessary expenditures, as determined by the MPCA. Any project components and costs
inconsistent with the Conceptual Plan will be required to have supporting documentation
for consideration of eligibility. Items that are determined ineligible will not be reimbursed.
The Grantee must submit a request in writing to the MPCA for approval prior to using the
contingency funds.
(b) Travel expenses. Reimbursement for travel and subsistence expenses actually and
necessarily incurred by the Grantee as a result of this grant agreement will be provided to
meet the duties listed in Clause 2; provided that the Grantee will be reimbursed for travel
and subsistence expenses in the same manner and in no greater amount than provided in
the current "Commissioner’s Plan” promulgated by the Commissioner of Minnesota
Management and Budget (MMB). The Grantee will not be reimbursed for travel and
subsistence expenses incurred outside Minnesota unless it has received the State’s prior
written approval for out of state travel. Minnesota will be considered the home state for
determining whether travel is out of state.
(c) Total obligation. The total obligation of the State for all compensation and
reimbursements to the Grantee under this grant agreement will not exceed $3,140,000.00
(Three Million One Hundred Forty Thousand Dollars and Zero Cents).
4.2 Payment
(a) Invoices. The State will promptly pay the Grantee after the Grantee presents an itemized
invoice for the services actually performed and the State’s Authorized Representative
accepts the invoiced services. Invoices must be submitted timely and according to the
following schedule: monthly or at least quarterly.
Invoices must be emailed to mpca.ap@state.mn.us, and contain the following
information:
Name of Grantee
Grantee project manager
Invoice number
Invoice date
MPCA project manager
SWIFT Contract No.
Invoicing period (actual working period)
Prevailing Wage documentation (if applicable)
If there is a problem with submitting an invoice electronically, please contact the Accounts
Payable Unit at 651‐757‐2491.
The Grantee shall submit an invoice for the final payment upon submittal of the final
progress and financial report within 30 (thirty) days of the original or amended end date
of this grant agreement. The State reserves the right to review invoices submitted after 30
(thirty) days and make a determination as to payment.
(b) Unexpended Funds. The Grantee must promptly return to the State any unexpended
funds that have not been accounted for annually in a financial report to the State due at
grant closeout.
4.3 Contracting and Bidding Requirements
Per Minn. Stat. §471.345, grantees that are municipalities as defined in Subd. 1 must follow
the law.
(a) For projects that include construction work and have a total project cost of $25,000 or
more, prevailing wage rules apply per Minn. Stat. §§177.41 through 177.44. These rules
require that the wages of laborers and workers should be comparable to wages paid for
similar work in the community as a whole.
(b) The grantee must not contract with vendors who are suspended or debarred in MN:
https://mn.gov/admin/osp/government/suspended‐debarred/
4.4 Prevailing Wage (if applicable)
Pursuant to Minnesota Statutes 177.41 to 177.44 and corresponding Minnesota Rules
5200.1000 to 5200.1120, this contract is subject to the prevailing wages as established by the
Minnesota Department of Labor and Industry. Specifically, all contractors and subcontractors
must pay all laborers and mechanics the established prevailing wages for work performed
under the contract. Failure to comply with the aforementioned may result in civil or criminal
penalties. Rates are listed in Attachment A.
In compliance with Minn. Stat. § 177.43, subd. 3 and §177.44, subd. 5, the wages of laborers,
workers, and the mechanics on projects financed in whole or part by State Funds should be
comparable to wages paid for similar work in the community as a whole. Project includes
erection, construction, remodeling, or repairing of a public building or other public work
financed in whole or part by State funds.
Any work on real property which uses the skill sets of any trades covered by Labor Code and
Class under prevailing wages is construction and requires prevailing wages. See
http://www.doli.state.mn.us/LS/PrevWage.asp for a list of affected trades.
The Contractor shall pay prevailing wages to its employees when conducting construction
activities under this agreement.
Applicability. In accordance with Minn. Stat. § 177.43, subd. 7. This does not apply to an
agreement or work under an agreement, under which:
A. the estimated total cost of completing the project is less than $2,500 and only one
trade or occupation is required to complete the work; or
B. the estimated total cost of completing the project is less than $25,000 and more than
one trade or occupation is required to complete it.
Choose from Commercial, Highway/Heavy, or Residential Wage Rates:
The prevailing wage rate requirements are attached as Attachment A.
Prevailing Wage Payroll Information:
In accordance with Minn. Stat. § 177.30, subd. 4, and § 177.43, subd. 3, the Contractor and
Subcontractor shall furnish to the Contracting Authority and the Project Owner:
• All payrolls, of all workers on the project, a certified payroll report via e‐mail as
attachments, a State of Minnesota Prevailing Wage Payroll Report as a Microsoft Excel
file and Statement of Compliance Form as a PDF file to the appropriate e‐mail
addresses: prevailingwage.pca@state.mn.us and Megan.Holthaus@state.mn.us.
• The Subject line on the Contractor’s or Subcontractor’s e‐mail must give their firm’s
name and the Contract or Purchase Order Number.
• These completed forms must be furnished not more than 14 days after the end of each
pay period.
• The State of Minnesota Prevailing Wage Payroll Report and Statement of Compliance
Form are available on the MMD website at
http://www.mmd.admin.state.mn.us/mn02000.htm. Submit the completed and signed
State of Minnesota Prevailing Wage Payroll Report as a Microsoft Excel file and the
Statement of Compliance Form as a PDF file, no other payroll forms will be accepted to
meet this requirement.
The prevailing wage payroll information forms that are submitted shall be maintained by the
contracting agency for a minimum of three years after final payment has been made on the
project. All of the data provided on the Prevailing Wage Payroll Information Form will be
public data, which is available to anyone upon request.
Refer vendor questions regarding the Prevailing Wage Laws to the Department of Labor and
Industry at 651‐284‐5091 or visit the website for Labor Standards Section, Prevailing Wage
http://www.doli.state.mn.us/LS/PrevWage.asp.
All construction work needs an IC‐134 form submitted by the Contractor before payment can
be made. The Contractor can find a copy of the IC‐134 online at the Minnesota Department of
Revenue website at https://www.revenue.state.mn.us/sites/default/files/2019‐01/ic134.pdf.
4.5 Reporting Requirements
The Grantee shall submit to the State quarterly status reports, based on the effective date of
this agreement.
5. Conditions of Payment
All services provided by the Grantee under this grant agreement must be performed to the State’s
satisfaction, as determined at the sole discretion of the State’s Authorized Representative/MPCA’s
Project Manager and in accordance with all applicable federal, state, and local laws, ordinances,
rules, and regulations. The Grantee will not receive payment for work found by the State to be
unsatisfactory or performed in violation of federal, state, or local law.
6. Authorized Representative
The State's Authorized Representative/Project Manager is Elizabeth Kaufenberg, 520 Lafayette
Road, St. Paul, MN 55155, 651‐757‐2481, elizabeth.kaufenberg@state.mn.us, or their successor, and
has the authority to monitor the Grantee’s performance and to accept the services provided under
this agreement. If the services are satisfactory, the MPCA’s Project Manager will certify acceptance
of each invoice submitted for payment.
The State's Project Manager is Megan Holthaus, 520 Lafayette Road, St. Paul, MN 55155, 651‐757‐
2843, Megan.Holthaus@state.mn.us, or their successor.
The Grantee’s Authorized Representative is Kristina Handt, City Administrator, 3880 Laverne
Avenue North, Lake Elmo, MN 55042, 651‐747‐3905, khandt@lakeelmo.org, or their successor. If
the Grantee’s Authorized Representative changes at any time during this grant agreement, the
Grantee must immediately notify the State.
7. Assignment, Amendments, Change Orders, Waiver, and Grant Agreement Complete
7.1 Assignment. The Grantee shall neither assign nor transfer any rights or obligations under this
grant agreement without the prior written consent of the State, approved by the same parties
who executed and approved this grant agreement, or their successors in office.
7.2 Amendments. Any amendments to this grant agreement must be in writing and will not be
effective until it has been executed and approved by the same parties who executed and
approved the original grant agreement, or their successors in office.
7.3 Change orders. If the State's Project Manager or the Grantee’s Authorized Representative
identifies a change needed in the workplan and/or budget, either party may initiate a Change
Order using the Change Order Form provided by the MPCA. Change Orders may not delay or
jeopardize the success of the Project, alter the overall scope of the Project, increase or
decrease the overall amount of the Contract/Agreement, or cause an extension of the term of
this Agreement. Major changes require an Amendment rather than a Change Order.
The Change Order Form must be approved and signed by the State's Project Manager and the
Grantee’s Authorized Representative in advance of doing the work. Documented changes
will then become an integral and enforceable part of the Agreement. The MPCA has the sole
discretion on the determination of whether a requested change is a Change Order or an
Amendment. The state reserves the right to refuse any Change Order requests.
7.4 Waiver. If the State fails to enforce any provision of this grant agreement, that failure does
not waive the provision or the State’s right to enforce it.
7.5 Grant agreement complete. This grant agreement contains all negotiations and agreements
between the State and the Grantee. No other understanding regarding this grant agreement,
whether written or oral, may be used to bind either party.
8. Indemnification
The Grantee must indemnify, save, and hold the State, its agents, and employees harmless from any
claims or causes of action, including attorney’s fees incurred by the State, arising from the
performance of this grant agreement by the Grantee or the Grantee’s agents or employees. This
clause will not be construed to bar any legal remedies the Grantee may have for the State's failure
to fulfill its obligations under this grant agreement.
9. State Audits
Under Minn. Stat. § 16B.98, subd.8, the Grantee’s books, records, documents, and accounting
procedures and practices of the Grantee or other party relevant to this grant agreement or
transaction are subject to examination by the State and/or the State Auditor or Legislative Auditor,
as appropriate, for a minimum of six years from the end of this grant agreement, receipt and
approval of all final reports, or the required period of time to satisfy all state and program retention
requirements, whichever is later.
10. Government Data Practices and Intellectual Property
10.1 Government data practices. The Grantee and State must comply with the Minnesota
Government Data Practices Act, Minn. Stat. Ch. 13, as it applies to all data provided by the
State under this grant agreement, and as it applies to all data created, collected, received,
stored, used, maintained, or disseminated by the Grantee under this grant agreement. The
civil remedies of Minn. Stat. § 13.08 apply to the release of the data referred to in this clause
by either the Grantee or the State. If the Grantee receives a request to release the data
referred to in this Clause, the Grantee must immediately notify the State. The State will give
the Grantee instructions concerning the release of the data to the requesting party before the
data is released. The Grantee’s response to the request shall comply with applicable law.
10.2 Intellectual property rights
(a) Intellectual property rights. The State owns all rights, title and interest in all of the
intellectual property rights, including copyrights, patents, trade secrets, trademarks, and
service marks in the Works and Documents created and paid for under this grant
agreement. Works means all inventions, improvements, discoveries (whether or not
patentable), databases, computer programs, reports, notes, studies, photographs,
negatives, designs, drawings specifications, materials, tapes, and disks conceived, reduced
to practice, created or originated by the Grantee, its employees, agents, and
subcontractors, either individually or jointly with others in the performance of this grant
agreement. Works includes “Documents.” Documents are the originals of any databases,
computer programs, reports, notes studies, photographs, negatives, designs, drawings,
specifications, materials, tapes, disks, or other materials, whether in tangible or electronic
forms, prepared by the Grantee, its employees, agents, or subcontractors, in the
performance of this grant agreement. The Documents shall be the exclusive property of
the State and all such Documents must be immediately returned to the State by the
Grantee, at the Grantee’s expense, upon the written request of the State, or upon
completion, termination, or cancellation of this grant agreement. To the extent possible,
those Works eligible for copyright protection under the United States’ Copyright Act will
be deemed to be “works made for hire.” The Grantee assigns all right, title, and interest it
may have in the Works and the Documents to the State. The Grantee must, at the request
of the State, execute all papers and perform all other acts necessary to transfer or record
the State’s ownership interest in the Works and Documents.
(b) Obligations.
(1) Notification. Whenever any invention, improvement, or discovery (whether or not
patentable) is made or conceived for the first time or actually or constructively
reduced to practice by the Grantee, including its employees and subcontractors, in the
performance of this grant agreement, the Grantee shall immediately give the State’s
Authorized Representative written notice thereof, and must promptly furnish the
Authorized Representative with complete information and/or disclosure therein.
(2) Representation. The Grantee must perform all acts, and take all steps necessary to
ensure that all intellectual property rights in the Works and Documents are the sole
property of the State, and that neither Grantee nor its employees, agents, or
subcontractors retain any interest in and to the Works and Documents. The Grantee
represents and warrants that the Works and Documents do not and will not infringe
upon any intellectual property rights of other persons or entities. Notwithstanding
Clause Liability, the Grantee shall indemnify, defend, to the extent permitted by the
Attorney General, and hold harmless the State, at the Grantee’s expense, from any
action or claim brought against the State to the extent that it is based on a claim that
all or part of the Works or Documents infringe upon the intellectual property rights of
others. The Grantee will be responsible for payment of any and all such claims,
demands, obligations, liabilities, costs, and damages, including, but not limited to,
attorney fees. If such a claim or action arises or in Grantee’s or the State’s opinion is
likely to arise, the Grantee must, at the State’s discretion, either procure for the State
the right or license to use the intellectual property rights at issue or replace or modify
the allegedly infringing Works or Documents as necessary and appropriate to obviate
the infringement claim. This remedy of the State will be in addition to and not
exclusive of other remedies provided by law.
(3) License. The State hereby grants a limited, no‐fee, noncommercial license to the
Grantee to enable the Grantee’s employees engaged in research and scholarly
pursuits to make, have made, reproduce, modify, distribute, perform, and otherwise
use the Works, including Documents, for research activities or to publish in scholarly
or professional journals, provided that any existing or future intellectual property
rights in the Works or Documents (including patents, licenses, trade or service marks,
trade secrets, or copyrights) are not prejudiced or infringed upon, that the Minnesota
Data Practices Act is complied with, and that individual rights to privacy are not
violated. The Grantee shall indemnify and hold harmless the State for any claim or
action based on the Grantee’s use of the Works or Documents under the provisions of
Clause 10.2(b)(2). Said license is subject to the State’s publicity and acknowledgement
requirements set forth in this grant agreement. The Grantee may reproduce and
retain a copy of the Documents for research and academic use. The Grantee is
responsible for security of the Grantee’s copy of the Documents. A copy of any
articles, materials or documents produced by the Grantee’s employees, in any form,
using or derived from the subject matter of this license, shall be promptly delivered
without cost to the State.
11. Workers’ Compensation
The Grantee certifies that it is in compliance with Minn. Stat. § 176.181, subd. 2, pertaining to
workers’ compensation insurance coverage. The Grantee’s employees and agents will not be
considered State employees. Any claims that may arise under the Minnesota Workers’
Compensation Act on behalf of these employees and any claims made by any third party as a
consequence of any act or omission on the part of these employees are in no way the State’s
obligation or responsibility.
12. Governing Law, Jurisdiction, and Venue
Minnesota law, without regard to its choice‐of‐law provisions, governs this grant agreement. Venue
for all legal proceedings out of this grant agreement, or its breach, must be in the appropriate state
or federal court with competent jurisdiction in Ramsey County, Minnesota.
13. Termination
13.1 Termination by the State. The State or Grantee may immediately terminate this grant
agreement with or without cause, upon 30‐days’ written notice to the other party. Upon
termination, the Grantee will be entitled to payment, determined on a pro rata basis, for
services satisfactorily performed.
13.2 Termination for cause. The State may immediately terminate this grant agreement if the State
finds that there has been a failure to comply with the provisions of this grant agreement, that
reasonable progress has not been made or that the purposes for which the funds were
granted have not been or will not be fulfilled. The State may take action to protect the
interests of the state of Minnesota, including the refusal to disburse additional funds and
requiring the return of all or part of the funds already disbursed.
13.3 Termination for insufficient funding. The State may immediately terminate this grant
agreement if:
(a) It does not obtain funding from the Minnesota Legislature.
(b) Or, if funding cannot be continued at a level sufficient to allow for the payment of the
services covered here. Termination must be by written or fax notice to the Grantee. The
State is not obligated to pay for any services that are provided after notice and effective
date of termination. However, the Grantee will be entitled to payment, determined on a
pro rata basis, for services satisfactorily performed to the extent that funds are available.
The State will not be assessed any penalty if the agreement is terminated because of the
decision of the Minnesota Legislature, or other funding source, not to appropriate funds.
The State must provide the Grantee notice of the lack of funding within a reasonable time
of the State’s receiving that notice.
14. Data Disclosure
Under Minn. Stat. § 270C.65, subd. 3, and other applicable law, the Grantee consents to disclosure
of its social security number, federal employer tax identification number, and/or Minnesota tax
identification number, already provided to the State, to federal and state tax agencies and state
personnel involved in the payment of state obligations. These identification numbers may be used in
the enforcement of federal and state tax laws which could result in action requiring the Grantee to
file state tax returns and pay delinquent state tax liabilities, if any.
15. Payment to subcontractors (if applicable)
As required by Minn. Stat. § 16A.1245, the prime contractor must pay all subcontractors, less any
retainage, within 10 calendar days of the prime contractor's receipt of payment from the State for
undisputed services provided by the subcontractor(s) and must pay interest at the rate of one and
one‐half percent per month or any part of a month to the subcontractor(s) on any undisputed
amount not paid on time to the subcontractor(s).
Signatures
CITY OF LAKE ELMO
WASHINGTON COUNTY STATE OF MINNESOTA
RESOLUTION NO. 2023-097
A RESOLUTION ORDERING THE PREPARATION OF A FEASIBILITY REPORT
AND PREPARATION OF PLANS AND SPECIFICATIONS FOR THE STILLWATER BOULEVARD (CSAH 14) TRUNK WATERMAIN IMPROVEMENTS
WHEREAS, the City is extending trunk watermain along Stillwater Boulevard (CSAH 14) to construct a secondary transmission main from the Jamaca Avenue trunk watermain to the Village area, the (PROJECT), to ensure a continued water supply under conditions of trunk watermain repairs/breaks; to meet the water supply delivery demands for the newly connected neighborhoods outside of the City growth areas; and to support the delivery of future water supply sources; and WHEREAS, the PROJECT is programmed in the Capiral Improvement Plan (CIP) for
construction in 2024; and WHEREAS, the PROJECT will install public watermain that abuts and makes connection to
City water available to several properties along the proposed improvement route; and WHEREAS, it is proposed to assess the benefiting properties for all or a portion of the cost of
the improvement, pursuant to the City’s Special Assessment Policy and Minnesota Statues Chapter 429.
NOW, THEREFORE, BE IT RESOLVED, 1. That the proposed improvement, called Stillwater Boulevard (CSAH 14) Trunk Watermain
Improvements, be referred to the City Engineer and FOCUS Engineering, to complete a feasibility report in accordance with Minnesota Statues Chapter 429 for the proposed improvements, and to report to the council with all convenient speed advising the council in a preliminary way as to
whether the proposed improvement is necessary, cost-effective, and feasible; whether it should be best made as proposed or in connection with some other improvement; the estimated cost of the improvement as recommended; and a description of the methodology used to calculate individual
assessments for affected parcels. 2. The City Engineer, together with SEH, Inc. are hereby designated as the project engineer and are directed to prepare Plans and Specifications for the making of such improvement. ADOPTED BY THE LAKE ELMO CITY COUNCIL ON THE THIRD DAY OF OCTOBER, 2023. CITY OF LAKE ELMO
By: __________________________ (Seal) Charles Cadenhead ATTEST: Mayor ________________________________ Julie Johnson City Clerk
TASK ORDER No. 25 – STILLWATER BOULEVARD (CSAH14) TRUNK WATERMAIN EXTENSION Page 1 of 4
TASK ORDER No. 25
CITY OF LAKE ELMO, MINNESOTA – SHORT ELLIOTT HENDRICKSON, INC.
PROFESSIONAL CONSULTING SERVICES AGREEMENT
In accordance with ARTICLE 1 of the Master AGREEMENT between the City of Lake Elmo (“CITY”) and
Short Elliott Hendrickson, Inc. (SEH) (“CONSULTANT”), dated August 13, 2014 (“AGREEMENT”), the
ENGINEER agrees to provide Professional Consulting Support Services as follows:
STILLWATER BOULEVARD (CASH14) TRUNK WATERMAIN EXTENSION
PROJECT OVERVIEW: The City of Lake Elmo requires professional design and construction phase
engineering services for a trunk watermain extension along Stillwater Boulevard (CSAH 14)
connecting the Village area to the Jamaca Avenue Trunk Watermain. The transmission line is required
to meet the water supply delivery demands for the newly connected neighborhoods outside of the
City growth areas (Parkview Estates; Cardinal Ridge; Cardinal View; Whistling Valley; Torre Pines; and
Stonegate); to support the delivery of future water supply sources, including potentially St. Paul
Regional Water Services; and to ensure a continued water supply under conditions of trunk
watermain repairs/breaks.
The services outlined in this task order are intended to assist the City to complete the preliminary and
final design, including the preparation of plans and specifications and contract documents, bidding
phase services, and construction phase support services as detailed in this Task Order.
SERVICES TO BE PROVIDED BY ENGINEER: SEH, Inc. shall provide the following Professional
Engineering Services:
1. Project Management throughout the course of the work for preparation of design documents
and construction phase services including submittal of a weekly progress memo and job to
date budget form.
2. Preparation of Plans and Specifications, and Contract Documents.
Project kick‐off meeting with city staff.
Work with city staff to develop critical success criteria for the project, obtain project
information and formalize the budget and schedule.
Confirm trunk water main pipe size and material using updated water system modeling
with current growth projections and water demands.
Identify small utility conflicts related to the proposed design to the City’s Project
Manager. The City will coordinate necessary relocation efforts with the respective
small utility company as needed.
Prepare preliminary pipe route layout and review with City to confirm location of trunk
watermain along the corridor.
TASK ORDER No. 25 – STILLWATER BOULEVARD (CSAH14) TRUNK WATERMAIN EXTENSION Page 2 of 4
Review the geotechnical evaluation services report as obtained by the City to evaluate
the subsurface conditions along the project corridor, and to inform the design
parameters and recommendations for watermain layout and pavement requirements.
Provide 60% plans and specifications to City for review, including design criteria and
assumptions memorandum.
Provide 90% plans and specifications to City for review, including updated design
criteria and assumptions memorandum.
Revise the final plans and specifications based on city comments.
Prepare opinion of probable cost based on final plans.
Identify permits required to complete the proposed work. The design shall incorporate
measures to meet compliance requirements for all permits necessary.
Prepare and submit any necessary permit applications for approval.
DELIVERABLES:
Preliminary Design memorandum summarizing the recommendations for watermain
installation and type of street improvements.
Plans in electronic format (PDF) and hard copy format (2 full size and 4 half size).
Specifications in electronic format and hard copy format (3 copies for the city and the
appropriate number for contracts and required permits).
Opinion of Total Probable Project Costs with total project cost breakdowns provided
by for application of the City assessment policy.
Design Memorandum summarizing final design assumptions and performance criteria
incorporated into the project design.
Identification of easements needed for the construction of the project. Easements
shall be placed on the final plans.
Completed project permit applications ready for signature by city representative.
3. Bidding Phase Services for each bid package.
Submit “Advertisement for Bids” to Stillwater Gazette and Quest CDN.
Distribute plans and specifications as requested by bidders.
Maintain planholder list.
Respond to bidders’ questions and issue addenda as necessary.
Tabulate bid in electronic format.
Prepare contract award recommendation letter.
4. Construction Phase Services.
Assist the City to prepare for the preconstruction meeting and attend meeting.
Provide technical and construction administration support throughout the project as
requested by the City’s Project Manager (assume 80 hours from the design engineer of
record).
Coordinate and provide construction staking.
TASK ORDER No. 25 – STILLWATER BOULEVARD (CSAH14) TRUNK WATERMAIN EXTENSION Page 3 of 4
Provide review of shop drawings and make recommendations regarding acceptability
of submittals.
Prepare and submit record drawings in electronic format (AutoCAD and PDF) and hard
copy format (1 full size and 2 half‐size) based upon staking information and
information provided by the contractor and city.
Prepare and submit the utility as‐built survey data as GIS Shape Files, including
relevant asset information (such as date of install, material type, size, structure type).
5. City Responsibilities. The city (or its consultants) will provide the following:
Provide geotechnical investigation services Report upon completion.
Coordination with the public and conduct public meetings.
Presentation(s) to the City Council.
Easement negotiations and acquisition, if needed.
Review of 60% and 90% plans and specifications.
Coordination with small utility companies if conflicts are identified.
Construction Administration of the Contract.
Construction Observation.
Retain Material and Compaction testing services based on recommend scope.
One year warranty inspections.
Preparation of Feasibility Report, if any, including assessment calculations, assessment
role and conduct Final Assessment Hearing.
TIMES FOR RENDERING SERVICES: CONSULTANT shall perform its services and provide deliverables
in accordance with the following schedule:
1. October 3, 2023 Council approves selection of Engineering Firm.
2. February 6, 2024 Council approves Plans and Specifications; Authorizes Ad for Bids.
3. March 7, 2024 Receive contractor bids.
4. March 19, 2024 Council accepts bids and awards contract.
5. September 30, 2024 Substantial Completion (watermain operational, ready for connection).
CITY’S REPRESENTATIVE AND CONTRACT ADMINISTRATION: The CITY’s representative with respect
to services rendered by CONSULTANT under this TASK ORDER shall be the City Engineer. Project
correspondence must be addressed to:
Chad Isakson, P.E., City Engineer
City of Lake Elmo
3880 Laverne Avenue North
Lake Elmo, MN 55042
651.300.4283
Email: Chad.Isakson@FOCUSEngineeringinc.com
TASK ORDER No. 25 – STILLWATER BOULEVARD (CSAH14) TRUNK WATERMAIN EXTENSION Page 4 of 4
COMPENSATION: Compensation to CONSUTLANT shall be based on the hourly billing rates for each
staff as assigned and provided in the CONSUTLANT’S Proposal and Fee Estimate for the work. Invoices
shall be submitted once each month and should be sent to the attention of the City Engineer.
Compensation to CONSUTLANT for Project Management, the Preparation of Plans and Specifications,
Contract Documents, and Bidding Phase Services shall be on an hourly rate basis in a not to exceed
amount of $209,600.00.
Compensation to the CONSUTLANT for the Construction Phase Services shall be on an hourly rate
basis in a not to exceed amount of $57,800.00.
ADDITIONAL SERVICES: If authorized by the City, CONSUTLANT shall furnish or obtain from others
Additional Services which are not considered under this Task Order. Such services shall be
compensated for on an Hourly Rate basis in an amount approved by the City prior to any services
being started or as otherwise mutually agreed. The City is not obligated to compensate CONSUTLANT
for services completed outside the approved scope of work which are completed prior to
CONSUTLANT submitting a written request to the City, and receiving written approval of the City.
ATTACHMENTS: The following documents are attached for reference:
1. ENGINEER’s Proposal and Fee Estimate dated September 28, 2023.
APPROVAL AND ACCEPTANCE: Approval and Acceptance of this Task Order, including the
attachment(s) listed above, shall incorporate this document as part of the AGREEMENT.
CONSUTLANT is authorized to begin performance of services upon receipt of a copy of this Task Order
signed by CITY.
The Effective Date of this Task Order is October 3, 2023.
SHORT ELLIOTT HENDRICKSON, INC. CITY OF LAKE ELMO, MINNESOTA
By _________________________________ By _______________________________ __
(Authorized Principal of the Firm) City Administrator
City of Lake Elmo - Proposal for Stillwater Boulevard (CSAH 14) Trunk Watermain Extension
SHORT ELLIOTT HENDRICKSON: PROJECT WORK PLAN
PROJECT NAME: Stillwater Boulevard (CSAH 14) Trunk Water Main Extension
SEH PROJECT NUMBER: LAKMO 174795
CLIENT: CITY OF LAKE ELMO
CLIENT CONTACT: Chad Isakson
PROJECT MANAGER: Brian Hare
TOTAL HOURS 1515 254 327 386 63 23 70 165 37 24 90 29 19 28
HOURLY BILLING RATE $225.00 $150.00 $126.00 $171.00 $175.00 $135.00 $225.00 $205.00 $180.00 $122.00 $218.00 $102.00 $102.00
TOTAL LABOR COST $250,210 $17,231 $267,400 $57,150.00 $49,050.00 $48,636.00 $10,773.00 $4,025.00 $9,450.00 $37,125.00 $7,585.00 $4,320.00 $10,980.00 $6,322.00 $1,938.00 $2,856.00
% OF TOTAL COST
Task DESCRIPTION OF TASK Brian Hare
Andrew
Olsen
Grad
Engineer Jeff Thene Theo Brown Greg Tvedt 2 Man Crew
Luke
Thompson
Josh
Palmateer
Noah
Odalen Emily Jennings
Anjie
Hanson
Melissa
Knutson
Sr. Project
Manager
Project
Engineer Lead Tech RLS
Survey Crew
Chief
Sr. Geotch
Engineer
Sr. Traffic
Engineer
Water
Resources
Engineer
Sr. Water
Resources
Engineer Admin.Accounting
1 PROJECT MANAGEMENT $28,425.00 $28,400.00
Project mgmt throughout, weekly progress memo and budget form (2hr/wk for 28wks)$12,600.00 $12,600.00 56
Internal Kick-off and design progress meetings (bi-weekly meetings for 28 weeks)$12,225.00 $12,225.00 30 14 14 1 2 2
QA/QC $3,600.00 $3,600.00 16
2 PREPARATION OF PLANS AND SPECIFICATIONS $166,615.00 $10,942.00 $177,600.00
Project Kick-off meeting $969.00 $969.00 1 1 1 1 1
Develop critical success criteria, obtain project info, budget and schedule $3,306.00 $3,306.00 2 28
Site visit with City to walk project area $1,092.00 $133.00 $1,225.00 2 2 2
Coordination with private utilities, private utility meeting $942.00 $942.00 4 2
Topographic Survey $23,425.00 $4,559.00 $27,984.00 4 101
Right of way verification: Review title work and right of way and all property impacts $2,800.00 $6,000.00 $8,800.00 16
Identify Right of Way and Easement Impacts for Project Area $1,329.00 $1,329.00 1 4 4
Identify and Relay Small Utility Conflicts to City's Project Manager $1,254.00 $1,254.00 2 2 4
Provide Recommendation on Amount and Location of Soil Borings $600.00 $600.00 4
Geotechnical Review and Drilling Coordination, and Recommendations $6,970.00 $6,970.00 34
Proposed Water Main Improvements $6,174.00 $6,174.00 2 18 24
Proposed Street and Storm Design Recommendations $6,174.00 $6,174.00 2 18 24
Alignments and Profiles $750.00 $750.00 2 2
Finalize Watermain Design $1,554.00 $1,554.00 2 4 4
Finalize Street Design $1,896.00 $1,896.00 2 4 4 2
Prepare Construction Documents
Title sheet $504.00 $504.00 4
Construction Phasing, Signing, Location Map $504.00 $504.00 4
Construction Notes $504.00 $504.00 4
Statement of Estimated Quantities $1,008.00 $1,008.00 8
General Notes, Tabulations, Schedules $504.00 $504.00 4
Construction Details $504.00 $504.00 4
Typical Sections $777.00 $777.00 1 2 2
Proposed Sections $777.00 $777.00 1 2 2
Alignment Tabulation and Survey Control $1,104.00 $1,104.00 4 4
Utility Coordination $2,208.00 $2,208.00 8 8
Existing Conditions and Removals $3,312.00 $3,312.00 12 12
Erosion Control and Restoration $3,748.00 $3,748.00 12 12 2
Storm Water Pollution Prevention Plan (SWPPP)$1,744.00 $1,744.00 8
Watermain Plan and Profiles $14,490.00 $14,490.00 2 60 40
Storm Sewer and BMP Design/Modeling/Plan Sheets $11,530.00 $11,530.00 2 16 60 8
Street and Storm Water Plan and Profiles $11,490.00 $11,490.00 2 40 40
Expenses
TotalLabor Total Task Total
9/28/2023 8:12 AM X:\KO\L\LAKMO\COMMON\Proposals\LAKMO P174795 - Stillwater Blvd (CSAH 14) Water Main Extension\THB_Stillwater Blvd Trunk Water Main Scope and fee 2023
City of Lake Elmo - Proposal for Stillwater Boulevard (CSAH 14) Trunk Watermain Extension
Cross Sections $6,406.00 $6,406.00 2 20 20 2
Traffic Control Plan $7,674.00 $7,674.00 2 4 24 20
Signing and Striping $2,568.00 $2,568.00 8 8 2
Constructability Review & Coordination $10,440.00 $10,440.00 16 40
Project Specifications $6,220.00 $6,220.00 8 16 2 2 12
60% Plans, Specifications, and Opinion of Probable Cost $2,808.00 $2,808.00 8 8
90% Plans, Specifications, and Opinion of Probable Cost $2,808.00 $2,808.00 8 8
Final Plans, Specifications, and Opinion of Probable Cost $2,808.00 $2,808.00 8 8
Preliminary Design Recommendations Memo $1,800.00 $1,800.00 8
60% Design Recommendations Memo $900.00 $900.00 4
90% Design Recommendations Memo $900.00 $900.00 4
Final Design Recommendations Memo $900.00 $900.00 4
$6,440.00 $250.00 $6,690.00 4 8 30 4
3 BIDDING SERVICES $3,618.00 $3,600.00
Submit ad for bids to Stillwater Gazette and Quest CDN $429.00 $429.00 1 2
Distribute plans and specs as requested to bidders $429.00 $429.00 1 2
Maintain planholders list $102.00 $102.00 1
Respond to bidders questions and issue addenda as necessary $1,554.00 $1,554.00 2 4 4
Tabulate bids in electronic format $552.00 $552.00 2 1
Prepare contract award reccomendation letter $552.00 $552.00 2 1
4 CONSTRUCTION ADMINISTRATION & STAKING SERVICES $51,552.00 $6,289.00 $57,800.00
Attend preconstruction meeting $792.00 $250.00 $1,042.00 2 2
JTD Invoices, Weekly Updates (2hr/wk for 20 weeks)$9,000.00 $9,000.00 40
Technical and construction admin support $11,040.00 $11,040.00 40 40
Provide review of shop drawings and make recommendations regarding submittals $2,760.00 $2,760.00 10 10
Coordinate and provide construction staking $21,000.00 $4,879.00 $25,879.00 3 45 64
Record drawings based on staking info and info from contractor and city $3,120.00 $200.00 $3,320.00 4 20
Utility as-built survey data as GIS shape files $3,840.00 $960.00 $4,800.00 4 24- -
Total:$267,400.00
PROJECT WORK PLAN ASSUMPTIONS:
1 Cost of title searches included for 22 parcels.
2 City will be responsible for easement negotiations and acquisition, if needed.
3 It is assumed that during field survey ample boundary irons are available to verify County GIS data.
4 It is assumed that the City will provide any plats along corridor to allow RLS to verify County GIS data.
5 No water modeling is included in this proposal. Any additional water main modeling sizing questions can be confirmed under separate SEH contract.
6 Assumes that a signed Traffic Control Plan will be required for project area. Additionally assumes CSAH 14 will be a westbound shoulder closure.
7 Assumes Traffic Control Plan for Stillwater Lane will include work zone map and phasing showing MMUTCD Field Manual Layouts that apply.
8 Traffic Control Plan does not include detailed layouts for showing traffic control devices customized to project location.
9 Assumes full reconstruction of Stillwater Lane.
10 It is assumed that coordination/submittals related to project funding will be handled by City staff.
Prepare and submit permit applications for approval (MDH, Washington Co., VBWD Erosion
Control/Sediment, VBWD Stormwater Management Permit)
9/28/2023 8:12 AM X:\KO\L\LAKMO\COMMON\Proposals\LAKMO P174795 - Stillwater Blvd (CSAH 14) Water Main Extension\THB_Stillwater Blvd Trunk Water Main Scope and fee 2023