HomeMy WebLinkAbout#06 - Washington County CIP City Comments STAFF REPORT
DATE: October 19, 2023
CONSENT
AGENDA ITEM: Approve City Comments on the Washington County DRAFT 2024-2028 Capital Improvement Plan (CIP)
SUBMITTED BY: Jack Griffin, City Engineer
REVIEWED BY: Kristina Handt, City Administrator Marty Powers, Public Works Director Sophia Jensen, City Planner
Chad Isakson, Assistant City Engineer
ISSUE BEFORE COUNCIL: Should the City Council approve the City comments to be submitted to
Washington County regarding the County’s DRAFT 2024-2028 Capital Improvement Plan? BACKGROUND: On October 3rd, City staff received notice from Washington County that the Draft
2024-2028 Capital Improvement Plan (CIP) was available for review and that comments must be received by November 3, 2023 for consideration when developing the final CIP.
As part of the annual budget process, Washington County prepares a five-year Capital Improvement Plan (CIP), which includes the county's tentative plans for roads, bridges, parks, land, trails, transit, and public facilities. The first year of this plan is included in the county's proposed 2024 budget. The “out-years” of 2025-2028 reflect projected needs and estimated costs, which may change based on future priorities and funding opportunities. Projects that were budgeted in prior years, and are not yet complete, are not reflected in the draft 2024-2028 CIP; funding for the completion of those projects has been set aside, and therefore aren’t reflected in future years’ CIP documents. A full copy of the draft CIP document is available online at the county website.
The attached packet highlights the substantial transportation roadway related projects included within the City of Lake Elmo over the next five years. Parks and Public Facility projects are generally not included in this review, with the exception of comments regarding the Central Greenway Regional Trail. It should also be noted that the County completes intersection control projects and pavement preservation projects each year but the specific work related to these improvements are not specifically identified within the CIP
document. The County is budgeting and average of $620,000 per year for one intersection control project, and has budgeted $34.1M over 5 years for various pavement maintenance and preservation projects. PROPOSAL DETAILS/ANALYSIS: Staff has reviewed the County’s Draft 2024-2028 CIP and has the following comment for council consideration:
• RB-2674 2025: CSAH 17 & TH 36 Intersection: The CSAH 17 and TH36 Intersection improvements remains a top priority Project for the City of Lake Elmo to address the safety
improvements needed along the TH 36 corridor, while maintaining safe and efficient access for Lake Elmo residents to TH 36. The City therefore continues to support the planning and construction of this project and emphasizes the need to maintain the proposed construction schedule and to maximize outside funding assistance in order to provide a financially viable project for the local communities.
• RB-2645 2026-2028: CSAH 13 Phase 3, from CSAH 6 to CSAH 14. Lake Elmo continues to support and encourage the County to initiate preliminary engineering and planning efforts along this
corridor to better identify the future improvements that will be needed in conjunction with the
development of the City owned property along Ideal Avenue and Stillwater Boulevard. The City, however, believes these efforts will need to be completed much sooner than the County’s planned schedule of 2026 to 2028. The City is requesting these planning efforts be initiated as soon as 2024 to
promote an efficiently planned infrastructure system to be coordinated with the pending development.
• RB-2201 Intersection Control Projects. Under this category description, the County lists a traffic signal at CSAH 15 and Hudson Boulevard to be implemented at some future date. The City supports the importance to have funding earmarked and available for a new signal at this intersection, to be
implemented as the area develops. The City is currently working with a developer that will include improvements in 2024 or 2025 to realign the Hudson Boulevard intersection with Manning Avenue/2nd Street N.
• RB-2652 2025: 58th Street Extension/CR 15 South Segment. Although this project resides outside of Lake Elmo, the Project includes a connection to be constructed between the new interchange at TH36/CSAH 15 extending through Oak Park Heights to Stillwater Boulevard. The City supports the roadway extension on the condition that the Sanctuary neighborhood access to the new interchange is
not degraded.
• New Planning and Design Projects. The City acknowledges and appreciates the addition of 4 new Planning and Preliminary Design Projects in the County CIP. The City recognizes the importance of addressing each of these project corridors and is supportive of each of these future planning initiatives.
In particular, the City considers the preliminary design work for Projects RB-2702 and RB-2802 to be a high priority that should be initiated as soon as 2026. Adequate pedestrian facilities along each of these corridors should be considered important design elements for each Project.
• RB-2701 2027-2028 Planning/Design: CSAH 19 and CSAH 10 Intersection.
• RB-2702 2027 Planning/Design: CSAH 14, from Klondike Avenue to 39th Street.
• RB-2801 2028 Planning/Design: CSAH 15, 30th Street to CSAH 14.
• RB-2802 2028 Planning/Design: CSAH 17, CSAH 14 to 43rd Street.
• RB-2684 2025: CSAH 15, from CSAH 10 to 30th Street North. Improvements to CSAH 15, south of 30th Street remain on the lower end of the City’s priorities to the extent that these improvements impact Lake Elmo.
• RB-2204 Pavement Preservation & Rehab. Under this category description, the County lists a potential pavement rehabilitation Project to be completed in the next few years along CSAH 13 (Inwood Ave N) from CSAH 10 to CSAH 6. The City has not comments at this time.
• PARK-9005 Central Greenway Regional Trail Feasibility Study. The City supports the continued work efforts to plan and construct the Central Greenway Regional Trail corridor through Lake Elmo,
including the proposed Feasibility Study to determine best design for crossing the railroad north of Lake Elmo Park Reserve. FISCAL IMPACT: No Fiscal Impacts at this time. However, County improvement projects completed within the City of Lake Elmo often contain a cost participation by the City.
OPTIONS: 1) The City Council can approve the City comments to be submitted to Washington County regarding the County’s 2024-2028 Capital Improvement Plan.
2) The City Council can approve the City comments, as amended, to be submitted to Washington
County regarding the County’s 2024-2028 Capital Improvement Plan.
RECOMMENDATION: Staff is recommending that the City Council approve the City comments to be
submitted to Washington County regarding the County’s 2024-2028 Capital Improvement Plan. The recommended motion for the action is as follows:
“Move to approve City comments to be submitted to Washington County regarding the County’s 2024-
2028 Capital Improvement Plan with comments to be submitted on or before November 3, 2023.”
ATTACHMENTS: 1. County CIP Location Map.
2. Summary packet of the Washington County Draft 2024-2028 Capital Improvement Plan.
3. Draft City Comment Letter.
36
10th
60th
5th
HudsonKeats Lake Elmo50th
15th Inwood34th
20th
27th
53rd
55th
Jane
Lake Jane
Jamaca57th
59th
Hill
47th
7th
31st
51st
43rd
39th Demontreville45th
38th
ManningStillwater
24th26th
42nd
Island58th9th
30th
32ndKimbro
21st
Jade6thIvoryHill
t
o
p
IsleOls
o
n
L
a
k
e
8thJulep
12th
Jewel
44th
56th
Iris22nd
37th
36th
35th LaverneJuniperAnnikaJasmineJamley LegionLily
Klondike16th
Upper 33Rd
ImperialLinden3rdKirkwood 33rd
Deer PondHytrail
IrvingHidden Bay4thJerome14thJune28th VillageTapestryJasper
Eagle Point
Jonquil
Wildflower
LaytonPrivateKelvinIronwoodHighlandsJaneroLe
e
w
a
r
d
Cimarron10th StreetKindr
e
d
JamesIrishPrairievie
wJack Pine49th
JayLower 31st
Marquess
IrvinLilacMonarchLower 8th LisbonBirch Bark40thLavender
KraftLampertBlazingstarWhistling Valley
Junco Little Bluestem
11thLady Slipper5t
h
S
t
r
e
e
t
Windbreak
Sunfish Lake Park InboundIvywoodInnsdale3rd Street Marquess TrailLang
l
y
JunoLan
s
i
n
g
JulianneUpper 30th
6th
S
t
r
e
e
t
Lisbon AvenueIrwinSunflower
41st
WB I9
4
T
o
I
n
w
o
o
d
A
v
e
N
Upper 7t
h
Queen
Upper 9th 57th StreetUpper 42Nd
27
t
h
S
t
r
e
e
t
15th Stree
t
Cherrywood
WB I94 To Keats
A
v
e
N
44th Street
41st Street
Jas
m
i
n
e
A
v
e
n
u
e
59th Street
HummingbirdJero
m
e
A
v
e
n
u
e
Keats Ave N To
W
B
I
9
4
Manning Ave N To W
B
I
9
4
Hill Trail
30th Street33rd Street24t
h
S
t
r
e
e
t
20th Street58th StreetLegion Lane
Lark
s
p
u
r
Demontreville Trail
HummingbordAccess21st
Laverne57th Street32nd ManningIrish35th
34th LilyLilac
55th
Jamaca
35th
Laverne56th
Stillwater36
Lake ElmoLanglyLaytonLilac33rd Lily10th StreetMan
n
i
n
g
6th StreetIsle21st
9th
57th
36th
Kirkwood
53rd
Linde
n
Whistling ValleyManning
50th
5th
33rd
Highlands
59th
6th Street
Innsda
le
Ir
o
nw
o
o
d
Linden
Legion Lane
LindenPrivate
Julep28th VillageLilac
IvyInnsdaleLower 8th
31st
57th
Lisbon
9th
39thKeats55th56th36
IsleJulepIrvin55th
Manning32nd
Laverne37thKelv
in
ManningLegion9th
Ivy
34th
LaytonLindenJade5thHudson
36th
39th
DOWNSLAKE
LAKE ELMOREGIONALPARK RESERVE
LAKE ELMO
LAKE JANE
SUNFISH LAKE
OLSONLAKE
LAKE DEMONTREVILLE
CLEARLAKE
HORSESHOELAKE
ROSELAKE
REIDPARK
VFWPARK
LIONS PARK
TANA RIDGEPARK
City of Woodbury
STONEGATEPARK
KRAMERLAKE
GOOSELAKEARMSTRONGLAKE
RIDGEPARK
KEATS AVE NEAGLE POINTLAKE
TABLYNPARK
HEIGHTSPARK
LAKE JANEHILLS PARK
PEBBLEPARK
City of Oakdale
West LakelandTownship
Baytown Township
City ofOak ParkHeights
City of GrantCity ofPine Springs
DEMONTREVILLEWILDLIFE PARK
DEMONTREVILLEPARK
KLEISPARK CARRIAGESTATIONPARK
SUNFISH LAKEPARK
City ofOak ParkHeights
StillwaterTownship
HOMESTEDPARK
7
HERITAGEPARK
VERONICAPOND
GOETSCHEL'SPOND
City ofAfton
TablynPark
Eagle PointCreek Estates
Lake ElmoHeights
Torre Pines
Farms ofLake Elmo
Parkview Estates
WildflowersShores
HuppertAdd
BeautCrest Estates FriedrichHghts
Kenridge Add
Prairie RidgeOffice Park
Eagle PointBusiness Park
Stonegate
Hammes CountryVista
Whistling Valley
MidlandMeadows
DavidNelson Est
TheHomestead
TartanMeadows
The Forest
Schwartz-Martinco Add
PackardPark
EdenPark
HeritageFarm
LonesomePine Add
DownsLake Est
MyronEllman
Elmo View
Cty AudPlat No. 8
Lake Elmo Park
Brookman Add
Sunfish Ponds
Hamlet OnSunfish Lake
ParkMeadows
Tapestry AtCharlottes' Grove
Berschen's Shores
DawcinAcres
LakeJaneHighlands
TealPass Est
Fox FireEstates
Meyer'sPineridgeKrausesAdd
Springborn'sGreen Acres
Arabian Hills
JudithMaryManor
Lake Elmo Vista
Rolling Hills Est
Prairie Hamlet
HiddenMeadowsOf Lake Elmo
Jesse'sHideaway
DiscoverCrossing
Arvold'sAcres
St. Croix'sSanctuary
TamarackFarm Est
CarriageStation
TanaRidgeJohn M DayFarm Add
The Fields ofSt. Croix2nd Add
The Fieldsof St. Croix
BluestemAt The Fieldsof St. Croix
BurrwoodEstBergmannAdd
DemontrevilleHighlands Add
Lane's DemontrevilleCountry ClubDemontrevilleHighlands Add
Olson Lake Add
Oace AcresAdd
LakeJaneHills
Lake JaneManor No. 1
ThreeLakesFarm Add
Bordners Garner
Farmettes
Royal Golf Club
Southwind
Hunters Crossing
HammesEstates
Savona
Boulder Ponds
Inwood
Lakewood Crossing2nd Addition
Easton Village
Wildflower
Cimarron
Legacy At Northstar
Village Preserve
ST. CROIX SANCTUARY PARK
EDENPARK
PILOTPARK
HAMMESPARK
GOOSE LAKEPARK
F
Map Date: November 2020010.5 Miles Created By: Planning Department
2024 Capital Improvement Plan
Washington County, Minnesota
PROJECTS BY CATEGORY
2024 2028thru
Total20242025202620272028CategoryProject #
Road & Bridge
RB-2201 3,070,000590,000 620,000 620,000 620,000 620,000Intersection Control Projects
RB-2203 1,000,000200,000 200,000 200,000 200,000 200,000Miscellaneous Safety & Traffic Capacity Projects
RB-2204 34,100,0007,050,000 6,300,000 6,350,000 8,050,000 6,350,000Pavement Preservation & Rehab
RB-2216 1,905,000205,000 350,000 450,000 450,000 450,000Structures & Roadway Stabilization
RB-2401 550,000550,000North Shop Salt Shed
RB-2402 600,000600,000North Shop Fuel Vault
RB-2403 500,000500,000CSAH 96 Guardrail Improvements
RB-2580 500,000200,000 300,000CSAH 18 Trail - La Lake to Woodlane
RB-2582 3,690,000830,000 2,860,000Gateway Trail Extension - Scandia
RB-2609 11,975,0001,175,000 10,800,000CSAH 32 - CSAH 33 (Everton Ave) to US TH 61
RB-2611 5,500,0005,500,000CSAH 33 - CSAH 32 to CSAH 2
RB-2629 800,000700,000 100,000CSAH 21- I-94 to 40th Street North
RB-2639 7,400,0007,400,000CSAH 5 - Sycamore Street to CSAH 96
RB-2641 150,000150,000CSAH 3 - CSAH 7 to CSAH 4
RB-2645 1,700,000600,000 500,000 600,000CSAH 13 - CSAH 6 to CSAH 14
RB-2650 950,000400,000 550,000CSAH 29 - TH 36 to CSAH 12
RB-2651 6,750,0001,350,000 1,350,000 1,350,000 1,350,000 1,350,000Construction Engineering, Inspection and Survey
RB-2652 11,000,0001,600,000 9,400,00058th Street Extension/County Highway 15 South Seg
RB-2658 450,000450,000CSAH 19 - CSAH 22 to Dale Road
RB-2663 7,500,0007,500,000CSAH 12 East Avenue - Hallam Avenue to CSAH 9
RB-2667 4,300,000500,000 200,000 3,600,000CSAH 19 & 80th Street Intersection
RB-2668 14,450,000150,000 800,000 13,500,000TH 120 - I-694 to CSAH 12
RB-2669 4,000,0004,000,000CSAH 2 Rehabilitation
RB-2672 10,400,000700,000 700,000 9,000,000CSAH 13 - CSAH 20 to Hargis Parkway
RB-2674 37,800,0001,000,000 36,800,000CSAH 17 at TH 36 Intersection
RB-2675 3,100,000400,000 200,000 2,500,000CR 74 - CR 38 to Geneva Avenue
RB-2677 2,000,0002,000,000CSAH 6 Jurisdictional Transfer
RB-2679 375,800375,800CSAH 12 Trail Project
RB-2682 1,900,000500,000 800,000 600,000CR 50 - TH 61 to CSAH 15
RB-2683 2,400,000200,000 100,000 2,100,000CSAH 11 Improvement Project
RB-2684 3,200,00050,000 3,150,000CSAH 15 - CSAH 10 to 30th Street
RB-2685 39,600,0004,000,000 3,000,000 32,600,000CR 19A - 100th Street Realignment
RB-2686 50,00050,000CSAH 20 & Pioneer Drive Study
RB-2687 120,000120,000CSAH 19 - US TH 61 to Dale Road Study
RB-2688 130,000130,000Radio Drive Pedestrian Management Study
RB-2690 11,201,000401,000 700,000 700,000 600,000 8,800,000CSAH 16 - Interlachen to TH 95
RB-2691 5,850,000350,000 400,000 100,000 5,000,000CSAH 20 - CSAH 22 to Military
RB-2692 450,000450,000CSAH 12 - Kimbro to CSAH 15
RB-2693 6,400,000400,000 500,000 500,000 5,000,000CSAH 96 Turnback Corridor
RB-2694 4,700,000500,000 200,000 4,000,000CSAH 18 - Settler's Ridge Intersection
RB-2695 1,300,000200,000 100,000 1,000,000CSAH 5 Sidewalk - Pine Tree Trail to Owens Street
RB-2696 400,000400,000CSAH 16-Interlachen to Settlers Ridge Parkway
RB-2697 900,000900,000CSAH 18 @ TH 95 Roundabout
RB-2701 600,000400,000 200,000CSAH 19 @ CSAH 10 Intersection
RB-2702 300,000300,000CSAH 14 - Klondike Avenue to 39th Street
RB-2703 500,000500,000CSAH 22 @ TH 95 Roundabout
RB-2801 400,000400,000CSAH 15 - 30th Street to CSAH 14
74
Total20242025202620272028CategoryProject #
RB-2802 600,000600,000CSAH 17 - CSAH 14 to 43rd Street
RB-2803 350,000150,000 200,000CSAH 14 Trail - TH 120 to Granada Avenue
RB-2804 100,000100,000CSAH 16 and Eagle Creek Lane
RB-2805 1,400,0001,400,000TH 61 at CSAH 8
RRA-2297-11 60,033,50047,870,200 12,163,300Gold Line Bus Rapid Transit (BRT)
RRA-2297-15 800,000800,000Newport Outlot A Pond Improvements
320,200,30088,217,000 86,683,300 71,260,000 38,970,000 35,070,000Road & Bridge Total
GRAND TOTAL 320,200,30088,217,000 86,683,300 71,260,000 38,970,000 35,070,000
75
2024 Capital Improvement Plan
Washington County, Minnesota Contact PWD
2024 2028thru Department Capital Road & Bridge Project
Description
The project scope includes an annual program for intersection control upgrades determined to be needed, but not incorporated, as part of a larger
roadway improvement project.
Projects under this program would typically be individually identified and programmed through the County's Intersection Control Ranking System
(ICRS).
The project scheduled for 2024 includes Americans with Disabilities Act (ADA) improvements at the intersection of County State Aid Highway
(CSAH) 16 (Valley Creek Road) and Queens Drive. Future projects may include improvements to CSAH 14 (34th Street North) at Hemmingway
Avenue North, County Road 50 (202nd Street North) at Trunk Highway 61, CSAH 15 (Manning Avenue) at Hudson Boulevard.
Project #RB-2201
Justification
High-level intersection controls (roundabouts and traffic signals) may be constructed at county highway intersections meeting criteria set forth in
the County Intersection Control Ranking System.
The county proactively plans for the installation of intersection controls to improve the safety and efficiency of traffic flow on the County Highway
System. The annual Intersection Control Ranking System (CRS) determines the priority of these installations.
The number of projects programmed varies depending on actual budget funding, the availability of matching funds, unforeseen development, or
intersection safety problems.
Budget Impact/Other
The typical traffic signal costs $1,500 per year to operate and maintain. This cost to the public is off-set by the increased traffic flow efficiency and
enhanced safety.
Useful Life 5+ yearsProject Name Intersection Control Projects Category Road & Bridge
Type Improvement
Location Various Roads District #Multiple
Total20242025202620272028Expenditures
100,00020,000 20,000 20,000 20,000 20,000Planning / Design
2,970,000570,000 600,000 600,000 600,000 600,000Construction
590,000 620,000 620,000 620,000 620,000 3,070,000Total
Total20242025202620272028Funding Sources
850,00010,000 210,000 210,000 210,000 210,000Local Contributions
2,220,000580,000 410,000 410,000 410,000 410,000State Aid
590,000 620,000 620,000 620,000 620,000 3,070,000Total
80
2024 Capital Improvement Plan
Washington County, Minnesota Contact PWD
2024 2028thru Department Capital Road & Bridge Project
Description
The project scope includes an annual program comprised of pavement preservation projects including:
1) seal coating
2) crack filling
3) pavement milling
4) overlays
5) hot and cold-in-place recycling
6) pavement reclamation
7) full-depth reclamation
8) minor subgrade corrections
9) right-of-way
2024 may include:
1) CSAH 5 (Stillwater Boulevard) - TH 36 to Croixwood
2) CSAH 13 (Inwood Avenue North) - CSAH 10 to CSAH 6
3) CSAH 2 (West Broadway Avenue) - county line to 19th Street
4) CSAH 13 (Hadley Avenue North/50th Street North) - 55th Street to Olson Lake Trail
5) CSAH 29 (Hilton Trail) - TH 36 to CSAH 12
6) CSAH 16 (Valley Creek Drive) trail pavement improvement
7) CSAH 19 (Keats Avenue South) - Central Greenway Trail
Project #RB-2204
Justification
These projects are scheduled to interrupt the normal deterioration of highways to extend the pavement life. Pavement condition is
measured/calculated annually and reported as the system-wide Pavement Condition Index (PCI) that assigns a value to each roadway segment on a
scale of 1-100, with higher numbers equating to better pavement condition. Public Works Performance Measures set two goals: 1) system-wide
average PCI = 72 or greater, and 2) no roadway PCI should be lower than 40.
Budget Impact/Other
Projects completed under the Pavement Preservation Program reduce operation and maintenance costs.
Useful Life 5+ yearsProject Name Pavement Preservation & Rehab Category Road & Bridge
Type Improvement
Location Various Roads District #Multiple
Total20242025202620272028Expenditures
33,800,0007,050,000 6,000,000 6,350,000 8,050,000 6,350,000
300,000300,000
Construction
Planning/Design
7,050,000 6,300,000 6,350,000 8,050,000 6,350,000 34,100,000Total
Total20242025202620272028Funding Sources
600,000600,000Planned Use of Fund Balance
3,150,000600,000 50,000 1,750,000 750,000State Aid
15,575,0001,900,000 3,425,000 3,650,000 3,650,000 2,950,000TAA - Preservation
1,475,0001,400,000 75,000TAA - Safety & Trails
13,300,0002,550,000 2,750,000 2,700,000 2,650,000 2,650,000Wheelage Tax
7,050,000 6,300,000 6,350,000 8,050,000 6,350,000 34,100,000Total
82
2024 Capital Improvement Plan
Washington County, Minnesota Contact PWD
2024 2028thru Department Capital Road & Bridge Project
Description
The project scope includes the following improvements to County State Aid Highway (CSAH) 13 (Ideal Avenue) in Oakdale and Lake Elmo:
1) safety improvements including widening for shoulders
2) pavement improvement
3) turn lane and intersection improvements
4) pedestrian and non-motorized upgrades
5) drainage improvements
Project #RB-2645
Justification
Increased traffic and development drive the need for roadway upgrades, including widening of the road and the railroad crossing. This area is also
a nexus for regional surface water drainage, hence the design needs to work toward accommodating and improving regional surface water
management in this area.
Budget Impact/Other
The project will increase operation and maintenance costs associated with additional pavement, drainage, and sidewalk infrastructure.
Useful Life 5+ yearsProject Name CSAH 13 - CSAH 6 to CSAH 14 Category Road & Bridge
Type Construction
Location Various
Total Project Cost:$1,700,000
District #Multiple
Total20242025202620272028Expenditures
1,100,000600,000 500,000Planning / Design
600,000600,000Right-of-Way
600,000 500,000 600,000 1,700,000Total
Total20242025202620272028Funding Sources
400,000400,000County Transportation Sales
Tax (Road & Bridge)
400,000100,000 100,000 200,000Local Contributions
900,000500,000 400,000State Aid
600,000 500,000 600,000 1,700,000Total
94
2024 Capital Improvement Plan
Washington County, Minnesota Contact PWD
2024 2028thru Department Capital Road & Bridge Project
Description
The project scope includes the following improvements to County State Aid Highway (CSAH) 15 (Manning Avenue):
1) new CSAH 15 highway segment south of Trunk Highway (TH) 36 which ties into the proposed interchange at Manning and TH 36
2) all necessary drainage and surface water management improvements
3) new regional trail and pedestrian ramp facilities
4) new access locations for proposed developments
This project addresses many regional traffic and safety goals. From a county standpoint, this proposed south segment of CSAH 15 connects
Manning Avenue to Stillwater Boulevard, which currently requires access to TH 36. From a Minnesota Department of Transportation's (MnDOT)
standpoint, this project reduces local trips on TH 36, where traffic volumes have increased due to the St. Croix River Crossing project. This project
also aids in development potential south of TH 36.
Project #RB-2652
Justification
Coordination with MnDOT, local partners, and developers strengthened the county's goal to complete this gap on the CSAH 15 corridor.
Budget Impact/Other
This project will increase operation and maintenance costs because of the added infrastructure.
Useful Life 5+ yearsProject Name 58th Street Extension/County Highway 15 South Seg Category Road & Bridge
Type Construction
Location Various
Total Project Cost:$12,820,300
District #3
Total20242025202620272028Expenditures
600,000600,000Planning / Design
9,400,0009,400,000Construction
1,000,0001,000,000Right-of-Way
1,600,000 9,400,000 11,000,000Total
Prior
1,820,300
Total
Total20242025202620272028Funding Sources
10,450,0001,550,000 8,900,000County Transportation Sales
Tax (Road & Bridge)
550,00050,000 500,000Local Contributions
1,600,000 9,400,000 11,000,000Total
Prior
1,820,300
Total
97
2024 Capital Improvement Plan
Washington County, Minnesota Contact PWD
2024 2028thru Department Capital Road & Bridge Project
Description
The project scope includes improvements to County State Aid Highway (CSAH) 17 at the intersection with Trunk Highway (TH) 36 in the cities of
Lake Elmo and Grant.
The work is expected to include:
1) a grade separated crossing of TH 36
2) ramps to provide access between CSAH 17 and TH 36
3) retaining walls
4) storm water treatment facilities
5) pedestrian facilities
6) intersection controls for frontage roads
7) frontage road extension on south side
Project #RB-2674
Justification
TH 36 users currently experience congestion (capacity constraints) during both A.M. and P.M. peak hours resulting from the existing signal at
CSAH 17 (Lake Elmo Avenue). This congestion results in an unacceptable level-of-service during peak hours which is expected to worsen as
traffic volumes are forecasted to increase. Due to the extended cycle lengths, CSAH 17 has long wait times before being served by the signal. The
existing, closely-spaced frontage road intersection on the north of TH 36 consistently queues traffic through the intersection.
This CSAH 17 intersection has a crash and severity rate that is significantly higher than the Minnesota Department of Transportation (MnDOT)
statewide system average for similar signalized intersections.
To date, $10 million in federal grants, and $20 million in state grants have been secured for the construction of this project.
Budget Impact/Other
This project will increase operation and maintenance costs because of the added infrastructure.
It is expected that local agencies, the State of Minnesota, and federal aid will provide funding for this project. If this funding is not obtained, this
project will be postponed until adequate funding is received.
Useful Life 5+ yearsProject Name CSAH 17 at TH 36 Intersection Category Road & Bridge
Type Construction
Location Lake Elmo/Grant
Total Project Cost:$41,834,300
District #Multiple
Total20242025202620272028Expenditures
36,800,00036,800,000Construction
1,000,0001,000,000Right-of-Way
1,000,000 36,800,000 37,800,000Total
Prior
4,034,300
Total
Total20242025202620272028Funding Sources
10,000,00010,000,000Federal Grants
3,500,000500,000 3,000,000Local Contributions
4,300,000500,000 3,800,000State Aid
20,000,00020,000,000State Grants
1,000,000 36,800,000 37,800,000Total
Prior
4,034,300
Total
104
2024 Capital Improvement Plan
Washington County, Minnesota Contact PWD
2024 2028thru Department Capital Road & Bridge Project
Description
The project scope includes the following improvements on County State Aid Highway (CSAH) 15 (Manning Avenue) between CSAH 10 (10th
Street North) and 30th Street.
1) addition of center left turn lanes at key locations
2) pavement rehabilitation
3) storm water treatment improvements
Project #RB-2684
Justification
CSAH 15 is the backbone of the county's transportation system, thus, is an important north-south route connecting Interstate 94 to Lake Elmo,
Stillwater, and beyond. These highway improvements are necessary to ensure the ongoing safe and efficient operation of this highway segment.
Budget Impact/Other
The project will increase operation and maintenance costs because of the added pavement widths and storm water infrastructure.
Useful Life 5+ yearsProject Name CSAH 15 - CSAH 10 to 30th Street Category Road & Bridge
Type Construction
Location Various
Total Project Cost:$3,450,000
District #3
Total20242025202620272028Expenditures
3,150,0003,150,000Construction
50,00050,000Right-of-Way
50,000 3,150,000 3,200,000Total
Prior
250,000
Total
Total20242025202620272028Funding Sources
275,00025,000 250,000Local Contributions
2,925,00025,000 2,900,000State Aid
50,000 3,150,000 3,200,000Total
Prior
250,000
Total
110
2024 Capital Improvement Plan
Washington County, Minnesota Contact PWD
2024 2028thru Department Capital Road & Bridge Project
Description
The project scope includes the following improvements at the intersection of County State Aid Highway (CSAH) 19 (Keats Avenue) and CSAH 10
(10th Street North):
1) evaluation for roundabout construction
2) park entrance improvements
3) roadway drainage and surface water management
4) pedestrian and bicycle facility improvements
Preliminary design along with public engagement will determine the final project scope, right-of-way acquisition required, and cost estimates
which will be included in a future capital improvement plan.
Project #RB-2701
Justification
Traffic growth and ongoing development in the region has increased volumes around this intersection.The current all-way stop control can be
confusing during peak traffic times and does not adequately service the demand. Delays are common and backups more than 1,000 feet occur
frequently. This intersection is ranked near the top of the County's Intersection Control Ranking System. It is well suited for a roundabout, but will
need significant reconstruction to address other needs.
Budget Impact/Other
This project will increase operation and maintenance costs because of the added infrastructure.
Useful Life 5+ yearsProject Name CSAH 19 @ CSAH 10 Intersection Category Road & Bridge
Type Construction
Location Lake Elmo
Total Project Cost:$600,000
District #3
Total20242025202620272028Expenditures
400,000400,000Planning / Design
200,000200,000Right-of-Way
400,000 200,000 600,000Total
Total20242025202620272028Funding Sources
200,000100,000 100,000Local Contributions
400,000300,000 100,000State Aid
400,000 200,000 600,000Total
123
2024 Capital Improvement Plan
Washington County, Minnesota Contact PWD
2024 2028thru Department Capital Road & Bridge Project
Description
The project scope will include an analysis of the County State Aid Highway (CSAH) 14 corridor between Klondike Avenue and 39th Street. The
analysis will be looking at current and future needs to provide a vision that helps guide improvement opportunities in this growing residential and
business corridor. This study will look at future needs regarding highway capacity, intersections, access, right-of-way, drainage, pedestrian/bicycle
facilities, utilities, etc.
Project #RB-2702
Justification
This section of highway suffers from a deteriorating pavement section, lack of pedestrian facilities, lack of shoulders, and poor vehicular operations.
Budget Impact/Other
This project will increase operation and maintenance costs because of the added infrastructure.
Useful Life 5+ yearsProject Name CSAH 14 - Klondike Avenue to 39th Street Category Road & Bridge
Type Construction
Location Lake Elmo
Total Project Cost:$300,000
District #3
Total20242025202620272028Expenditures
300,000300,000Planning / Design
300,000 300,000Total
Total20242025202620272028Funding Sources
300,000300,000State Aid
300,000 300,000Total
124
2024 Capital Improvement Plan
Washington County, Minnesota Contact PWD
2024 2028thru Department Capital Road & Bridge Project
Description
The project scope includes the following improvements to County State Aid Highway (CSAH) 15 (Manning Avenue) from 30th Street to CSAH 14
(Stillwater Boulevard/40th Street South):
1) highway expansion from two-lane undivided to four-lane divided highway
2) construction of trails on both east and west side of highway
3) drainage improvements, including storm water treatment facilities
4) railroad crossing review
Preliminary design, along with public engagement, will determine the final project scope, right-of-way acquisition required, and cost estimates.
The estimated cost is based on past per mile costs of similar improvements.
Project #RB-2801
Justification
CSAH 15 is the backbone of the county's transportation system, thus, is an important north-south route connecting Interstate 94 to Lake Elmo,
Stillwater, and beyond. These highway improvements are necessary to ensure the ongoing safe and efficient operation of this highway segment.
Budget Impact/Other
The project will increase operation and maintenance costs because of the added pavement widths and storm water infrastructure.
Useful Life 5+ yearsProject Name CSAH 15 - 30th Street to CSAH 14 Category Road & Bridge
Type Construction
Location Various
Total Project Cost:$400,000
District #3
Total20242025202620272028Expenditures
400,000400,000Planning / Design
400,000 400,000Total
Total20242025202620272028Funding Sources
100,000100,000Local Contributions
300,000300,000State Aid
400,000 400,000Total
126
2024 Capital Improvement Plan
Washington County, Minnesota Contact PWD
2024 2028thru Department Capital Road & Bridge Project
Description
The project scope includes the following improvements to County State Aid Highway (CSAH) 17 (Lake Elmo Avenue) from CSAH 14 (Stillwater
Boulevard) to 43rd Street:
1) highway expansion from two-lane undivided to four-lane divided highway
2) construction of trails on both east and west side of highway
3) drainage improvements, including storm water treatment facilities
4) intersection control improvement at CSAH 17 at CSAH 14
Preliminary design, along with public engagement, will determine the final project scope, right-of-way acquisition required, and cost estimates.
The estimated cost is based on past per mile costs of similar improvements.
Project #RB-2802
Justification
This portion of County State Aid Highway (CSAH) 17 is a north-south minor arterial serving regional traffic from Lake Elmo to north of Highway
36. Land development in the area continues, including the Schiltgen Farms development. Improvements to CSAH 17 will
provide increased capacity and improved pedestrian opportunities, and allow for appropriate access for this regional growth.
Budget Impact/Other
The project will increase operation and maintenance costs because of the added pavement widths and stormwater infrastructure.
Useful Life 5+ yearsProject Name CSAH 17 - CSAH 14 to 43rd Street Category Road & Bridge
Type Construction
Location Lake Elmo
Total Project Cost:$600,000
District #3
Total20242025202620272028Expenditures
600,000600,000Planning / Design
600,000 600,000Total
Total20242025202620272028Funding Sources
100,000100,000Local Contributions
500,000500,000State Aid
600,000 600,000Total
127
2024 Capital Improvement Plan
Washington County, Minnesota Contact PWD
2024 2028thru Department Capital Parks Projects
Description
The project scope includes a feasibility study to determine best design for crossing the railroad north of Lake Elmo Park Reserve.
Project #PARK-9005
Justification
As areas of central Washington County continue to develop, demand for trail facilities increase. This project will build off of the 13 miles of trail
south of Lake Elmo Park Reserve. The proposed segment within Lake Elmo is the next segment needed to continue the implementation of the full
vision of this regional trail. A feasibility study will determine best methods for connecting to a future trail along County Road 14.
Budget Impact/Other
This project will increase operation and maintenance costs because of the added infrastructure. Cost estimate details will be a product of the 2027
design process. Additional funding is expected to be needed for construction.
Useful Life 5+ yearsProject Name Central Greenway Regional Trail Feasibility Study Category Parks & Land
Type Improvement
Location Lake Elmo
Total Project Cost:$100,000
District #3
Total20242025202620272028Expenditures
100,000100,000Planning / Design
100,000 100,000Total
Total20242025202620272028Funding Sources
100,000100,000State Sales Tax
100,000 100,000Total
53
3880 Laverne Avenue North • Lake Elmo • Minnesota 55042
Phone: (651) 747-3900 • Fax: (651) 747-3901 • www.lakeelmo.org
October 18, 2023
Mr. Xai Thao via email: xai.thao@co.washington.mn.us
County Budget/Financial Analyst
Washington County Office of Administration
14949 62nd Street North
Stillwater, MN 55082
Mr. Thao:
The City of Lake Elmo has reviewed the County’s Draft 2024-2028 Capital Improvement Plan (CIP). After
reviewing these projects and in reviewing other potential transportation needs in Lake Elmo, we have
the following comments:
1) RB-2674 2025: CSAH 17 & TH 36 Intersection: The CSAH 17 and TH36 Intersection improvements
remains a top priority Project for the City of Lake Elmo to address the safety improvements needed
along the TH 36 corridor, while maintaining safe and efficient access for Lake Elmo residents to TH
36. The City therefore continues to support the planning and construction of this project and
emphasizes the need to maintain the proposed construction schedule and to maximize outside
funding assistance in order to provide a financially viable project for the local communities.
2) RB-2645 2026-2028: CSAH 13 Phase 3, from CSAH 6 to CSAH 14. Lake Elmo continues to support
and encourage the County to initiate preliminary engineering and planning efforts along this
corridor to better identify the future improvements that will be needed in conjunction with the
development of the City owned property along Ideal Avenue and Stillwater Boulevard. The City,
however, believes these efforts will need to be completed much sooner than the County’s planned
schedule of 2026 to 2028. The City is requesting these planning efforts be initiated as soon as 2024
to promote an efficiently planned infrastructure system to be coordinated with the pending
development.
3) RB-2201 Intersection Control Projects. Under this category description, the County lists a traffic
signal at CSAH 15 and Hudson Boulevard to be implemented at some future date. The City supports
the importance to have funding earmarked and available for a new signal at this intersection, to be
implemented as the area develops. The City is currently working with a developer that will include
improvements in 2024 or 2025 to realign the Hudson Boulevard intersection with Manning
Avenue/2nd Street N.
4) RB-2652 2025: 58th Street Extension/CR 15 South Segment. Although this project resides outside
of Lake Elmo, the Project includes a connection to be constructed between the new interchange at
TH36/CSAH 15 extending through Oak Park Heights to Stillwater Boulevard. The City supports the
roadway extension on the condition that the Sanctuary neighborhood access to the new
interchange is not degraded.
5) New Planning and Design Projects. The City acknowledges and appreciates the addition of 4 new
Planning and Preliminary Design Projects in the County CIP. The City recognizes the importance of
addressing each of these project corridors and is supportive of each of these future planning
initiatives. In particular, the City considers the preliminary design work for Projects RB-2702 and RB-
2802 to be a high priority that should be initiated as soon as 2026. Adequate pedestrian facilities
along each of these corridors should be considered important design elements for each Project.
• RB-2701 2027-2028 Planning/Design: CSAH 19 and CSAH 10 Intersection.
• RB-2702 2027 Planning/Design: CSAH 14, from Klondike Avenue to 39th Street.
• RB-2801 2028 Planning/Design: CSAH 15, 30th Street to CSAH 14.
• RB-2802 2028 Planning/Design: CSAH 17, CSAH 14 to 43rd Street.
6) RB-2684 2025: CSAH 15, from CSAH 10 to 30th Street North: Improvements to CSAH 15, south of
30th Street remain on the lower end of the City’s priorities to the extent that these improvements
impact Lake Elmo.
7) RB-2204 Pavement Preservation & Rehab. Under this category description, the County lists a
potential pavement rehabilitation Project to be completed in the next few years along CSAH 13
(Inwood Ave N) from CSAH 10 to CSAH 6. The City has not comments at this time.
8) PARK-9005 Central Greenway Regional Trail Feasibility Study. The City supports the continued work
efforts to plan and construct the Central Greenway Regional Trail corridor through Lake Elmo,
including the proposed Feasibility Study to determine best design for crossing the railroad north of
Lake Elmo Park Reserve.
Please feel free to contact me at 651.747.3905, or at KHandt@lakeelmo.org, with any questions you
may have regarding Lake Elmo’s comments.
Sincerely,
Kristina Handt
City Administrator
cc: Frank Ticknor, Washinton County Deputy Director
Marty Powers, Public Works Director
Jack Griffin, PE, City Engineer