HomeMy WebLinkAbout#04 - MPCA Grant Amendment for Hamlet on Sunfish STAFF REPORT
DATE: November 21, 2023
CONSENT
AGENDA ITEM: Approve MPCA Grant Agreement Amendment #3 for the Hamlet on Sunfish Lake Street and Utility Improvements SUBMITTED BY: Jack Griffin, City Engineer REVIEWED BY: Kristina Handt, City Administrator Sarah Sonsalla, City Attorney Clarissa Hadler, Finance Director Marty Powers, Public Works Director Chad Isakson, Project Engineer
ISSUE BEFORE COUNCIL: Should the City Council approve the Grant Agreement Amendment #3 with the MPCA for the Hamlet on Sunfish Lake Street and Utility Improvements?
BACKGROUND: On February 4, 2020, the city council approved a Grant Agreement with MPCA to extend city water to serve the properties in the Hamlet on Sunfish Lake subdivision. The current grant expires December 31, 2023.
PROPOSAL DETAILS/ANALYSIS: The Project warranty period expired on September 20, 2023, however, some warranty repair work may not be completed until sometime in 2024. Therefore, the City requested a time extension to the Grant Agreement to ensure that all potential warranty period costs will be
covered by the Grant. The Grant Amendment extends the expiration date until December 31, 2024. OPTIONS:
1) Approve the Grant Agreement Amendment #3 with the MPCA for the Hamlet on Sunfish Lake Street and Utility Improvements. 2) Do not approve the Grant Agreement Amendment #3. FISCAL IMPACT: Not applicable. RECOMMENDATION: Staff is recommending that the City Council Approve, as part of the Consent
Agenda, the Grant Agreement Amendment #3 with the MPCA for the Hamlet on Sunfish Lake Street and Utility Improvements. If removed from the Consent Agenda, the recommended motion for this action is as follows:
“Move to approve Grant Agreement Amendment #3 with the MPCA for the Hamlet on Sunfish Lake Street and Utility Improvements.” ATTACHMENTS: 1. MPCA Grant Agreement Amendment #3.
Grant Agreement
Amendment #3
State of Minnesota
Doc Type: Contract
SWIFT Contract Number: 165904
Agency Interest ID: 224243
Activity ID: PRO20190016
Contract Start Date: March 2, 2020 Total Contract Amount: $3,398,200.00
Original Contract Expiration Date: October 31, 2023 Original Contract: $2,712,200.00
Current Contract Expiration Date: December 31, 2023 Previous Amendment(s) Total: $686,000.00
Requested Contract Expiration Date: December 31, 2024 This Amendment: $0
This amendment is by and between the State of Minnesota, acting through its Commissioner of the
Minnesota Pollution Control Agency, 520 Lafayette Road North, St. Paul, MN 55155-4194 (“MPCA” or
“State”) and City of Lake Elmo, 3800 3880 Laverne Avenue North, Lake Elmo, MN 55042 ("Grantee" or
"Contractor").
Recitals
1. The State has a grant contract with the Grantee identified as SWIFT Contract Number 165904
("Original Grant Agreement") to provide the Hamlet on Sunfish Lake Extension of Municipal Water
Supply Project.
2. The Original Agreement is being amended to extend the expiration date, revise well sealing
language, and update authorized representatives.
3. The State and the Grantee are willing to amend the Original Grant Agreement as stated below.
Grant Agreement Amendment
In this Amendment, changes to pre-existing Agreement language will use strike through for deletions
and underlining for insertions.
REVISION 1. Clause 1. "Term of Grant Agreement" is amended as follows:
1. Term of Grant Agreement
1.1 Effective date: March 2, 2020, or the date the State obtains all required signatures under
Minn. Stat. § 16B.98, subd. 5, whichever is later. Per Minn.Stat.§16B.98 Subd. 7, no payments
will be made to the Grantee until this grant contract is fully executed.
1.2 Expiration date: December 31, 2023 December 31, 2024, or until all obligations have been
satisfactorily fulfilled, whichever occurs first.
1.3 Survival of terms. The following clauses survive the expiration or cancellation of this grant
agreement: Indemnification; State Audits; Government Data Practices and Intellectual
Property; Publicity and Endorsement; Governing Law, Jurisdiction, and Venue; and Data
Disclosure.
REVISION 2. Clause 2. "Grantee's Duties and Well Sealing" is amended as follows:
2. Grantee’s Duties and Well Sealing
2.1 Grantee’s duties. The Grantee, who is not a state employee, will perform the duties specified
in Revised Attachment A Amendment 23, which is attached and incorporated into this grant
agreement.
2.2 Well Sealing. All associated wells are required to be properly sealed and abandoned as part of
the project within the timeframe of the grant agreement. All well sealing will follow
Minnesota Department of Health (MDH) regulations and will only be done by licensed well
contractors.
Reimbursement for individual/residential water service connections and well sealing will not
occur until proof of well sealing has been provided to MPCA.
MPCA may identify certain wells as potential monitoring wells. If agreed upon by MPCA, the
City and the well owner, MPCA will assume responsibility of converting those wells to
monitoring wells. In these instances, proof of well sealing is not required for reimbursement
of individual/residential water service connection costs.
REVISION 3. Clause 6 "Authorized Representative" is amended as follows:
6. Authorized Representative
The State's Authorized Representative is Gary Krueger, 520 Lafayette Road, St. Paul, MN 55155,
651-757-2509, gary.krueger@state.mn.us, Elizabeth Kaufenberg, 520 Lafayette Road, St. Paul, MN
55155, 651-757-2481, elizabeth.kaufenberg@state.mn.us, or their successor, and has the authority
to monitor the Grantee’s performance and to accept the services provided under this agreement. If
the services are satisfactory, the MPCA’s Project Manager will certify acceptance of each invoice
submitted for payment.
The State’s Project Manager is Megan Holthaus, 520 Lafayette Road North, St. Paul, MN 55155, 651-
757-2843, megan.holthaus@state.mn.us, or their successor, and has the authority to monitor the
Grantee’s performance and receive invoices from the Grantee.
The Grantee’s Authorized Representative is Kristina Handt, 3880 Laverne Avenue North, Lake Elmo,
MN 55042, 651-747-3905, khandt@lakeelmo.org, or their successor. If the Grantee’s Authorized
Representative changes at any time during this grant agreement, the Grantee must immediately
notify the State.
Except as amended herein, the terms and conditions of the Original Grant Agreement and all previous
amendments and change orders remain in full force and effect. The Original Grant Agreement and any
previous amendments and change orders are incorporated into this amendment by reference.
Signatures
Title Name Signature Date
\t1\ \n1\ \s1\ \d1\
\t2\ \n2\ \s2\ \d2\
\t3\ \n3\ \s3\ \d3\
\t4\ \n4\ \s4\ \d4\
\t5\ \n5\ \s5\ \d5\
\t6\ \n6\ \s6\ \d6\
www.pca.state.mn.us • 651-296-6300 • 800-657-3864 • Use your preferred relay service • Available in alternative formats
e-admin9-38 • 3/11/16 Page 1 of 2
Project Workplan
Doc Type: Contract
Swift #: 165904
AI #: 224243
Activity ID #: PRO20190016
Project Title: Hamlet on Sunfish Lake Extension of Municipal Water Supply Project
1. Project Summary:
Organization: City of Lake Elmo (the City)
Contact name: Kristina Handt
Address: 3880 Laverne Ave North
Lake Elmo, MN 55042
Phone: 651-747-3905
E-mail: khandt@lakeelmo.org
Minnesota Pollution Control Agency (MPCA) contact:
MPCA project manager: Tim Lockrem Megan Holthaus
Address: 520 Lafayette Road North
St. Paul, MN 55155
Phone: 651-757-2686 2843
E-mail: Timothy.lockrem@state.mn.us megan.holthaus@state.mn.us
Project information
Start date:
3/2/2020 End date: 12/31/2023 12/31/2024
Total estimated costs: $3,398,200.00
Revised Attachment A Amendment 23
www.pca.state.mn.us • 651-296-6300 • 800-657-3864 • Use your preferred relay service • Available in alternative formats
e-admin9-38 • 3/11/16 Page 2 of 2
2. Statement of Problems, Opportunities, and Existing Conditions
The Hamlet on Sunfish Lake neighborhood is located at the intersection of Kindred Way North and 43rd Street
North. This project will extend clean drinking water to 41 homes located in the Hamlet on Sunfish Lake
neighborhood in the City of Lake Elmo by extending the municipal water system into the neighborhood prior to
reconstructing the neighborhood streets as scheduled for improvement in 2021 in the City's street capital
improvement plan. The project extends the public watermain into the neighborhood from the intersection of
Kindred Way North and 43rd Street North, then along the public streets to the south end of the neighborhood at
Kindred Court, then east to make a looped watermain connection to the adjacent Legacy at North Star
development. The southern loop properties reside in an area where PFAS contamination exceeds HBV and well
advisories have been issued and all properties, including the northern loop, reside within the Special Well
Construction Area designated by the Minnesota Department of Health in March, 2007 due to the proximity of
PFAS in the groundwater. Individual water service stubs will be installed to the edge of right-of-way at each of
the 41 residential properties. The project will include restoration following the watermain installation and this
will include a street reclamation for the public streets along with boulevard sodding to restore all disturbed
areas. Sanitary sewer utility repairs/replacement may be incorporated as part of the project, but these costs will
be 100% assessed to the benefitting properties.
The project will include grant funding and administrative processes for ensuring each property completes the
private service connection from the right-of-way to each home, including water meter installation, sealing of the
private well, and all permitting and connection fees. The City intends to implement the public improvement
portion of the project that remains within the public right-of-way and will require property owners to contract
directly for the work to be completed on individual properties. The private property work will be funded on a
reimbursement basis.
In accordance with the City's standard CIP process a feasibility study and project design will be completed in
2020 to ready the project for 2021 construction. Bids will be received in early 2021 with construction to
commence in May 2021. The watermain will be tested, operational and ready for connection to the individual
properties in late 2021.
No environmental review is required to implement this project. The project will require the following permits:
• Minnesota Department of Health (MDH) Watermain Extension Permit.
• Met Council/MPCA Sanitary Sewer Permit (if sewer repairs are needed).
• Valley Branch Watershed District Permit.
• MPCA NPDES Construction Permit.
3. Measurable Outcomes
The City will report at least quarterly to the MPCA regarding progress of the project. The City will also report to
the MPCA as part of the quarterly report the itemized costs incurred for that quarter for reimbursement by the
MPCA. Monthly reimbursement requests can be provided as determined by the City.