#14 - City Center Change Order 3
STAFF REPORT DATE: November 21, 2023 CONSENT AGENDA ITEM: City Center-Public Works Addition Change Order #3 SUBMITTED BY: Kristina Handt, City Administrator BACKGROUND: At the November 3, 2021 meeting, Council awarded bids for the new city center and public works addition. Also established at that time was Guaranteed Maximum Price (GMP) with H+U for construction costs. The GMP was $13,402,788. At the July 5, 2022 meeting, the city council approved change orders for the motor power clarifications ($109,862) and public works revisions ($122,789). That approval did not include increasing the GMP for H+U at th time as it was unknown which contingency would be needed to cover these costs. ISSUE BEFORE COUNCIL: Should Council approve Change Order #3 for the City Center Public Works Addition Project and increase H+U’s GMP by $232,651? PROPOSAL: A copy of the proposed change order is included in your packet. This change order doesn’t increase the project costs but rather allocates additional resources in the budget from city contingency to H+U’s GMP for increases the council already approved in July 2022. FISCAL IMPACT: With this pay request, the project remains within the overall budget of $15,727,941 by reducing the city’s contingency and increasing H+U’s GMP by an equal amount. OPTION: 1) Approve Change Order #3 2) Don’t approve Change Order #3 RECOMMENDATION: If removed from the consent agenda: “Motion to approve Change Order #3 for the New City Center and Public Works Addition.” ATTACHMENTS: • Change Order #3 AIA® Document G701™ – 2017 Change Order AIA Document G701™ – 2017. Copyright © 1979, 1987, 2000 , 2001 and 2017 by The American Institute of Architects. All rights reserved. The “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are registered trademarks and may not be used without permission. This draft was produced by AIA software at 11:43:57 ET on 03/31/2022 under Order No.6009857342 which expires on 01/14/2023, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail copyright@aia.org. User Notes: (3B9ADA4A) 1 PROJECT: (Name and address) CONTRACT INFORMATION: CHANGE ORDER INFORMATION: Lake Elmo City Center & Public Works Contract For: General Construction Change Order Number: 003 3880 Laverne Ave North Lake Elmo, MN 55042 Date: October 25, 2021 Date: November 13, 2023 OWNER: (Name and address) ARCHITECT: (Name and address) CONTRACTOR: (Name and address) City of Lake Elmo Leo A Daly H + U Construction 3800 Laverne Ave N Lake Elmo, MN 55402 730 Second Ave South, Suite 1300 Minneapolis, MN 55402 5555 W 78th Street, Suite A Minneapolis, MN 55439 THE CONTRACT IS CHANGED AS FOLLOWS: (Insert a detailed description of the change and, if applicable, attach or reference specific exhibits. Also include agreed upon adjustments attributable to executed Construction Change Directives.) Revisions previously approved by Lake Elmo City Council for the scopes of work related to ASI-12R Motor Power Clarifications in the amount of $109,862 and PR-12R Public Works Revisions in the amount of $122,789 represent value added work not originally included in the GMP or the GMP's construction contingency. These revisions require the use of project contingency funds which require a change order to the GMP to cover the additonal scope of work. The original Guaranteed Maximum Price was $ 13,402,788.00 The net change by previously authorized Change Orders $ 0.00 The Guaranteed Maximum Price prior to this Change Order was $ 13,402,788.00 The Guaranteed Maximum Price will be increased by this Change Order in the amount of $ 232,651.00 The new Guaranteed Maximum Price including this Change Order will be $ 13,635,439.00 The Contract Time will be increased by ninety-eight (98) days. The new date of Substantial Completion will be July 7, 2023 for the portion of the project related to the Lake Elmo City Center Project only excluding the exterior wood trim scope of work, the southwest stormwater basin system, the exterior landscaping and the exterior landscaping planters. NOTE: This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price, or the Contract Time, that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor, in which case a Change Order is executed to supersede the Construction Change Directive. NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER. Leo A Daly H + U Construction City of Lake Elmo ARCHITECT (Firm name) CONTRACTOR (Firm name) OWNER (Firm name) SIGNATURE SIGNATURE SIGNATURE Todd LaVold, PM Joe Ullhorn, Partner Kristina Handt, City Administrator PRINTED NAME AND TITLE PRINTED NAME AND TITLE PRINTED NAME AND TITLE 11/13/2023 DATE DATE DATE