HomeMy WebLinkAbout#08 - Launch Crossroads Security Reduction STAFF REPORT DATE: January 2, 2024 CONSENT AGENDA ITEM: Accept Improvements and Approve Security Reductions for the Launch Crossroads First Addition SUBMITTED BY: Jack Griffin, City Engineer REVIEWED BY: Clark Schroeder, Interim City Administrator Sophia Jensen, City Planner Marty Powers, Public Works Director Clarissa Hadler, Finance Director Chad Isakson, Assistant City Engineer ISSUE BEFORE COUNCIL: Should the City Council accept the improvements and approve security reductions for the Launch Crossroads First Addition? PROPOSAL DETAILS/ANALYSIS: Staff has received and processed a request to accept the improvements and reduce the development security for Launch Crossroads First Addition. This request has been reviewed and is being recommended for approval in accordance with the approved Development Agreement. Approval of this reduction is contingent on the developer having a positive escrow balance in the minimum amount required by the city, and the developer being current with all payments and obligations required by the Development Agreement. The Development Security amount is recommended to be reduced as follows: Current Security Amount Proposed Security Amount 1. Launch Crossroads First Addition $ 3,460,753 $ 1,041,043 The warranty periods for the Subdivision’s public improvements will be initiated as outlined on the attached Certificate of Completion. Twenty-five percent (25%) of the original security amount will be retained until the applicable warranty periods have expired and all warranty corrective work has been completed. FISCAL IMPACT: It is the City’s goal to retain at all times during the subdivision improvements a security amount that is adequate to ensure completion of all elements of the improvements as protection to the city tax payers against the potential of developer default. RECOMMENDATION: Staff is recommending that the City Council, as part of the Consent Agenda, accept the improvements and approve the security reductions as detailed in the attached respective worksheets for Launch Crossroads First Addition, contingent on the developer being current with all payments and obligations in accordance with the Development Agreement, including a positive escrow balance as required by the City. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to accept the improvements and approve the security reductions as detailed in the attached respective worksheets for Launch Crossroads First Addition, contingent on the developer being current with all payments and obligations in accordance with the Development Agreement.” ATTACHMENTS: 1. Certificate of Completion – Launch Crossroads First Addition. 2. Security Reduction Worksheet – Launch Crossroads First Addition. CERTIFICATE OF COMPLETION DATE OF ISSUANCE: JANUARY 2, 2024 OWNER: CITY OF LAKE ELMO, MN DEVELOPER: AIRLAKE DEVELOPMENT INC. AND CROSSROADS EAST, LLC SUBDIVISION NAME: CROSSROADS EAST FIRST ADDITION PROJECT NO.: 2021.112 This Certification of Completion applies to all work under the Development Agreement This Certification of Completion applies to the following specified parts of the Development Agreement Section 32.A (4th Amendment to the DA): Public Improvements excluding grading and landscaping I do hereby certify that the work to which this Certificate applies has been constructed in accordance with the Development Agreement dated February 15, 2022 and subsequent amendments 1, 2, 3, and 4. The above-mentioned improvement is hereby declared to be complete and acceptance of this work is recommended. DATE OF COMPLETION: January 2, 2024 Chad Isakson Reg. No. 49028 FOCUS Engineering, inc. Section 30.A Warranty Period Begins January 2, 2024 and ends January 2, 2026 Section 30.B Warranty Period Begins January 2, 2024 and ends January 2, 2025 LAUNCH-CROSSROADS Time of Performance: December 31, 2022DEVELOPMENT AGREEMENT AMOUNTSCATEGORY CONSTRUCTION 125% REMARKS #1 #2 #3 #4 #5 #6Grading $468,200 $585,250100%$585,250Sanitary Sewer $489,910 $612,38875%$459,291Watermain $314,777 $393,47175%$295,103Storm Sewer (w/pond structures) $167,791 $209,73975%$157,304Streets + Sidewalks $834,438 $1,043,04875%$782,286Bituminous Trails $31,896 $39,87075%$29,903Surface Water Facilities $57,050 $71,31375%$53,484Street Lighting NA NAStreet and Traffic Signs $8,720 $10,90075%$8,175Private Utilities (electricity, gas, etc.) NA NALandscaping $343,645 $429,556Tree Preservation and Restoration NA NAWetland Mitigation and Buffers NA NAMonuments NA NAErosion Control $46,925 $58,65675%$43,992Record Drawings $5,250 $6,56375%$4,922TOTALS $2,768,602 $3,460,753RELEASED AMOUNTS:$2,419,710 $0 $0 $0 $0 $0CUMULATIVE AMOUNTS:$2,419,710SECURITY AMOUNT REMAINING:$1,041,043DATE:1/2/2024REDUCTIONS