MEMORANDUM
To: Clark Schroeder, City Administrator, Lake Elmo
From: Paul Aplikowski | PA
Date: January 18, 2024
Revised February 5, 2024
Comm. No: 232224
Subject: Independent School District #834
Submittal to City of Lake Elmo on behalf of Stillwater Area Public Schools,
for the proposed New Lake Elmo Elementary School project, located at the
intersection of Lake Elmo Avenue North and Tenth Street North, Lake Elmo,
Minnesota (Property ID #2602921440001)
Comprehensive Plan Amendment and Zoning Map Amendment Submittal Narrative:
On behalf of the Stillwater Area Public Schools, we are submitting for city staff review of a
comprehensive plan amendment and zoning map amendment for the proposed new
Lake Elmo Elementary School site. The proposed 1,100-student elementary school building would
replace the current Lake Elmo Elementary School located at 11030 Stillwater Boulevard, Lake Elmo,
Minnesota. The new building is proposed to be a total of 148,000 square feet and will likely be a
two-story structure. At this time, the exact footprint size is unknown as the design of the building is
still in progress.
The 47.6-acre site is currently zoned as Agricultural (A) and will require rezoning to Public Facilities
(PF) to accommodate the proposed educational use. A Conditional Use Permit will be submitted
after rezoning has been completed. In addition to rezoning the parcel, we understand that the
Comprehensive Plan will need the future land use guidance for this site amended from Rural Area
Development (RAD) to Institutional (INST). Based on comments received on the Sketch Plan
Review submittal, we are continuing to show access to the site from both adjacent roads (Tenth
Street North and Lake Elmo Avenue North). To help facilitate site safety, the District will endeavor
to keep the bus and visitor traffic separate. The visitor entry will be designed to allow on-site
stacking of waiting vehicles.
Aside from onsite parking and the school building itself, the site is proposed to include several
other amenities that have the potential to be jointly used by the school and the City of Lake Elmo
residents. Currently two ball fields, a greenspace field, and playground facilities are planned for the
site. We are aware of the need for onsite stormwater control.
MEMORANDUM
Page 2 of 2
The District desires the new school building to be connected to the City’s municipal sanitary sewer
and drinking water supply. We understand that this will require an extension of the MUSA
boundary to include this site. In the comments received on the previously submitted Sketch Plan
Review from the Lake Elmo City engineering department, it was stated that all proposed uses on
the property should be served by the City public drinking water supply due to the PFAS
groundwater contamination in the surrounding area. This is in alignment with guidance received
from the Minnesota Department of Natural Resources.
Through analysis of 12 months of utility bills from the District’s newest facility (Brookview
Elementary), our research indicates that 578,000 gallons of water were used over a 12-month period.
This equates to an average of six gallons of water used per student per day. For the new facility,
which will serve an estimated 1,100 students, this would extrapolate to 6,600 gallons of water per
day.
Feel free to contact Wold Architects and Engineers or the District with any questions or concerns
you may have.
AM/MN-EDU-ISD834/ES_New Lake Elmo/232224/_Admin/2024.02.05 Revised Memo to Clark Schroeder
C.S.A.H. NO. 17 (LAKE ELMO AVE. N.)C.S.A.H. NO. 10 (10TH STREET NORTH)14141416161616151515PID#2602921440001WETLAND NOTE:NO WETLANDS PRESENT BASED ON AN SEPTEMBER2023 EXAMINATION BY BOPRAY ENVIRONMENTALAND A PREVIOUS 'NO WETLANDS PRESENT'DETERMINATION PER 'NOTICE OF DECISION' BY THEVALLEY BRANCH WATERSHED DISTRICT DATED12/31/2020CONTACT:Tony WillgerStillwater Area Public Schools1875 South Greeley St.Stillwater, MN 55082Phone: 651.351.8374Email:willgert@stillwaterschools.orgUNDERGROUND UTILITIES NOTES:THE UNDERGROUND UTILITIES SHOWN HAVE BEENLOCATED FROM FIELD SURVEY INFORMATION ANDEXISTING DRAWINGS. THE SURVEYOR MAKES NOGUARANTEE THAT THE UNDERGROUND UTILITIESSHOWN COMPRISE ALL SUCH UTILITIES IN THE AREA,EITHER IN SERVICE OR ABANDONED. THE SURVEYORFURTHER DOES NOT WARRANT THAT THEUNDERGROUND UTILITIES SHOWN ARE IN THE EXACTLOCATION INDICATED ALTHOUGH HE DOES CERTIFYTHAT THEY ARE LOCATED AS ACCURATELY ASPOSSIBLE FROM THE INFORMATION AVAILABLE. THISSURVEY HAS NOT PHYSICALLY LOCATED THEUNDERGROUND UTILITIES. GOPHER STATE ONE CALLLOCATE TICKET NUMBER(S) 232783758. SOME MAPSWERE RECEIVED, WHILE OTHER UTILITIES DID NOTRESPOND TO THE LOCATE REQUEST. ADDITIONALUTILITIES OF WHICH WE ARE UNAWARE MAY EXIST.LE23147SURVLE147BOUNDARY/TOPOGRAPHICSURVEYCOUNTY/CITY:REVISIONS:PROJECT LOCATION:LAND SURVEYING, INC.CORNERSTONESuite #2001970 Northwestern AveStillwater, MN 55082Phone 651.275.8969Fax 651.275.8976dan@cssurvey.netDATEREVISIONPROJECT NO.FILE NAMEXXXXCALL BEFORE YOU DIG!TWIN CITY AREA:TOLL FREE:1-800-252-1166651-454-0002Gopher State One CallLEGAL DESCRIPTION:LAKE ELMO AVE. N.1. BEARINGS ARE BASED ON COORDINATES SUPPLIEDBY THE WASHINGTON COUNTY SURVEYORS OFFICE.2. UNDERGROUND UTILITIES SHOWN PER GOPHER ONELOCATES AND AS-BUILTS PLANS PROVIDED BY THECITY OF LAKE ELMO.3. THERE MAY SOME UNDERGROUND UTILITIES, GAS,ELECTRIC, ETC. NOT SHOWN OR LOCATED.4. LIDAR ELEVATION DATA RELIED UPON FOR INTERIORTOPOGRAPHIC INFORMATION. CHECK SHOTS TOVERIFY LIDAR ACCURACY WERE TAKEN ASINDICATED BY THE SPOT ELEVATIONS NOTED IN THEGRAPHICS. SOME VARIATION FROM THE ACTUALGROUND ELEVATIONS MAY OCCUR DUE TO OURINABILITY TO VERIFY AREAS IN HEAVY TREE COVER.TOPOGRAPHY ON ALL ROAD SURFACES AND ROADDITCHES WERE DEVELOPED BASED ON FIELD SURVEYSHOTS TAKEN IN OCTOBER 2023.SURVEY NOTES:CITY OF LAKE ELMOWASHINGTONCOUNTY(LEGAL DESCRIPTION IS PER LAND TITLE, INC. AS AGENT FORFIRST AMERICAN TITLE INSURANCE COMPANY TITLECOMMITMENT NO. 683144 DATED AUG. 9, 2023.)The Southeast 1/4 of the Southeast 1/4 of Section 26,Township 29, Range 21, Washington County, Minnesota, andall that part of the Southwest 1/4 of the Southeast 1/4, lyingEasterly of the West 435.6 feet of the East 2006 feet of theSouth 1/2 of the Southeast 1/4 of said Section, WashingtonCounty, Minnesota. Abstract Property10-11-2023PRELIMINARY ISSUE12-19-2023INITIAL ISSUECERTIFICATION:I hereby certify that this plan was prepared byme, or under my direct supervision, and that I ama duly Licensed Land Surveyor under the laws ofthe state of Minnesota.Daniel L. Thurmes Registration Number: 25718Date:__________________GROSS PARCEL AREA = 2,072,858 SQ. FT. / 47.59 ACRES10TH STREET ESMT.= 78,522 SQ. FT. / 1.80 ACRESLAKE ELMO AVE ESMT.= 63,513 SQ. FT. / 1.46 ACRESNET PARCEL AREA= 1,930,823 SQ. FT. / 44.33 ACRESAREA:STILLWATER SCHOOLSLAKE ELMO SITE0NORTH6012012-19-2023LEGEND:UNDERGROUND ELECTRICUNDERGROUND CABLE TVUNDERGROUND FIBER OPTICUNDERGROUND TELEPHONEOVERHEAD UTILITYUNDERGROUND GASSANITARY SEWERSTORM SEWERWATERMAINFENCECURB [TYPICAL]CONTOURSTREELINEFOUND MONUMENTSET 1/2" IRON PIPEMARKED RLS NO. 25718CABLE TV PEDESTALAIR CONDITIONERELECTRIC MANHOLEELECTRIC METERELECTRIC PEDESTALELECTRIC TRANSFORMERLIGHT POLEGUY WIREPOWER POLEGAS MANHOLEGAS METERTELEPHONE MANHOLETELEPHONE PEDESTALSANITARY CLEANOUTSANITARY MANHOLECATCH BASINSTORM DRAINFLARED END SECTIONSTORM MANHOLEFIRE DEPT. CONNECTIONHYDRANTCURB STOPWATER WELLWATER MANHOLEWATER METERPOST INDICATOR VALVEWATER VALVEBOLLARDFLAG POLEMAIL BOXTRAFFIC SIGNUNKNOWN MANHOLESOIL BORINGSPOT ELEVATIONTRAFFIC SIGNALCONIFEROUS TREEDECIDUOUS TREE(THE FOLLOWING EXCEPTIONS APPEAR ON THE LAND TITLE,INC. AS AGENT FOR FIRST AMERICAN TITLE INSURANCECOMPANY TITLE COMMITMENT NO. 683144 DATED AUG. 9,2023.)13. Easement for utility purposes per Book 118 of Deeds,page 551, as Document Number 101676, Book 135 ofDeeds, pages 373-374 as Document Number 118648.Assignment per Document Number 471911. Quit ClaimDeed conveyance to Northwestern Bell TelephoneCompany d/b/a US West Communications per DocumentNumber 611259. Definition of Easement per DocumentNumber 639079. Corrective Definition of Easements perDocument Number 797893. (SHOWN GRAPHICALLY).14. Highway Easement per Book 245 of Deeds, page 271,as Document Number 219558. (SHOWN GRAPHICALLY).15. Slope Easement per Book 245 of Deeds, page 272.(SHOWN GRAPHICALLY).16. Highway and Slope Easement per Book 256 of Deeds,page 159-160, as Document Number 228200. (SHOWNGRAPHICALLY).TITLE NOTES:BENCHMARKSELEVATIONS BASED ON INFORMATION AS SHOWN ONTHE TKDA WATERMAIN PLANS - SHEET C502 DATED4/15/2014. TOP NUT HYDRANT 400 ' N. OF 10THSTREET. ELEVATION = 939.3713141516
C.S.A.H. NO. 17 (LAKE ELMO AVE. N.)C.S.A.H. NO. 10 (10TH STREET NORTH)10TH STREET NORTH COURT
12THSTREETNORTH11THSTREETNORTHADDRESS: 10684 10THSTREET CT NOWNER: BENCKHANNAH & ANDREWLOT AREA: 1.5 ACREZONING: RSADDRESS: 10674 10THSTREET CT NOWNER: LUDWIGMICHEAL & PATRICIALOT AREA: 1.5 ACREZONING: RSADDRESS: 10664 10THSTREET CT NOWNER: WEMEIERBARBARA & GARYLOT AREA: 2.0 ACREZONING: RSADDRESS: 10654 10THSTREET CT NOWNER: KIMBERELYDALE JR & LORI A.LOT AREA: 1.8 ACREZONING: RSADDRESS: 10644 10THSTREET CT NOWNER: JOHNSONISAIAH & ROBYNLOT AREA: 1.6 ACREZONING: RSADDRESS: 10386 10THSTREET NOWNER: OAKDALEGUN CLUBLOT AREA: 22.5 ACREZONING: RRADDRESS: 1515 KEATSAVE NOWNER: WASHINGTONCOUNTYLOT AREA: 239.5 ACREZONING: PFADDRESS: 1515 KEATSAVE NOWNER: WASHINGTONCOUNTYLOT AREA: 12.4 ACREZONING: PFADDRESS: 1326 LAKEELMO AVE NOWNER: FRANCESANNE PETERSON TRSLOT AREA: 6.9 ACREZONING: RSADDRESS: 1326 LAKEELMO AVE NOWNER: FRANCESANNE PETERSON TRSLOT AREA: 0.7 ACREZONING: RSADDRESS: 1515 KEATSAVE NOWNER: WASHINGTONCOUNTYLOT AREA: 12.4 ACREZONING: PFADDRESS: 11031 14THSTREET NOWNER: CITY OF LAKEELMOLOT AREA: 2.7 ACREZONING: AADDRESS: -OWNER: HOMESTEADHOMEOWNERSLOT AREA: 8.5 ACREZONING: PFADDRESS: 11066 12THSTREET NOWNER: DUFAULTCHASE & JANETLOT AREA: 1.5 ACREZONING: RSADDRESS: 11040 12THSTREET NOWNER: DREYER PHILIP& MARY SUE SCHRANTZLOT AREA: 1.7 ACREZONING: RSADDRESS: 11047 12THSTREET NOWNER: HENDRICKSSTEPHEN & SUSANLOT AREA: 1.6 ACREZONING: RSADDRESS: 11075 12THSTREET NOWNER: VALLOTLAWRENCE & JUDITHLOT AREA: 1.6 ACREZONING: RSADDRESS: 11066 11THSTREET NOWNER: GUTIERREZSTEVEN & EMILYLOT AREA: 1.5 ACREZONING: RSADDRESS: 11048 11THSTREET NOWNER: HILLS JEFEREY& KATHRYNLOT AREA: 2.1 ACREZONING: RSADDRESS: 11063 11THSTREET NOWNER: BERKOWITZROBERT & SARAHLOT AREA: 1.6 ACREZONING: RSADDRESS: 11025 10THSTREET NOWNER: LUJAIN WADICO LLCLOT AREA: 0.8 ACREZONING: CADDRESS: 978 LAKEELMO AVE NOWNER: HOLMGRENTERI & STEVENLOT AREA: 2.5 ACREZONING: RSADDRESS: 10895 10THSTREET NOWNER: STEINMANTHOMAS & DEBRALOT AREA: 1.6 ACREZONING: RSADDRESS: 10841 10THSTREET NOWNER: JOHNSONBENJAMINLOT AREA: 4.1 ACREZONING: RSADDRESS: 10759 10THSTREET NOWNER: LUKINMICHAEL & ANNLOT AREA: 12.0 ACREZONING: RRADDRESS: 10699 10THSTREET NOWNER: MAMMENGAROBERT & CARRIELOT AREA: 12.0 ACREZONING: RRADDRESS: 10639 10THSTREET NOWNER: LOCKETTKENNETH III & JILLLOT AREA: 12.0 ACREZONING: RRADDRESS: -OWNER: MHC CIMARRON LLCLOT AREA: 104.1 ACREZONING: MDRADDRESS: 928 LAKE ELMOAVE NOWNER: HER KOU & KENGLOT AREA: 6.9 ACREZONING: RS122826262819222124PLAYGROUNDSTORMWATERBASIN #4STORMWATER
BASIN #3
STORMWATERBASIN #1OPEN FIELD15NEW ELEMENTARYFFE: 932.00 (ARCH: 100'-0")STORMWATERBASIN #2NOTE THE PROPOSED BUILDING IS FORREFERENCE ONLY AND IS NOT THE FINAL DESIGN0NORTH50100200SYMBOL LEGENDPARCEL INFOPID: 26.029.21.44.0001LOT SIZE: 47.59 ACRESZONING: AGRICULTURAL (A)LEGAL DESCRIPTION: PT OF S1/2 OF SE1/4 BEING E 1570.4FT SECTION 26 TOWNSHIP 029 RANGE 0213524 Labore RoadWhite Bear Lake, MN 55110651.481.9120 (f) 651.481.9201www.larsonengr.comC 2024 Larson Engineering, Inc. All rights reserved.3524 Labore RoadWhite Bear Lake, MN 55110651.481.9120 (f) 651.481.9201www.larsonengr.comLarsonEngineering, Inc.NorthCheck:Drawn:Date:Comm:Scale:Greg A. Buchal, P.E.Date: Lic. No.:01.19.202423793I hereby certify that this plan, specifications or reportwas prepared by me or under my direct supervisionand that I am a duly licensed Professional Engineerunder the laws of the state of Minnesota.GABMTH01.19.202412236128RevisionsDescriptionDateNumFEDCBA12345678MNStillwater Area PublicSchools ISD #834NEW LAKE ELMOELEMENTARYSCHOOL1875 Greeley Street SouthStillwater, MN 55082Lake Elmo, MN 55042P:\Projects\Projects - 2023\12236128 - New Stillwater Elementary School - Wold\C. Design\Drawing Files - Lake Elmo\12236128 - C000 Overall Plan.dwg
01/19/2024 - LAKE ELMO ELEMENTARYZONING MAP AMENDMENT SUBMISSION(CONCEPTUAL PLAN - DO NOT USEFOR CONSTUCTION)C000CONCEPTUAL -ZONING ANDPROPERTYINFO PLANPROPOSED ROADWAY/TRAILSBITUMINOUS PAVEMENTPROPOSED HEAVY-DUTYBITUMINOUS PAVEMENTPROPOSED CONCRETE PAVEMENTEASEMENT LINERIGHT-OF-WAY LINEPROPERTY LINE
SB7 DSB4 DSB3 DSB2 DSB5 ASB6 ASB1 CSB8 DSB9 BC.S.A.H. NO. 17 (LAKE ELMO AVE. N.)C.S.A.H. NO. 10 (10TH STREET NORTH)122826262819222124PLAYGROUNDSTORMWATERBASIN #4STORMWATER
BASIN #3
STORMWATERBASIN #1OPEN FIELD15NEW ELEMENTARYFFE: 932.00 (ARCH: 100'-0")STORMWATERBASIN #2NOTE THE PROPOSED BUILDING IS FORREFERENCE ONLY AND IS NOT THE FINAL DESIGN24'18'24'36'24'18'24'24'18'24'36'24'18'24'24'2
4
'39'206 PARKING STALLS,STALLS SHOWN ARE A TYPICALOF 18' LONG X 9' WIDEDRIVE LANES SHOWN ARE ATYPICAL OF 24' WIDEONE-WAY STUDENTDROP OFF LANESMAIN ENTRANCEBUSES AND TRUCKSENTRANCE ONLYSTUDENT DROP-OFFAND TEACHER PARKINGENTRANCELOADING/UNLOADINGZONE24'33'15 BUS PARKINGSTALLS24'20'ADDITIONAL R.O.W.DEDICATIONADDITIONAL R.O.W.DEDICATION50'75'
50'75'50'75'50'75'50'75'2 LITTLE LEAGUE /SOFTBALL FIELDS6' FENCE ADJACENTTO GUN RANGESYMBOL LEGENDPROPOSED ROADWAY/TRAILSBITUMINOUS PAVEMENTPROPOSED HEAVY-DUTYBITUMINOUS PAVEMENTPROPOSED CONCRETE PAVEMENTSOIL BORING MARKERPROJECT AREA CALCULATIONSTOTAL SITE AREA:2,072,858 SF(47.59 AC)100%IMPERVIOUS AREAS:NEW SCHOOL 148,000 SF(3.40 AC)7.14%SIDEWALK/BIT. TRAILS34,886 SF(0.80 AC)1.68%PARKING/ROADWAYS174,764 SF (4.01 AC)8.43%SPORTFIELDS/PLAYGROUND49,228 SF(1.13 AC)2.37%TOTAL NEW IMPERVIOUS406,878 SF(9.34 AC)19.63%EXISTING ROADWAY60,687 SF(1.39 AC)2.93%(10 ST N & LAKE ELMO AVE N)TOTAL EXISTING IMPERVIOUS60,687 SF(1.39 AC)2.93%TOTAL SITE IMPERVIOUS467,565 SF(10.73 AC)22.56%STORMWATER BASINS:BASIN #18,668 SF (0.20 AC)0.42%BASIN #218,649 SF(0.43 AC)0.90%BASIN #323,648 SF(0.54 AC)1.14%BASIN #423,347 SF(0.54 AC)1.13%TOTAL BASIN AREA74,312 SF(1.71 AC)3.59%RIGHT OF WAY:EXISTING R.O.W.142,035 SF(3.26 AC)6.85%PROPOSED R.O.W.211,177 SF (4.85 AC)10.19%ADDITIONAL R.O.W DEDICATION 69,142 SF (1.59 AC)3.33%OPEN SPACE:REMAINING OPEN SPACE1,380,491 SF (31.69 AC)66.60%EASEMENT LINERIGHT-OF-WAY LINEPROPERTY LINE3524 Labore RoadWhite Bear Lake, MN 55110651.481.9120 (f) 651.481.9201www.larsonengr.comC 2024 Larson Engineering, Inc. All rights reserved.3524 Labore RoadWhite Bear Lake, MN 55110651.481.9120 (f) 651.481.9201www.larsonengr.comLarsonEngineering, Inc.0NORTH3060120NorthCheck:Drawn:Date:Comm:Scale:Greg A. Buchal, P.E.Date: Lic. No.:01.19.202423793I hereby certify that this plan, specifications or reportwas prepared by me or under my direct supervisionand that I am a duly licensed Professional Engineerunder the laws of the state of Minnesota.GABMTH01.19.202412236128RevisionsDescriptionDateNumFEDCBA12345678MNStillwater Area PublicSchools ISD #834NEW LAKE ELMOELEMENTARYSCHOOL1875 Greeley Street SouthStillwater, MN 55082Lake Elmo, MN 55042P:\Projects\Projects - 2023\12236128 - New Stillwater Elementary School - Wold\C. Design\Drawing Files - Lake Elmo\12236128 - C100 Paving.dwg
01/19/2024 - LAKE ELMO ELEMENTARYZONING MAP AMENDMENT SUBMISSION(CONCEPTUAL PLAN - DO NOT USEFOR CONSTUCTION)C100CONCEPTUAL -SITE PLANSB1
C.S.A.H. NO. 17 (LAKE ELMO AVE. N.)C.S.A.H. NO. 10 (10TH STREET NORTH)122826262819222124PLAYGROUND15NEW ELEMENTARYFFE: 932.00 (ARCH: 100'-0")NOTE THE PROPOSED BUILDING IS FORREFERENCE ONLY AND IS NOT THE FINAL DESIGN900905910915920923923919919923923924926925927928929928927930925920920924924920915910930
931
929
928
927
926
925
930
929
928
927
926
93092992892792692592093193
0
92
9
93
1
93
2
93
3933932931931
935939932933933932931930929928929930935940935940929
928
9309309299289259269279289299
2
5
9
2
6
9249259269279289269269259249219259249209
2
7
9
2
2926920922916 927926927928930929925920922.25 TC921.75 GL922.30 TC921.80 GL930.50 TC930.00 GL932.00 FFE923.00 TC922.50 GL922.76 TC922.26 GL932.00 FFE926.00 TC925.50 GL924.75 TC924.25 GL931.75 TS928.00 C928.25 TC927.75 GL929.75 TC929.25 GL929.10 TC928.60 GL927.90 TC927.40 GL931.50 TC931.00 GL928.50 TC928.00 GL927.50 TC927.00 GL931.25 TC930.75 GL928.25 TC927.75 GL933.75 TC933.25 GL931.00 TC930.50 GL932.70 TC932.20 GL932.70 TC932.20 GL932.10 TC931.60 GL929.25 TC928.75 GL929.75 TC929.25 GL926.75 TC926.25 GL926.75 TC926.25 GL927.25 TC926.75 GL924.25 TC923.75 GL934.25 TC933.75 GL934.50 TC934.00 GL934.50 TC934.00 GL932.00 TC931.50 GL932.50 TC932.00 GL932.00 FFE932.00 FFE932.00 FFE924930934934932EXISTING LANDLOCKED INFILTRATIONAREA, AREA WILL BE DESIGNED TOMEET THE VBWD STANDARDSEXISTING LANDLOCKED INFILTRATIONAREA, AREA WILL BE DESIGNED TOMEET THE VBWD STANDARDS150' (TYP.)15
0
'
(
T
Y
P
.
)1.Tree protection consisting of snow fence or safety fence installed at the drip line shall be in place prior to beginningany grading or demolition work at the site.2.All elevations with an asterisk (*) shall be field verified. If elevations vary significantly, notify the Engineer forfurther instructions.3.Grades shown in paved areas represent finish elevation.4.All construction shall be performed in accordance with state and local standard specifications for construction.5.Permittees must not excavate infiltration systems to final grade, or within three (3) feet of final grade, until thecontributing drainage area has been constructed and fully stabilized unless they provide rigorous erosionprevention and sediment controls (e.g., diversion berms) to keep sediment and runoff completely away from theinfiltration area.GRADING NOTESPROPOSED CONTOURS - MAJOR INTERVALGRADE BREAK LINEPROPOSED CONTOURS - MINOR INTERVAL949950950EXISTING CONTOURS2.0%950.00 TC949.50 GLGRADE SLOPESPOT ABBREVIATIONS:TC - TOP OF CURBGL - GUTTER LINEB - BITUMUNOUSC - CONCRETESYMBOL LEGENDSYMBOL LEGENDCITY OF LAKE ELMOSITE RESTORATION PLAN NOTES1.RESTORE ALL DISTURBED AREAS WITH 6 INCHES OF TOPSOIL CONFORMING TO MNDOT 3877.2.PROTECT ALL STORM SEWER INLETS AS SPECIFIED HEREIN AND MAINTAIN UNTIL STREETCONSTRUCTION IS COMPLETED.3.MAINTAIN ALL SILT FENCE AND REPAIR OR REPLACE AS NEEDED OR REQUIRED UNTIL TURF HAS BEENESTABLISHED.4.RESTORATION WORK SHALL BEGIN WITHIN 7 DAYS OF FINAL GRADING.5.BOULEVARD AND DITCH RESTORATION INCLUDES FINE GRADING, WHICH INCLUDES THE REMOVAL OF ROCKS,DEBRIS AND SOIL CHUNKS, WHILE MAINTAINING POSITIVE DRAINAGE.1.THE CONTRACTOR SHALL CONDUCT OPERATIONS AND IMPLEMENT MINNESOTA POLLUTION CONTROL AGENCY (MPCA)BEST MANAGEMENT PRACTICES (BMP) TO CONTROL SITE SILTATION AND EROSION INTO DRAINAGE WAYS. THECONTRACTOR SHALL COMPLY WITH ALL CONDITIONS AND COMPLETION DATES RELATIVE TO ALL PERMITS ISSUED FORTHE WORK TO BE COMPLETED. THE ENGINEER MAY ISSUE A STOP WORK ORDER FOR ALL DEVELOPMENT WORK ANDBUILDING CONSTRUCTION FOR NONCOMPLIANCE WITH THESE MEASURES.2.SEQUENCING. ALL SILT FENCE AND OTHER EROSION CONTROL MEASURES SHALL BE IN PLACE AND APPROVED BYENGINEER PRIOR TO ANY REMOVALS, EXCAVATION OR CONSTRUCTION AND SHALL BE MAINTAINED UNTIL VIABLE TURFOR GROUND COVER HAS BEEN ESTABLISHED AND APPROVED BY THE ENGINEER.3.SILT FENCE. THE CONTRACTOR SHALL INSTALL SILT FENCE AT THE LOCATIONS SHOWN ON THE PLANS AND INACCORDANCE WITH THE CITY STANDARD DETAILS. SILT FENCE DAMS AND INTERIM SUMPS SHALL BE PLACED TOINTERCEPT SILT FROM CONCENTRATED RUNOFF FROM OPEN GRADED AREAS. ADDITIONAL SILT FENCE SHALL BEREQUIRED AS DIRECTED BY THE ENGINEER.4.STOCKPILES. ALL STOCKPILE AREAS SHALL HAVE SILT FENCE OR SEDIMENT TRAPPING SYSTEMS PLACED AROUND THEENTIRE PERIMETER.5.INLET PROTECTION. THE CONTRACTOR SHALL INSTALL INLET PROTECTION ON ALL EXISTING STORM SEWER INLETS INACCORDANCE WITH THE CITY STANDARD DETAILS. INLET PROTECTION SHALL ALSO BE PROVIDED ON ALL PROPOSEDSTORM SEWER INLETS IMMEDIATELY FOLLOWING CONSTRUCTION OF THE INLET. INLET PROTECTION MUST BEINSTALLED IN A MANNER THAT WILL NOT IMPOUND WATER FOR EXTENDED PERIODS OF TIME OR IN A MANNER THATPRESENTS A HAZARD TO VEHICULAR OR PEDESTRIAN TRAFFIC.6.TEMPORARY SEDIMENT BASINS. THE CONTRACTOR SHALL INCORPORATE TEMPORARY SEDIMENT BASINS THROUGHOUTTHE CONSTRUCTION SITE TO CAPTURE RUNOFF AND SLOW THE FLOW OF WATER AND ALLOW SEDIMENT TO SETTLEOUT. TEMPORARY SEDIMENT BASINS SHALL BE INSTALLED AS DIRECTED BY THE CITY ENGINEER.7.ROCK CONSTRUCTION ENTRANCE. A ROCK ENTRANCE SHALL BE CONSTRUCTED AND MAINTAINED AS SHOWN ON THEPLAN TO REDUCE TRACKING OF SILT AND DIRT ONTO THE PUBLIC STREETS. A GEOTEXTILE FABRIC SHALL BE PLACEDUNDERNEATH THE ROCK. THE ROCK SHALL BE PERIODICALLY REPLENISHED TO MAINTAIN THE INTENDEDPERFORMANCE. MUD AND DEBRIS SHALL BE REMOVED OR SCRAPED FROM TIRES AND VEHICLE UNDERCARRIAGE PRIORTO LEAVING THE SITE.8.STREET SWEEPING. ALL STREETS USED FOR ACCESS TO THE SITE AND HAUL ROUTES USED FOR CONSTRUCTIONEQUIPMENT AND MATERIAL SUPPLIES SHALL BE CLEANED AT THE END OF EACH WORKING DAY. THE CITY OR ENGINEERMAY ORDER ADDITIONAL SWEEPING OF THE STREETS AS DEEMED REQUIRED AT DEVELOPER/CONTRACTOR EXPENSE.9.DEWATERING. EACH EXCAVATION SHALL BE KEPT DRY DURING THE COURSE OF ALL WORK HEREIN, INCLUDINGSUBGRADE CORRECTION, PIPE INSTALLATION, STRUCTURE CONSTRUCTION AND BACKFILLING, TO THE EXTENT THAT NODAMAGE FROM HYDROSTATIC PRESSURE, FLOATATION OR OTHER DAMAGE RESULTS. ALL EXCAVATIONS SHALL BEDEWATERED TO A DEPTH OF AT LEAST 3 INCHES BELOW THE BOTTOM OF THE CONCRETE SLAB OR PIPE TO BEINSTALLED THEREIN. THE CONTRACTOR MAY USE ANY METHOD OR COMBINATION OF METHODS FOR DEWATERING HECHOOSES; HOWEVER, ALL DEWATERING METHODS AND EQUIPMENT WHICH IN THE OPINION OF THE ENGINEER, AREINEFFECTIVE SHALL BE ABANDONED, IMPROVED, REPLACED OR THERWISE ALTERED TO OBTAIN EFFECTIVEDEWATERING. THE CONTRACTOR SHALL PROVIDE ALL POWER, PUMPS, MATERIALS AND APPARATUS NECESSARY, ANDSHALL BE RESPONSIBLE FOR DISPOSING OF THE WATER PUMPED FROM THE EXCAVATION IN A MANNER WHICH WILL NOTINTERFERE WITH OTHER WORK WITHIN THE AREA AND NOT TO DAMAGE PUBLIC OR PRIVATE PROPERTY. THECONTRACTOR WILL BE HELD RESPONSIBLE FOR THE CONDITION OF ANY PIPE, CONDUIT, DITCH, CHANNEL OR NATURALWATERCOURSE UTILIZED FOR DRAINAGE PURPOSES, AND ALL EROSION, SEDIMENT OR OTHER ADVERSE RESULTS OFTHEIR USE SHALL BE REPAIRED.10.POSITIVE DRAINAGE AND PROTECTION. THE CONTRACTOR SHALL MAINTAIN POSITIVE DRAINAGE THROUGHOUT THESITE AT ALL TIMES. LOW POINTS WITHIN AND ALONG ROADWAYS ARE EXPRESSLY PROHIBITED. THE CONTRACTORSHALL BE RESPONSIBLE FOR TEMPORARY DITCHES, PIPING OR OTHER MEANS TO FACILITATE PROPER DRAINAGEDURING CONSTRUCTION. TO PROTECT PREVIOUSLY GRADED AREAS FROM EROSION, WOOD FIBER BLANKET SHALL BEPLACED IMMEDIATELY ON STEEP SLOPES (1:3 OR GREATER) AND EMBANKMENTS, PERMANENT AND TEMPORARY PONDS,AND OUTLETS AND OVERFLOWS TO PROTECT THE COMPLETED GRADE AND MINIMIZE SILT IN THE RUNOFF.11.DRAINAGE DITCHES. THE NORMAL WETTED PERIMETER OF ANY TEMPORARY OR PERMANENT DRAINAGE DITCH ORSWALE THAT DRAINS WATER FROM ANY PORTION OF THE CONSTRUCTION SITE, OR DIVERTS WATER AROUND THE SITE,MUST BE STABILIZED WITHIN 200 LINEAL FEET FROM THE PROPERTY EDGE, OR FROM THE POINT OF DISCHARGE INTOANY SURFACE WATER. STABILIZATION OF THE LAST 200 LINEAL FEET MUST BE COMPLETED WITHIN 24 HOURS AFTERCONNECTING TO A SURFACE WATER. STABILIZATION OF THE REMAINING PORTIONS OF ANY TEMPORARY ORPERMANENT DITCHES OR SWALES MUST BE COMPLETE WITHIN 14 DAYS AFTER CONNECTING TO A SURFACE WATER ANDCONSTRUCTION IN THAT PORTION OF THE DITCH HAS TEMPORARILY OR PERMANENTLY CEASED. TEMPORARY ORPERMANENT DITCHES OR SWALES THAT ARE BEING USED AS A SEDIMENT CONTAINMENT SYSTEM (WITH PROPERLYDESIGNED ROCK DITCH CHECKS, BIO ROLLS, SILT DIKES, ETC.) DO NOT NEED TO BE STABILIZED. THESE AREAS MUST BESTABILIZED WITHIN 24 HOURS AFTER NO LONGER BEING USED AS A SEDIMENT CONTAINMENT SYSTEM.12.TURF ESTABLISHMENT. ALL EXPOSED SOIL AREAS MUST BE STABILIZED AS SOON AS POSSIBLE TO LIMIT SOIL EROSIONBUT IN NO CASE LATER THAN 14 DAYS AFTER THE CONSTRUCTION ACTIVITY IN THAT PORTION OF THE SITE HASTEMPORARILY OR PERMANENTLY CEASED.13.MAINTENANCE AND INSPECTION. EROSION CONTROL MEASURES SHALL BE MAINTAINED THROUGHOUT THECONSTRUCTION AND UNTIL SATISFACTORY ESTABLISHMENT OF PERMANENT GROUND COVER IS OBTAINED. ALLEROSION AND SEDIMENTATION CONTROL MEASURES, AND STORMWATER OUTFALLS MUST BE INSPECTED WEEKLY, ANDWITHIN 24 HOURS OF THE SITE RECEIVING 0.5 INCHES OF RAIN. REPAIRS MUST BE MADE ON THE SAME DAY ORFOLLOWING DAY OF THE INSPECTION. UNSATISFACTORY CONDITIONS NOT REPAIRED OR CLEANED UP WITHIN48-HOURS OF NOTIFICATION SHALL RESULT IN A STOP WORK ORDER, AND/OR SAID WORK SHALL BE COMPLETED ATCONTRACTOR'S EXPENSE.14.REMOVAL. THE CONTRACTOR SHALL REMOVE AND DISPOSE OF ALL TEMPORARY EROSION CONTROL MEASURES,STRUCTURES AND DEVICES ONLY AFTER RECEIVING ENGINEER APPROVAL. ALL DEBRIS, STAKES, AND SILTS ALONG SILTFENCES SHALL BE REMOVED AND DISPOSED OFF SITE. THE CONTRACTOR SHALL HAND RAKE SILTED AREAS ALONG THEFENCE LOCATIONS TO PROVIDE A SMOOTH FINAL GRADE AND SHALL RESTORE THE GROUND SURFACE WITH SEED ORSOD, AS REQUIRED, TO MATCH THE FINISHED GRADE TO THE ADJACENT AREA.15.FINAL STORM SEWER SYSTEM. AT THE COMPLETION OF THE WORK AND BEFORE THE FINAL WALK THROUGH, THECONTRACTOR SHALL REMOVE STORM SEWER INLET PROTECTION MEASURES AND THOROUGHLY FLUSH THE STORMSEWER SYSTEM. SEDIMENT AND DEBRIS SHALL BE COMPLETELY REMOVED AND CLEANED AT THE INLETS, OUTLETS, ANDDOWNSTREAM OF EACH OUTLET. RIPRAP AND GEOTEXTILE FABRIC MAY REQUIRE REPLACEMENT AS DIRECTED BY THEENGINEER TO OBTAIN A LIKE NEW INSTALLATION ACCEPTABLE TO THE CITY16.DITCH CHECK (BIOROLL BLANKET SYSTEM). BIOROLL AND BLANKET SYSTEMS SHALL BE INSTALLED AS DITCH CHECKSONLY IN SPECIFIED LOCATIONS AS APPROVED BY THE CITY ENGINEER. BIOROLLS ARE NOT TO BE UTILIZED IN AREASWHERE VEHICLE AND CONSTRUCTION TRAFFIC OCCUR.17.FLOTATION SILT CURTAIN. FLOTATION SILT CURTAIN SHALL BE UTILIZED WHEN CONSTRUCTION ACTIVITIES OCCURDIRECTLY ADJACENT TO LAKES, STREAMS OR WETLANDS IN ORDER TO CONTAIN SEDIMENTS NEAR THE BANKS OFWORKING AREAS. THE INSTALLATION OF FLOTATION SILT CURTAINS WILL BE REQUIRED AS DIRECTED BY THE CITYENGINEER.18.CONCRETE WASHOUT ONSITE. ALL LIQUID AND SOLID WASTES GENERATED BY CONCRETE WASHOUT OPERATIONS MUSTBE CONTAINED IN A LEAK-PROOF CONTAINMENT FACILITY OR IMPERMEABLE LINER. A COMPACTED CLAY LINER THATDOES NOT ALLOW WASHOUT LIQUIDS TO ENTER GROUND WATER IS CONSIDERED AN IMPERMEABLE LINER. THE LIQUIDAND SOLID WASTES MUST NOT CONTACT THE GROUND, AND THERE MUST NOT BE RUNOFF FROM THE CONCRETEWASHOUT OPERATIONS OR AREAS. LIQUID AND SOLID WASTES MUST BE DISPOSED OF PROPERLY AND IN COMPLIANCEWITH MPCA REGULATIONS. A SIGN MUST BE INSTALLED ADJACENT TO EACH WASHOUT FACILITY TO INFORM CONCRETEEQUIPMENT OPERATORS TO UTILIZE THE PROPER FACILITIES.CITY OF LAKE ELMO GRADING ANDEROSION STANDARD PLAN NOTESEO - EMERGENCY OVERFLOWTW - TOP OF WALLBW - BOTTOM OF WALL (F/G)(*) - EXISTING TO BE VERIFIED3524 Labore RoadWhite Bear Lake, MN 55110651.481.9120 (f) 651.481.9201www.larsonengr.comC 2024 Larson Engineering, Inc. All rights reserved.3524 Labore RoadWhite Bear Lake, MN 55110651.481.9120 (f) 651.481.9201www.larsonengr.comLarsonEngineering, Inc.0NORTH3060120NorthCheck:Drawn:Date:Comm:Scale:Greg A. Buchal, P.E.Date: Lic. No.:01.19.202423793I hereby certify that this plan, specifications or reportwas prepared by me or under my direct supervisionand that I am a duly licensed Professional Engineerunder the laws of the state of Minnesota.GABMTH01.19.202412236128RevisionsDescriptionDateNumFEDCBA12345678MNStillwater Area PublicSchools ISD #834NEW LAKE ELMOELEMENTARYSCHOOL1875 Greeley Street SouthStillwater, MN 55082Lake Elmo, MN 55042P:\Projects\Projects - 2023\12236128 - New Stillwater Elementary School - Wold\C. Design\Drawing Files - Lake Elmo\12236128 - C200 Grading.dwg
01/19/2024 - LAKE ELMO ELEMENTARYZONING MAP AMENDMENT SUBMISSION(CONCEPTUAL PLAN - DO NOT USEFOR CONSTUCTION)C200CONCEPTUAL -GRADING PLAN
C.S.A.H. NO. 17 (LAKE ELMO AVE. N.)C.S.A.H. NO. 10 (10TH STREET NORTH)122826262819222124PLAYGROUNDSTORMWATERBASIN #4STORMWATER
BASIN #3
STORMWATERBASIN #1OPEN FIELD15NEW ELEMENTARYFFE: 932.00 (ARCH: 100'-0")STORMWATERBASIN #2NOTE THE PROPOSED BUILDING IS FORREFERENCE ONLY AND IS NOT THE FINAL DESIGNBASIN #1 OUTLETBASIN #2 OUTLETGRADING WILL MAINTAIN A DITCH SECTION TOSERVICE RESIDENTIAL LOTS SOUTH OF 10TH ST NAND SERVE AS AN OUTLET FOR BASIN #2EXISTING LANDLOCKED INFILTRATIONAREA, AREA WILL BE DESIGNED TOMEET THE VBWD STANDARDSBASIN #3 OUTLETBASIN #4 OUTLETGRAVITY SANITARYSEWER SYSTEMCONNECT TO EXISTING SANITARY FORCE MAIN(ONGOING COORDINATION WITH THE CITY OF LAKEELMO FOR HOW THIS CONNECTION SHALL BE MADE)HYDRANT (TYP.)W/ 150' SERVICE RADIUS150' (TYP.)1
5
0
'
(
T
Y
P
.
)8" WM8" WM6" SAN8" WM8" WM8" WM8" WM8" WMHYDRANT (TYP.)W/ 150' SERVICE RADIUSEXISTING LANDLOCKED INFILTRATIONAREA, AREA WILL BE DESIGNED TOMEET THE VBWD STANDARDSCABLE UNDERGROUND LINEFIBER OPTIC UNDERGROUND LINEELECTRIC UNDERGROUND LINEELECTRIC OVERHEAD LINETELEPHONE UNDERGROUND LINESTORM SEWER PIPESANITARY SEWER PIPENATURAL GAS UNDERGROUND LINEWATERMAIN PIPEDRAINTILE PIPECITY OF LAKE ELMO'S STANDARD PLANNOTES FOR SANITARY SEWER PLANSSYMBOL LEGEND1.ALL SANITARY SEWER AND ACCESORIES MUST BE CONSTRUCTED INACCORDANCE WITH THE CITY OF LAKE ELMO STANDARD SPECIFICATIONS ANDDETAILS.2.ALL SANITARY SEWER PVC PIPE SHALL BE INSTALLED IN ACCORDING TO CITY OFSTANDARD DRAWING 103 "GRANULAR MATERIAL BEDDING METHOD" (FOR PVCSANITARY SEWER PIPE).3.UNLESS NOTED OTHERWISE, ALL SMOOTH WALLED SANITARY SEWER PVC PIPEAND FITTINGS SHALL BE SDR 35 WITH ELASTOMETRIC GASKETED JOINTS.4.ALL SANITARY SEWER SERVICES SHALL BE 4-INCH PVC, SCH. 40.5.SMOOTH WALLED PVC PIPE AND FITTINGS SHALL CONFORM WITH THEREQUIREMENTS OF ASTM D-3034 FOR THE SIZE, STANDARD DIMENSION RATION(SDR), AND STRENGTH REQUIREMENTS INDICATED ON THE PLANS,SPECIFICATIONS, AND SPECIAL PROVISIONS.6.REINFORCED CONCRETE PIPE AND FITTINGS SHALL CONFORM WITH THEREQUIREMENTS OF MnDOT SPEC 3236 (REINFORCED CONCRETE PIPE) FOR THETYPE, SIZE, AND STRENGTH CLASS SPECIFIED HEREIN.7.JOINTS OF MANHOLE RISER SECTIONS SHALL BE TONGUE AND GROOVE WITHRUBBER "O" RING JOINTS PROVIDED ON ALL SANITARY SEWER MANHOLES.8.SANITARY SEWER INLET AND OUTLET PIPES SHALL BE JOINED TO THE MANHOLEWITH A GASKETED, FLEXIBLE, WATERTIGHT CONNECTION TO ALL DIFFERENTIALSETTLEMENT OF THE PIPE AND MANHOLE.9.A 1'-0" TO 1'-4" MANHOLE SECTION SHALL BE INSTALLED UNDER THE CONESECTION TO ALLOW FOR HEIGHT ADJUSTMENT WHENEVER POSSIBLE.10.ALL SERVICE LINE STUBS MUST HAVE 2" x 2" HARDWOOD MARKER WITH METALSPIKE RUNNING FROM THE END OF PIPE TO FINISHED GRADE ELEVATION.11.UPON MARKING A CONNECTION TO AN EXISTING SANITARY SEWER STUB ORMANHOLE, DIRT AND DEBRIS SHALL BE PREVENTED FROM ENTERING THEEXISTING SEWER BY IMMEDIATELY INSTALLING WATERTIGHT PLUGS AS NEEDEDIN THE EXISTING MANHOLE.12.ALL MAINLINE SANITARY SEWER AND SERVICES SHALL HAVE TRACER WIRE PERCITY SPECIFICATIONS AND DETAILS.EASEMENT LINESETBACK LINERIGHT-OF-WAY LINEPROPERTY LINECITY OF LAKE ELMO'S STANDARD PLANNOTES FOR WATERMAIN PLANS1.ALL WATERMAIN AND ACCESSORIES MUST BE CONSTRUCTED IN ACCORDANCEWITH THE CITY OF LAKE ELMO STANDARD SPECIFICATIONS AND DETAILS.2.MANIPULATION OF EXISTING VALVES SHALL BE PERFORMED ONLY BY CITYPERSONNEL.3.WATERMAIN SHALL BE DUCTILE IRON PIPE, ENCASED IN POLYETHYLENE,CLASS--52.4.ALL FITTINGS SHALL COMPLY WITH CEAM SPEC. 2611.2.A1. ALL FITTINGS SHALL BEDUCTILE IRON PIPE WITH POLYETHYLENE ENCASEMENT. ALL CONNECTIONS SHALLBE INSTALLED UTILIZING COR -- BLUE NUTS & BOLTS.5.USE GATE VALVES FOR ALL APPLICATIONS UP THROUGH 12 INCHES.6.GATE VALVES SHALL BE RESILIENT WEDGE AMERICAN FLOW CONTROL SERIES2500 OR APPROVED EQUAL. GATE VALVES MUST COMPLY WITH CEAM SPEC2611.2.C.2.7.USE BUTTERFLY VALVES FOR ALL APPLICATIONS GREATER THAN 12INCHES.8.BUTTERFLY VALVES SHALL BE MUELLER LINESEAL III, OR APPROVED EQUAL.BUTTERFLY VALVES SHALL COMPLY WITH CEAM SPEC. 26 11.2.CA.9.BOLTS AND NUTS ON ALL VALVES AND HYDRANTS SHALL BE STAIN LESS STEEL.10.ALL HYDRANTS SHALL BE INSTALLED 5.0 FEET BACK OF CURB.11.HYDRANTS SHALL BE WATEROUS "PACER," MODEL WB-67 OR APPROVEDEQUAL, FITTED WITH FH 800 SERIES FLEX STAKE AND PAINTED RED.12.HYDRANTS SHALL HAVE TWO OUTLET NOZZLES FOR 2- 12 (1. D.) HOSECONNECTIONS ANDONE 4" STORZ NOZZLE (MODEL WB--67) AND PENTAGON NUT END CAP.13.THE CURB STOP SERVICE ASSEMBLY SHALL HAVE A MINIMUM 1 -- FT ADJUSTMENTRANGE AND SHALLEXTEND 6 INCHES ABOVE FINISHED GRADE FULLY EXTENDED.14.THE CONTRACTOR SHALL BE RESPONSIBLE FOR PROVIDING WATER TO HOMESAND BUSINESSESWHOSE WATER SUPPLY IS DISRUPTED DURING THE COURSE OF THE PROJECT.LIGHT POLESTORM MANHOLEFLARED ENDCURB INLETCATCH BASINWATER SHUTOFFGATE VALVE & BOXHYDRANTSANITARY MANHOLE3524 Labore RoadWhite Bear Lake, MN 55110651.481.9120 (f) 651.481.9201www.larsonengr.comC 2024 Larson Engineering, Inc. All rights reserved.3524 Labore RoadWhite Bear Lake, MN 55110651.481.9120 (f) 651.481.9201www.larsonengr.comLarsonEngineering, Inc.0NORTH3060120NorthCheck:Drawn:Date:Comm:Scale:Greg A. Buchal, P.E.Date: Lic. No.:01.19.202423793I hereby certify that this plan, specifications or reportwas prepared by me or under my direct supervisionand that I am a duly licensed Professional Engineerunder the laws of the state of Minnesota.GABMTH01.19.202412236128RevisionsDescriptionDateNumFEDCBA12345678MNStillwater Area PublicSchools ISD #834NEW LAKE ELMOELEMENTARYSCHOOL1875 Greeley Street SouthStillwater, MN 55082Lake Elmo, MN 55042P:\Projects\Projects - 2023\12236128 - New Stillwater Elementary School - Wold\C. Design\Drawing Files - Lake Elmo\12236128 - C300 Sanitary And WM.dwg
01/19/2024 - LAKE ELMO ELEMENTARYZONING MAP AMENDMENT SUBMISSION(CONCEPTUAL PLAN - DO NOT USEFOR CONSTUCTION)C300CONCEPTUAL -UTILITY PLAN
C.S.A.H. NO. 17 (LAKE ELMO AVE. N.)C.S.A.H. NO. 10 (10TH STREET NORTH)122826262819222124PLAYGROUNDSTORMWATERBASIN #4STORMWATER
BASIN #3
STORMWATERBASIN #1OPEN FIELD15NEW ELEMENTARYFFE: 932.00 (ARCH: 100'-0")STORMWATERBASIN #2NOTE THE PROPOSED BUILDING IS FORREFERENCE ONLY AND IS NOT THE FINAL DESIGN33'50'75'SCREENING TREESSCREENING TREESSCREENING TREESSCREENING TREESSCREENING TREESSCREENING TREES3524 Labore RoadWhite Bear Lake, MN 55110651.481.9120 (f) 651.481.9201www.larsonengr.comC 2024 Larson Engineering, Inc. All rights reserved.3524 Labore RoadWhite Bear Lake, MN 55110651.481.9120 (f) 651.481.9201www.larsonengr.comLarsonEngineering, Inc.0NORTH3060120NorthCheck:Drawn:Date:Comm:Scale:Greg A. Buchal, P.E.Date: Lic. No.:01.19.202423793I hereby certify that this plan, specifications or reportwas prepared by me or under my direct supervisionand that I am a duly licensed Professional Engineerunder the laws of the state of Minnesota.GABMTH01.19.202412236128RevisionsDescriptionDateNumFEDCBA12345678MNStillwater Area PublicSchools ISD #834NEW LAKE ELMOELEMENTARYSCHOOL1875 Greeley Street SouthStillwater, MN 55082Lake Elmo, MN 55042P:\Projects\Projects - 2023\12236128 - New Stillwater Elementary School - Wold\C. Design\Drawing Files - Lake Elmo\12236128 - C400 Landscape Plan.dwg
01/19/2024 - LAKE ELMO ELEMENTARYZONING MAP AMENDMENT SUBMISSION(CONCEPTUAL PLAN - DO NOT USEFOR CONSTUCTION)C400CONCEPTUAL -LANDSCAPINGPLANSYMBOL LEGENDEASEMENT LINERIGHT-OF-WAY LINEPROPERTY LINEGENERAL1.Landscape areas to have 4" colored hardwood wood mulch over weed barrierfabric and 6" black steel edging as needed.2.All trees not planted in landscaped areas shall have shredded hardwood mulchplaced around the tree at 4' diameter and 6" deep.3.All disturbed areas to receive 6" of good quality topsoil and seed or sod asindicated. See Landscape Plan.4.Landscape Contractor is responsible for coordination with the GeneralContractor, to protect the new improvements on and off-site during landscapework activities. Report any damage to the General Contractor immediately.5.Plant size and species substitutions must be approved in writing prior toacceptance in the field.6.Landscape Contractor is responsible for ongoing maintenance of all newlyinstalled material until time of owner acceptance. Any acts of vandalism ordamage which may occur prior to owner acceptance shall be the responsibilityof the contractor. Contractor shall provide the owner with a maintenanceprogram including, but not limited to, pruning, fertilization and disease/pestcontrol.7.Landscape Contractor shall provide the owner with a watering scheduleappropriate to the project site conditions and to plant material growthrequirements.8.Landscape Contractor shall guarantee newly planted material through onecalendar year from the date of written owner acceptance. Plants that exhibitmore than 10% die-back damage shall be replaced at no additional cost to theowner. The contractor shall also provide adequate tree wrap and deer/rodentprotection measures for the plantings during the warranty period.9.There will be no site irrigation until the summer of 2024, any watering prior tosummer 2024 will be the responsibility of the contractor. Contractor to workwith the District on irrigation install at time of final grade, but prior to siterestoration.LANDSCAPING NOTESSTORMWATER SEED MIXLANDSCAPE AREASODPLANTING SCHEDULE2-1/2" CalB & BAmerican ElmUlmus AmericanaCOMMON NAMEBOTANICAL NAMESIZECONTAINERQTYRoundleaf ServiceberryAmelanchier Sanguinea24"PotBush CinquefoilPotentilla Fruticosa24"PotCrisp Leaf SpireaSpirea x Bumalda (Crispa)24"6' Ht6' HtB & BB & BAmerican LarchLarix LaricinaNorthern White CedarThuja Occidentallis52873524100101DECIDUOUS TREES, SEE DETAIL 6/C602SHRUBS, SEE DETAIL X/CX00CONIFEROUS TREES, SEE DETAIL 6/C6022-1/2" CalB & BBur OakQuercus Macrocarpa256' HtB & B96Eastern White PinePinus StrobusPotNote: The landscape plan has not been developed in accordance with theCity of Lake Elmos Standards. This landscape plan is conceptual andongoing coordination will be had with the City of Lake Elmo to bring thisplan in accordance with their standards.
PAGE 1 of 3
MEMORANDUM
Date: January 31, 2024
To: Sophia Jensen, City Planner Re: ISD 834 Lake Elmo Elementary School
Cc: Nathan Fuerst, Planning Consultant PID 26‐029‐21‐44‐0001
Marty Powers, Public Works Director Comprehensive Plan Amendment/Rezoning
Chad Isakson, PE, Assistant City Engineer
From: Jack Griffin, PE, City Engineer
Engineering has reviewed the ISD 834 Lake Elmo Elementary School Site Plans to be located at the corner of Lake
Elmo Avenue (CSAH 17) and 10 Street (CSAH 10). The review consisted of the following documentation received
on January 24, 2024:
Comprehensive Plan Amendment/Rezoning Narrative dated January 18, 2024.
Site Survey dated December 19, 2023.
Conceptual Site Plans, Sheets C000, C100, C200, C300, and C400, dated January 19, 2024.
APPLICATION NARRATIVE AND SITE PLAN SUMMARY
1. 1,100‐student elementary school building. 148,000 SF 2‐story building.
2. Located on 47.6 acres at northwest corner of Lake Elmo Avenue (CSAH 17) and 10th Street (CSAH 10).
3. Request to rezone parcel to Public Facilities and expand MUSA for public sewer service.
4. Request to connect to city water.
5. Replaces current Lake Elmo elementary school building at 11030 Stillwater Boulevard.
6. Access requested from Lake Elmo Avenue (CSAH 17) and 10th street (CSAH 10) for separated bus and
visitor entry/egress. Visitor entry will be designed to allow on‐site stacking of waiting vehicles.
7. Site to include elementary school, bus access and parking lot, visitor access and parking lot, ballfields,
open fields, playground, greenspace, and stormwater management.
TRANSPORTATION IMPROVMENTS, ACCESS AND COLLECTOR STREETS
1. County Roadway Right‐of‐way Dedication. Additional right‐of‐way dedication has been shown along both
Lake Elmo Avenue (CSAH 17) and 10th Street North (CSAH 10) to provide a total of 75‐feet from the
roadway centerline. The additional right‐of‐way dedication must be verified that the measurements are
provided from the physical roadway centerline and not a survey Section line.
2. Small/Dry Utility Corridor Preservation. Minimum 10‐ft wide drainage and utility easement must be
dedicated along all the full frontage of the public right‐of‐way, including Lake Elmo Avenue (CSAH 17) and
10th Street (CSAH 10). The 10‐ft. easement corridor must be preserved for the installation of small/dry
utilities and remain free from all encroachments, including trees, retaining walls, storm sewer, and
stormwater BMPs. Grading within the easement areas must be less than 4:1 slope. The required 10‐ft
drainage and utility easements have not been shown on the site plans and the proposed grading plan
shows both steep slope and landscaping encroachments.
3. Access Management. The proposed access location along both Lake Elmo Avenue (CSAH 17) and 10th
Street (CSAH 10) must be approved by Washington County. An access management plan must be
submitted that provides the offset distances from the proposed access locations to all adjacent
intersections and driveways.
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Chad Isakson, P.E. 651.300.4285
PAGE 2 of 3
4. Turn Lane Improvements. As part of the site improvements, dedicated right and left turn lanes must be
constructed along Lake Elmo Avenue (CSAH 17) and 10th Street (CSAH 10) at both access locations. The
required turn lanes have not been shown on the proposed site plans. Turn lanes must be constructed
meeting Washington County standards.
5. Secondary Access. The site shows a single access for busing and a single access for all other vehicles.
Internal connectivity between the two access locations is not provided. Emergency vehicle access
requirements must be reviewed and approved by the Lake Elmo Fire Department.
6. Traffic Signal Improvements. The installation of a traffic signal at the intersection of Lake Elmo Avenue
(CSAH 17) and 10th Street (CSAH 10) should also be included as part of the site improvements to provide
additional traffic control for peak demands as well as provide safe pedestrian crossings at the
intersection.
7. Bituminous Trails. The site improvements must include and show on the site plans the construction of a
bituminous trail along the full length both Lake Elmo Avenue (CSAH 17) and 10th Street (CSAH 10).
Pedestrian connectivity should be planned as part of the school site, including internal pedestrian
connections, connection to the County Park Preserve, and safe pedestrian crossings for each County
roadway at each access location.
STORMWATER MANAGEMENT
1. The site plan is subject to a storm water management plan (SWMP) meeting State, Valley Branch
Watershed District (VBWD) and City rules. Storm water facilities proposed as part of the site plan to meet
State and VBWD permitting requirements must be constructed in accordance to City Engineering Design
Standards dated January 2022, even though the facilities will remain privately owned.
2. The stormwater management mitigation must be provided for all required site improvements, including
the County roadway and intersection improvements, County roadway turn lanes, and all bituminous trails.
If any of these improvements are not constructed as part of the site development, then the stormwater
management should be oversized to preserve capacity for these improvements to be constructed by
others.
3. All stormwater facilities and BMPs will be privately owned and maintained by the school district. The
school district will be required to provide a Stormwater Maintenance and Easement Agreement in
accordance with the City’s standard form of agreement.
4. All storm water basins must be placed in easements in accordance with the Stormwater Maintenance and
Easement Agreement. The easements must fully incorporate the 100‐year HWL, 10‐foot maintenance
bench and all maintenance access roads. Maintenance access roads meeting city standards must be
provided for all storm water facilities and structures.
5. The SWMP will be required to verify that rate control and volume control requirements are met for all
points of discharge from the site. The existing and proposed drainage exhibits must clearly show and label
all points of discharge from the site, including any required public improvements and turn lanes. The
SWMP rate control tables must reference each discharge location independently and combined.
6. Overland emergency overflows or outlets will be required as part of the site plan.
7. All wetlands and wetland buffers must be delineated and protected by easement.
8. Minimum floor elevations must be at least 2 feet higher than the adjacent 100‐year HWL elevation. Also,
all low opening elevations for all buildings must be at least 1‐ft higher than any adjacent emergency
overflow elevation (EOF).
9. All localized low points must be protected within a drainage easement.
MUNICIPAL WATER SUPPLY
1. Due to the PFAS groundwater contamination in the surrounding area, all proposed uses on the property
should be served by the City public drinking water supply.
2. Connection to the municipal water system is available to the existing trunk watermain running along Lake
Elmo Avenue (CSAH 17). The applicant will be responsible for connecting to the existing 16‐inch trunk
watermain located near the proposed Lake Elmo Avenue (CSAH 17) driveway entrance and running a
PAGE 3 of 3
minimum 8‐inch ductile iron watermain internal to the site and throughout the property as necessary to
provide connection to all proposed uses.
3. A second watermain connection will be required to create a looped network by extending the watermain
south through the proposed 10th Street (CSAH 10) entrance, then east along 10th Street (CSAH 10) to
connect back to the existing trunk watermain at the intersection with Lake Elmo Avenue (CSAH 17).
4. Watermain oversizing may be required to ensure adequate water supply and fire suppression once the
site development water demands are known.
5. The project will require the placement of fire hydrants and water system valves internal to the site as
determined by the Lake Elmo Public Works Director and Fire Department.
6. Minimum 30‐foot easements centered over the pipe/hydrant will be required when not located within
the public right‐of‐way. Easements must be free from all encroachments, including retaining walls, trees,
fences, small/dry utilities, or storm water management BMPs. Easements must be dedicated to the city as
part of the project.
SANITARY SEWER SYSTEM
1. The proposed site is located outside of the city designated Municipal Urban Service Area (MUSA) for
sanitary sewer service. The Comprehensive Plan Amendment application requests the expansion of the
city designated MUSA to allow the proposed elementary school to be served by public sanitary sewer.
2. The public sanitary sewer system is not readily available to serve this property. The applicant will be
required to extend sanitary sewer service to the site as part of the site improvements. The discharge or
connection manhole location to the city sewer system is at the intersection of Lake Elmo Avenue (CSAH
17) and 5th Street North, roughly 3,500 to 3,800 feet from the proposed school location.
3. Sewer System Extension to be privately owned. Since there are no other benefitting properties to be
served by sewer between the connection manhole and the school site, the sewer extension would be
considered a sewer service rather than a public sewer main line, and would be owned and operated
privately by the school district.
4. Sanitary Lift Station and Forcemain. The sewer extension improvements would likely require the
construction of a new sanitary lift station to be installed near the new school building. The school sewer
service would discharge by gravity to the new lift station with a 3,500 ft. to 3,800 ft. long forcemain
installed along the Lake Elmo Avenue right‐of‐way, and discharging to the proposed connection manhole.
5. No sanitary sewer oversizing is anticipated for these improvements.
LAKE ELMO FIRE DEPARTMENT – OFFICE OF THE FIRE MARSHAL
Fire Prevention, Code Enforcement, and Public Education
“Proudly Serving Neighbors and Friends”
October 24, 2023
Sophia Jensen, Planner
City of Lake Elmo
Re: Comprehensive Plan Amendment PID 2602921440001.
Prepared by: Anthony Svoboda, Fire Marshal
Approved by: Dustin Kalis, Fire Chief
Applicable Codes:
• 2020 Minnesota State Fire Code
• 2020 Minnesota State Building Code
• Lake Elmo Fire Department Fire Code Policies
• NFPA 13, 2016 edition
• NFPA 13D, 2016 edition
Fire Department Comments:
1) All roads and drive lanes shall meet the Lake Elmo Fire Department requirements for widths and turning
radiuses.
2) Approved fire apparatus roads shall be provided and maintained throughout all development phases in
coordination with engineering, public works, planning, and fire departments. In accordance with MSFC D104.2,
two fire apparatus access roads shall be maintained at all times.
3) Project construction phasing shall accommodate emergency access to the entire construction zone at all times,
generally meaning two separate means of entrance/exit as defined in the code. Phasing plan to be approved by
the fire department prior to construction.
4) An approved signage and marking plan shall be determined for all No Parking and Fire Lane access roads. On-
street parking shall be provided in approved locations following review by Engineering and Public Works. Parking
shall be prohibited on both sides of private drive lanes.
5) Street names and addressing shall be consistent with the Washington County Uniform Street Naming and
Property Numbering System.
6) Fire hydrants shall be provided in approved locations following review by Engineering and Public Works.
LAKE ELMO FIRE DEPARTMENT – OFFICE OF THE FIRE MARSHAL
Fire Prevention, Code Enforcement, and Public Education
“Proudly Serving Neighbors and Friends”
7) Building address numbers shall be plainly visible from the street fronting the property and shall be contrasting
color from the background. Size and placement of address numbers shall be approved by the fire and planning
departments.
8) A fire sprinkler system shall be installed in commercial buildings in accordance with the Minnesota State Fire
Code and Chapter 1306 of the Minnesota State Building Code. A permit is required prior to work.
a. Fire Department sprinkler connection locations shall be approved prior to installation.
9) A fire alarm system shall be installed in commercial buildings in accordance with the Minnesota State Fire Code
(907.2.3) and Lake Elmo Ordinances. A permit is required prior to work.
10) An emergency responder radio coverage amplifier shall be installed throughout the building if the fire
department determines that signal strength is not reliable.
11) An exterior door numbering system shall be utilized to determine exterior doors on all sides of the building.
Door numbering convention shall be approved by the fire department prior to installation.
12) A KNOX rapid access lockbox shall be installed in an approved location, on all commercial buildings.
a. Multiple KNOX rapid access lockboxes may be required as determined by the fire department.
13) KNOX locking Fire Department Connection Caps shall be installed on all fire department connections.
14) All gates, whether manual or electric, shall be accompanied by either a KNOX lock or KNOX gate control switch
for rapid access.
15) All parking areas shall be capable of supporting the imposed load of fire apparatus weighing up to 75,000
pounds.
Questions, clarifications, or the request to provide code documents can be made using the contact information listed
below.
Respectfully,
1
Nathan Fuerst
From:John P. Hanson <jhanson@barr.com>
Sent:Wednesday, January 24, 2024 1:25 PM
To:Sophia Jensen
Subject:RE: Lake Elmo Land Use Review - January 2nd Batch
Cauon: This email originated outside our organizaon; please us e cauon.
Hi Sophia,
The project will require a Valley Branch Watershed District (VBWD) permit. Once a complete VBWD permit applicaon is
submi&ed, we will review it for conformance to VBWD rules and regulaons.
The site includes two landlocked depressions and another depression. Two more depressions that are mostly off the
site, extend onto the site. While the proposed school building appears to be more than 2 feet higher than the ulmate
overflows of the depressions, the conceptual plan shows filling below the 100-year flood levels of some of the
depressions. Compensatory storage will be needed for any fill below the 100-year flood levels of any depression.
John
John P. Hanson, PE
Valley Branch Watershed District Engineer
Barr Engineering Co. | 4300 MarketPointe Drive | Bloomington, MN 55435
office: 952.832.2622 | cell: 612.590.1785
JHanson@barr.com | www.barr.com | www.vbwd.org
From: Sophia Jensen <SJensen@lakeelmo.org>
Sent: Wednesday, January 24, 2024 8:27 AM
To: John P. Hanson <jhanson@barr.com>; Jack Griffin <Jack.Griffin@focusengineeringinc.com>; Dustin Kalis
<DKalis@lakeelmo.org>; Anthony Svoboda <ASvoboda@lakeelmo.org>; Daniel Elder
<Daniel.Elder@co.washington.mn.us>; Kelli Matzek <Kelli.Matzek@co.washington.mn.us>; Connor Schaefer
<Connor.Schaefer@co.washington.mn.us>
Cc: Nathan Fuerst <nathan.fuerst@bolton-menk.com>
Subject: Lake Elmo Land Use Review - January 2nd Batch
CAUTION: This email originated from outside of your organization.
You are being asked to review the following applicaon as a stakeholder in the area of a pending land use
applicaon. Please see link below.
Sllwater Schools Comprehensive Plan Amendment and Rezoning: PID 26.029.21.44.0001. Sllwater Schools
has submi&ed a comprehensive plan amendment applicaon to amend the City’s comprehensive plan to
reguide the property from Rural area development to instuonal and be included into the MUSA boundary .
A great place to live, work and play…today and tomorrow
Government Center | 14949 62nd Street North | P. O. Box 6 | Stillwater, MN 55082-0006
P: 651-430-6001 | F: 651-430-6017 | TTY: 651-430-6246
www.co.washington.mn.us
Washington County is an equal opportunity organization and employer
ADMINISTRATION
Kevin Corbid, County Administrator
Jan Lucke, Deputy County Administrator
Jennifer Wagenius, Deputy County Administrator
February 5, 2024
Sophia Jensen
City Planner
City of Lake Elmo
RE: Lake Elmo – Stillwater Schools Comprehensive Plan Amendment
City Planner Jensen:
Washington County has received and reviewed the City’s Comprehensive Plan Amendment to alter the property
guidance from Rural Area Development to Institutional and be included into the MUSA boundary and the
additional zoning map amendment. Washington County does not oppose the proposed Comprehensive Plan
Amendment. Attached are general comments related to the site plan provided by the Stillwater Area Public
Schools that have been shared previously with both the City of Lake Elmo and the school district.
Thank you for the opportunity to comment.
Sincerely,
Kelli Matzek
Senior Planner
Cc: Gary Kreisel, Washington County Commissioner – District 3
Jennifer Wagenius, Washington County Deputy County Administrator
Wayne Sandberg, Washington County Public Works Director
Emily Jorgensen, Washington County Administration Planning Manager
Dr. Michael Funk, Stillwater Area Public Schools Superintendent
Mark Drommerhausen, Stillwater Area Public Schools Executive Director of Operations
Washington County Public Works
The location of the proposed school is adjacent to the intersection of two busy county highways. There are some
specific site development challenges and concerns that the county believes the city council should be made aware
of as they consider this planning amendment.
These comments were previously shared with Stillwater Area Public Schools on April 17, 2023, and the City of Lake
Elmo on October 24, 2023.
Washington County 2040 Comprehensive Plan – Chapter 5: Transportation
a. Functional Classification - Per the Washington County 2040 Comprehensive Plan, Chapter 5 – Figure 3
shows the functional classification of both roadways. County 17 is a Collector. County 10 is an A-minor
Arterial Reliever – serving east west regional trips. Both highways are on the County State Aid Highway
System and serve as important commuter routes and are the designated truck routes in the area.
b. Traffic Volume Forecast and Concerns - Washington County 2040 Comprehensive Plan Chapter 5: Figure 7
shows current traffic volumes on County 10 in this area range from 4,200 to 6,066 vehicles per day. On
County 17 traffic volumes are in the range of 3,500 vehicles per day currently.
Additionally, Figure 25 shows traffic volumes are forecasted to increase significantly, with or without the
school development. Traffic on County 10 is expected to increase to 13,800 by 2040, and traffic on County
17 will increase to a range of 5,800 to 6,900 vehicles per day by 2040. These increases indicate a need,
especially on County 10, for additional capacity improvements including the possibility of additional
through lanes. This roadway expansion should be accounted for in proposed site plans to ensure the
school site can accommodate the forecasted growth.
Figure 26 shows the future volume to capacity ratio on county highways expected by 2040. This is a
measure of congestion and an indication of where highway expansion will be needed in the future. Note
that County 10 in this area shows traffic volume exceeding roadway capacity – further reinforcing the
future need for expansion of this roadway. Given this analysis, it can be foreshadowed that not only will
the roadway need an increase in capacity, but that the intersection of County 10 and County 17 will need
significant upgrades, including intersection control such as a roundabout or stoplight.
The roadway type, volume, speed and character of traffic on these highways will not change as a result of
a school nearby. History tells us that the volume and conflicts related to school uses will likely increase
over and above the existing county comprehensive plan forecasts. This is due to the nature of school
traffic as well as the increased sensitivity of the community around school safety and traffic conflicts. This
is especially important to note as schools tend to be traffic generators throughout the days and on
weekends.
c. Right of Way Dedication - Washington County 2040 Comprehensive Plan Chapter 5: Figure 27 indicates a
need for 150 foot right of way on both County 10 and County 17. Thus, a minimum of 75 feet of right-of-
way from the centerline should be secured at the time of development along both County 10 and County
17. The city will be responsible for the costs of future right-of-way acquisition if not secured at the time of
development, in accordance with Washington County Cost Participation Policy #8001 as previously
referenced.
d. Access- All access will need to come off the county highway system for this proposed school site. This
presents some additional challenges that will need to be addressed in design.
School sites typically generate significant traffic volume and queuing; therefore, the County would require
a traffic study to better understand the anticipated traffic operations at the proposed access locations and
affected nearby intersections as part of the County’s access permitting process. It should be noted that
queuing of traffic on the county highway system presents significant safety issues. The design of the site
must accommodate all expected queuing at peak operating times.
Site sketches shared with the county propose two entrances: a bus entrance on County 10 and a visitor
entrance on County 17. The county anticipates that the proposed bus cul-de-sac driveway from County 10
would be particularly problematic with respect to safety and operations. The close spacing from this
proposed driveway to the arterial intersection of County 10 and County 17 creates a risk that traffic
queues will sometimes obstruct the bus driveway or lead to a shortage of available gaps for buses to exit
the site, particularly when the intersection experiences a surge of other school traffic. This will be
exacerbated when this intersection is improved. The location of this access will need to be evaluated
further.
e. Turn Lanes -Any access from this property should be planned to include the construction of turn lanes on
the county highway. Lane geometry should be developed such that intersection control such as a stop
light can be added in the future.
f. Internal circulation -The school should plan for internal circulation from all access points on the site. The
site plan should never use the county highway system as a circulator route to access various points of the
property.
g. Future Sport Fields -The county is not likely to permit an additional street to accommodate future
expansion. Access to future site expansion should be planned and considered during initial site planning.
h. Pedestrian and Bike Access – The County will want to collaborate with the city and the school district to
consider and plan for pedestrian infrastructure within walking distance of the school, notwithstanding any
current policies related to bus transportation. The pedestrian routes should connect with nearby
neighborhoods, both existing and planned, and should provide reasonably direct access into the school
site itself. The construction of sidewalks and trails is a public benefit that will improve the community. The
County will want to work with the City and the School to determine when and where these trails are
constructed. Washington County Cost Participation Policy #8001 will provide guidance on cost share.
i. Site Drainage - All site drainage features will need to be addressed on the school property. No ponding or
site drainage appurtenances will be allowed in the current or future county right of way.
j. Landscaping- No landscaping or screening of the property will be allowed in the current or future county
right of way. All landscaping should be included on the school property.
k. Noise and Lighting- County highway traffic produces noise that should be considered in the site design.
Similarly – lighting can be a key safety element and lighting should be considered as part of the site
planning.
Washington County Public Health and Environment
• Any sewage tank(s), drywells/cesspools, or SSTS component(s) located during land altering or construction
phases shall be properly abandoned. A County permit for septic system abandonment shall be submitted
to the Washington County Department of Public Health and Environment.
• Any water supply wells located during land altering or construction phases need to be sealed according to
Minnesota Department of Health regulations to mitigate potential groundwater contamination.
• All solid and hazardous waste, including waste from historic dumping, must be removed from the property
and managed at an appropriately permitted waste disposal facility.
• The planning considerations taken towards PFAS on the proposed school site is aligned with the
Washington County Groundwater Plan. Full awareness of the scope and impact of the PFAS contamination
and a full dedication towards safety must be adhered to when developing or populating the site.