HomeMy WebLinkAbout#22 - Hudson Blvd Segment A Improvements STAFF REPORT DATE: May 7, 2024 REGULAR AGENDA ITEM: Approve Resolution Receiving Feasibility Report, Calling Hearing on Improvement, Approving Plans and Specifications, and Ordering Advertisement for Bid for the Hudson Boulevard Improvements Segment A SUBMITTED BY: Jack Griffin, City Engineer REVIEWED BY: Clark Schroeder, Interim City Administrator Clarissa Hadler, Finance Director Marty Powers, Public Works Director Chad Isakson, Assistant City Engineer ISSUE BEFORE COUNCIL: Should the City Council accept the Feasibility Report, call a Public Hearing, approve the Plans and Specifications, and Order the Advertisement for Bids for the Hudson Boulevard Improvements Segment A, from Inwood Avenue (CSAH 13) to 1,400 feet east of Jade Trail, with the Improvement Hearing to be held at the June 18, 2024 council meeting? BACKGROUND: On December 5, 2023, following a presentation on the preliminary design findings and recommendations, the City Council authorized the preparation of the feasibility report, and the plans and specifications for the Hudson Boulevard Improvements Segment A, from Inwood Avenue (CSAH 13) to 1,400 feet east of Jade Trail (“Project”). The Project was initiated as part of the City’s annual Capital Street Improvement Program which provides for the long-term planning and management of street and transportation infrastructure throughout the city. PROPOSAL DETAILS/ANALYSIS: A Feasibility Report has been prepared to address the pavement rehabilitation improvements programmed for construction in 2024. The report serves to identify the necessary improvements, the estimated project costs, and to consider the assessment of a portion of the project costs to properties adjacent to and benefitting from the improvements. The Project includes pavement rehabilitation of Hudon Boulevard North, from Inwood Avenue (CSAH 13) to approximately 1,400 feet east of Jade Trail, including approximately 4,340 feet (0.82 miles) of commercial access frontage road and consisting of a Full-Depth Reclamation (FDR). From Jade Trail to the east property line of 9242 Hudson Boulevard, the roadway will be widened to accommodate a 3-lane section with a two-way continuous turn lane to accommodate the existing commercial driveway access spacing. The areas consisting of roadway widening and new turn lanes will include a full reconstruction consistent with the city standard pavement section for collector streets. The north side of Hudson Boulevard will be urbanized with new concrete curb and gutter, storm sewer, and a new 8-ft. wide bituminous trail to create a continuous trail from Inwood Avenue (CSAH 13) to Keats Avenue (CSAH 19). The Full Depth Pavement Reclamation (FDR) will include an 8‐inch recycled aggregate base with a new 4-inch bituminous surface. Based on the testing performed and the in‐place pavement layer thicknesses, there is sufficient material to perform FDR. The FDR approach provides a design life similar to that of reconstruction and is less expensive. It also disrupts crack patterns, reducing the potential for reflective cracking. Structurally, the overall capacity of the street will meet a 10-ton design. Permanent right-of-way/easement acquisition is not required for the improvements as proposed. Temporary construction easements may be required for trail construction and driveway approaches, including 8500, 8550, and 8650 Hudson Boulevard. The Project will require careful utility coordination with existing electrical and telecommunication utility owners. The urbanization of the north boulevard and construction of the new trail may incur several conflicts that require mitigation. Utility coordination efforts are in progress and coordination efforts will be implemented through project competition. Stormwater management will be implemented to mitigate rate and volumes increases in accordance with South Washington Watershed District (SWWD) rules. A combination of BMPs are proposed, including vegetated swales with check dams, expanded city owned detention pond within the Boulder Ponds subdivision, SAFL Baffles/filtration, and manhole flow control structures. The urbanization of the north boulevard with new trail will alter drainage patterns within the public right-of-way, requiring storm sewer piping to replace existing open ditches. The total estimated project cost is $2,580,000. A portion of the project is proposed to be assessed to the benefitting properties, which includes 10 commercial properties with direct driveway access along the proposed improved frontage of Hudon Boulevard North (see attached assessable property exhibit). In addition, the roadway segment is designated as a Municipal State Aid Street (MSAS) which is eligible to receive MSA funds to pay for all or a portion of the improvements that are state aid eligible and if the improvements meet state aid design standards. The preliminary assessment roll is attached to this Report showing the proposed assessment amount for each of the 10 benefitting properties. Street and drainage improvement assessments for commercial properties are based on assessing 100% of the adjusted street costs (reduced by MSAS funds) on a lineal foot basis. With the total improvement frontage of 8,680 feet, the adjusted unit assessment for commercial street frontage is $132.00 per foot. Assessments for street and drainage improvements are levied over a 15- year period and charged an interest rate of 1% over the bond rate for the project. In addition, the plans and specifications have been completed for the improvements and are ready to be advertised for contractor bids. A bid date has been scheduled for June 6, 2024. Contractor bids will be received and reviewed by staff with a tentative staff recommendation for award of contract to be presented for council consideration at the June 18, 2024 council meeting. FISCAL IMPACT: The total estimated project cost is $2,580,000. The improvements may be funded through a combination of Municipal State Aid Funds, in the amount of $1,436,000; Special Assessments, in the estimated amount of $437,976, and General Tax levy funds in the estimated amount of $706,024. RECOMMENDATION: Staff is recommending that the City Council approve a Resolution, receiving the Feasibility Report, calling a public hearing, approving the plans and specifications, and ordering the advertisement for bids for the Hudson Boulevard Improvements Segment A, from Inwood Avenue (CSAH 13) to 1,400 feet east of Jade Trail. The recommended motion for this action is as follows: “Move to approve Resolution No. 2024-053, receiving the Feasibility Report, Calling Hearing on Improvement, Approving the Plans and Specifications, and Ordering the Advertisement for Bids for the Hudson Boulevard Improvements Segment A, from Inwood Avenue (CSAH 13) to 1,400 feet east of Jade Trail.” ATTACHMENTS: 1. Resolution Receiving a Feasibility Report, Calling for Hearing on Improvement, Approving Plans and Specifications, and Ordering Advertisement for Bids. 2. Notice of Hearing on Improvement. 3. Preliminary Assessment Roll and Exhibit. 4. Location Map. 5. Proposed Improvement Exhibit. 6. Project Schedule. 7. Advertisement for Bids. Feasibility Report (available for review at City Hall). Project Plans and Specifications (available for review at City Hall). CITY OF LAKE ELMO WASHINGTON COUNTY STATE OF MINNESOTA RESOLUTION NO. 2024-053 A RESOLUTION RECEIVING A FEASIBILITY REPORT, CALLING HEARING ON IMPROVEMENT, APPROVING PLANS AND SPECIFICATIONS AND ORDERING ADVERTISEMENT FOR BIDS FOR THE HUDSON BOULEVARD IMPROVEMENTS – SEGMENT A WHEREAS, pursuant to City Council resolution, adopted on December 5, 2023, a feasibility report has been prepared by FOCUS Engineering, Inc. for the Hudson Boulevard Improvements Segment A, from Inwood Avenue (CSAH 13) to 1,400 feet east of Jade Trail; and WHEREAS, the feasibility report recommends that benefitting properties be assessed all or a portion of the cost of the improvements pursuant to the City’s Special Assessment Policy and Minnesota Statutes, Chapter 429; and WHEREAS, the feasibility report provides information regarding whether the proposed improvement is necessary, cost-effective, and feasible; whether it should best be made as proposed or in connection with some other improvement; the estimated cost of the improvements as recommended; and a description of the methodology used to calculate individual assessments for affected parcels; and WHEREAS, pursuant to City Council resolution, adopted on December 5, 2023, the City Engineer, together with KLJ, Inc., has prepared plans and specifications for the Hudson Boulevard Improvements Segment A, from Inwood Avenue (CSAH 13) to 1,400 feet east of Jade Trail and has presented such plans and specifications to the Council for approval. NOW, THEREFORE, BE IT RESOLVED, 1. That the City Council will consider the improvements in accordance with the report and the assessments of the abutting properties for all or a portion of the cost of the improvements pursuant to Minnesota Statues, Chapter 429 at an estimated total project cost of $2,580,000. 2. A public hearing shall be held on such proposed improvements on the 18th day of June, 2024 in the council chambers of City Hall, at or approximately after 7:00 P.M. and the clerk shall give mailed and published notice of such hearing and improvement as required by law. 3. Such plans and specifications, a copy of which is on file at Lake Elmo City Hall, and made a part hereof, are hereby approved. 4. The City Clerk shall prepare and cause to be inserted in the official paper and posted online with Quest Construction Data Network (QuestCDN.com) an advertisement for bids upon the making of such improvements under such approved plans and specifications. The advertisement shall be published for at least 21 days, shall specify the work to be done, and shall state that sealed bids provided by following required electronic bidding procedures outlined by QuestCDN prior to the specified bid date and time and accompanied by a bid bond or cashier’s check made payable to the City of Lake Elmo in an amount not less than 5% of the amount of such bid will be considered. ADOPTED BY THE LAKE ELMO CITY COUNCIL ON THE SEVENTH DAY OF MAY, 2024. CITY OF LAKE ELMO By: __________________________ Charles Cadenhead (Seal) Mayor ATTEST: ________________________________ Julie Johnson City Clerk CITY OF LAKE ELMO NOTICE OF HEARING ON IMPROVEMENT HUDSON BOULEVARD IMPROVEMENTS – SEGMENT A Notice is hereby given that the City Council of Lake Elmo will conduct a public hearing on Tuesday, June 18, 2024, at or approximately after 7:00 PM to consider the making of the following improvements, pursuant to Minnesota Statutes, Sections 429.011 to 429.111: The project includes pavement rehabilitation of Hudon Boulevard North, from Inwood Avenue (CSAH 13) to approximately 1,400 feet east of Jade Trail, including approximately 4,340 feet (0.82 miles) of collector roadway, and consisting of a Full Depth Reclamation (FDR), drainage improvements, and urbanizing the north side of Hudson Boulevard with a new bituminous trail. From Jade Trail to the east property line of 9242 Hudson Boulevard, the roadway will be widened to accommodate a 3-lane section with a two-way continuous turn lane to accommodate the existing commercial driveway access spacing. The area proposed to be assessed for the street improvements include the 10 commercial properties with direct driveway access to Hudon Boulevard North, from Inwood Avenue (CSAH 13) to approximately 1,400 feet east of Jade Trail. The estimated total cost for the project is $2,580,000. A reasonable estimate of the impact of the assessment will be available at the hearing. Such persons as desiring to be heard with reference to the proposed improvements will be heard at this meeting. DATED: May 7, 2024 BY ORDER OF THE LAKE ELMO CITY COUNCIL Charles Cadenhead, Mayor (Published in the Stillwater Gazette on May 10, 2024 and May 17, 2024) LEGEND FIGURE NO. 6 ASSESSABLE PROPERTIES HUDSON BOULEVARD IMPROVEMENTS SEGMENT A PROJECT NO. 2023.120 MAY, 2024 ASSESSABLE PROPERTY (COMMERCIAL) 8665 9200 89 1 0 8500 8650 JA D E T R A I L N HUDSON BLVD N EAGL E P O I N T B L V D Feet 0 300 600HUDSON BLVD IMPROVEMENTS (SEGMENT A) HUDSON BLVD N 8515 8511 89 8 0 9220 9242 5TH ST N CITY OF LAKE ELMO, MN. MAY, 2024 HUDSON BOULEVARD IMPROVEMENTS - SEGMENT A ASSESSABLE PROPERTIES PRELIMINARY ASSESSMENT ROLL PAGE 1 of 1 NO. NAME PID ASSESSABLE COMMERCIAL FRONTAGE (FT) STREET AND DRAINAGE ASSESSMENT AMOUNT 1 CITY & COUNTY CREDIT UNION 8500 HUDSON BLVD N 144 11TH ST E ST PAUL MN 55101 3302921420010 308 $40,656 2 HOA HOTELS LLC 8511 HUDSON BLVD N 1501 RIVER DR MOLINE IL 61265 3302921430009 206 $27,192 3 MACHINE SHED LLC 8515 HUDSON BLVD N 1501 RIVER DR MOLINE IL 61265 3302921430010 206 $27,192 4 MLL HIGH POINTE LLC 8650 HUDSON BLVD N 155 FEDERAL ST #604 BOSTON MA 02210 3302921440007 616 $81,312 5 8665 HUDSON BLVD LLC 8665 HUDSON BLVD N 1905 2ND ST N STILLWATER MN 55082 3302921440037 617 $81,444 6 COLLISION CONSULTING SERVICES LLC 8910 HUDSON BLVD N 8910 HUDSON BLVD N LAKE ELMO MN 55042 3302921440003 176 $23,232 7 AWESOME WOODBURY LLC 8980 HUDSON BLVD N 7601 WAYTAZA BLVD MINNEAPOLIS MN 55426 3302921440005 200 $26,400 8 HSRE LAKE ELMO LLC 9200 HUDSON BLVD N 9200 HUDSON BLVD N LAKE ELMO MN 55042 3402921330005 328 $43,296 9 LAMPERT YARDS INC 9220 HUDSON BLVD N 1850 COMO AVE ST PAUL MN 55108 3402921330004 328 $43,296 10 GATSBY INV I LLC 9242 HUDSON BLVD N 2550 UNIVERSITY AVE W #305S ST PAUL MN 55114 3402921340004 333 $43,956 TOTAL 3318 $437,976 ADDRESS MAILING ADDRESS CITY OF LAKE ELMO HUDSON BOULEVARD N LEGEND HUDSON BOULEVARD IMPROVEMENTS SEGMENT A PROJECT NO. 2023.120 MAY 2024 HUDSON BOULEVARD N SEGMENT A PROJECT LOCATION FIGURE NO. 1 LOCATION MAP M G P M M GP M GP G P M G P M M M G P M M M M M M M GPGP G P G P 100 105 12' THRU 12' LTL 12' THRU 12' RTL 12' THRU 12' THRU 12' RTL 12' THRU 12' LTL 12' THRU 12' THRU 12' LTL 12' THRU 12' RTL 12' LTL 12' LTL STA. 100+19.40 (HUDSON) S.A.P. 206-120-002 BEGIN PROJECT (HUDSON) { HUDSON BLVD 8' TRAIL 8' TRAIL 8' TRAIL 8' TRAIL C S A H 1 3 ( I N W O O D A V E ) E A G L E P O I N T L N LAKE ELMO CITY OF OAKDALE CITY OF B624 C&G B624 C&G B 624 CURB & GUTTER PROTECT EXISTING CURB & GUTTER PROTECT EXISTING FOR IMPROVEMENTS WITHIN COUNTY RIGHT-OF-WAY COORDINATION WITH WASHINGTON COUNTY OFFSET LEFT TURN LANES IMPROVED GEOMETRY ALLOWS FOR - SIGNAL IMPROVMENTS AT INWOOD AVE (CSAH 13) - SIGNING IMPROVEMENTS - PAVEMENT MARKING IMPROVEMENTS - DRAINAGE IMPROVMENTS - IMPROVED ADA FACILITIES - NEW SHARED USE TRAIL ON NORTH SIDE OF HUDSON BOULEVARD - NEW BITUMINOUS ROADWAY PAVMENT - IMPROVED ROADWAY GEOMETRY FOR A MORE CONSISTENT CORRIDOR IMPROVEMENTS INCLUDE: TOTAL LENGTH OF PROJECT IMPROVEMENTS: 0.82 MILES MA T C H L I N E - S T A . 1 0 6 + 0 0 . 0 0 ( H U D S O N ) 4 / 2 9 / 2 0 2 4 6 : 4 7 : 5 5 P M k e v i n c o u r t n e y CITY OF LAKE ELMO 8 OF 1 SHEET PROPOSED 2024 IMPROVEMENTS HUDSON BOULEVARD 50 SCALE IN FEET PROPSOED DRAINAGE DRAINAGE & UTILITY EASEMENT CONSTRUCTION LIMITS TEMPORARY EASEMENT EXISTING R/W PROPSOED DITCH TURF ESTABLISHMENT DRIVEWAY, & MEDIAN PROPOSED CONCRETE WALK, 8" AGGREGATE BASE CLASS 6 2.25" BITUMINOUS PAVEMENT PROPOSED TRAIL 12" SELECT GRANULAR EMBANKMENT 8" AGGREGATE BASE CLASS 6 4" BITUMINOUS PAVEMENT PROPOSED ROADWAY EXPANSION 8" RECLAIMED AGGREGATE 4" BITUMINOUS PAVEMENT PROPOSED FULL-DEPTH RECLAMATION PROPSOED CURB & GUTTER LEGEND M GP G P M M M M M GPGPG P G P M M G P M M G PG P M M DI 110 107 12' THRU 12' LTL 12' THRU 12' THRU 12' LTL 12' THRU 12' LTL 12' THRU 12' RTL 12' THRU STA. 110+96.61 (HUDSON) S.A.P. 206-120-002 BEGIN EXCEPTION 8' TRAIL 8' TRAIL 8' TRAIL E A G L E P O I N T B L V D (HUDSON) { HUDSON BLVD B624 C&G B624 C&G B624 C&G CURB & GUTTER PROTECT EXISTING INTO AMIRA DEVELOPMENT. PROPOSED HUDSON BOULEVARD IMPROVEMENTS WILL TIE AMRIA DEVELOPMENT PLANNED FOR CONSTRUCTION IN 2024. MA T C H L I N E - S T A . 1 1 3 + 0 0 .0 0 ( H U D S O N ) M A T C H L I N E - S T A. 1 0 6 + 0 0 . 0 0 ( H U D S O N ) 4 / 2 9 / 2 0 2 4 6 : 4 8 : 0 1 P M k e v i n c o u r t n e y CITY OF LAKE ELMO 8 OF 2 SHEET PROPOSED 2024 IMPROVEMENTS HUDSON BOULEVARD 50 SCALE IN FEET PROPSOED DRAINAGE DRAINAGE & UTILITY EASEMENT CONSTRUCTION LIMITS TEMPORARY EASEMENT EXISTING R/W PROPSOED DITCH TURF ESTABLISHMENT DRIVEWAY, & MEDIAN PROPOSED CONCRETE WALK, 8" AGGREGATE BASE CLASS 6 2.25" BITUMINOUS PAVEMENT PROPOSED TRAIL 12" SELECT GRANULAR EMBANKMENT 8" AGGREGATE BASE CLASS 6 4" BITUMINOUS PAVEMENT PROPOSED ROADWAY EXPANSION 8" RECLAIMED AGGREGATE 4" BITUMINOUS PAVEMENT PROPOSED FULL-DEPTH RECLAMATION PROPSOED CURB & GUTTER LEGEND M M M G P G P M GP M M M M M M M MM 115 120118 (HUDSON) { HUDSON BLVD INTO AMIRA DEVELOPMENT. PROPOSED HUDSON BOULEVARD IMPROVEMENTS WILL TIE AMRIA DEVELOPMENT PLANNED FOR CONSTRUCTION IN 2024. INTO AMIRA DEVEL PROPOSED HUDSON B AMRIA DEVELOPMENT NO HUDSON BOULEVARD IMPROVEMENTS PROPOSED ON THIS SHEET. M A T C H L I N E - S T A . 1 2 0 + 0 0 . 0 0 ( H U D S O N ) M A T C H L I N E - S T A. 1 1 3 + 0 0 . 0 0 ( H U D S O N ) 4 / 2 9 / 2 0 2 4 6 : 4 8 : 0 6 P M k e v i n c o u r t n e y CITY OF LAKE ELMO 8 OF 3 SHEET PROPOSED 2024 IMPROVEMENTS HUDSON BOULEVARD 50 SCALE IN FEET PROPSOED DRAINAGE DRAINAGE & UTILITY EASEMENT CONSTRUCTION LIMITS TEMPORARY EASEMENT EXISTING R/W PROPSOED DITCH TURF ESTABLISHMENT DRIVEWAY, & MEDIAN PROPOSED CONCRETE WALK, 8" AGGREGATE BASE CLASS 6 2.25" BITUMINOUS PAVEMENT PROPOSED TRAIL 12" SELECT GRANULAR EMBANKMENT 8" AGGREGATE BASE CLASS 6 4" BITUMINOUS PAVEMENT PROPOSED ROADWAY EXPANSION 8" RECLAIMED AGGREGATE 4" BITUMINOUS PAVEMENT PROPOSED FULL-DEPTH RECLAMATION PROPSOED CURB & GUTTER LEGEND G P G P G P M DI M G PG P M G PG P M G P G P M 1 2 0 125 123 D I 1 2' P A S S IN G 1 2' T H R U 12 ' THRU 6' SHLD 12' THRU 12' THRU 6' SHLD12' THRU 12' THRU 1:15 12 ' RTL STA. 120+89.82 (HUDSON) S.A.P. 206-120-002 END EXCEPTION 8' TRAIL 8' TRAIL 8 ' TRA IL B624 C&G INTO AMIRA DEVELOPMENT. PROPOSED HUDSON BOULEVARD IMPROVEMENTS WILL TIE AMRIA DEVELOPMENT PLANNED FOR CONSTRUCTION IN 2024. CURB & GUTTER PROTECT EXISTIN (HUDSON) { HUDSON BLVD I-94 WB M A T C H LI N E - S T A. 1 2 7 + 2 5. 0 0 ( H U D S O N) MA T C H L IN E - S T A . 1 2 0 + 0 0 .0 0 (H U D S O N ) 4 / 2 9 / 2 0 2 4 6 : 4 8 : 1 1 P M k e v i n c o u r t n e y CITY OF LAKE ELMO 8 OF 4 SHEET PROPOSED 2024 IMPROVEMENTS HUDSON BOULEVARD 50 SCALE IN FEET PROPSOED DRAINAGE DRAINAGE & UTILITY EASEMENT CONSTRUCTION LIMITS TEMPORARY EASEMENT EXISTING R/W PROPSOED DITCH TURF ESTABLISHMENT DRIVEWAY, & MEDIAN PROPOSED CONCRETE WALK, 8" AGGREGATE BASE CLASS 6 2.25" BITUMINOUS PAVEMENT PROPOSED TRAIL 12" SELECT GRANULAR EMBANKMENT 8" AGGREGATE BASE CLASS 6 4" BITUMINOUS PAVEMENT PROPOSED ROADWAY EXPANSION 8" RECLAIMED AGGREGATE 4" BITUMINOUS PAVEMENT PROPOSED FULL-DEPTH RECLAMATION PROPSOED CURB & GUTTER LEGEND M DI M GP M DI G P G P G P G P M M 130 132 6' SHLD 12' THRU 12' THRU 6' SHLD 12' THRU 12' THRU 1:40 13' TWLTL 8' TRAIL 8' TRAIL J A D E T R A I L (HUDSON) { HUDSON BLVD CURB & GUTTER PROTECT EXISTING CURB & GUTTER PROTECT EXISTING I-94 WB M A T C H L I N E - S T A . 1 3 4 + 3 0 . 0 0 ( H U D S O N ) MA T C H L I N E - S T A . 1 2 7 + 2 5 . 0 0 ( H U D S O N ) 4 / 2 9 / 2 0 2 4 6 : 4 8 : 1 6 P M k e v i n c o u r t n e y CITY OF LAKE ELMO 8 OF 5 SHEET PROPOSED 2024 IMPROVEMENTS HUDSON BOULEVARD 50 SCALE IN FEET PROPSOED DRAINAGE DRAINAGE & UTILITY EASEMENT CONSTRUCTION LIMITS TEMPORARY EASEMENT EXISTING R/W PROPSOED DITCH TURF ESTABLISHMENT DRIVEWAY, & MEDIAN PROPOSED CONCRETE WALK, 8" AGGREGATE BASE CLASS 6 2.25" BITUMINOUS PAVEMENT PROPOSED TRAIL 12" SELECT GRANULAR EMBANKMENT 8" AGGREGATE BASE CLASS 6 4" BITUMINOUS PAVEMENT PROPOSED ROADWAY EXPANSION 8" RECLAIMED AGGREGATE 4" BITUMINOUS PAVEMENT PROPOSED FULL-DEPTH RECLAMATION PROPSOED CURB & GUTTER LEGEND M M M M MB M MB 135 140 MH MH MH MH 6' SHLD 12' THRU 6' SHLD 12' THRU 13' TWLTL 13' TWLTL 12' THRU 8' TRAIL12' THRU 8' TRAIL J A D E T R A I L (HUDSON) { HUDSON BLVD B624 C&G B624 C&G B624 C&G TO CITY OWNED POND PROPOSED POND MODIFICATIONS I-94 WB M A T C H L I N E - S T A . 1 4 1 + 3 0 . 0 0 ( H U D S O N ) MA T C H L I N E - S T A . 1 3 4 + 3 0 . 0 0 ( H U D S O N ) 4 / 2 9 / 2 0 2 4 6 : 4 8 : 2 1 P M k e v i n c o u r t n e y CITY OF LAKE ELMO 8 OF 6 SHEET PROPOSED 2024 IMPROVEMENTS HUDSON BOULEVARD 50 SCALE IN FEET PROPSOED DRAINAGE DRAINAGE & UTILITY EASEMENT CONSTRUCTION LIMITS TEMPORARY EASEMENT EXISTING R/W PROPSOED DITCH TURF ESTABLISHMENT DRIVEWAY, & MEDIAN PROPOSED CONCRETE WALK, 8" AGGREGATE BASE CLASS 6 2.25" BITUMINOUS PAVEMENT PROPOSED TRAIL 12" SELECT GRANULAR EMBANKMENT 8" AGGREGATE BASE CLASS 6 4" BITUMINOUS PAVEMENT PROPOSED ROADWAY EXPANSION 8" RECLAIMED AGGREGATE 4" BITUMINOUS PAVEMENT PROPOSED FULL-DEPTH RECLAMATION PROPSOED CURB & GUTTER LEGEND M MM MB MB 145 148 MH MH 6' SHLD 12' THRU 13' LTL 6' SHLD 12' THRU 8' TRAIL 13' TWLTL 13' TWLTL STA. 148+05.22 (HUDSON) END FULL DEPTH RECLAMATION 12' THRU 8' TRAIL 1:45 12' THRU (HUDSON) { HUDSON BLVD B624 C&G B624 C&G I-94 WB M A T C H L I N E - S T A . 1 4 8 + 3 0 . 0 0 ( H U D S O N ) M A T C H L I N E - S T A . 1 4 1 + 3 0 . 0 0 ( H U D S O N ) 4 / 2 9 / 2 0 2 4 6 : 4 8 : 2 7 P M k e v i n c o u r t n e y CITY OF LAKE ELMO 8 OF 7 SHEET PROPOSED 2024 IMPROVEMENTS HUDSON BOULEVARD 50 SCALE IN FEET PROPSOED DRAINAGE DRAINAGE & UTILITY EASEMENT CONSTRUCTION LIMITS TEMPORARY EASEMENT EXISTING R/W PROPSOED DITCH TURF ESTABLISHMENT DRIVEWAY, & MEDIAN PROPOSED CONCRETE WALK, 8" AGGREGATE BASE CLASS 6 2.25" BITUMINOUS PAVEMENT PROPOSED TRAIL 12" SELECT GRANULAR EMBANKMENT 8" AGGREGATE BASE CLASS 6 4" BITUMINOUS PAVEMENT PROPOSED ROADWAY EXPANSION 8" RECLAIMED AGGREGATE 4" BITUMINOUS PAVEMENT PROPOSED FULL-DEPTH RECLAMATION PROPSOED CURB & GUTTER LEGEND M M M M M M 150 155 148 12' THRU 6' SHLD STA. 153+45.22 (HUDSON) S.A.P. 206-120-002 END PROJECT 6' SHLD 12' THRU 12' THRU 6' SHLD 1:45 12' THRU 1:45 IN ORDER TO TAPER INTO THE EXISTING ROADWAY SECTION. HUDSON BOULEVARD IMPROVMENT PROJECT EXTENDED TO THE EAST HENDRIX DEVELOPMENT NOT ANTICIPATED FOR 2024 CONSTRUCTION. (HUDSON) { HUDSON BLVD I-94 WB M A T C H L I N E - S T A . 1 4 8 + 3 0 . 0 0 ( H U D S O N ) 4 / 2 9 / 2 0 2 4 6 : 4 8 : 3 1 P M k e v i n c o u r t n e y CITY OF LAKE ELMO 8 OF 8 SHEET PROPOSED 2024 IMPROVEMENTS HUDSON BOULEVARD 50 SCALE IN FEET PROPSOED DRAINAGE DRAINAGE & UTILITY EASEMENT CONSTRUCTION LIMITS TEMPORARY EASEMENT EXISTING R/W PROPSOED DITCH TURF ESTABLISHMENT DRIVEWAY, & MEDIAN PROPOSED CONCRETE WALK, 8" AGGREGATE BASE CLASS 6 2.25" BITUMINOUS PAVEMENT PROPOSED TRAIL 12" SELECT GRANULAR EMBANKMENT 8" AGGREGATE BASE CLASS 6 4" BITUMINOUS PAVEMENT PROPOSED ROADWAY EXPANSION 8" RECLAIMED AGGREGATE 4" BITUMINOUS PAVEMENT PROPOSED FULL-DEPTH RECLAMATION PROPSOED CURB & GUTTER LEGEND          PROJECT SCHEDULE  CITY OF LAKE ELMO  HUDSON BOUELVARD IMPROVEMENTS – SEGMENT A   INWOOD AVENUE (CSAH 13) to 1,400 EAST OF JADE TRAIL  PROJECT NO. 2023.120        AUGUST 15, 2023  Council authorizes preparation of Preliminary Design.    DECEMBER 5, 2023  Presentation  of Preliminary  Design  Findings  and  Recommendations.  Authorize  preparation of Feasibility Report and Plans and Specifications.    MAY 7, 2024  Council accepts the Feasibility Report and Calls for Public Hearing. Council approves  Plans and Specifications and orders Advertisement for Bids.    JUNE 6, 2024      Project Bid Date: Receive contractor bids.    JUNE 13, 2024      Property owner informational meeting.    JUNE 18, 2024  Public Improvement Hearing. Council Orders the Improvement. Council accepts  Bids and awards Contract.     JULY, 2024    Conduct Pre‐Construction Meeting and issue Notice to Proceed.   NOVEMBER 15, 2024    Substantial Completion.   JUNE 6, 2025      Final Completion.    *Final Assessment Hearing Schedule TDB  SECTION 0100 – ADVERTISEMENT FOR BIDS HUDSON BOULEVARD IMPROVEMENTS – SEGMENT A PROJECT NO. 2023.120 FOR THE CITY OF LAKE ELMO WASHINGTON COUNTY, MINNESOTA Notice is hereby given that bids will be received online through QuestCDN.com until 10:00 AM CDST, on Thursday, June 6, 2024, via QuestCDN for furnishing all work and materials for the construction, complete in place, of the Hudson Boulevard Improvements – Segment A project, consisting of the major work items in the following approximate quantities: 11,729 CU YD Excavation (Common) 5,939 CU YD Embankment (Select Granular & Common) 21,809 SQ YD Subgrade Preparation 18,417 SQ YD Full Depth Reclamation 5,278 TON Bituminous Pavement (9.5,C & 12.5,C) 404 TON Bituminous Trail (9.5,B) 2,948 LIN FT Concrete Curb and Gutter (B618 & B624) 2,432 SQ FT Concrete Walk 1,375 LIN FT Storm Sewer (RCP, multiple sizes) 1 SYSTEM Revise Signal System This project is subject to Responsible Contractor Certification and prevailing wage guidelines. The bid opening will be conducted via Microsoft TEAMS Meeting, at which time the bids will be publicly opened and read aloud: Lake Elmo Hudson Boulevard Improvements – Segment A Bid Opening Thursday, June 6, 202410:00 AM (CDST) Join Teams Meeting: https://tinyurl.com/4ymwtj2s Any person monitoring the meeting remotely may be responsible for any documented costs. Message and data rates may apply. Bids must be submitted electronically through QuestCDN no later than the date and time noted above, on the Proposal Forms provided in accordance with the Contract Documents, Plans, and Specifications as prepared by KLJ Engineering, www.kljeng.com, which are on file for inspection in the office of the City Clerk and City Engineer. For this project, the City will only be accepting online electronic bids through QuestCDN. To access the electronic bid form, download the project document and click the bidding button at the top of the advertisement. Prospective bidders must be on the plan holders list through QuestCDN for bids to be accepted. Bids will only be accepted from Contractors who purchase Bidding Documents as specified above. Complete digital Proposal Forms, Plans, and Specifications for use by Contractors submitting a bid are available at www.QuestCDN.com. Digital plan documents may be downloaded for a non-refundable fee of $30.00 by inputting Quest Project No. 9110190 on the website’s Project search page. Please contact QuestCDN at (952) 233-1632 or info@QuestCDN.com for assistance in free membership registration, downloading, and working with this digital project information. No bid will be considered unless submitted online prior to the time noted above for the closing of the bids, and accompanied by a bid bond in an amount not less than five percent (5%) of the total bid as a guarantee that the bidder, if successful, will enter into a contract with the City to perform the work described in the proposal. This deposit will be subject to forfeiture as provided by law. The deposits for the three lowest bidders will be retained by the City until the contract has been awarded and executed but not longer than sixty (60) days. No bid may be withdrawn for a period of sixty (60) days following the bid opening. The City reserves the right to reject any or all bids, to waive informalities or to award the contract to the lowest responsible bidder, in the best interest of the City. For Bids exceeding $50,000, the Bidder shall submit to the City a signed statement under oath by an owner or officer verifying compliance with each of the minimum criteria in Minnesota Statutes, section 16C.285, subdivision 3 on the Responsible Contractor Verification Form included with the Bid Proposal. Dated: May 7, 2024 Julie Johnson, City Clerk City of Lake Elmo PUBLISHED: QuestCDN.com: May 13, 2024 Stillwater Gazette: May 10, 2024 END OF DOCUMENT