HomeMy WebLinkAbout#07 - Pay Request 8 for Tapestry Sewer Project STAFF REPORT DATE: June 18, 2024 CONSENT AGENDA ITEM: Approve Pay Request No. 8 for the Tapestry Sanitary Sewer Extension SUBMITTED BY: Chad Isakson, Project Engineer REVIEWED BY: Nicole Miller, City Administrator Marty Powers, Public Works Director Clarissa Hadler, Finance Director Jack Griffin, City Engineer ISSUE BEFORE COUNCIL: Should the City Council approve Pay Request No. 8 for the Tapestry Sanitary Sewer Extension? BACKGROUND: A-1 Excavating was awarded a construction contract on May 17, 2022 to complete the Tapestry Sanitary Sewer Extension. PROPOSAL DETAILS/ANALYSIS: A-1 Excavating has submitted Partial Pay Request No. 8 in the amount of $22,280.63. The request has been reviewed and payment is recommended in the amount requested. In accordance with the contract documents, the City has retained 5% of the total work completed. The amount retained is $40,415.44. FISCAL IMPACT: None. Partial payment is proposed in accordance with the Contract for the project. Payment remains within the authorized scope and budget. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Pay Request No. 8 for the Tapestry Sanitary Sewer Extension. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve Pay Request No. 8 to A-1 Excavating. in the amount of $22,280.63 for the Tapestry Sanitary Sewer Extension”. ATTACHMENTS: 1. Partial Pay Estimate No. 8.