HomeMy WebLinkAbout#09 - Boulder Ponds 2nd & 3rd Add Security Release STAFF REPORT
DATE: October 15, 2024
CONSENT
AGENDA ITEM: Approve Release of Warranty Security for Public Improvements and
Landscaping for Boulder Ponds 2nd and 3rd Addition.
SUBMITTED BY: Jack Griffin, City Engineer
REVIEWED BY: Nicole Miller, City Administrator Marty Powers, Public Works Director
Clarissa Hadler, Finance Director
Sophia Jensen, City Planner
Chad Isakson, Assistant City Engineer
ISSUE BEFORE COUNCIL: Should the City Council approve release of warranty security for the public
improvements and landscaping for Boulder Ponds 2nd and 3rd Addition?
PROPOSAL DETAILS/ANALYSIS: Staff has received and processed a request to release all warranty
securities for Boulder Ponds 2nd and 3rd Addition. These requests have been reviewed and are being
recommended for approval in accordance with the approved Development Agreements. Each approval is
contingent on the developer having a positive escrow balance in the minimum amount required by the city,
and the developer being current with all payments and obligations. The Development Security amounts are
recommended to be reduced as follows.
Current Security Amount Proposed Security Amount
1. Boulder Ponds 2nd Addition: $67,500 $0
2. Boulder Ponds 3rd Addition: $201,391 $0
FISCAL IMPACT: Release of the warranty security closes out the public improvements and landscaping
portion of the developments. The operation and maintenance of the public facilities becomes the
responsibility of the city going forward.
RECOMMENDATION: Staff is recommending that the City Council, as part of the Consent Agenda,
approve the of warranty securities as detailed in the attached respective worksheets for Boulder Ponds 2nd
and 3rd Additions. The release of security is contingent on the developer being current with all payments
and obligations in accordance with the Development Agreement, including a positive escrow balance as
may be required by the City. If removed from the consent agenda, the recommended motion for the action
is as follows:
“Move to approve the release of the warranty securities as detailed in the attached respective
worksheets for Boulder Ponds 2nd and 3rd Additions, contingent on the developer being current with all
payments and obligations in accordance with the Development Agreement, including a positive escrow
balance as may be required by the City”
ATTACHMENTS:
1. Security Reduction Worksheet – Boulder Ponds 2nd Addition.
2. Security Reduction Worksheet – Boulder Ponds 3rd Addition.
BOULDER PONDS 2ND ADDITION Time of Performance: October 31, 2016
DEVELOPMENT AGREEMENT AMOUNTS
CATEGORY CONSTRUCTION 125% REMARKS #1 #2 #3 #4 #5 #6
Grading NA NA Included in Boulder Ponds 1st Addition
Sanitary Sewer $73,000 $91,250 100%$68,438 $22,813
Watermain $67,000 $83,750 100%$62,813 $20,938
Storm Sewer (w/pond structures) $39,500 $49,375 100%$37,031 $12,344
Streets $84,175 $105,219 100%$78,914 $26,305
Sidewalks/Trails $19,850 $24,813 100%$18,609 $6,203
Surface Water Facilities $13,000 $16,250 100%$12,188 $4,063
Street Lighting $12,000 $15,000 100%$11,250 $3,750
Street Signs and Traffic Control Signs $1,600 $2,000 100%$1,500 $500
Private Utilities (electricity, natural gas, telephone, and cable)
Landscaping $75,000 $93,750 100%$26,250 $67,500
Tree Preservation and Restoration NA NA
Wetland Mitigation and Buffers $1,000 $1,250 100%$938 $313
Monuments $1,800 $2,250 100%$1,688 $563
Erosion Control $36,650 $45,813 100%$34,359 $11,453
Miscellaneous Facilities NA NA
Record Drawings $2,500 $3,125 100%$2,344 $781
TOTALS $427,075 $533,844 RELEASED AMOUNTS:$247,195 $26,250 $43,750 $82,875 $66,273 $67,500
CUMMULATIVE AMOUNTS:$247,195 $273,445 $317,195 $400,070 $466,344 $533,844
SECURITY AMOUNT REMAINING:$286,648 $260,398 $216,648 $133,773 $67,500 $0
DATE: 9/5/2017 10/1/2019 6/16/2020 6/16/2020 7/6/2021 10/15/2024
REDUCTIONS
BOULDER PONDS 3RD ADDITION Time of Performance: October 31, 2019
DEVELOPMENT AGREEMENT AMOUNTS
CATEGORY CONSTRUCTION 125% REMARKS #1 #2 #3 #4 #5 #6
Grading $66,470 $83,088 $83,088
Sanitary Sewer $101,852 $127,315 $95,486 $31,829
Watermain $130,412 $163,015 $122,261 $40,754
Storm Sewer (w/pond structures) $55,845 $69,806 $52,355 $17,452
Streets and Sidewalks $147,956 $184,945 $138,709 $46,236
Trails $18,275 $22,844 $17,133 $5,711
Surface Water Facilities $55,849 $69,811 $52,358 $17,453
Street Lighting $24,000 $30,000 $22,500 $7,500
Street Signs and Traffic Control Signs $738 $923 $692 $231
Private Utilities (electricity, natural gas, telephone, and cable)
Landscaping $103,522 $129,403 $97,052 $32,351
Tree Preservation and Restoration NA NA
Wetland Mitigation and Buffers NA NA
Monuments $3,300 $4,125 $3,094 $1,031
Erosion Control $12,450 $15,563 $11,672 $3,891
Hudson Blvd. Turn Lanes $217,516 $271,895 $203,921 $67,974
Record Drawings $5,000 $6,250 $4,688 $1,563
TOTALS $943,185 $1,178,981 RELEASED AMOUNTS:$300,835 $507,121 $97,052 $72,583 $201,391
CUMMULATIVE AMOUNTS:$300,835 $807,956 $905,008 $977,590 $1,178,981
SECURITY AMOUNT REMAINING:$878,146 $371,025 $273,973 $201,391 $0
DATE:3/5/2019 4/20/2021 12/7/2021 5/17/2022 10/15/2024
REDUCTIONS