HomeMy WebLinkAbout#17 - 2024 Striping Pay Request 1 STAFF REPORT DATE: November 6, 2024 CONSENT AGENDA ITEM: Accept Improvements and Approve Pay Request No. 1 (FINAL) for the 2024 Striping Project SUBMITTED BY: Mike Rusenovich, Project Engineer REVIEWED BY: Nicole Miller, City Administrator Clarissa Hadler, Finance Director Jack Griffin, City Engineer Marty Powers, Public Works Director ISSUE BEFORE COUNCIL: Should the City Council accept the improvements and approve Pay Request No. 1 (FINAL) for the 2024 Striping Project? BACKGROUND: The City entered into an agreement with Sir Lines-A-Lot LLC, dated August 20, 2024, to complete pavement striping/markings for the street segments that were seal coated as part of the 2024 Seal Coat Project. PROPOSAL DETAILS/ANALYSIS: The 2024 Striping Project has been fully completed. The Project Engineer has prepared a Certificate of Completion and is recommending acceptance of the improvements and release of payment in full. The one-year warranty period will begin on November 6, 2024, and will extend to November 6, 2025. Sir Lines-A-Lot LLC has submitted Pay Request No. 1 (FINAL) in the amount of $13,686.77. The request has been reviewed and payment is recommended in the amount requested. FISCAL IMPACT: None. Payment is proposed in accordance with the contract for the project. Payment remains within the authorized scope and budget amount. RECOMMENDATION: Staff is recommending that the City Council, as part of the Consent Agenda, accept the improvements and approve Pay Request No. 1 (FINAL) to Sir Lines-A-Lot LLC in the amount of $13,686.77 for the 2024 Striping Project. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to accept the improvements and approve Pay Request No. 1 (FINAL) to Sir Lines-A- Lot LLC in the amount of $13,686.77 for the 2024 Striping Project”. ATTACHMENTS: 1. Contractor Invoice dated October 23, 2024. 2. Engineer’s Certificate of Completion dated November 6, 2024. Remit To:Sir Lines-A-Lot LLC 7175 CAHILL RD EDINA MN 55439 To:City of Lake Elmo 3800 Laverne Ave N Lake Elmo MN 55042 INVOICE - Application for Payment Project:Lake Elmo 2024 Striping Project No.: Invoice No.:H24-0995-001 Invoice Date:10/23/24 Period Thru:10/31/24 Customer Project No.: 0 ----------- TO DATE ------------------- THIS PERIOD -------- ITEM NO.ITEM UM $ PRICE UNITS $ AMOUNTS UNITS $ AMOUNT 1 4in SOLID LINE - WHITE ACRYLIC LATEX LF 0.29 24,125.00 6,996.25 24,125.00 6,996.25 2 4in BROKEN LINE - YELLOW ACRYLIC LATEX LF 0.14 2,369.00 331.66 2,369.00 331.66 3 4in SOLID LINE - YELLOW ACRYLIC LATEX LF 0.29 2,724.00 789.96 2,724.00 789.96 4 4in DOUBLE SOLID LINE - YELLOW ACRYLIC LATEX LF 0.58 9,080.00 5,266.40 9,080.00 5,266.40 5 24in SOLID LINE - WHITE ACRYLIC LATEX LF 7.50 23.00 172.50 23.00 172.50 7 ADA PARKING STALL SYMBOLS EA 65.00 2.00 130.00 2.00 130.00 Billing Totals:$13,686.77 $13,686.77 Please include SLAL invoice number on all correspondence. Page 1 of 1 CITY OF LAKE ELMO, MN 2024 STRIPING PROJECT PROJECT NO. 2024.108 CERTIFICATE OF COMPLETION DATE OF ISSUANCE: NOVEMBER 6, 2024 OWNER: CITY OF LAKE ELMO, MN CONTRACTOR: SIR LINES-A-LOT, LLC. PROJECT NAME: 2024 STRIPING PROJECT PROJECT NO.: 2024.108 This Certification of Completion applies to all work under the Contract Documents This Certification of Completion applies to the following specified parts of the Contract Documents I do hereby certify that the work to which this Certificate applies has been constructed in accordance with the Contract dated August 20, 2024. The above-mentioned improvement is hereby declared to be complete and acceptance of this work is recommended. DATE OF COMPLETION: NOVEMBER 6, 2024 Michael Rusenovich Reg. No. 58717 FOCUS Engineering, Inc. THE WARRANTY PERIOD BEGINS November 6, 2024 AND ENDS November 6, 2025