HomeMy WebLinkAbout#18 - Torre Pines Street & Utilities Pay Request 9 STAFF REPORT DATE: November 6, 2024 CONSENT AGENDA ITEM: Approve Pay Request No. 8 (Final) for the Torre Pines Street and Utility Improvements SUBMITTED BY: Chad Isakson, Project Engineer REVIEWED BY: Nicole Miller, City Administrator Sarah Sonsalla, City Attorney Clarissa Hadler, Finance Director Marty Powers, Public Works Director Jack Griffin, City Engineer ISSUE BEFORE COUNCIL: Should the City Council approve Pay Request No. 8 (Final) for the Torre Pines Street and Utility Improvements? BACKGROUND: Jacon, LLC was awarded a construction contract on January 4, 2022 to complete the Torre Pines Street and Utility Improvements. The contractor has completed the work in accordance with the contract, plans, and specifications, including all punch list items. The warranty period has expired and final payment effectively closes out the project. PROPOSAL DETAILS/ANALYSIS: Jacon, LLC has submitted Partial Pay Request No. 8 (Final) in the amount of $31,138.19. Final documentation has not been provided by the contractor, which includes the consent of surety, contractor lien waivers, and IC-134s. These documents are required by the contract to release final funds. The city has received communications from the surety company demanding project funds to be held or, if released, paid to the surety. The city has also received communications from subcontractors informing the city that they have not been paid by the general contractor for their work on the project. The city has been seeking resolution on the matter from the general contractor but has received limited communication in return. On October 2, 2024 the city attorney sent communications to the surety company to verify they will accept funds in exchange for a release from all outstanding payment claims. A formal response has not yet been received. In order for the city to seek reimbursement for all Project expenditures, it is critical that final payments be processed prior to the MPCA Grant Agreement expiration on December 31, 2024. Therefore, staff is recommendation that the city council approve the final payment subject to making the payment to contractor’s surety, provided that the surety accepts payment and releases the city from all outstanding claims or future payment obligations related to the Project. FISCAL IMPACT: None. Final payment is being recommended within the authorized project scope and budget. The final total project cost is projected to be $1,794,700 of which $875,000 is related to street improvements, $622,800 is public watermain improvements and $296,900 is private water connection and well sealing costs. The project is being paid through the MPCA Grant (3M Settlement funds) and the total project costs have come in below the authorized grant amount of $2,243,000. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Pay Request No. 8 (Final) for the Torre Pines Street and Utility Improvements subject to making the payment to contractor’s surety, provided the surety accepts payment and releases the city from all outstanding claims or future payment obligations related to the Project. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve Pay Request No. 8 (Final) in the amount of $31,138.19 for the Torre Pines Street and Utility Improvements subject to making the payment to contractor’s surety, provided the surety accepts payment and releases the city from all outstanding claims or future payment obligations related to the Project”. ATTACHMENTS: 1. Partial Pay Estimate No. 8 (Final). 2. Certification of Completion. 3. Surety Correspondence. PROJECT PAY FORM PARTIAL PAY ESTIMATE NO. PERIOD OF ESTIMATE TO PROJECT OWNER:CONTRACTOR: 1. Original Contract Amount 2. Net Change Order Sum 3. Revised Contract (1+2) 4. *Work Completed 5. *Stored Materials 6. Subtotal (4+5) 7. Retainage* 8. Previous Payments 9. Amount Due (6-7-8) *Detailed Breakdown Attached START DATE:ON SCHEDULE SUBSTANTIAL COMPLETION:X FINAL COMPLETION: ENGINEER'S CERTIFICATION:FOCUS Engineering, inc. DATE CONTRACTOR'S CERTIFICATION:CONTRACTOR DATE APPROVED BY OWNER:CITY OF LAKE ELMO, MINNESOTA DATE DATE No.Approval Date Amount $1,344,107.16 Additions Deductions -$98,579.50 CO-2 12/20/2022 $0.00 $0.00 $1,245,527.66 CO-1 7/19/2022 $9,927.00 $0.00 $1,245,527.66 $1,245,527.66 CCO-3 4/1/2024 $108,506.50 $0.00 $1,214,389.47 $0.000.0% CONTRACT TIME TOTALS $9,927.00 $108,506.50 $31,138.19 NET CHANGE ($98,579.50) CONTRACT CHANGE ORDER SUMMARY PAY ESTIMATE SUMMARY 8 (FINAL) 4/1/20248/1/2023FROM TORRE PINES STREET AND UTILITY IMPROVEMENTS PROJECT NO. 2020.122 CITY OF LAKE ELMO 3880 LAVERNE AVENUE NORTH LAKE ELMO, MN 55042 ATTN: JACK GRIFFIN, CITY ENGINEER JACON, LLC 3900 Labore Road Vadnais Heights, MN 55110 ATTN: Dwight Johnson 6/1/2022 10/14/2022 REVISED DAYS REMAINING 135 Per CO-29/2/2022 ORIGINAL DAYS BY BY YES NO The undersigned Contractor certifies that to the best of their knowledge, information and belief the work covered by this payment estimate has been completed in accordance with the contract documents, that all amounts have been paid by the contractor for work for which previous payment estimates was issued and payments received from the owner, and that current payment shown herein is now due. The undersigned certifies that the work has been reviewed and to the best of their knowledge and belief, the quantities shown in this estimate are correct and the work has been performed in accordance with the contract documents. ENGINEER 4/1/2024 BY FOCUS Engineering, inc.PROJECT PAYMENT FORM 10/10/2024 PARTIAL PAY ESTIMATE NO. 8 (FINAL) TORRE PINES STREET AND UTILITY IMPROVEMENTS CITY OF LAKE ELMO, MINNESOTA PROJECT NO. 2020.122 QUANTITY UNIT PRICE AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT 1 EA 20 $250.00 $5,000.00 0.00 $0.00 20.00 $5,000.00 2 LF 1,785 $3.00 $5,355.00 0.00 $0.00 93.00 $279.00 3 LF 80 $3.00 $240.00 0.00 $0.00 80.00 $240.00 4 EA 23 $200.00 $4,600.00 0.00 $0.00 22.00 $4,400.00 5 EA 34 $253.68 $8,625.12 0.00 $0.00 28.00 $7,103.04 6 EA 34 $253.68 $8,625.12 0.00 $0.00 1.00 $253.68 7 SY 600 $19.17 $11,502.00 0.00 $0.00 507.00 $9,719.19 8 EA 4 $500.00 $2,000.00 0.00 $0.00 4.00 $2,000.00 9 LF 40 $120.00 $4,800.00 0.00 $0.00 40.00 $4,800.00 10 EA 1 $577.31 $577.31 0.00 $0.00 1.00 $577.31 11 EA 9 $6,129.00 $55,161.00 0.00 $0.00 9.00 $55,161.00 12 LF 5 $1,528.00 $7,640.00 0.00 $0.00 0.00 $0.00 13 SF 90 $23.00 $2,070.00 0.00 $0.00 90.00 $2,070.00 14 EA 9 $2,128.00 $19,152.00 0.00 $0.00 9.00 $19,152.00 15 EA 7 $2,785.00 $19,495.00 0.00 $0.00 7.00 $19,495.00 16 LF 16 $92.00 $1,472.00 0.00 $0.00 5.00 $460.00 17 EA 23 $674.00 $15,502.00 0.00 $0.00 23.00 $15,502.00 18 EA 1 $633.00 $633.00 0.00 $0.00 1.00 $633.00 19 EA 23 $682.00 $15,686.00 0.00 $0.00 23.00 $15,686.00 20 EA 1 $868.00 $868.00 0.00 $0.00 1.00 $868.00 21 LF 850 $26.04 $22,134.00 0.00 $0.00 839.00 $21,847.56 22 LF 11 $126.70 $1,393.70 0.00 $0.00 16.00 $2,027.20 23 LF 12 $134.00 $1,608.00 0.00 $0.00 14.00 $1,876.00 24 LF 150 $65.00 $9,750.00 0.00 $0.00 122.00 $7,930.00 25 LF 4,400 $63.75 $280,500.00 0.00 $0.00 4,158.00 $265,072.50 26 LB 2,100 $4.28 $8,988.00 0.00 $0.00 1,796.00 $7,686.88 27 EA 34 $1,417.00 $48,178.00 0.00 $0.00 26.00 $36,842.00 28 SF 100 $9.98 $998.00 0.00 $0.00 128.00 $1,277.44 29 LF 35 $44.36 $1,552.60 0.00 $0.00 11.00 $487.96 30 EA 1 $1,725.00 $1,725.00 0.00 $0.00 1.00 $1,725.00 31 EA 3 $1,600.00 $4,800.00 0.00 $0.00 3.00 $4,800.00 32 LF 24 $195.00 $4,680.00 0.00 $0.00 8.00 $1,560.00 33 LF 7 $250.00 $1,750.00 0.00 $0.00 3.00 $750.00 34 EA 1 $750.00 $750.00 0.00 $0.00 1.00 $750.00 35 LS 1 $4,200.00 $4,200.00 0.00 $0.00 1.00 $4,200.00 36 EA 1 $11,500.00 $11,500.00 0.00 $0.00 1.00 $11,500.00 37 EA 18 $683.31 $12,299.58 0.00 $0.00 18.00 $12,299.58 38 EA 5 $575.00 $2,875.00 0.00 $0.00 5.00 $2,875.00 39 EA 7 $657.14 $4,599.98 0.00 $0.00 7.00 $4,599.98 40 LF 500 $17.48 $8,740.00 0.00 $0.00 500.00 $8,740.00 41 CY 40 $150.00 $6,000.00 0.00 $0.00 40.00 $6,000.00 42 SY 13,200 $10.16 $134,112.00 0.00 $0.00 13,200.00 $134,112.00 43 CY 2,200 $22.41 $49,302.00 0.00 $0.00 2,200.00 $49,302.00 44 CY 800 $11.00 $8,800.00 0.00 $0.00 185.00 $2,035.00 45 CY 800 $23.00 $18,400.00 0.00 $0.00 185.00 $4,255.00 46 CY 2,550 $20.00 $51,000.00 0.00 $0.00 2,300.00 $46,000.00 47 TN 1,310 $96.85 $126,873.50 0.00 $0.00 1,237.71 $119,872.21 48 TN 1,750 $101.74 $178,045.00 0.00 $0.00 1,432.88 $145,781.21 49 GAL 970 $2.00 $1,940.00 0.00 $0.00 725.00 $1,450.00 50 EA 3 $690.00 $2,070.00 0.00 $0.00 3.00 $2,070.00 51 EA 7 $51.75 $362.25 0.00 $0.00 7.00 $362.25 52 EA 1 $189.75 $189.75 0.00 $0.00 1.00 $189.75 53 SF 56 $69.00 $3,864.00 0.00 $0.00 56.00 $3,864.00 54 EA 2 $201.25 $402.50 0.00 $0.00 2.00 $402.50 55 EA 1 $402.50 $402.50 0.00 $0.00 1.00 $402.50 56 EA 1 $322.00 $322.00 0.00 $0.00 1.00 $322.00 57 SY 810 $2.85 $2,308.50 0.00 $0.00 496.00 $1,413.60 58 HR 20 $150.00 $3,000.00 0.00 $0.00 17.00 $2,550.00 $1,209,419.41 $0.00 $1,082,630.34 SIGN PANELS TYPE C STREET NAME BLADE SIGN (2 BLADES) STREET NAME BLADE SIGN (2 BLADES), INCLUDING POST STREET NAME BLADE SIGN (3 BLADES) SEED MIXTURE 35-241 & EROSION CONTROL BLANKET STREET SWEEPER WITH PICK UP BROOM SUBTOTAL BASE BID TYPE SP 12.5 BITUMINOUS NON WEARING COURSE MIXTURE (2,C) BITUMINOUS MATERIAL FOR TACK COAT CONCRETE APPROACH NOSE REMOVE SIGNS & POST SALVAGE AND REINSTALL SIGN PANEL COMMON EXCAVATION (EV) (P) SUBGRADE EXCAVATION GRANULAR BORROW (CV) AGGREGATE BASE, CLASS 6 (CV) TYPE SP 9.5 BITUMINOUS WEARING COURSE MIXTURE (2,C) PATCH DOGHOUSES PATCH INVERT JET AND CLEAN STORM PIPE RANDOM RIPRAP CL III WITH FABRIC REMOVE AND DISPOSE OF BITUMINOUS PAVEMENT 15" RCP STORM SEWER, CL 5 SALVAGE & REINSTALL 12" RCP FLARED END SECTION SALVAGE & REINSTALL 18" RCP STORM SEWER 6' DIA CBMH WITH CASTING PER DETAIL 406 SALVAGE AND REINSTALL CASTING WITH NEW RINGS ITEM DESCRIPTION OF PAY ITEM UNIT CONTRACT THIS PERIOD TOTAL TO DATE BASE BID INLET PROTECTION 16" X 8" WET TAP, INCL 8" GATE VALVE & BOX HYDRANT HYDRANT EXTENSION SILT FENCE, MACHINE SLICED SEDIMENT CONTROL LOG, TYPE WOOD FIBER TEMPORARY MAILBOX CLEARING GRUBBING CLEAR BRUSH DITCH GRADING (AT FLARED END) DITCH GRADING CONCRETE HYDRANT SPLASH PAD 6" GATE VALVE AND BOX 8" GATE VALVE AND BOX VALVE BOX EXTENSION 1.5" CORPORATION STOP W/ SADDLE 2" CORPORATION STOP 1.5" CURB STOP & BOX 2" CURB STOP & BOX 1.5" TYPE "K" COPPER WATER SERVICE 2" TYPE "K" COPPER WATER SERVICE 4" DIP, CL. 52 WATERMAIN, INCL POLY WRAP 6" DIP, CL. 52 WATERMAIN, INCL POLY WRAP 10" HDPE WATERMAIN, DIRECTIONAL DRILL DUCTILE IRON FITTINGS 10" HDPE TO 8" DIP TRANSITION FITTINGS 4" INSULATION REMOVE AND DISPOSE OF EXISTING STORM SEWER PIPE REMOVE AND DISPOSE OF EXISTING STORM SEWER STRUCTURE CONNECT TO EXISTING STORM SEWER PIPE 12" RCP STORM SEWER, CL 5 QUANTITY UNIT PRICE AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT ITEM DESCRIPTION OF PAY ITEM UNIT CONTRACT THIS PERIOD TOTAL TO DATE 74 LS 1 $9,000.00 $9,000.00 0.00 $0.00 1.00 $9,000.00 75 LS 1 $5,117.50 $5,117.50 0.00 $0.00 1.00 $5,117.50 76 LF 225 $5.00 $1,125.00 0.00 $0.00 172.00 $860.00 77 LF 50 $8.00 $400.00 0.00 $0.00 50.00 $400.00 78 SY 80 $10.35 $828.00 0.00 $0.00 90.00 $931.50 79 SY 35 $32.00 $1,120.00 0.00 $0.00 0.00 $0.00 80 LF 2,000 $6.18 $12,360.00 0.00 $0.00 2,099.00 $12,971.82 81 SY 80 $75.90 $6,072.00 0.00 $0.00 90.00 $6,831.00 82 SY 35 $113.85 $3,984.75 0.00 $0.00 0.00 $0.00 83 LF 2,000 $32.49 $64,980.00 0.00 $0.00 2,111.00 $68,586.39 84 CY 300 $30.00 $9,000.00 0.00 $0.00 393.00 $11,790.00 85 SY 150 $7.67 $1,150.50 0.00 $0.00 1,233.00 $9,457.11 86 SY 1,700 $11.50 $19,550.00 0.00 $0.00 2,350.00 $27,025.00 $134,687.75 $0.00 $152,970.32 TOTALS - BASE CONTRACT $1,344,107.16 $0.00 $1,235,600.66 CO1-1 LS 1 $9,927.00 $9,927.00 0.00 $0.00 1.00 $9,927.00 $9,927.00 $0.00 $9,927.00 CO 3-1 LS 1 -$108,506.50 -$108,506.50 0.00 $0.00 0.00 $0.00 -$108,506.50 $0.00 $0.00 TOTALS - REVISED CONTRACT $1,245,527.66 $0.00 $1,245,527.66 SUBTOTAL BID ALTERNATE 2 BID ALTERNATE 2 - SPOT CURB REPLACEMENT MOBILIZATION TRAFFIC CONTROL SAWCUT BITUMINOUS PAVEMENT SAWCUT CONCRETE PAVEMENT REMOVE AND DISPOSE OF BITUMINOUS PAVEMENT (DRIVEWAY) REMOVE AND DISPOSE OF CONCRETE PAVEMENT (DRIVEWAY) REMOVE AND DISPOSE OF CONCRETE CURB & GUTTER - SPOT REPAIR BITUMINOUS DRIVEWAY PAVEMENT 6" CONCRETE DRIVEWAY PAVEMENT B618 CONCRETE CURB & GUTTER - SPOT REPAIR SODDING, TYPE LAWN TOPSOIL BORROW (LV) SEED MIXTURE 25-131 & HYDRAULIC MULCH SUBTOTAL - CHANGE ORDER NO. 1 ADD TRACER WIRE FOR ALL PROJECT SERVICES AND HYDRANTS SUBTOTAL - COMPENSATING CHANGE ORDER NO. 3 COMPENSATING CHANGE ORDER NO. 3 COMPENSATING CHANGE ORDER CHANGE ORDER NO. 1 CITY OF LAKE ELMO, MN TORRE PINES STREET, AND UTILITY IMPROVEMENTS PROJECT NO. 2020.122 CERTIFICATE OF COMPLETION DATE OF ISSUANCE: October 29, 2024 OWNER: CITY OF LAKE ELMO, MN CONTRACTOR: JACON LLC PROJECT NAME: TORRE PINES STREET AND UTILITY IMPROVEMENTS PROJECT NO.: 2020.122 This Certification of Completion applies to all work under the Contract Documents This Certification of Completion applies to the following specified parts of the Contract Documents I do hereby certify that the work to which this Certificate applies has been constructed in accordance with the Contract dated January 6, 2022. The above-mentioned improvement is hereby declared to be complete and acceptance of this work is recommended. DATE OF COMPLETION: September 29, 2023 Chad Isakson Reg. No. 49028 FOCUS Engineering, inc. THE WARRANTY PERIOD BEGINS September 29, 2023 AND ENDS September 29, 2024 Fifth Street Towers 150 South Fifth Street, Suite 700 Minneapolis, MN 55402 (612) 337-9300 telephone (612) 337-9310 fax kennedy-graven.com Affirmative Action, Equal Opportunity Employer MICHELLE E. WEINBERG Attorney at Law Direct Dial: (612) 337-9227 Email: mweinberg@kennedy-graven.com October 2, 2024 VIA FEDEX OVERNIGHT DELIVERY Tim Taylor Granite Re, Inc. 14001 Quailbrook Drive Oklahoma City, Oklahoma 73134 RE: Demand to Freeze Contract Funds for Torre Pines Street and Utility Improvements Project and Whistling Valley Street Project (Project No. 2020.123) PRINCIPAL: Jacon LLC BOND NO. GRMN45745A Dear Mr. Taylor: We represent the City of Lake Elmo (“City”), the obligee under the above-reference bond, which was provided by Jacon, LLC (“Contractor”) in connection with the City’s Torre Pines and Whistling Valley Street Projects. On August 24, 2023, the City received two letters from Granite Re, Inc. (“Surety”) instructing the City to freeze the contract funds because the Surety had received potential bond claims. A copy of these letters are enclosed for your convenience. The City has frozen the Project funds as requested, and currently holds the following amounts: $31,138.19 (Torre Pines) and $74,339.16 (Whistling Valley), or a total balance of $105,477.35. Copies of the final pay applications and change orders are also enclosed. The City is now ready to close out the Projects. All work has been completed, but the City has been unable to obtain the final paperwork indicating that all outstanding subcontractor contracts have been paid. It is the City’s understanding that the Contractor has declared bankruptcy and will not be addressing the subcontractor claims. The grant obtained by the City for these Projects requires that they be completely closed out before the end of this calendar year. The City is prepared to transmit the remaining Project funds to the Surety in exchange for a release from all outstanding payment claims. Please contact me as soon as possible to discuss the release of funds and close-out of these Projects. DOCSOPEN\LA515\1\979602.v1-9/30/24 Thank you for your prompt attention to this matter. Regards, KENNEDY & GRAVEN, CHARTERED /s/ Michelle E. Weinberg Michelle E. Weinberg Enclosures cc: Sarah Sonsalla, City Attorney Chad Isakson (Chad.Isakson@focusengineeringinc.com)