HomeMy WebLinkAbout#19 - Whistling Valley Street and Utilities Pay Request 12 STAFF REPORT DATE: November 6, 2024 CONSENT AGENDA ITEM: Approve Pay Request No. 11 (Final) for the Whistling Valley Street and Utility Improvements SUBMITTED BY: Chad Isakson, Project Engineer REVIEWED BY: Nicole Miller, City Administrator Sarah Sonsalla, City Attorney Clarissa Hadler, Finance Director Marty Powers, Public Works Director Jack Griffin, City Engineer ISSUE BEFORE COUNCIL: Should the City Council approve Pay Request No. 11 (Final) for the Whistling Valley Street and Utility Improvements? BACKGROUND: Jacon, LLC was awarded a construction contract on January 4, 2022 to complete the Whistling Valley Street and Utility Improvements. The contractor has completed the work in accordance with the contract, plans, and specifications, including all punch list items. The warranty period has expired and final payment effectively closes out the project. PROPOSAL DETAILS/ANALYSIS: Jacon, LLC has submitted Partial Pay Request No. 11 (Final) in the amount of $74,339.16. Final documentation has not been provided by the contractor, which includes the consent of surety, contractor lien waivers, and IC-134s. These documents are required by the contract to release final funds. The city has received communications from the surety company demanding project funds to be held or, if released, paid to the surety. The city has also received communications from subcontractors informing the city that they have not been paid by the general contractor for their work on the project. The city has been seeking resolution on the matter from the general contractor but has received limited communication in return. On October 2, 2024 the city attorney sent communications to the surety company to verify they will accept funds in exchange for a release from all outstanding payment claims. A formal response has not yet been received. In order for the city to seek reimbursement for all Project expenditures, it is critical that final payments be processed prior to the MPCA Grant Agreement expiration on December 31, 2024. Therefore, staff is recommendation that the city council approve the final payment subject to making the payment to contractor’s surety, provided that the surety accepts payment and releases the city from all outstanding claims or future payment obligations related to the Project. FISCAL IMPACT: None. Final payment is being recommended within the authorized project scope and budget. The final total project cost is projected to be $3,295,000 of which $1,641,400 is related to street improvements, $1,238,300 is public watermain improvements and $415,300 is private water connection and well sealing costs. The project is being paid through the MPCA Grant (3M Settlement funds) and the total project costs have come in below the authorized grant amount of $3,660,000. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Pay Request No. 11 (Final) for the Whistling Valley Street and Utility Improvements subject to making the payment to contractor’s surety, provided the surety accepts payment and releases the city from all outstanding claims or future payment obligations related to the Project. If removed from the consent agenda, the recommended motion for the action is as follows: “Move to approve Pay Request No. 11 (Final) in the amount of $74,339.16 for the Whistling Valley Street and Utility Improvements subject to making the payment to contractor’s surety, provided the surety accepts payment and releases the city from all outstanding claims or future payment obligations related to the Project”. ATTACHMENTS: 1. Partial Pay Estimate No. 11 (Final). 2. Certification of Completion. 3. Surety Correspondence. PROJECT PAY FORM PARTIAL PAY ESTIMATE NO. PERIOD OF ESTIMATE TO PROJECT OWNER:CONTRACTOR: 1. Original Contract Amount 2. Net Change Order Sum 3. Revised Contract (1+2) 4. *Work Completed 5. *Stored Materials 6. Subtotal (4+5) 7. Retainage* 8. Previous Payments 9. Amount Due (6-7-8) *Detailed Breakdown Attached START DATE:ON SCHEDULE SUBSTANTIAL COMPLETION: FINAL COMPLETION: ENGINEER'S CERTIFICATION:FOCUS Engineering, inc. DATE CONTRACTOR'S CERTIFICATION:CONTRACTOR DATE APPROVED BY OWNER:CITY OF LAKE ELMO, MINNESOTA DATE DATE BY BY YES NO The undersigned Contractor certifies that to the best of their knowledge, information and belief the work covered by this payment estimate has been completed in accordance with the contract documents, that all amounts have been paid by the contractor for work for which previous payment estimates was issued and payments received from the owner, and that current payment shown herein is now due. The undersigned certifies that the work has been reviewed and to the best of their knowledge and belief, the quantities shown in this estimate are correct and the work has been performed in accordance with the contract documents. ENGINEER 4/2/2024 BY 4/18/2022 5/25/2023 REVISED DAYS REMAINING 402 0 -312 10/14/2022 ORIGINAL DAYS CONTRACT CHANGE ORDER SUMMARY PAY ESTIMATE SUMMARY 11(FINAL) 4/1/20249/1/2023FROM WHISTLING VALLEY UTILITY AND STREET IMPROVEMENTS PROJECT NO. 2020.123 CITY OF LAKE ELMO 3800 LAVERNE AVENUE NORTH LAKE ELMO, MN 55042 ATTN: JACK GRIFFIN, CITY ENGINEER JACON, LLC 3900 LABORE ROAD VADNAIS HEIGHTS, MN 55110 ATTN: DANN REZABEK CONTRACT TIME TOTALS $173,260.35 $94,248.90 $74,339.16 NET CHANGE $79,011.45 CO-5 12/20/2022 $0.00 $0.00 $0.000.0% CCO-6 4/2/2024 $94,248.90 $2,275,278.74 CO-3 7/19/2022 $2,802.29 $0.00 $0.00 CO-4 9/2/2022 $12,432.00 $0.00 $2,349,617.90 CO-1 3/15/2022 $141,959.85 $0.00 $2,349,617.90 CO-2 6/7/2022 $16,066.21 $0.00 $2,349,617.90 No.Approval Date Amount $2,270,606.45 Additions Deductions $79,011.45 FOCUS Engineering, inc.PROJECT PAYMENT FORM Account Manager 10/10/2024 PARTIAL PAY ESTIMATE NO. 11(FINAL) WHISTLING VALLEY UTILITY AND STREET IMPROVEMENTS CITY OF LAKE ELMO, MINNESOTA PROJECT NO. 2020.123 QUANTITY UNIT PRICE AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT 1 LUMP SUM 1 $122,784.30 $122,784.30 0.00 $0.00 1.00 $122,784.30 2 ACRE 1 $12,012.90 $12,012.90 0.00 $0.00 1.00 $12,012.90 3 LIN FT 4679 $5.43 $25,406.97 0.00 $0.00 4,823.00 $26,188.89 4 SQ YD 13 $31.05 $403.65 0.00 $0.00 0.00 $0.00 5 SQ YD 30 $10.35 $310.50 0.00 $0.00 22.00 $227.70 6 SQ YD 34 $190.00 $6,460.00 0.00 $0.00 34.00 $6,460.00 7 LIN FT 670 $5.00 $3,350.00 0.00 $0.00 670.00 $3,350.00 8 SQ YD 55 $35.00 $1,925.00 0.00 $0.00 50.00 $1,750.00 9 SQ YD 23218 $5.00 $116,090.00 0.00 $0.00 23,218.00 $116,090.00 10 SQ YD 200 $10.35 $2,070.00 0.00 $0.00 200.00 $2,070.00 11 EACH 19 $45.00 $855.00 0.00 $0.00 19.00 $855.00 12 EACH 37 $341.89 $12,649.93 0.00 $0.00 10.00 $3,418.90 13 EACH 46 $200.00 $9,200.00 0.00 $0.00 46.00 $9,200.00 14 EACH 18 $150.00 $2,700.00 0.00 $0.00 28.00 $4,200.00 15 EACH 12 $50.00 $600.00 0.00 $0.00 12.00 $600.00 16 CU YD 10448 $0.79 $8,253.92 0.00 $0.00 693.00 $547.47 17 SQ FT 824 $7.32 $6,031.68 824.00 $6,031.68 824.00 $6,031.68 18 CU YD 4890 $31.20 $152,568.00 0.00 $0.00 5,165.00 $161,148.00 19 CU YD 3869 $20.30 $78,540.70 0.00 $0.00 3,939.00 $79,961.70 20 HOUR 40 $120.00 $4,800.00 0.00 $0.00 29.00 $3,480.00 21 TON 2210 $90.00 $198,900.00 0.00 $0.00 1,916.74 $172,506.60 22 TON 2945 $83.00 $244,435.00 0.00 $0.00 2,506.37 $208,028.71 23 TON 200 $156.00 $31,200.00 0.00 $0.00 55.03 $8,584.68 24 GAL 1628 $2.00 $3,256.00 0.00 $0.00 1,050.00 $2,100.00 25 LIN FT 1458 $14.00 $20,412.00 0.00 $0.00 1,458.00 $20,412.00 26 EACH 14 $250.00 $3,500.00 0.00 $0.00 14.00 $3,500.00 27 LIN FT 55 $21.00 $1,155.00 0.00 $0.00 40.00 $840.00 28 EACH 1 $420.00 $420.00 0.00 $0.00 1.00 $420.00 29 EACH 1 $12,300.00 $12,300.00 0.00 $0.00 1.00 $12,300.00 30 EACH 2 $1,500.00 $3,000.00 0.00 $0.00 2.00 $3,000.00 31 EACH 18 $675.00 $12,150.00 0.00 $0.00 19.00 $12,825.00 32 EACH 14 $500.00 $7,000.00 0.00 $0.00 14.00 $7,000.00 33 EACH 2 $4,025.00 $8,050.00 0.00 $0.00 2.00 $8,050.00 34 EACH 12 $7,500.00 $90,000.00 0.00 $0.00 12.00 $90,000.00 35 EACH 71 $770.00 $54,670.00 0.00 $0.00 44.00 $33,880.00 36 EACH 37 $485.00 $17,945.00 0.00 $0.00 37.00 $17,945.00 37 EACH 37 $550.00 $20,350.00 0.00 $0.00 37.00 $20,350.00 38 LIN FT 1189 $36.60 $43,517.40 0.00 $0.00 1,212.00 $44,359.20 39 EACH 11 $3,283.15 $36,114.65 0.00 $0.00 11.00 $36,114.65 40 LIN FT 112 $116.70 $13,070.40 0.00 $0.00 85.00 $9,919.50 41 LIN FT 816 $81.00 $66,096.00 0.00 $0.00 485.00 $39,285.00 42 LIN FT 6691 $71.25 $476,733.75 0.00 $0.00 6,993.00 $498,251.25 43 SQ YD 56 $34.00 $1,904.00 0.00 $0.00 23.60 $802.40 44 LB 3040 $6.83 $20,763.20 0.00 $0.00 3,026.00 $20,667.58 45 LIN FT 3849 $30.36 $116,855.64 0.00 $0.00 4,889.00 $148,430.04 46 LIN FT 1310 $30.80 $40,348.00 0.00 $0.00 1,665.00 $51,282.00 47 LIN FT 5284 $13.86 $73,236.24 0.00 $0.00 4,311.00 $59,750.46 48 SQ YD 13 $110.00 $1,430.00 0.00 $0.00 13.00 $1,430.00 49 EACH 19 $2,079.00 $39,501.00 0.00 $0.00 19.00 $39,501.00 50 LUMP SUM 1 $6,500.00 $6,500.00 0.15 $975.00 1.00 $6,500.00 51 SQ FT 63.31 $130.00 $8,230.30 0.00 $0.00 63.31 $8,230.30 52 EACH 10 $340.00 $3,400.00 0.00 $0.00 10.00 $3,400.00 53 LIN FT 1000 $3.00 $3,000.00 0.00 $0.00 0.00 $0.00 54 EACH 34 $220.00 $7,480.00 0.00 $0.00 34.00 $7,480.00 55 CU YD 678 $40.25 $27,289.50 0.00 $0.00 669.00 $26,927.25 56 SQ YD 6401 $11.67 $74,699.67 0.00 $0.00 4,812.00 $56,156.04 57 ACRE 0.5 $4,500.00 $2,250.00 0.60 $2,700.00 1.80 $8,100.00 58 SQ YD 2505 $2.60 $6,513.00 2,420.00 $6,292.00 8,712.00 $22,651.20 59 CY YD 50 $149.50 $7,475.00 0.00 $0.00 58.00 $8,671.00 60 EACH 2 $1,750.00 $3,500.00 0.00 $0.00 1.00 $1,750.00 61 LIN FT 12301 $3.00 $36,903.00 0.00 $0.00 12,180.00 $36,540.00 $2,412,566.30 $15,998.68 $2,318,317.40 NOTE: ** PREVAILING WAGE COSTS INCLUDED IN UNIT PRICE PER CHANGE ORDER NO.1 Orig. Contract Amount $2,270,606.45 TOTALS - BASE CONTRACT $2,412,566.30 $15,998.68 $2,318,317.40 ADJUST CASTING ADJUST CATCH BASIN REMOVE CASTING GEOTEXTILE FABRIC, TYPE V GEOGRID MOBILIZATION** REMOVE BITUMINOUS WALK REMOVE SIGN SALVAGE AND REINSTALL MAIL BOX ASSEMBLY** CLEARING AND GRUBBING** REMOVE CONCRETE CURB AND GUTTER REMOVE CONCRETE DRIVEWAY PAVEMENT REMOVE BITUMINOUS DRIVEWAY PAVEMENT SALVAGE AND REINSTALL DRIVEWAY PAVERS SAWING PAVEMENT (FULL DEPTH) REMOVE SEWER PIPE (STORM) REMOVE BITUMINOUS PAVEMENT (P)** ITEM DESCRIPTION OF PAY ITEM UNIT CONTRACT THIS PERIOD TOTAL TO DATE TYPE SP 9.5 WEARING COURSE MIX (2,B) (DRIVEWAYS & TRAIL) BITUMINOUS MATERIAL FOR TACK COAT 4" PVC SCHEDULE 40 PERF PE PIPE DRAIN W/ BACKFILL AND WRAP DRAINTILE CLEANOUT 12" HDPE STORM SEWER PIPE AGGREGATE BASE CL 6 (CV)(P)** COMMON EXCAVATION (P)** STREET SWEEPING TYPE SP 9.5 WEARING COURSE MIX (2,C) TYPE SP 12.5 WEARING COURSE MIXTURE (2,C) 12" FLARED END SECTION 6" CONCRETE HEADWALL CONCRETE FLUME FURNISH AND INSTALL CASTING ASSEMBLY R-3067-V CONNECT DRAINTILE TO EXISTING STORM STRUCTURE CONNECT TO EXISTING WATERMAIN HYDRANT AND GATE VALVE ASSEMBLY 10" HDPE TO 8" DIP TRANSITION FITTING 1.5" CURB STOP & BOX 1.5" CORPORATION STOP 1.5" TYPE K COPPER PIPE 8" GATE VALVE AND BOX 6" WATERMAIN DUCTILE IRON CL 52 8" WATERMAIN DUCTILE IRON CL 52 10" HDPE DR 11 WATERMAIN (DIRECTIONAL DRILLING) W/ 4700 LB TRACER WIRE** 4" INSULATION DUCTILE IRON FITTINGS CONCRETE CURB AND GUTTER DESIGN D412 CONCRETE CURB AND GUTTER DESIGN B618 24" CONCRETE RIBBON CURB 6" CONCRETE DRIVEWAY PAVEMENT INSTALL CONCRETE PEDESTRIAN RAMP TRAFFIC CONTROL SIGN PANELS TYPE C SIGN PANELS TYPE SPECIAL (STREET NAME SIGN) SILT FENCE PREASSEMBLED STORM DRAIN INLET PROTECTION COMMON TOPSOIL BORROW PULVERIZED (LV) SODDING TYPE MINERAL** SEEDING (SEED MIXTURE TYPE 25-141) EROSION CONTROL BLANKETS CATEGORY 3N CLASS 3 RIP-RAP WITH GEOTEXTILE FABRIC TEMPORARY ROCK CONSTRUCTION ENTRANCE SEDIMENT CONTROL LOG QUANTITY UNIT PRICE AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT ITEM DESCRIPTION OF PAY ITEM UNIT CONTRACT THIS PERIOD TOTAL TO DATE ITEM CO1-1 N/A 0 $141,959.85 $0.00 0.00 $0.00 0.00 $0.00 $0.00 $0.00 $0.00 ITEM CO2-1 LS 1 $16,066.21 $16,066.21 0.00 $0.00 1.00 $16,066.21 $16,066.21 $0.00 $16,066.21 CO3-1 LS 1 $368.00 $368.00 0.00 $0.00 1.00 $368.00 CO3-2 LF 53 $45.93 $2,434.29 0.00 $0.00 53.00 $2,434.29 $2,802.29 $0.00 $2,802.29 CO4-1 EA 12 $1,036.00 $12,432.00 0.00 $0.00 12.00 $12,432.00 $12,432.00 $0.00 $12,432.00 CHANGE ORDER NO.5 CO5-1 TIME EXTENSION N/A N/A $0.00 $0.00 0.00 $0.00 0.00 $0.00 $0.00 COMPENSATING CHANGE ORDER NO. 6 CO6-1 COMPENSATING CHANGE ORDER LS 1 -$94,248.90 -$94,248.90 0.00 $0.00 0.00 $0.00 -$94,248.90 $0.00 $0.00 TOTALS - CHANGE ORDERS -$62,948.40 $0.00 $31,300.50 TOTALS - REVISED CONTRACT $2,349,617.90 $15,998.68 $2,349,617.90 SUBTOTAL - COMPENSATING CHANGE ORDER NO. 6 SUBTOTAL - CHANGE ORDER NO. 2 ADD TRACER WIRE FOR ALL PROJECT SERVICES AND HYDRANTS CHANGE ORDER NO. 3 SALVAGE OF EXISTING BASE MATERIAL SUBTOTAL - CHANGE ORDER NO. 3 CONCRETE VALLEY GUTTER CHANGE ORDER NO. 4 HYDRANT SPLASH PAD SUBTOTAL - CHANGE ORDER NO. 4 CHANGE ORDER NO. 2 CHANGE ORDER NO.1 PREVAILING WAGE - **See note above and Change Order-1 for detail SUBTOTAL - CHANGE ORDER NO. 1 CITY OF LAKE ELMO, MN WHISTLING VALLEY STREET, AND UTILITY IMPROVEMENTS PROJECT NO. 2020.123 CERTIFICATE OF COMPLETION DATE OF ISSUANCE: October 29, 2024 OWNER: CITY OF LAKE ELMO, MN CONTRACTOR: JACON LLC PROJECT NAME: WHISTLING VALLEY STREET AND UTILITY IMPROVEMENTS PROJECT NO.: 2020.123 This Certification of Completion applies to all work under the Contract Documents This Certification of Completion applies to the following specified parts of the Contract Documents I do hereby certify that the work to which this Certificate applies has been constructed in accordance with the Contract dated January 5, 2022. The above-mentioned improvement is hereby declared to be complete and acceptance of this work is recommended. DATE OF COMPLETION: September 29, 2023 Chad Isakson Reg. No. 49028 FOCUS Engineering, inc. THE WARRANTY PERIOD BEGINS September 29, 2023 AND ENDS September 29, 2024 Fifth Street Towers 150 South Fifth Street, Suite 700 Minneapolis, MN 55402 (612) 337-9300 telephone (612) 337-9310 fax kennedy-graven.com Affirmative Action, Equal Opportunity Employer MICHELLE E. WEINBERG Attorney at Law Direct Dial: (612) 337-9227 Email: mweinberg@kennedy-graven.com October 2, 2024 VIA FEDEX OVERNIGHT DELIVERY Tim Taylor Granite Re, Inc. 14001 Quailbrook Drive Oklahoma City, Oklahoma 73134 RE: Demand to Freeze Contract Funds for Torre Pines Street and Utility Improvements Project and Whistling Valley Street Project (Project No. 2020.123) PRINCIPAL: Jacon LLC BOND NO. GRMN45745A Dear Mr. Taylor: We represent the City of Lake Elmo (“City”), the obligee under the above-reference bond, which was provided by Jacon, LLC (“Contractor”) in connection with the City’s Torre Pines and Whistling Valley Street Projects. On August 24, 2023, the City received two letters from Granite Re, Inc. (“Surety”) instructing the City to freeze the contract funds because the Surety had received potential bond claims. A copy of these letters are enclosed for your convenience. The City has frozen the Project funds as requested, and currently holds the following amounts: $31,138.19 (Torre Pines) and $74,339.16 (Whistling Valley), or a total balance of $105,477.35. Copies of the final pay applications and change orders are also enclosed. The City is now ready to close out the Projects. All work has been completed, but the City has been unable to obtain the final paperwork indicating that all outstanding subcontractor contracts have been paid. It is the City’s understanding that the Contractor has declared bankruptcy and will not be addressing the subcontractor claims. The grant obtained by the City for these Projects requires that they be completely closed out before the end of this calendar year. The City is prepared to transmit the remaining Project funds to the Surety in exchange for a release from all outstanding payment claims. Please contact me as soon as possible to discuss the release of funds and close-out of these Projects. DOCSOPEN\LA515\1\979602.v1-9/30/24 Thank you for your prompt attention to this matter. Regards, KENNEDY & GRAVEN, CHARTERED /s/ Michelle E. Weinberg Michelle E. Weinberg Enclosures cc: Sarah Sonsalla, City Attorney Chad Isakson (Chad.Isakson@focusengineeringinc.com)