HomeMy WebLinkAbout#08 - South Water Treatment Plant & Wells Engineering & Geotech
STAFF REPORT
DATE: August 6, 2025
CONSENT
TO: City Council
FROM: Jack Griffin, Sr. Project Manager
AGENDA ITEM: Authorize Engineering Services and Geotechnical Investigation for the
South Water Treatment Plant and Wells
REVIEWED BY: Nicole Miller, City Administrator
Clarissa Hadler, Finance Director
Marty Powers, Public Works Director
Nate Stanley, City Engineer
CORE STRATEGIES:
☐ Vibrant, inclusive, connected community ☐ Efficient, reliable, innovative services
☐ Responsive, transparent, adaptive governance ☐ Balanced Finances now and future
☒ Managed Growth ☒ Resilient Infrastructure
BACKGROUND: The City is seeking to construct the South Water Treatment Plant and Well 6 on the
northeast corner of Inwood Avenue (CSAH 13) and 10th Street (CSAH 10). The project is part of the
revised Water Supply Plan to construct new production wells (Well 6, and Well 3 or 7) to be located in the
south growth area and high‐pressure zone. Preliminary site investigations have identified approximately
8.2 acres to be acquired from parcel 28.029.142.0005, owned by Voran 711 Land Holdings LLC.
ISSUE BEFORE COUNCIL: Should the City Council approve the engineering services task order with
Stantec and geotechnical services contract with Braun Intertec for the South Water Treatment Plant and
Well 6 Project?
PROPOSAL DETAILS/ANALYSIS: The MPCA Grant Agreement Amendment #2 for the South Water
Treatment Plant and Well 6 Project has been prepared to fund Phase 2 of the Preliminary Site Investigations,
including a topographic survey and map of the existing conditions, wetland delineations, geotechnical
investigations, and the construction of a test well for Well 6.
The City is preparing to enter into a purchase option agreement with the property owner that will allow
right-of-entry by the City and its’s consultants/contractors for the purpose of conducting due diligence
investigations prior to closing on the property. The due diligence investigations to be completed are as
identified above and as further detailed in the attached engineering services proposal prepared by Stantec
and dated July 11, 2025, and the attached geotechnical services proposal prepared by Braun Intertec and
dated June 27, 2025.
FISCAL IMPACT: The Amended Grant Agreement provides for reimbursement to the City in the not to
exceed amount of $265,000; an increase of $155,000. Grant Amendment #2 also extends the expiration
date from December 31, 2025 to June 30, 2026. The Engineering Services Contract with Stantec includes
Preliminary Design and Site Investigation Services and that will be reimbursed by the Amended Grant
Agreement. The Braun Intertec Geotechnical Services will also be reimbursed by the Amended Grant
Agreement.
Construction and Engineering costs associated with the Test Well are not grant reimbursable, as they are
deemed to be associated with population growth. Engineering Services related to the test well are estimated
to be $30,000 and are part of the Stantec Task Order #5 Amendment. Test Well Construction costs are
estimated at $125,000. Contractor quotes/bids will be presented to Council for approval at a future date.
Test Well costs will be funded through the Water Enterprise Fund.
RECOMMENDATION: Staff is recommending the City Council approve the Stantec Task Order #5,
Amendment 2 for the South WTP and Wells in the not-to-exceed amended amount of $178,000 (an increase
of $88,000), and approve the Braun Intertec Proposal for Geotechnical Services in the not-to-exceed
amount of $53,000. The Recommended motion is as follows:
Motion to approve the Stantec Task Order #5, Amendment 2 for the South WTP and Wells in the
not-to-exceed amended amount of $178,000, and approve the Braun Intertec Proposal for
Geotechnical Services in the not-to-exceed amount of $53,000, contingent upon the MPCA Grant
Agreement, Amendment 2 being fully executed.
ATTACHMENTS:
1. Preliminary Design Site Investigations – Phase 2 Budget Worksheet.
2. Stantec Task Order #5, Amendment 2 for the South WTP and Wells.
SOUTH WATER TREATMENT PLANT AND WELL 6
CITY OF LAKE ELMO
SWIFT Contract 237685 Grant Amount:$110,000
Expiration Date: 31-Dec-25
PRELIMINARY DESIGN SITE INVESTIGATIONS - PHASE 2
DATE: JULY 2025
PROJECT MANAGEMENT/COORDINATION AND CITY REPRESENTATION (Bolton & Menk) $24,000
TOPOGRAPHIC SURVEY & EXISTING CONDITIONS MAPPING (Stantec) $27,000
WETLAND DELINEATION (Stantec) $18,000
GEOTECHNICAL INVESTIGATIONS (see attached Braun Proposal with 10% contingency) $53,000
PRELIMINARY SITE AND UTILITY LAYOUT (Stantec) $13,000
TEST WELL CONSTRUCTION FOR WELL 6 $175,000
Estimated Test Well Construction (Well Contractor - TBD) $125,000
Estimated Costs related to 2,500 LF temprary discharge pipe to redirect well
development and test pumping dishcares due to PFAS $20,000
Engineering Services: Design (Stantec) $13,000
Engineering Services: Construction Services (Stantec) $17,000
Estimated TOTAL Preliminary Design Site Investigation Costs $310,000
Estimated TOTAL Costs paid direclty by City (Test Well 6) $155,000
Estimated TOTAL Grant Amendment Amount $265,000
Contrant Time Extension Request 31-Mar-26
TASK ORDER No. 5 – South Water Treatment Plant and Wells – Amendment #2 Page 1 of 2
TASK ORDER No. 5 – A2
CITY OF LAKE ELMO, MINNESOTA - STANTEC CONSULTING SERVICES INC.
PROFESSIONAL ENGINEERING SERVICES AGREEMENT
In accordance with ARTICLE 1 of the Master AGREEMENT between the City of Lake Elmo (“CITY”) and
Stantec Consulting Services Inc. (“ENGINEER”), dated May 1, 2012 (“AGREEMENT”), the ENGINEER
agrees to provide Professional Engineering Support Services as follows:
SOUTH WATER TREAMENT PLANT AND WELLS – AMENDMENT #2
PROJECT OVERVIEW/PROFESSIONAL ENGINEERING SERVICES:
Task Order No. 5: The South Area Production Well and Treatment Study, Task Order 5, was authorized
for Professional Engineering Services to review and identify potential sites for at least two new
production Wells (Well 6, and Well 3 or 7), and identify the proposed scope of improvements for
permanent PFAS treatment for the south area production Wells.
Amendment #1: Task Order No. 5 Amendment #1 provides a partial engineering services budget
increase to continue with preliminary design services necessary to secure property for the water
treatment plant on the sites identified, and to continue working with the MPCA to refine and finalize
the scope of improvements to be approved by the MPCA for the South Water Treatment Plat full
project grant application.
Amendment #2: Task Order No. 5 Amendment #2 provides a continuation of the preliminary design
services necessary to secure property for the water treatment plant on the identified 8.2 acre site, and
specifically includes services to complete Topographic Survey and Existing Conditions Mapping, Wetland
Delineation, engineering services for design and construction services for Test Well 6, and a Preliminary
Site and Utility Layout based on the topographic survey and added site conditions. The scope of services
are further detailed in the attached engineering service proposal.
CITY RESPONSIBILITIES: The CITY (or its consultants) will provide the following:
1. Meet with ENGINEER on a periodic basis to discuss the work in progress.
2. Assist with property access for site reviews. Provide property information and record drawings
available for proposed sites to be evaluated.
3. Provide information on the existing water infrastructure as needed.
TIMES FOR RENDERING SERVICES: The work to be completed under this Task Order is considered
urgent due to the CITY’s need to have at least 1 new production well and the South Water Treatment
Plant online by May 30, 2027. The work shall be prioritized to provide preliminary design findings and
recommendations as needed to verify the feasibility of the proposed water treatment plant site, and
the site for Well 6, so that the City may pursue the acquisition of the site.
TASK ORDER No. 5 – South Water Treatment Plant and Wells – Amendment #2 Page 2 of 2
CITY’S REPRESENTATIVE AND CONTRACT ADMINISTRATION: The CITY’s representative with respect
to services rendered by ENGINEER under this TASK ORDER shall be the City Engineer. Project
correspondence must be addressed to:
Jack Griffin, P.E., Sr. Project Manager
City of Lake Elmo
3800 Laverne Avenue North
Lake Elmo, MN 55042
612.544.1352
Email: jack.griffin@bolton-menk.com
COMPENSATION: ENGINEER proposes to complete the Services as outlined in this letter on an hourly
rate basis together with reimbursable expenses in the not to exceed amounts as follows:
TASK ORDER NO. 5
Original TO#5 (Preliminary Design Services) $30,000
Amendment #1 (Continue with Preliminary Design Services) $60,000
Amendment #2 (Continue with Preliminary Design Services) $88,000
TOTAL SERVICES AUTHORIZED $178,000
Payment for Services shall be in accordance with ARTICLE 3.2 of the Master AGREEMENT. Invoices
should be sent once per month to the attention of the City Engineer.
ATTACHMENTS: Work to be implemented in accordance with the South Area Production Wells and
Treatment Plant Technical Memorandum dated April 4, 2024; incorporated herein by reference, and
Amendment #2 work to be completed in accordance with the Stantec Preliminary Investigations and
Design Support Proposal dated July 11, 2025.
APPROVAL AND ACCEPTANCE: Approval and Acceptance of this Task Order, including the
attachment(s) listed above, shall incorporate this document as part of the AGREEMENT. ENGINEER is
authorized to begin performance of services upon receipt of a copy of this Task Order signed by CITY.
The Effective Date of this Task Order is August 6, 2025.
STANTEC CONSULTING SERVICES INC. CITY OF LAKE ELMO, MINNESOTA
By _________________________________ By _______________________________ __
(Authorized Principal of the Firm) Nicole Miller, City Administrator