HomeMy WebLinkAbout#11 - 15th St. Improvements Pay Req STAFF REPORT
DATE: January 7, 2025
CONSENT
AGENDA ITEM: Accept Improvements and Approve Pay Request No. 2 (Final) for the 15th
Street North Improvements
SUBMITTED BY: Chad Isakson, Project Engineer
REVIEWED BY: Nicole Miller, City Administrator Marty Powers, Public Works Director
Clarissa Hadler, Finance Director
Jack Griffin, City Engineer
ISSUE BEFORE COUNCIL: Should the City Council accept improvements and approve Pay Request
No. 2 (Final) for the 15th Street North Improvements?
BACKGROUND: Bituminous Roadways, Inc. was awarded a construction contract on May 7, 2024 to
complete the 15th Street North Improvements. The contractor has now completed the work in accordance
with the contract, plans, and specifications, including all punch list items.
PROPOSAL DETAILS/ANALYSIS: Bituminous Roadways, Inc. has submitted Partial Pay Request No.
2 (Final) in the amount of $17,678.23. The Project Engineer has prepared a Certificate of Completion
indicating that all work is completed, including all punch list items, and is recommending the acceptance
of the improvements and release of final retainage. The one-year warranty will begin on November 7, 2024
and will extend through November 7, 2025.
FISCAL IMPACT: None. Final payment is being recommended within the authorized scope and budget
for the project. The final total project cost came in at $458,900 versus the post-bid approved project cost of
$532,000. The total final project cost includes contingency funds for professional services required to be
performed throughout the warranty period. The improvements were funded through a combination of
Municipal State Aid Funds, in the amount of $330,000; Special Assessments, in the amount of $64,400,
and General Tax levy funds in the amount of $64,500
RECOMMENDATION: Staff is recommending that the City Council, as part of the Consent Agenda,
accept the improvements and approve Pay Request No. 2 (Final) for the 15th Street North Improvements.
If removed from the consent agenda, the recommended motion for the action is as follows:
“Move to accept the improvements and approve Pay Request No. 2 (final) to Bituminous Roadways,
Inc. in the amount of $17,678.23 for the 15th Street North Improvements”.
ATTACHMENTS:
1. Partial Pay Estimate No. 2 (Final).
2. Certificate of Completion.
PROJECT PAY FORM
PARTIAL PAY ESTIMATE NO.
PERIOD OF ESTIMATE
TO
PROJECT OWNER: CONTRACTOR:
1. Original Contract Amount
2. Net Change Order Sum
3. Revised Contract (1+2)
4. *Work Completed
5. *Stored Materials
6. Subtotal (4+5)
7. Retainage*
8. Previous Payments
9. Amount Due (6-7-8)
*Detailed Breakdown Attached
START DATE:ON SCHEDULE
SUBSTANTIAL COMPLETION:X
FINAL COMPLETION:
ENGINEER'S CERTIFICATION: KLJ Engineering, inc.
DATE
CONTRACTOR'S CERTIFICATION: CONTRACTOR
DATE
APPROVED BY OWNER:CITY OF LAKE ELMO, MINNESOTA
DATE DATE
No.Approval
Date
Amount $381,004.40
Additions Deductions -$27,439.70
2 11/29/2024 $27,439.70 $353,564.70
1 8/9/2024 $0.00 $0.00 $353,564.70
$353,564.70
$0.00
$335,886.47
$0.000.0%
CONTRACT TIME
TOTALS $0.00 $27,439.70 $17,678.23
NET CHANGE ($27,439.70)
CONTRACT CHANGE ORDER SUMMARY PAY ESTIMATE SUMMARY
2 (Final)
9/30/20249/1/2024FROM
15TH ST SEGMENT IMPROVEMENTS
PROJECT NO. 2023.121 and SAP 206-110-002
CITY OF LAKE ELMO
3880 LAVERNE AVENUE NORTH
LAKE ELMO, MN 55042
ATTN: CHAD ISAKSON, P.E., PROJECT ENGINEER
BITUMINOUS ROADWAYS, INC.
3080 LEXINGTON AVE SO
EAGAN, MN 55121
ATTN: PAUL HILDESTAD, PROJECT MANAGER
8/5/2024
10/1/2024
REVISED DAYS
REMAINING
57
0
1
9/15/2024
ORIGINAL DAYS
BY
BY
YES
NO
The undersigned Contractor certifies that to the best of their
knowledge, information and belief the work covered by this payment
estimate has been completed in accordance with the contract
documents, that all amounts have been paid by the contractor for
work for which previous payment estimates was issued and payments
received from the owner, and that current payment shown herein is
now due.
The undersigned certifies that the work has been reviewed and to the
best of their knowledge and belief, the quantities shown in this
estimate are correct and the work has been performed in accordance
with the contract documents.
ENGINEER
BY
FOCUS Engineering, inc.PROJECT PAYMENT FORM
12/3/2024
12/3/2024
Mark Rohweder Digitally signed by Mark Rohweder
DN: C=US, E=mark.rohweder@kljeng.com,
CN=Mark Rohweder
Date: 2024.12.03 12:13:22-07'00'
PAUL HILDESTAD Digitally signed by PAUL HILDESTAD
DN: C=US, E=PAUL.HILDESTAD@BITROADS.COM,
CN=PAUL HILDESTAD
Date: 2024.12.03 13:24:36-06'00'
PARTIAL PAY ESTIMATE NO.2
15TH ST SEGMENT IMPROVEMENTS
CITY OF LAKE ELMO, MINNESOTA
PROJECT NO. 2023.121 and SAP 206-110-002
QUANTITY UNIT PRICE AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT
1 2021.501/00010 LUMP SUM 1 $22,000.00 $22,000.00 1.00 $22,000.00 1.00 $22,000.00
2 2104.502/01220 EACH 1 $42.00 $42.00 1.00 $42.00 1.00 $42.00
3 2104.502/02445 EACH 1 $26.00 $26.00 1.00 $26.00 1.00 $26.00
4 2104.502/03300 EACH 5 $42.00 $210.00 5.00 $210.00 5.00 $210.00
5 2104.503/00205 LIN FT 172 $2.75 $473.00 172.00 $473.00 172.00 $473.00
6 2104.504/00120 SQ YD 18 $22.00 $396.00 18.00 $396.00 18.00 $396.00
7 2112.604/00010 SQ YD 2140 $6.25 $13,375.00 0.00 $0.00 0.00 $0.00
8 2112.604/00010 SQ YD 10701 $2.00 $21,402.00 10,701.00 $21,402.00 10,701.00 $21,402.00
9 2118.507/00080 CU YD 146 $43.00 $6,278.00 146.00 $6,278.00 146.00 $6,278.00
10 2123.610/00410 HOUR 20 $100.00 $2,000.00 9.00 $900.00 9.00 $900.00
11 2130.523/00010 M GALLON 59 $55.00 $3,245.00 6.00 $330.00 6.00 $330.00
12 2215.504/00010 SQ YD 11658 $3.00 $34,974.00 11,658.00 $34,974.00 11,658.00 $34,974.00
13 2215.507/00010 CU YD 1295 $17.00 $22,015.00 1,295.00 $22,015.00 1,295.00 $22,015.00
14 2232.504/00060 SQ YD 29 $7.00 $203.00 0.00 $0.00 0.00 $0.00
15 2357.506/00010 GALLON 749 $1.00 $749.00 600.00 $600.00 600.00 $600.00
16 2360.509/12300 TON 1294 $85.00 $109,990.00 1,244.44 $105,777.40 1,244.44 $105,777.40
17 2360.509/22305 TON 1294 $85.00 $109,990.00 1,251.19 $106,351.15 1,251.19 $106,351.15
18 2563.601/00010 LUMP SUM 1 $8,500.00 $8,500.00 1.00 $8,500.00 1.00 $8,500.00
19 2564.602/01515 EACH 5 $700.00 $3,500.00 5.00 $3,500.00 5.00 $3,500.00
20 2564.602/01520 EACH 1 $26.00 $26.00 1.00 $26.00 1.00 $26.00
21 2564.618/00010 SQ FT 15 $65.00 $975.00 15.00 $975.00 15.00 $975.00
22 2573.502/00110 EACH 2 $100.00 $200.00 2.00 $200.00 2.00 $200.00
23 2573.502/00140 EACH 8 $155.00 $1,240.00 8.00 $1,240.00 8.00 $1,240.00
24 2573.503/00064 LIN FT 728 $2.75 $2,002.00 728.00 $2,002.00 728.00 $2,002.00
25 2574.508/00011 POUND 73 $5.60 $408.80 0.00 $0.00 0.00 $0.00
26 2575.508/21111 POUND 37 $31.00 $1,147.00 0.00 $0.00 0.00 $0.00
27 2575.523/00020 M GALLON 4 $1,000.00 $4,000.00 0.00 $0.00 0.00 $0.00
28 2582.503/40106 LIN FT 5136 $1.45 $7,447.20 5,168.00 $7,493.60 5,168.00 $7,493.60
29 2582.503/40124 LIN FT 12 $65.65 $787.80 15.00 $984.75 15.00 $984.75
30 2582.503/40404 LIN FT 1284 $2.65 $3,402.60 2,592.00 $6,868.80 2,592.00 $6,868.80
$381,004.40 $353,564.70 $353,564.70
TOTALS - CONTRACT $381,004.40 $353,564.70 $353,564.70
SALVAGE SIGN
SAWING BIT PAVEMENT (FULL DEPTH)
INSTALL SIGN
INSTALL DELINEATOR / MARKER PANEL
FULL DEPTH RECLAMATION
HAUL FULL DEPTH RECLAMATION (LV)
SUBGRADE CORRECTION
SUBGRADE PREPARATION
AGGREGATE SURFACING (CV) FROM STOCKPILE
STREET SWEEPER (WITH PICKUP BROOM)
WATER
TRAFFIC CONTROL
BITUMINOUS MATERIAL FOR TACK COAT
TYPE SP 12.5 NON WEAR COURSE MIX (2,C)
TYPE SP 9.5 WEARING COURSE MIX (2,C)
SIGN
STORM DRAIN INLET PROTECTION
CULVERT END CONTROLS
CONTRACT THIS PERIOD TOTAL TO DATE
REMOVE BITUMINOUS PAVEMENT
ITEM MN/DOT NO.DESCRIPTION OF PAY ITEM UNIT
MOBILIZATION
REMOVE SIGN
SALVAGE DELINEATOR/ MARKER PANEL
MILL BITUMINOUS SURFACE (2.0'')
BASE BID TOTALS
SEDIMENT CONTROL LOG TYPE COMPOST
FERTILIZER TYPE 1
SEED MIXTURE 21-111
RAPID STABILIZATION METHOD 3
6'' SOLID LINE MULTI COMP GR IN (WR)
24'' SOLID LINE MULTI COMP GR IN (WR)
4'' DBLE SOLID LINE MULTI COMP GR IN (WR)
CITY OF LAKE ELMO, MN 15TH ST IMPROVEMENTS S.A.P. 206-110-002 PROJECT NO. 2023.121 CERTIFICATE OF COMPLETION DATE OF ISSUANCE: November 22, 2024 OWNER: CITY OF LAKE ELMO, MN CONTRACTOR: BITUMINOUS ROADWAYS, INC. PROJECT NAME: 15TH ST IMPROVEMENTS PROJECT NO.: S.A.P. 206-11-002; City Project No. 2022.121 This Certification of Completion applies to all work under the Contract Documents This Certification of Completion applies to the following specified parts of the Contract Documents I do hereby certify that the work to which this Certificate applies has been constructed in accordance with the Contract dated June 27, 2024. The above-mentioned improvement is hereby declared to be complete and acceptance of this work is recommended. DATE OF COMPLETION: November 7, 2024 Kevin Courtney, P.E. Reg. No. 58728 KLJ Engineering, inc. THE WARRANTY PERIOD BEGINS November 7, 2024 AND ENDS November 7, 2025