HomeMy WebLinkAbout#17 - Rescue 1 Hose Storage and Equipment Refurbish STAFF REPORT
DATE: January 7, 2025
CONSENT
TO: City Council
FROM: Dustin Kalis, Fire Chief
AGENDA ITEM: CIP Project F-004 – Rescue 1 Hose Storage and Equipment Refurbish
REVIEWED BY: Nicole Miller, City Administrator
Clarissa Hadler, Finance Director
BACKGROUND:
The Fire Department is requesting to approval to refurbish the hose and equipment storage area
of Rescue 1. This project will refurbish existing hose storage area to include preconnected hose
capabilities and refurbish tool and equipment areas to better utilize available equipment storage
space. The 2025-2034 Capital Improvement Plan included this project for 2025.
ISSUE BEFORE COUNCIL:
Should the City Council approve the Rescue 1 hose storage and equipment refurbish
recommended by staff, as outlined in the 2025 Capital Improvement Plan?
PROPOSAL DETAILS/ANALYSIS:
The fire department replaces or refurbishes vehicles on a rotating basis based on each individual
vehicles need. This project will allow for better apparatus utilization and response capability.
The Rescue 1 refurbishment will provide a refurbish of the existing hose storage area to include
preconnected hose capabilities and refurbish tool and equipment areas to better utilize available
storage space for updated equipment. The project will be completed by Rosenbauer as they were
the original builders of the apparatus.
FISCAL IMPACT:
The cost of this project has a budgeted amount of $30,000.00 and will be funded through the
vehicle replacement fund as identified in the 2025 CIP.
OPTIONS:
- Approve Rescue 1 hose storage and equipment refurbish project.
- Do not approve project.
RECOMMENDATION: If removed from the consent agenda…
“Motion to approve the purchase of 2025 CIP Project F-004 - 2025 Rescue 1 hose storage and
equipment refurbish at a cost not to exceed $30,000.00 as detailed in the City’s Purchasing
Policy.”
ATTACHMENTS:
• Project estimate from Rosenbauer America.
Lake Elmo MN R1 14674
Work to be Quoted to customer
Front bumper-Re do gravel shield to accommodate 200’ of 1 ¾” fire
hose and 200’ of 2 ½” both on swivel chicksands. This will require
different bumper extensions as well as new lid . 20 hr
L1- Remove current crosslay hose storage ,li le giant ladder framing
,and divider wall providing storage for unused floa ng backboard.
Provide and install self latching slide master pull out shelf half depth
of the transverse compartment and as wide as allowable mounted on
raised por on of comp . Provide and install a slide master out and
down shelf as wide and deep as compartment will allow (turtle le
both trays ). Provide a means to store two brooms , two shovels ,two
new York hooks in upper le por on of compartment. 13 hr
L2- Customer would like a price on a CTECH tool box and installa on
in lower le corner of compartment replacing current box. The
compartment currently has two adjustable shelves we would flip
these over and mount out and down shelves with trays and turtle le
. The larger of the two li le giant ladders will be moved to the far
right side of L2 and the exis ng tool board will be adjusted to
accommodate this . 13hr
R1- Remove crosslay hose storage , remove cribbing struts and
divider they are mounted to, same as L1. Provide and install half
body depth latching slide master with tray (turtle led) with
sta onary tool board mounted to the tray (right side ). Storage of
same combined tools as L1 (brooms ,NY hooks ,shovels ). The Axe ,
sledge hammer and possibly hi li jack from the front of the tool
board in R2 will be relocated to the new sta onary tool board
mounted to the slide master tray right side . 14 hr
R2- Remount large cribbing struts originally in R1/L1 to the exis ng
gear grid tool board or front wall what ever works be er , also
improve exis ng strut mounts to save space and ease of use . 10 hr
Add a addi onal 15hr for extra fabrica on of unknown parts
1.Two half body depth slide master latching slide out trays
(L1/R1). Es mated @ $2800 for both together.
2.One slide master out and down tray compartment width
“unknown depth”. L1 Es mated @ $660
3.Two out and down slide master shelves replacing L2 adjustable
shelves . Es mated @ $1300 for both together.
4.Poten al Ctech tool box replacing current cra sman box (L2)
$2200
Es mated labor Hours totaling: 85 @ $185.00 = $15,725
Es mated purchase parts totaling: $6960.00.
Es mated Materials cost totaling: $4000.00.
Es mate total: $26,685.00 this is subject to change once we get exact
measurements for the slides and out and downs.