HomeMy WebLinkAbout#06 - Easton Village 7th Security Reduction STAFF REPORT
DATE: January 21, 2025
CONSENT
AGENDA ITEM: Accept Sanitary Sewer and Watermain Improvements and Approve
Security Reductions for Easton Village 7th Addition
SUBMITTED BY: Nate Stanley, City Engineer
REVIEWED BY: Nicole Miller, City Administrator
Jason Stopa, Community Development Director Marty Powers, Public Works Director
Chad Isakson, Assistant City Engineer
ISSUE BEFORE COUNCIL: Should the City Council accept the public sanitary sewer and watermain
improvements and approve security reductions for the Easton Village 7th Addition?
PROPOSAL DETAILS/ANALYSIS: Staff has received and processed a request to accept the public
sanitary sewer and watermain improvements and reduce the development security for the Easton Village
7th Addition. This request has been reviewed and is recommended for approval in accordance with the
approved Development Agreement, and contingent on the developer being current with all other payments
and obligations in accordance with the Development Agreement, including a positive escrow balance as
required by the City. The Development Security amount is recommended to be reduced as follows:
Current Security Amount Proposed Security Amount
1. Easton Village 7th Addition $ 1,137,575 $ 830,410
The Easton Village 7th Addition public sanitary sewer and watermain improvements are in the warranty
period as identified on the attached Certificate of Completion. Twenty-five percent (25%) of the original
security amount will be retained until the warranty periods have expired.
FISCAL IMPACT: It is the City’s goal to retain at all times during the subdivision improvements a
security amount that is adequate to ensure completion of all elements of the improvements as protection to
the city tax payers against the potential of developer default.
RECOMMENDATION: Staff is recommending that the City Council, as part of the Consent Agenda,
accept the public sanitary sewer and watermain improvements and approve the security reductions as
detailed in the attached worksheet for the Easton Village 7th Addition, all contingent on the developer being
current with all other payments and obligations in accordance with the Development Agreement, including
a positive escrow balance as required by the City. If removed from the consent agenda, the recommended
motion for the action is as follows:
“Move to accept the public sanitary sewer and watermain improvements and approve the security
reductions as detailed in the attached worksheet for the Easton Village 7th Addition, all contingent on
the developer being current with all other payments and obligations in accordance with the
Development Agreement.”
ATTACHMENTS:
1. Watermain and Sanitary Sewer Certificate of Completion – Easton Village 7th Addition.
2. Security Reduction Worksheet – Easton Village 7th Addition.
CERTIFICATE OF COMPLETION
DATE OF ISSUANCE: JANUARY 21, 2025
OWNER: CITY OF LAKE ELMO, MN
DEVELOPER: CHASE DEVELOPMENT, INC.
SUBDIVISION
NAME:
EASTON VILLAGE 6TH AND 7TH ADDITIONS
PROJECT NO.: 2021.122
This Certification of Completion applies to all work under the Development Agreement
This Certification of Completion applies to the following specified parts of the Development
Agreement
Section 35.A – Public sanitary sewer and watermain
Section 35.B – Public improvements including street construction, including concrete curb
and gutter, sidewalks and trails, materials and equipment.
I do hereby certify that the work to which this Certificate applies has been constructed in accordance
with the Development Agreement dated April 8, 2024. The above-mentioned improvement is
hereby declared to be complete, and acceptance of this work is recommended.
DATE OF COMPLETION: January 21, 2025
Chad Isakson Reg. No. 49028
Bolton & Menk, Inc.
Section 35.A Warranty Period Begins January 21, 2025 and ends January 21, 2027
Section 35.B Warranty Period Begins
and ends
EASTON VILLAGE 7TH ADDITION June 30, 2026
DEVELOPMENT AGREEMENT AMOUNTS
CATEGORY CONSTRUCTION 125% REMARKS #1 #2 #3 #4 #5 #6
Site Grading Agreement NA NA
Sanitary Sewer $142,816 $178,520 75%$133,890
Watermain $184,827 $231,034 75%$173,275
Storm Sewer $109,907 $137,384
Streets and Sidewalks $343,977 $429,971
Trails $12,150 $15,188
Surface Water Facilities NA NA
Street Lighting $12,000 $15,000 By Xcel Energy
Street Signs and Traffic Control Signs $3,925 $4,906
Private Utilities (electricity, natural gas, telephone, and cable)NA NA
Landscaping $34,134 $42,668
Tree Preservation and Restoration NA NA
Wetland Mitigation and Buffers NA NA
Monuments $2,400 $3,000
Erosion Control $58,924 $73,655
Misc. NA NA
Record Drawings $5,000 $6,250
TOTALS $910,060 $1,137,575 RELEASED AMOUNTS:$307,165 $0 $0 $0 $0 $0
CUMMULATIVE AMOUNTS:$307,165
SECURITY AMOUNT REMAINING:$830,410
DATE:1/21/2025
Time of Performance:
REDUCTIONS