HomeMy WebLinkAbout#11 - 2026 Street and Utility Improvements STAFF REPORT DATE: June 3, 2025 REGULAR TO: City Council FROM: Nate Stanley, City Engineer AGENDA ITEM: Authorize Preliminary Design, Geotechnical Services and Feasibility Report for the 2026 Street and Utility Improvements REVIEWED BY: Nicole Miller, City Administrator Clarissa Hadler, Finance Director Marty Powers, Public Works Director Chad Isakson, Assistant City Engineer Jack Griffin, Senior Project Manager CORE STRATEGIES: ☐ Vibrant, inclusive, connected community ☐ Efficient, reliable, innovative services ☒ Responsive, transparent, adaptive governance ☐ Balanced Finances now and future ☒ Managed Growth ☒ Resilient Infrastructure BACKGROUND: The City maintains a 10-year revolving Street Capital Improvement Program (Street CIP) to promote the strategic use of limited financial resources while maintaining, developing or replacing the City’s local street network to an acceptable level of service. The Street CIP consists of a 10- year overview of scheduled capital street projects to address pavements that have or are projected to exceed their useful pavement service life and can no longer be effectively maintained, and to address transportation capacity limitations. The 10-year horizon of the CIP provides the city with an opportunity to evaluate project priorities annually and to adjust the timing, scope, and cost of projects as new information becomes available. ISSUE BEFORE COUNCIL: Should the City Council authorize preliminary design, geotechnical services and the preparation of a feasibility report for the 2026 Street and Utility Improvements? PROPOSAL DETAILS/ANALYSIS: The following public streets have been identified for improvement in 2026: • 26th Street North, Inwood Avenue North to Imperial Avenue North (Lake Elmo Heights); • 27th Street North, Inwood Avenue North to Imperial Avenue North (Lake Elmo Heights); • Imperial Avenue North (Lake Elmo Heights); • Innsdale Avenue North, 27th Avenue North to CDS (Lake Elmo Heights); • Insdale Avenue North, Stillwater Boulevard to CDS (Lake Elmo Heights); • Inwood Avenue North, Stillwater Boulevard to CDS (Eagle Point Creek Estates) The project will include street and drainage improvements along and within the public right-of-way, with the type and extent of the street improvement to be based upon a geotechnical services investigation of the existing pavement sections and conditions. Existing storm sewer inspections will be conducted to identify storm sewer repairs or corrections deemed necessary to restore or improve the existing roadway drainage. There is existing public watermain along the streets, which was installed in 2005. Minor water system repairs and or corrections may be incorporated into the improvements as needed. All areas reside outside of the City’s planned MUSA boundaries, therefore, no sanitary sewer extensions are planned with this Project. In order to initiate the improvement, the council must authorize the preparation of a feasibility report as required by the statutory process for public improvements that are specially assessed. The feasibility report will advise on the scope of recommended improvements; provide estimated project costs; identify easement and right-of-way, permits and other requirements of other local agencies needed to implement the improvements; recommend whether the improvements should be best made as proposed or in connection with some other improvement; and advise if the improvements are necessary, cost effective, and feasible. The report will also provide a proposed preliminary assessment roll for each of the benefitting properties based upon the City’s Special Assessment Policy for Local Improvements. The City Engineer has prepared the project work plan and engineering services task order to initiate detailed topographic survey and preliminary design for this Project. These preliminary design efforts are recommended for this Project to better identify the specific infrastructure improvements that will be needed, before reliable costs and proposed assessments can be determined and brought forward in the feasibility report. The City Engineer worked with Bolton & Menk, Inc. to prepare a preliminary design scope of work and fee estimate. Staff is recommending that the City authorize the City Administrator to sign a Task Order for Preliminary Design Services with Bolton & Menk in the amount of $59,879. The City Engineer also obtained proposals from AET, Inc. and Braun Intertec for Geotechnical Investigations. The Geotechnical Services will review the in-place roadway structure and soil conditions and provide recommendations on proposed roadway improvements. Staff is recommending that the City authorize the City Administrator to retain AET, Inc. in the amount of $13,991.25 (Braun Intertec proposal was in the amount of $20,830). A project schedule is attached and outlines the implementation timeframe necessary to address public involvement, acquire field survey, identify and obtain project related easements, complete the detailed design, and to receive contractor bids to ready the improvements for construction in 2026. FISCAL IMPACT: $101,804.25. If authorized, Bolton & Menk will complete topographic survey and preliminary design services in a not-to-exceed amount of $59,879; City Engineering staff will be the engineering lead for all services and prepare the feasibility report in a not-to-exceed amount of $27,934 and AET Inc. will complete Geotechnical Services in a not-to-exceed amount of $13,991.25. If the improvements are ordered, the preliminary design costs will be charged against the project fund and become assessable to the benefitting properties. Should the project not be constructed, these costs cannot be assessed. OPTIONS: • Approve preliminary design, geotechnical services, and preparation of a feasibility report. • Do not move forward with the project. RECOMMENDATION: Staff is recommending that the City Council approve a Resolution Ordering Preparation of Preliminary Design, Geotechnical Services and Feasibility Report for the 2026 Street and Utility Improvements. The recommended motion for this action is as follows: Motion to approve Resolution No. 2025-043, ordering preparation of Preliminary Design, Geotechnical Services and Feasibility Report for the 2026 Street and Utility Improvements. ATTACHMENTS: 1. Resolution Ordering Preparation of Preliminary Design, Geotechnical Services and Feasibility Report for the 2026 Street and Utility Improvements. 2. Project Location Map. 3. Project Schedule. 4. Bolton & Menk Task Order for Preliminary Design Engineering Support Services. CITY OF LAKE ELMO WASHINGTON COUNTY STATE OF MINNESOTA RESOLUTION NO. 2025-043 A RESOLUTION ORDERING THE PREPARATION OF PRELIMINARY DESIGN, GEOTECHNICAL SERVICES AND FEASIBILITY REPORT FOR THE 2026 STREET AND UTILITY IMPROVENTS WHEREAS, the City maintains a 10-year revolving Street Capital Improvement Program (Street CIP) to promote the strategic use of limited financial resources while maintaining, developing or replacing the City’s local street network; and WHEREAS, the Street CIP represents the City’s long-range street improvement program that identifies the present and future needs and priorities, and develops a schedule of public improvements to address the most essential improvements first; and WHEREAS, the public streets located along 26th Street North, from Inwood Avenue North to Imperial Avenue North (Lake Elmo Heights); 27th Street North, Inwood Avenue North to Imperial Avenue North (Lake Elmo Heights); Imperial Avenue North, from the north cul-de-sac to the south cul-de-sac (Lake Elmo Heights); Innsdale Avenue North, from 27th Street North to the cul-de-sac (Lake Elmo Heights); Innsdale Avenue North, from Stillwater Boulevard to the cul-de-sac (Lake Elmo Heights); and Inwood Avenue North, from Stillwater Boulevard to the cul-de-sac (Eagle Point Creek Estates), have been identified for improvement in the year 2026; and WHEREAS, it is proposed to assess the benefiting properties for all or a portion of the cost of the improvement, pursuant to the City’s Special Assessment Policy and Minnesota Statues Chapter 429. NOW, THEREFORE, BE IT RESOLVED, 1. That the proposed improvement, called 2026 Street and Utility Improvements, be referred to the City Engineer, and his consultants to complete the preliminary design engineering, geotechnical investigations, and prepare a feasibility report in accordance with Minnesota Statues Chapter 429 for the proposed improvements, and to report to the council with all convenient speed advising the council in a preliminary way as to whether the proposed improvement is necessary, cost-effective, and feasible; whether it should be best made as proposed or in connection with some other improvement; the estimated cost of the improvement as recommended; and a description of the methodology used to calculate individual assessments for affected parcels. ADOPTED BY THE LAKE ELMO CITY COUNCIL ON THE THIRD DAY OF JUNE, 2025. CITY OF LAKE ELMO By: __________________________ Charles Cadenhead (Seal) Mayor ATTEST: ________________________________ Julie Johnson City Clerk 36 10th 60th 5th Hudson Ke a t s La k e E l m o 50th 15th In w o o d 34th 20th 27th 53rd 55th Jane Lake Jane Ja m a c a 57th 59th Hi l l 47th 7th 31st 51st 43rd 39th De m o n t r e v i l l e 45th 38th Ma n n i n g Stillwater 24th 26th 42nd Islan d 58t h 9th 30th 32nd Ki m b r o 21st Ja d e 6t h Iv o r y H i l l t o p Is l e O l s o n L a k e 8th Julep 12th Jewel 44th 56th Ir i s 22nd 37th 36th 35th La v e r n e Jun i p e r Ann i k a Jasmine Ja m l e y Le g i o n L i l y Kl o n d i k e 16th Upper 33Rd Imp e r i a l Lin d e n 3rd Ki r k w o o d 33rd Deer Pond Hy t r a i l Irving Hid d e n B a y 4th Jerom e 14th Ju n e 28th Vi l l a g e Tapestry Ja s p e r Eagle Poi n t Jonquil Wildflower La y t o n Pr i v a t e Ke l v i n I r o n w o o d Highla n d s Ja n e r o L e e w a r d Ci m a r r o n 10 t h S t r e e t Kind r e d Ja m e s Ir i s h Prairiev i e w Ja c k P i n e 49th Ja y Lower 31st Marquess Ir v i n Li l a c Mo n a r c h Lower 8th L i s b o n Birc h B a r k 40thLav e n d e r Kr a f t La m p e r t Bl a z i n g s t a r Whistling Valley J u n c o Li t t l e B l u e s t e m 11th La d y S l i p p e r 5 t h S t r e e t Windbreak Su n f i s h L a k e P a r k I n b o u n d Iv y w o o d In n s d a l e 3rd Street Ma r q u e s s T r a i l L a n g l y Ju n o La n s i n g Ju l i a n n e Upper 30th 6t h S t r e e t Lisbon Avenue Ir w i n Sunflower 41st WB I 9 4 T o I n w o o d A v e N Upper 7 t h Queen Upper 9th 57 t h S t r e e t Upper 42Nd 2 7 t h S t r e e t 15th Str e e t Cherrywoo d WB I94 To Ke a t s A v e N 44th Street 41st Street Ja s m i n e A v e n u e 59th Street Hu m m i n g b i r d Jer o m e A v e n u e Keats Ave N T o W B I 9 4 Manning Ave N T o W B I 9 4 Hill Trail 3 0 t h S t r e e t 33 r d S t r e e t 24t h S t r e e t 20 t h S t r e e t 58t h S t r e e t Legion Lane Lar k s p u r Demontreville Tra i l Hu m m i n g b o r d Ac c e s s 21st La v e r n e 57 t h S t r e e t 32nd Ma n n i n g Ir i s h 35th 34th Li l y Lilac 55th Jamaca 35th La v e r n e 56th Sti l l w a t e r 36 La k e E l m o La n g l y La y t o n Li l a c 33rd Li l y 10 t h S t r e e t M a n n i n g 6th Street Is l e 21st 9th 57th 36th Kirkwood 53rd Lind e n Whistli n g V a l l e y Ma n n i n g 50th 5th 33rd Highlands 59th 6th Street I n n s d a l e I r o n w o o d Linden Legion Lane LindenPr i v a t e Julep 28th Vi l l a g e Lilac Iv y Inn s d a l e Lower 8th 31st 57th Lisbon 9th 39th Ke a t s 55th 56 t h 36 Isle Jule p Ir v i n 55th Man n i n g 32nd La v e r n e 37th K e l v i n Ma n n i n g Le g i o n 9th Ivy 34th La y t o n Li n d e n Ja d e 5th Hudson 36th 39t h DOWNSLAKE LAKE ELMOREGIONALPARK RESERVE LAKE ELMO LAKE JANE SUNFISH LAKE OLSONLAKE LAKE DEMONTREVILLE CLEARLAKE HORSESHOELAKE ROSELAKE REIDPARK VFWPARK LIONS PARK TANA RIDGEPARK City of Woodbury STONEGATEPARK KRAMERLAKE GOOSELAKEARMSTRONGLAKE RIDGEPARK KE A T S A V E N EAGLE POINTLAKE TABLYNPARK HEIGHTSPARK LAKE JANEHILLS PARK PEBBLEPARK City of Oakdale West LakelandTownship Baytown Township City ofOak ParkHeights City of GrantCity ofPine Springs DEMONTREVILLEWILDLIFE PARK DEMONTREVILLEPARK KLEISPARK CARRIAGESTATIONPARK SUNFISH LAKEPARK City ofOak ParkHeights StillwaterTownship HOMESTEDPARK 7 HERITAGEPARK VERONICAPOND GOETSCHEL'SPOND City ofAfton TablynPark Eagle PointCreek Estates Lake ElmoHeights Torre Pines Farms ofLake Elmo Parkview Estates WildflowersShores HuppertAdd BeautCrest Estates FriedrichHghts Kenridge Add Prairie RidgeOffice Park Eagle PointBusiness Park Stonegate Hammes CountryVista Whistling Valley MidlandMeadows DavidNelson Est TheHomestead TartanMeadows The Forest Schwartz-Martinco Add PackardPark EdenPark HeritageFarm LonesomePine Add DownsLake Est MyronEllman Elmo View Cty AudPlat No. 8 Lake Elmo Park Brookman Add Sunfish Ponds Hamlet OnSunfish Lake ParkMeadows Tapestry AtCharlottes' Grove Berschen's Shores DawcinAcres LakeJaneHighlands TealPass Est Fox FireEstates Meyer'sPineridge KrausesAdd Springborn'sGreen Acres Arabian Hills JudithMaryManor Lake Elmo Vista Rolling Hills Est Prairie Hamlet HiddenMeadowsOf Lake Elmo Jesse'sHideaway DiscoverCrossing Arvold'sAcres St. Croix'sSanctuary TamarackFarm Est CarriageStation TanaRidgeJohn M DayFarm Add The Fields ofSt. Croix2nd Add The Fieldsof St. Croix BluestemAt The Fieldsof St. Croix BurrwoodEstBergmannAdd DemontrevilleHighlands Add Lane's DemontrevilleCountry ClubDemontrevilleHighlands Add Olson Lake Add Oace AcresAdd LakeJaneHills Lake JaneManor No. 1 ThreeLakesFarm Add Bordners Garner Farmettes Royal Golf Club Southwind Hunters Crossing HammesEstates Savona Boulder Ponds Inwood Lakewood Crossing2nd Addition Easton Village Wildflower Cimarron Legacy At Northstar Village Preserve ST. CROIX SANCTUARY PARK EDENPARK PILOTPARK HAMMESPARK GOOSE LAKEPARK F Map Date: November 2020010.5 Miles Created By: Planning Department \\Minneapolis4\Offices\Focus\CLIENTS\Lake Elmo\1-Client Management\City Council Schedule\2025 CC meetings\06-03-2025\READY-2026 Street Project Order Feasibility, Authorize Survey & Preliminary Design\3-Project Schedule.docx PROJECT SCHEDULE CITY OF LAKE ELMO 2026 STREET AND UTILITY PROJECT June 3, 2025 Council authorizes preparation of Preliminary Design, Geotechnical Services and Feasibility Report. August 13, 2025 Neighborhood informational meeting on scope of improvements. September 16, 2025 Presentation of Feasibility Report and Preliminary Design, City Council accepts Feasibility Report and orders Public Hearing on improvements. September 25, 2025 Neighborhood informational meeting to review improvements and preliminary assessments. October 21, 2025 Council conducts Public Hearing on improvements and orders Preparation of Final Plans and Specifications. January 6, 2026 Council approves final plans and authorizes advertisement for bids. February 5, 2026 Project Bid Date: Receive Contractor Bids. February 17, 2026 Council accepts bids and awards contract. March, 2026 Conduct Pre-Construction Meeting and issue Notice to Proceed. · August 28, 2026 Substantial Completion · October 16, 2026 Final Completion *Final Assessment Hearing Schedule TBD TASK ORDER NO. 28 – 2026 STREET AND UTILITY IMPROVEMENTS Page 1 of 4 TASK ORDER No. 28 CITY OF LAKE ELMO, MINNESOTA – BOLTON AND MENK, INC. PROFESSIONAL CONSULTING SERVICES AGREEMENT In accordance with ARTICLE 1 of the Master AGREEMENT between the City of Lake Elmo (“CITY”) and Bolton and Menk, Inc. (“ENGINEER”), dated MARCH 20, 2013 (“AGREEMENT”), the ENGINEER agrees to provide Professional Consulting Support Services as follows: 2026 STREET AND UTILITY IMPROVEMENTS PROJECT OVERVIEW: This Project includes Professional Engineering Services for the 2026 Street and Utility Improvements, to be authorized in phases and beginning with preliminary design and feasibility report support services. Upon completion of the preliminary design and feasibility report support services, this Task Order may be later amended to authorize the preparation of plans and specifications and/or construction phase support services as may be applicable. The improvements include the rehabilitation of the public streets, consisting of approximately 7,200 feet (1.4 miles) of local streets located in 2 neighborhoods as follows: • 26th Street North, Inwood Avenue North to Imperial Avenue North (Lake Elmo Heights) • 27th Street North, Inwood Avenue North to Imperial Avenue North (Lake Elmo Heights) • Imperial Avenue North (Lake Elmo Heights) • Innsdale Avenue North, 27th Avenue North to CDS (Lake Elmo Heights) • Innsdale Avenue North, Stillwater Boulevard to CDS (Lake Elmo Heights) • Inwood Avenue North, Stillwater Boulevard to CDS (Eagle Point Creek Estates) The improvements will consist of either a full street reconstruction or full-depth pavement reclamation, to be determined through a detailed geotechnical investigation. New concrete curb and gutter will be installed to replace the existing bituminous curb. In addition to the street improvements, the storm sewer or drainage along each street will be reviewed and upgraded as necessary to prevent water from standing on or along the street, and to repair or replace existing storm sewer infrastructure as recommended through the preliminary design site investigations. The neighborhoods are served by existing City watermain and a review of the existing infrastructure will be completed. Any improvements or repairs will be recommended as a part of the preliminary design. All project streets are outside of the City’s MUSA boundary and therefore, no sanitary sewer extensions will be considered at this time. SERVICES TO BE PROVIDED BY ENGINEER: Bolton and Menk, Inc., Inc. shall provide the following Professional Engineering Services: 1. Project management throughout the course of work for preparation of preliminary design documents including a monthly PMT meeting, and submittal of a weekly progress memo and job to date budget form. TASK ORDER NO. 28 – 2026 STREET AND UTILITY IMPROVEMENTS Page 2 of 4 2. Work with city staff to develop success criteria for the project, obtain project information and formalize the budget and schedule. 3. Review of existing as-built plans as made available by the CITY. 4. Site visit to review existing pavement conditions, drainage patterns and to define project limits based on existing pavements. 5. Survey: Coordinate Gopher State One Call utility locates and perform topographic survey of existing conditions within project limits for the purposes of preparing design documents. 6. Perform condition review of existing drainage and storm sewer systems, perform unconfined visual observations, and make recommendations regarding additional storm sewer televising , if needed. 7. Make recommendations of storm sewer repairs and new storm sewer improvements to be completed as part of the project. 8. Review Geotechnical Report findings and recommendations obtained by the CITY . 9. Prepare preliminary design including street rehabilitation recommendations, watermain layout, where applicable, and stormwater management. 10. Review County GIS maps and half section maps to review existing right-of-way and easements within the project area. Identify right of way and easement needs to construct the proposed infrastructure. 11. Identify any major utility conflicts related to the proposed preliminary design. 12. Identify permits required to complete the proposed work. 13. Prepare Preliminary Design Memorandum outlining the proposed scope of improvements and a summary of the stormwater management plan for meeting watershed permit requirements. 14. Prepare opinion of probable cost based on the preliminary design layout . Project Costs shall be categorized as directed by the CITY for the purpose of preparing preliminary assessment calculations and for use in the feasibility report. Assessment calculations to be performed by the CITY. 15. Prepare Exhibit(s) showing the proposed improvements for use in the Feasibility Report. DELIVERABLES: • Preliminary Plans in electronic format (PDF). • Preliminary Opinion of Total Probable Project Costs. • Preliminary Design Memorandum summarizing preliminary final design assumptions, proposed scope of improvements, watershed management requirements and mitigation measures, and other performance criteria incorporated into the project. • Identification of easements needed for the construction of the Project. Preliminary easement needs Exhibit(s), if needed. • Feasibility Report Exhibit(s). CITY ENGINEER RESPONSIBILITES: The CITY ENGINEER (or its consultants) will provide the following: 1. Retain geotechnical investigation and provide copy of geotechnical report. 2. Coordination with the public and conduct public meetings. 3. Presentation(s) to the City Council. 4. Easement negotiations and acquisition. 5. Review of preliminary plans. TASK ORDER NO. 28 – 2026 STREET AND UTILITY IMPROVEMENTS Page 3 of 4 6. Preparation of the Feasibility Report, including assessment calculations, assessment Role and Conduct Public Improvement Hearing. TIMES FOR RENDERING SERVICES: ENGINEER and CITY ENGINEER shall perform their services and provide deliverables in accordance with the following schedule, contingent upon receipt of the Geotechnical Services Report. 1. June 3, 2025. Preliminary Design Services and Feasibility Report preparation authorized. 2. September 16, 2025. Presentation of Preliminary Design Findings and Recommendations to Council, Presentation of Feasibility Report to Council. CITY’S REPRESENTATIVE AND CONTRACT ADMINISTRATION: The CITY’s representative with respect to services rendered by ENGINEER under this TASK ORDER shall be the City Engineer. Project correspondence must be addressed to: Nate Stanley, P.E., City Engineer City of Lake Elmo 3800 Laverne Avenue North Lake Elmo, MN 55042 763.358.1997 Email: nathan.stanley@bolton-menk.com COMPENSATION: Compensation to ENGINEER shall be based on the hourly billing rates for each staff as assigned and provided in the ENGINEER’S Proposal and Fee Estimate for the work. Invoices shall be submitted once each month and should be sent to the attention of the City Engineer. Payment for Services shall be in accordance with ARTICLE 3.2 of the Master AGREEMENT. Compensation to CITY ENGINEER shall be based upon the Professional Services AGREEMENT, including any Amendments to said AGREEMENT. Compensation to ENGINEER for Project Management, Topographic Survey, and the Preliminary Design Services shall be on an hourly rate basis in a not-to-exceed amount of $59,879. Compensation to CITY ENGINEER for Project Management, Public Engagement, and Preparation of Feasibility Report shall be on an hourly rate basis in a not-to-exceed amount of $27,934. ADDITIONAL SERVICES: If authorized by the CITY, ENGINEER shall furnish or obtain from others Additional Services which are not considered under this Task Order. Such services shall be compensated for on an Hourly Rate basis in an amount approved by the City prior to any services being started or as otherwise mutually agreed. The CITY is not obligated to compensate ENGINEER for services completed outside the approved scope of work which are completed prior to ENGINEER submitting a written request to the CITY, and receiving written approval of the CITY. ATTACHMENTS: ENGINEER’s Fee Estimate for 2026 Street and Utility Preliminary Design Services. CITY ENGINEER’s Fee Estimate for the 2026 Street and Utility Feasibility Report. TASK ORDER NO. 28 – 2026 STREET AND UTILITY IMPROVEMENTS Page 4 of 4 APPROVAL AND ACCEPTANCE: Approval and Acceptance of this Task Order, including the attachment(s) listed above, shall incorporate this document as part of the AGREEMENT. ENGINEER and CITY ENGINEER are authorized to begin performance of services upon receipt of a copy of this Task Order signed by CITY. The Effective Date of this Task Order is June 3, 2025. BOLTON AND MENK, INC. CITY OF LAKE ELMO, MINNESOTA By _________________________________ By ______________________________________ (Authorized Principal of the Firm) City Administrator Client:City of Lake Elmo Project:2026 Street and Utility Improvements TASK NO.WORK TASK DESCRIPTION Pr o j e c t M a n a g e r Mi k e W a r n e r Pr o j e c t E n g i n e e r Co l e t o n N e l s o n En g i n e e r i n g Te c h n i c i a n St o r m w a t e r M a n a g e r Br e n t J o h n s o n St o r m w a t e r E n g i n e e r Br i a n R u c k e r Su r v e y M a n a g e r Ro n A l w i n Gr a d u a t e S u r v e y o r Je f f C o r n e l l Su r v e y F i e l d Te c h n i c i a n Su r v e y C r e w (2 - p e r s o n ) Cl e r i c a l Co u r t n e y M a u l Totals 1.0 Preliminary Design 1.1 Project Management 10 2 12 1.2 Develop Critical Success Criteria 1 1 2 1.3 Review Existing As-Built Plans 2 2 4 1.4 Site Visit to Review Existing Conditions 4 4 8 1.5 Topographic Survey of Existing Conditions 1 4 10 12 80 12 4 123 1.6 Review Condition of Existing Storm Sewer System 1 12 10 23 1.7 Recommendation of Storm Sewer Repairs and Modifications 1 4 1 16 22 1.8 Review Geotechnical Report 2 4 6 1.9 Preliminary Design and Stormwater Management Plan 8 4 24 1 6 43 1.10 Review Existing R/W and Easements and Identify Needs 1 4 2 7 1.11 Identify Major Private Utility Conflicts 1 2 3 1.12 Identify Applicable Permits 1 2 1 2 6 1.13 Prepare Preliminary Design Memo 4 20 4 28 1.14 Prepare Preliminary Opinion of Probable Costs 2 16 18 1.15 Prepare Feasibility Report Exhibit(s)2 4 20 26 TOTAL HOURS - TASK 1 39 75 66 3 28 12 12 80 12 4 331 BOLTON & MENK, INC. 2026 Street and Utility Improvements City of Lake Elmo, Minnesota Client: City of Lake Elmo Project: 2026 Street and Utility Improvements TASK NO.WORK TASK DESCRIPTION Pr o j e c t M a n a g e r Mi k e W a r n e r Pr o j e c t E n g i n e e r Co l e t o n N e l s o n En g i n e e r i n g Te c h n i c i a n St o r m w a t e r M a n a g e r Br e n t J o h n s o n St o r m w a t e r E n g i n e e r Br i a n R u c k e r Su r v e y M a n a g e r Ro n A l w i n Gr a d u a t e S u r v e y o r Je f f C o r n e l l Su r v e y F i e l d Te c h n i c i a n Su r v e y C r e w (2 - p e r s o n ) Cl e r i c a l Co u r t n e y M a u l Total Hours Total Cost 1.0 Preliminary Design 39 75 66 3 28 12 12 80 12 4 331 $59,879 TOTAL HOURS 39 75 66 3 28 12 12 80 12 4 331 AVERAGE HOURLY RATE $204.00 $163.00 $152.00 $230.00 $170.00 $205.00 $140.00 $196.00 $325.00 $124.00 SUBTOTAL $7,956 $12,225 $10,032 $690 $4,760 $2,460 $1,680 $15,680 $3,900 $496 $59,879TOTAL FEE BOLTON & MENK, INC. 2026 Street and Utility Improvements City of Lake Elmo, Minnesota Client: City of Lake Elmo Project: 2026 Street and Utility Project Feasibility Report Task No.Work Task Description Sr . P r o j e c t Ma n a g e r Pr o j e c t M a n a g e r Pr o j e c t E n g i n e e r Co m m u n i c a t i o n s Sp e c i a l i s t Ad m i n i s t r a t i v e As s i s t a n t Totals 1.0 Feasibility Report 1.1 Project Management and Coordination 12 12 8 32 1.2 Public Meetings and Outreach 8 8 8 16 4 44 1.3 Review of Preliminary Design Materials 2 2 8 12 1.4 Preparation of Preliminary Assessment Roll 12 12 1.5 Preparation of Feasibility Report 4 8 40 4 56 1.6 QA/QC 2 2 2 6 Subtotal Hours - Task 1 28 32 78 16 8 162 Estimated Hours Bolton & Menk, Inc. Client: City of Lake Elmo Project: 2026 Street and Utility Project Feasibility Report Task No.Work Task Description Sr . P r o j e c t Ma n a g e r Pr o j e c t Ma n a g e r Pr o j e c t E n g i n e e r Co m m u n i c a t i o n s S p e c i a l i s t Ad m i n i s t r a t i v e As s i s t a n t Total Hours Total Cost 1.0 Feasibility Report 28 32 78 16 8 162 $27,934 Total Hours 28 32 78 16 8 162 Average Hourly Rate $225.00 $188.00 $159.00 $144.00 $114.00 Subtotal $6,300 $6,016 $12,402 $2,304 $912 Detailed Cost Estimate Total Not-to-Exceed Fee Bolton & Menk, Inc. $27,934