HomeMy WebLinkAbout#10 - Well 2 PFAS Removal Pay Req 3 STAFF REPORT DATE: June 17, 2025 CONSENT TO: City Council FROM: Chad Isakson, Project Engineer AGENDA ITEM: Approve Pay Request No. 3 for the Well No. 2 PFAS Removal Equipment REVIEWED BY: Nicole Miller, City Administrator Clarissa Hadler, Finance Director Marty Powers, Public Works Director Nate Stanley, City Engineer CORE STRATEGIES: ☐ Vibrant, inclusive, connected community ☐ Efficient, reliable, innovative services ☐ Responsive, transparent, adaptive governance ☐ Balanced Finances now and future ☐ Managed Growth ☒ Resilient Infrastructure BACKGROUND: Aqueous Vets, LLC was awarded a construction contract on October 15, 2024 to supply the City Well No. 2 PFAS Removal Equipment. ISSUE BEFORE COUNCIL: Should the City Council approve Pay Request No. 3 for the Well No. 2 PFAS Removal Equipment? PROPOSAL DETAILS/ANALYSIS: Aqueous Vets, LLC has submitted Partial Pay Request No. 3 in the amount of $60,526.87. The request has been reviewed and payment is recommended in the amount requested. In accordance with the contract documents, the City has retained 5% of the total work completed. The amount retained is $24,837.30. FISCAL IMPACT: None. Partial payment is proposed in accordance with the Contract for the project. Payment remains within the authorized scope and budget. The Project is being funded through a 3M Settlement Grant. RECOMMENDATION: Staff is recommending that the City Council approve, as part of the Consent Agenda, Pay Request No. 3 for the Well No. 2 PFAS Removal Equipment. If removed from the consent agenda, the recommended motion for the action is as follows: Motion to approve Pay Request No. 3 in the amount of $60,526.87 to Aqueous Vets, LLC for the Well No. 2 PFAS Removal Equipment. ATTACHMENTS: 1. Partial Pay Estimate No. 3. PROJECT PAY FORM PARTIAL PAY ESTIMATE NO. PERIOD OF ESTIMATE TO PROJECT OWNER: CONTRACTOR: 1. Original Contract Amount 2. Net Change Order Sum 3. Revised Contract (1+2) 4. *Work Completed 5. *Stored Materials 6. Subtotal (4+5) 7. Retainage* 8. Previous Payments 9. Amount Due (6-7-8) *Detailed Breakdown Attached START DATE: ON SCHEDULE MILESTONE 1 (EQ. DELIVERED) MILESTONE 2 (MEDIA INSTALL) SUBSTANTIAL COMPLETION:X FINAL COMPLETION: ENGINEER'S CERTIFICATION: DATE CONTRACTOR'S CERTIFICATION:CONTRACTOR DATE APPROVED BY OWNER:CITY OF LAKE ELMO, MINNESOTA DATE DATE BY YES NO The undersigned Contractor certifies that to the best of their knowledge, information and belief the work covered by this payment estimate has been completed in accordance with the contract documents, that all amounts have been paid by the contractor for work for which previous payment estimates was issued and payments received from the owner, and that current payment shown herein is now due. The undersigned certifies that the work has been reviewed and to the best of their knowledge and belief, the quantities shown in this estimate are correct and the work has been performed in accordance with the contract documents. ENGINEER BY 11/18/2024 8/1/2025 REVISED DAYS 256 04/30/2025 ORIGINAL DAYS 5/16/2025 5/30/2025 REMAINING 0 CONTRACT CHANGE ORDER SUMMARY PAY ESTIMATE SUMMARY 3 5/30/20255/9/2025FROM WELL 2 PFAS REMOVAL EQUIPMENT PROJECT NO. 2023.115 CITY OF LAKE ELMO 3880 LAVERNE AVENUE NORTH LAKE ELMO, MN 55042 ATTN: JACK GRIFFIN, CITY ENGINEER AQUEOUS Vets, LLC 16761 CLEAR CREEK ROAD REDDING, CA 96001 ATTN: LINDSIE HABEN, PROJECT/COST ACCOUNTANT CONTRACT TIME TOTALS $0.00 $0.00 $60,526.87 NET CHANGE $0.00 $24,837.305.0% $411,381.81 $0.00 $496,745.98 $660,970.71 $496,745.98 No.Approval Date Amount $660,970.71 Additions Deductions $0.00 FOCUS Engineering, inc. PROJECT PAYMENT FORM PARTIAL PAY ESTIMATE NO.3 WELL 2 PFAS REMOVAL EQUIPMENT CITY OF LAKE ELMO, MINNESOTA PROJECT NO. 2023.115 QUANTITY UNIT PRICE AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT BASE BID 1 LS 1 $9,500.00 $9,500.00 0.15 $1,425.00 0.80 $7,600.00 2 LS 1 $315,000.00 $315,000.00 0.15 $47,250.00 0.80 $252,000.00 3 LS 1 $24,000.00 $24,000.00 0.15 $3,600.00 0.80 $19,200.00 4 EA 25 $350.00 $8,750.00 3.75 $1,312.50 20.00 $7,000.00 5 LS 1 $6,500.00 $6,500.00 1.00 $6,500.00 1.00 $6,500.00 6 LS 1 $14,500.00 $14,500.00 0.25 $3,625.00 0.25 $3,625.00 7 LS 1 $29,124.06 $29,124.06 0.00 $0.00 1.00 $29,124.06 8 CY 546 $428.57 $233,999.22 0.00 $0.00 354.90 $152,099.49 9 LS 1 $19,597.43 $19,597.43 0.00 $0.00 1.00 $19,597.43 $660,970.71 $63,712.50 $496,745.98 TOTALS: BASE CONTRACT $660,970.71 $63,712.50 $496,745.98 BASE BID TOTALS 800 GPM LEAD/LAG ANION EXCHANGE TREATMENT SYSTEM FOR WELL NO. 2 (2 TANKS) CARTRIDGE FILTER HOUSING AND ACCESSORIES CARTRIDGE FILTERS FREIGHT TO JOBSITE (LAKE ELMO, MN) FIELD SERVICES TAXES (EQUIPMENT AND MATERIALS ONLY: @ 8.38%) PRE-RINSED ANION EXCHANGE (IX) MEDIA - PUROLITE PUROFANE 694E TAXES (RINSED IX MATERIAL ONLY: @ 8.38%) PROJECT SUBMITTAL AND O&M MANUALS ITEM DESCRIPTION OF PAY ITEM UNIT CONTRACT THIS PERIOD TOTAL TO DATE