HomeMy WebLinkAbout#04 - 0-I-94 Lift Station and FM STAFF REPORT DATE: July 1, 2025 REGULAR TO: City Council FROM: Nate Stanley, City Engineer AGENDA ITEM: I-94 Lift Station and Forcemain Improvements – Authorize Purchase of New Pumps REVIEWED BY: Nicole Miller, City Administrator Clarissa Hadler, Finance Director Marty Powers, Public Works Director Chad Isakson, Assistant City Engineer CORE STRATEGIES: ☐ Vibrant, inclusive, connected community ☐ Efficient, reliable, innovative services ☐ Responsive, transparent, adaptive governance ☐ Balanced Finances now and future ☒ Managed Growth ☒ Resilient Infrastructure BACKGROUND: Improvements to the I-94 Lift Station and Forcemain located on Hudson Boulevard are being completed as part of the 2025 Capital Improvement Plan. The Project was moved up in the CIP to address immediate concerns with a fatigued forcemain that has resulted in multiple breaks and high-cost emergency repairs. The replacement of a failing 90-inch CMP culvert with a 72-inch RCP culvert is included in the scope of improvements as well. On June 17, 2025, the City Council approved the plans and specifications and ordered the advertisement for bid for the project. ISSUE BEFORE COUNCIL: Should the City Council authorize the purchase of new pumps for the I-94 Lift Station? PROPOSAL DETAILS/ANALYSIS: As part of the forcemain design, the sanitary sewer service area was reviewed and analyzed to address current and future operations, based on the ultimate sanitary sewer service needs provided by the Planning Department. The system was also reviewed with respect to the Met Council sewer improvements currently in construction, to ensure that the lift station operations are capable for meeting Met Council interim and ultimate discharge conditions. Through this review it has been determined that the lift station pumps will need to be replaced, with the new pumps being operational at the time the new forcemain is placed into operation. The recommended replacement pumps have been identified for direct purchase by the city. Pump Information: • Three (3) Flygt pumps are recommended for purchase from Electric Pump (sole seller of the city’s preferred pump). o Initial operation of the station will have 1 pump running at a time to meet Met Council capacity restrictions. The anticipated pumping rate is 1,100 GPM with one pump operational. o The ultimate operation of the station will have 2 pumps running at a time o Two (2) mixing pipe attachments to stir up grease formations • Ultimate pumping rate of 1,700 GPM o Meets ultimate MUSA needs planned for this lift station • No electrical or generator systems require modifications with the proposed pumps • An impeller can be changed out for a low cost increase in pumping rate if future needs require a higher pumping rate and Met Council’s system can accept it. The pumps are necessary for the continued operation of the city lift station once the new forcemain is installed and the new Met Council connection is live. Both projects are planned to be in place in the fall of 2025. The estimated lead time on delivery of new pumps is 15 weeks after a purchase order is signed. FISCAL IMPACT: The estimated cost to purchase three pumps, install them, and complete programming adjustments is estimated to be $170,000. Staff is requesting authorization to purchase the pumps from Electric Pump to be paid for out of the Sanitary Sewer Enterprise Fund. Installation and programming efforts will be quoted out or hired per the city’s purchasing policy at a later date. RECOMMENDATION: Staff is recommending that the City Council authorize the purchase of three new pumps for the I-94 Lift Station. The recommended motion is: “Motion to authorize the purchase of three new Flygt pumps for the I-94 Lift Station within the authorized $170,000 project budget.” ATTACHMENTS: 1. None