STAFF REPORT <br />DATE: January 16, 2024 <br /> CONSENT <br /> <br />AGENDA ITEM: Accept Improvements, Approve Compensating Change Order No. 3, and <br />Approve Pay Request No. 5 (Final) for the 2023 Trail Improvements <br /> <br />SUBMITTED BY: Mike Rusenovich, Project Engineer <br /> <br />REVIEWED BY: Clark Schroeder, Interim City Administrator Marty Powers, Public Works Director <br /> Jack Griffin, City Engineer <br /> Chad Isakson, Assistant City Engineer <br /> <br /> <br />ISSUE BEFORE COUNCIL: Should the City Council accept the improvements, approve Compensating <br />Change Order No. 3, and approve Pay Request No. 5 (Final) for the 2023 Trail Improvements? <br /> <br />BACKGROUND: OMG Midwest Inc., DBA Minnesota Paving & Materials was awarded a construction <br />contract on June 6, 2023 for the 2023 Trail Improvements. The contractor has completed the work in <br />accordance with the contract, plans, and specifications, including all punch list items. <br /> <br />PROPOSAL DETAILS/ANALYSIS: A compensating change order has been prepared and executed to <br />adjust the final contract amount by $23,050.63 based on the actual quantities installed for the Project. In <br />addition, the contractor has submitted Pay Request No. 5 (Final) in the amount of $39,245.07. The Project <br />Engineer has reviewed these requests and is recommending approval of the compensating change order, <br />final pay estimate and the acceptance of the improvements. A Certificate of Completion has been prepared <br />indicating that all work is completed, including all punch list items, and is recommending the acceptance <br />of the improvements and release of final retainage. Project acceptance will initiate the one-year warranty <br />period, which will begin on January 16, 2024 and will expire on January 16, 2025. <br /> <br />FISCAL IMPACT: Final payment is being recommended within the authorized scope and approved <br />change orders for the project. The final construction contract amount came in at $582,535.70 vs. the original <br />construction contract amount of $549,359.21. Project costs came in higher than estimated due to three main <br />factors, including additional tree removal requirements as directed by the city, additional subgrade <br />corrections due to unsuitable soil materials, and added construction materials to address revised trail <br />alignments in the field. <br /> <br />In the Spring of 2024, it is anticipated that the city will incur additional costs to address private sprinkler <br />system repairs over several properties. <br /> <br />RECOMMENDATION: Staff is recommending that the City Council, as part of the Consent Agenda, <br />accept the improvements, approve Compensating Change Order No. 3 and approve Pay Request No. 5 <br />(Final) for the 2023 Trail Improvements. If removed from the consent agenda, the recommended motion <br />for the action is as follows: <br />