Public Works Operational Assessment
May 2025
1
Agenda
2
Project Overview
Observations
Analysis and Recommendations
Michelle
2
3
Project Overview
3
Project Goals
4
4
5
Project Work Completed
5
6
Observations
Emily
6
General Observations
7
Growth within the City is the #1 workload driver within the Department
Growth in workload has far outpaced the rate of population growth
The Department provides a high level of service, has identified appropriate service level targets, and meets those targets
Continuing to meet service level targets is likely unsustainable
Much of the City’s infrastructure is new – this will change and impacts will be negative unless planned for proactively
7
Staffing Observations
The Department last created additional Operator positions in 2019
From 2019 to 2023, the Department has experienced rapid growth in its major service areas, cumulatively increasing by:
74% increase in sewer customers
39% increase in sewer pipe length
43% increase in water customers
55% increase in water pipe length
23% increase in park acreage
8
Emily
8
Sewer Customer Accounts per PW FTE
9
9
10
Analysis and Recommendations
Michelle
10
Yearly Planning and Prioritization
Observations
Many DPW projects are seasonal or periodic
Communication to operators is task-oriented rather than project-oriented
Recommendations
Create an annual work plan to articulate when significant work initiatives are scheduled or expected to take place
Plan should identify the activities to be undertaken, which weeks of the year the activity is expected to occur, along with staffing and resource requirements
Prominently post the work plan in the workplace
Review periodically
11
11
Organizational Structure & Staffing - PTO
Observations
There has been tension between Operators wanting to take PTO and the Department wanting to be staffed to get work done
There are enough Operators with enough time off that on average at least one Operator would be absent each workday
Demand for PTO is clustered around holidays, the summer, on school breaks, etc.
The summer schedule of 9x4 + 4 has positive and negative outcomes
The longer summer hours are more productive
Everyone wants Fridays off
12
12
Organizational Structure & Staffing - PTO
Recommendations
Separate the operators into two groups during the summer, a Mon – Thurs group and a Tues – Fri group. Each group works 4 10-hour days
Everyone gets a 3-day weekend (except whoever is on call)
This may reduce total demand for PTO in the summer
10-hour days are likely to be more productive
Use the annual work plan to revisit PTO limits
Determine what minimum staffing levels are needed throughout the year
The need to be able to allow for PTO can inform the annual work plan
Potentially plan for “low power” weeks around holidays
13
13
Organizational Structure & Staffing
Observations
Workloads have increased over the last 6 years, but operator staffing has not
The Lead Operator role is not a supervisory position – but sort of is
The Lead Operator’s “span of control” is high at 8 operators
The addition of PFAS treatment will only complicate the operation of the water system
Some operators do not feel comfortable with rounds because they do not do them often
If more operators are hired, doing rounds will become less frequent for each operator
This infrequency makes it harder to train new operators, harder for existing operators to retain knowledge, and harder to gain a feel for the system.
14
14
Organizational Structure & Staffing
Recommendation
Increase staffing by 2 Operators and 1 Lead Operator
A 2nd Lead Operator will help reduce span of control, especially as more Operators are added
The 2nd Lead Operator should be scheduled opposite the 1st during summer hours, assuming 4x10 work schedules are implemented
Given the budget timing and current staff size, aim to fill 2 new positions (1 Lead Operator, 1 Operator) this year
15
15
Organizational Structure & Staffing
Recommendation
Designate ~6 Operators as Utility Specialists. Limit these operators to Operator II’s and I’s (ideally, I’s). Limit on-call rotations to this group of “Utility Specialists”
Will concentrate and amplify experience and knowledge in the mechanical / treatment components of the utility system
May require some incentive to entice Operators to be Utility Specialists
16
16
Organizational Structure & Staffing
Observations
The City recently lost an admin assistant who was assigned 0.4 FTE to DPW
DPW has need for administrative / clerical assistance
Recommendation
Hire an administrative assistant to assist with DPWs administrative needs
Ideally, this person would have PW or utility experience
This person should be computer literate, able to learn new software packages, and able to read and navigate in a map in GIS
Create a binder of SOPs for this person to use to help expand their role
This position should start at 0.5 FTE in DPW, but may be adjusted in the future
17
Adam was spending a lot of his time dealing with complaints; the AA would be developing the severity of the issue, service requests, etc. This would be a great use of the AA’s time,
especially since Adam is going to do planning. just make sure we articulate this.
17
Organizational Structure & Staffing
Observation
DPW is using non-ASCE-certified Operators to do some auto repair and maintenance
Recommendation
Either hire a certified mechanic or sign a service contract with a local vendor
Auto repair is not a core function of DPW
Having non-certified mechanics work on vehicles likely exposes the City to liability
Basic maintenance, such as oil changes or tire rotations are often included free as part of a service contract
18
18
Organizational Structure & Staffing
Observations
The City’s Parks Master Plan calls for a Parks Director
The MP does not provide guidance on role / scope of the Parks Director position
It is rare to have a Parks Director without a separate Parks Department or staff
Recommendation
Stakeholders should collaborate as to the proper role / title / timing of a Parks leadership position
Parks Advisory Board, City Council, and City staff should conduct a workshop to identify:
Position title and role
Timing of hiring
Location within the City’s organizational structure
19
Adam was spending a lot of his time dealing with complaints; the AA would be developing the severity of the issue, service requests, etc. This would be a great use of the AA’s time,
especially since Adam is going to do planning. just make sure we articulate this.
19
Work Processes
Observations
The City uses Beehive as an asset management system
Beehive appears to be well-implemented, but lacks a Parks module
Beehive is neither used as a work order system nor do Operators use it much in the field beyond as a tool for locates/GIS mapping
Recommendation
Implement Beehive as a full CMMS for DPW
Obtain the Parks module and tablets to be issued to Operators in the field
Develop Beehive’s capabilities to issue and track work orders
Invest in training for staff to learn how to use Beehive properly – write and assign work orders, enter data, search work orders, etc.
20
20
Leadership Training
Observations
Leadership / supervisory positions are often left to “figure out” how to do the leadership and supervising parts of their jobs
Morale is low among operators, some of whom report experiencing high levels of work-related anxiety
Recommendation
Obtain leadership training for the Director, Assistant Director, and Lead Operator(s) to foster the soft skills necessary for positive morale and conduct within the workplace
21
21
Safety
Observation
Safety issues were reported that outline a culture that deprioritizes safety over efficiency and productivity
Operators are concerned that jobs are assigned with fewer staff than knowledgeable 3rd parties would recommend
Recommendation
Work to instill and sustain a culture of safety
Ensure appropriate staffing for all activities that require multiple operators, specifically for street work, tree trimming, and manhole operations
Develop SOPs and guidelines for safety that are mutually agreed upon between operators and management
Provide appropriate channels to report unsafe activities or direction that undercuts agreed upon safety practices
22
22
QA