HomeMy WebLinkAboutResolution 2005-126CITY OF LAKE ELMO
WASHINGTON COUNTY, MINNESOTA
RESOLUTION NO. 2005-126
A RESOLUTION APPROVING CHANGE ORDER NO. I
FOR WATER SYS'T'EMS INTERCONNECT PHASE III PROJECT
BE IT RESOLVED, that the Lake Elmo City Council hereby approves Change
Order No. 1 for the Water Systems Interconnect Phase III Project, Chris Riley Utilities,
Inc., for the Interim Completion Date shall be December 15, 2005 to install 16" and 12"
watermain from the north side of TI-I5 to the east end of the project on 31St Street and
June 15, 2006 shall be the Completion Date for all remaining work, verified by the City
Engineer in his memo dated November 10, 2005.
ADOPTED, by the Lake .Elmo City Council the 15th day.- o €N-ax n/ er. 2005.
Dean A. Johnston, Mayor
CHANGE ORDER
TKDA
Engineers- Architects - Planners
Saint Paul, MN November 8 20 05 Proj. No. 13186.000 ` Change Order No. I
To Chris Rilpy Utilities Inc.
for Water System Interconnect - Phase III (Jamaca Avenue Stillwater Boulevard and 31 st Streets)
for City of Lake Elmo. Minnesota
You are hereby directed to make the following change to your contract dated
September 20 _ _, 2005 . The change and the work affected thereby is subject to all contract stipulations and
covenants. This Change Order will (ine-rease) (decrease) (not change) the contract sum by
ZeroDollars and 00I 1001-- ..................... .. ......... .... ..... . ......................... . .............................(S 0.00 }.
This change order provides for changes in the work of this contract according to the following:
The Interim Completion Date shall be December 15, 2005, to install 16" and .12"
watermain from the north side of TU 5 to the east end of the Project on 31 st Street.
;tune 15, 2006; shall be the Completion Date for all remaining work.
NET CHANGE
Amotint of Original Contract
Additions approved to date (Nos. }
Deductions approved to date (Nos. )
Contract amount to date
Amount of this Change Order O (Deduct) (No Change)
Revised Contract Amount
Approved. City of Lake Elmo. Minnesota TKDA
Owner
By
By
Thomas D. Pre , P.E.
Approved Chris Riley Utilities, .Inc. White - Owner
Contractor Pink - Contractor
Blue - TKDA
$ 612,000.32
$ 612,000.32
$ 612,000.32