HomeMy WebLinkAboutResolution 2007-086CITY OF LAKE ELMO
WASHINGTON COUNTY
STATE OF MINNESOTA
RESOLUTION NO. 2007-086
A RESOLUTION ACCEPTING WORK
FOR PHASE I OF THE WATER SYSTEM INTERCONNECTION PROJECT
WHEREAS, pursuant to a written contract signed with the City on April 5,
2005, Riley Brothers Construction has satisfactorily completed Phase I of the
Water System Interconnection project in accordance with such contract.
WHEREAS, the one-year Warranty for the improvements began on
November 13, 2007, and will end on November 12, 2008, and a one-year
Warranty inspection will be completed in October, 2008, and the contractor will
be required to repair or replace, as directed by the City, any work or materials
that are found to be defective, at the Contractor's sole cost and expense,
NOW, THEREFORE, BE IT RESOLVED, the work completed under said
contract is hereby accepted and approved, and,
BE IT FURTHER RESOLVED that the City Administrator and Mayor are
hereby directed to issue a proper order for the final payment on such contract,
taking the contractor's receipt in full.
Date.- November 20, 2007 CITY OF LAKE ELMO Y"\1
BY'
Dean Johnston
Mayor
ATTEST:
Susan L. Hoyt
City Administrator
This resolution. was adopted by the City Council of the City of Lake Elmo
on the 20th day of November, 2007, by a vote of 5 Ayes and 0 Nays,
Mayor Johnston - Aye
Council Member DeLapp Aye
Council Member Johnson Aye
Council Member Park Aye
Council Member Smith Aye
Resolution No.