HomeMy WebLinkAboutResolution 2007-082CITY OF LAKE ELMO
WASHINGTON COUNTY
STATE OF MINNESOTA
RESOLUTION NO. 2007-082
A RESOLUTION ACCEPTING WORK
FOR PHASE IV OF THE WATER SYSTEM INTERCONNECTION PROJECT
WHEREAS, pursuant to a written contract signed with the City on May 12,
2006, Ellingson Companies has satisfactorily completed Phase IV of the Water
System Interconnection project in accordance with such contract.
WHEREAS, the one-year Warranty for the improvements began on
October 23, 2007, and will end on October 22, 2008, and a one-year Warranty
inspection will be completed in September, 2008, and the contractor will be
required to repair or replace, as directed by the City, any work or materials that
are found to be defective, at the Contractor's sole cost and expense,
NOW, THEREFORE, BE IT RESOLVED, the work completed under said
contract is hereby accepted and approved, and,
BE IT FURTHER RESOLVED that the City Administrator and Mayor are
hereby directed to issue a proper order for the final payment on such contract,
taking the contractor's receipt in full.
Date: November 5, 2007 CITY OF LAKE ELMO
By: VIA
Dean Johnston
Mayor
ATTEST-
Susan L. Hoyt
City Administrator
This resolution. was adopted by the City Council of the City of Lake Elmo on the
5th day of November 20079 by a vote of 5 Ayes and 0 Nays.
Mayor Johnston - Aye
Council Member DeLapp Aye
Council Member Johnson Aye
Council Membef Park Aye
Council Member Smith Aye