Minutes of March 26, 2018
Chairman Dodson called to order the meeting of the Lake Elmo Planning Commission at
7:00 p.m.
COMMISSIONERS PRESENT: Emerson, Dodson, Johnson, Dorschner, Weeks, & Hartley
COMMISSIONERS ABSENT: Lundquist, Kreimer and Pearce
STAFF PRESENT: Planning Director Becker and City Planner Prchal
Approve Agenda:
The agenda was accepted as presented.
Approve Minutes: March 12, 2018
M/S/P: Dorschner/Dodson, move to table the March 12, 2018 minutes until the changes
requested are made, Vote: 6-0, motion carried unanimously.
Public Hearing – Variance – 8728 Demontreville Trail –Setback Variance
Prchal started his presentation regarding a variance request to the setback for an
accessory structure at 8728 Demontreville Trail. The structure needs to be repaired and
the applicant would like to expand. This structure is currently non-conforming because
it is 7.3 feet from the lot line when 10 is required for this district. This lot is zoned as RR,
but is substantially smaller than other RR parcels.
There are four conditions that must be met to approve the variance. 1) Practical
difficulties which the staff feels is met. This seems to be a reasonable request as
everything besides the side yard setback is met. 2) Unique circu mstances which staff
feels is met because the garage was built before zoning. 3) Character of locality which
staff feels is met because this is a heavily wooded area with the nearest home being 400
feet away. 4) Adjacent properties and Traffic which staff feels is met because a side yard
variance will not impact traffic or supply of air and light to adjacent properties.
Dorschner is wondering what the property to the North is zoned. Prchal stated that
parcel is also zoned RR and the home on that lot is over 400 feet away. Dodson asked
what the impervious coverage is. Prchal stated that there is a change to impervious, but
there is no maximum impervious amount for RR zoning district. Emerson asked if the
2
Lake Elmo Planning Commission Minutes; 3-26-18
property to the north can be developed in the future. Prchal stated that the property to
the North would need a minimum of 20 acres, but it might be difficult with the wetland.
Dorschner asked if there was discussion if something smaller might work. The applicant
Brooks Moening, stated that his preference would be to maintain the current width of
the garage. The actual concrete slab is in good shape and can be reused. To go
narrower, would be a challenge to park 2 cars inside. Moening stated that the roof is
sagging and the walls are in rough shape and the structure needs to be replaced.
Public Hearing opened at 7:17 pm
No one spoke and there were no written comments.
Public Hearing closed at 7:18 pm
M/S/P: Hartley/Johnson, move to recommend approval of the request from Brooks
Moening for a variance from minimum side yard setback, subject to recommended
findings and conditions of approval listed in the staff report , Vote: 6-0, motion carried
unanimously.
Business Item – Zoning Text Amendment – Subdivision Ordinance
Becker started her presentation regarding the subdivision ordinance update. This
update includes the Planning Commissions recommended updates from the February
26th 2018 meeting. The Planning Commission is recommending that for a minor
subdivision which results in no more than 4 parcels, there will not be a lengthy platting
process, but would require the lots to have a plat submitted with lot and block
descriptions. There is clarifying language for a lot line adjustment so there is not
confusion between a lot line adjustment and minor subdivision.
Becker stated that language was added to require a developer to provide proof that a
replacement reserve amount is created in accordance with MN statute 515(b)(3)-1141 if
a CIC community is created. The proposed ordinance codifies additional application
requirements that are currently in ordinance. Becker stated that a deadline for
recording the plat of 120 days was included to make it consistent with the major
subdivision process.
Dodson suggested on page 1 that 153.09 be changed to read “Major Subdivision –
Preliminary subdivision approval” and 153.10 be changed to read “Major Subdivision –
Final subdivision approval”. Dodson asked if all building permits are available after
approval of final plat and if D(1) should be changed to preliminary instead of final plat.
Becker stated that building permits are only allowed after a number of items outlined in
the developer’s agreement are met after final approval.
3
Lake Elmo Planning Commission Minutes; 3-26-18
Hartley is wondering in B(4) on page 4 what constitutes commercial or industrial land. It
would be hard to do based on zoning when there are mixed use districts. Becker stated
that she can check with the City attorney about that as this language was take n from
state statute.
Dodson is wondering if the Park Commission needs to review a minor subdivision.
Becker stated it is a good idea. Dodson asked what N.G.V.D. stands for. Becker stated it
is an industry term that it can be written out in the ordinance instead of abbreviated.
The Planning Commission discussed the 350 feet notification requirement and if that is
adequate. Becker stated there have not been complaints.
Dodson is wondering if under supplemental information there should be a requ irement
to submit a narrative of what has changed from sketch plan to preliminary subdivision
review and preliminary to final review. Becker stated there is already language for
preliminary to final review and she will add that from sketch plan to prelimi nary review.
Dodson asked if the variance procedures needs to say something about being consistent
with the Comprehensive Plan. Becker stated that she can add that language.
Dodson asked if the PUD section should say something about being consistent with the
Comprehensive Plan. Dodson was surprised that the PUD sections was so short. Becker
stated that the PUD information is more extensive in the zoning code. Dodson is
wondering if that section should be referenced somewhere in this code. Becker stated
that it does already refer to the PUD ordinance. Dodson thinks the specific code should
be referenced.
There was discussion about the engineering standards and if specifics should be listed in
the ordinance. Becker stated the reference is better because if the standards change,
the ordinance would need to be changed if directly in the ordinance. There was
discussion surrounding what should be included in the ordinance and what should be
included in the engineering standards. Weeks stated that the subdivision ordinance is
not just for the developer, but is also a checklist for staff and that anything that does not
conflict with engineering standards should be outlined in the ordinance .
Johnson is wondering why the City would not accept a bo nd vs. letter of credit. Weeks
thinks it is important that a developer know up front what they need in order to be able
to develop property. Emerson thinks it is a lot more difficult to collect on a bond and
takes longer to collect on it. Johnson is con cerned that a letter of credit ties up a large
amount of money and smaller developers might have a difficult time coming up with
that amount of money. Dodson is wondering if there could be wording that a bond
might be considered with City Council approval. Emerson is wondering what other
Cities do. Becker stated she is not sure, but she can pass along the bond option to the
City Council.
4
Lake Elmo Planning Commission Minutes; 3-26-18
M/S/P: Dorschner/Hartley, move to recommend approval of the proposed amendments
to the City’s Subdivision Regulations Ordinance with changes discussed , Vote: 6-0,
motion carried unanimously.
City Council Updates – March 20, 2018 Meeting
i) Wildflower at Lake Elmo 3rd Addition Final Plat & PUD - passed
ii) Hammes 3rd Addition Developer Agreement - passed
iii) Sign Variance for Park Dental – 8980 Hudson Blvd - passed
iv) Royal Golf at Lake Elmo 1st Addition Development Agreement - passed
Staff Updates
1. Upcoming Meetings
a. April 9, 2018 – cancelled
b. April 23, 2018 – Easton 4th – possible joint meeting w/CC
2. MAC CEP Report Open House April 4 at 6pm at Oakland Middle School
3. Comprehensive Plan Update – Open House April 11 7-9 pm
Meeting adjourned at 8:49 pm
Respectfully submitted,
Joan Ziertman
Planning Program Assistant