Approve Agenda:
M/S/P: Dorschner/Emerson, move to approve the agenda as presented, Vote: 4-0,
motion carried unanimously.
Approve Minutes: September 10, 2018
M/S/P: Dorschner/Dodson, move to approve the September 10, 2018 Minutes as
presented, Vote: 4-0, motion carried unanimously.
Public Hearing – Easement Vacation Request Zawadski Homes
Prchal started his presentation regarding an easement vacation request to vacate a
drainage and utility easement between 9829 and 9843 Whistling Valley Road in
Whistling Valley 2nd addition to allow combination of the two lots. Th ere is a sanitary
sewer line that runs across the front of the two lots that will need to be kept in mind
when building on the lot.
Emerson asked why the remaining part of the easement was retained. Prchal stated
that maybe the applicant could address that. Dodson asked if the two lots were being
combined, why that wasn’t included as a motion. Prchal stated the lot combination
would be done administratively. Dodson asked if this development is on community
septic and if they have looked at the potential down side of having fewer homes on the
system. Prchal stated that the president of the HOA stated that the HOA assessments
are based on the number of lots, so this would change the division of that.
Jay Johnson, Zawadski Homes, stated that the vacation should be for the entire length
of the lot and that must have been a surveyor error.
2
Lake Elmo Planning Commission Minutes; 10-10-18
Public Hearing opened at 7:11 pm
Paul Torgerson, President of Whistling Valley HOA, there are some issues created when
you take a grid of lots and change the configuration without planning for the potential
impact. The HOA board has not met to discuss this. They recently became aware of this
situation. Torgerson would request that the HOA have the opportunity to work with the
City and the homeowner to work out those issues and how those should be handled.
There is a total of 43 lots in the neighborhood. There are already a number of
circumstances where homeowners own the adjacent lot and the vacant lots are billed
differently.
Steve Zawadski, Zawadski Homes, they had anticipated this question a little bit. The
client they are working with is open to talking about what would make sense.
Public Hearing closed at 7:17 pm
Dorschner doesn’t have a problem with the easement vacation and lot combination.
Dodson’s concern that is with the approval, the HOA loses any leverage to negotiate
terms. Weeks stated that she doesn’t believe that at all. The City does not have
anything to do with HOA business. Weeks feels that is a risk of a homeowner buying in
a development that has an HOA to read and understand all of the HOA rules. Dorschner
stated that he feels this can be resolved by just adding a recommended condition of
approval that the applicant shall provide evidence that they have settled the combined
lot dues assessment with the HOA.
Weeks doesn’t think a condition of approval such as that is enforceable. Weeks thinks
that the assessment of two vacant lots is as much as the assessment for an occupied lot.
Paul Torgerson stated that it isn’t just the septic system, it is all of the costs of the
common areas. The HOA structure provides for 43 lots and it would become 42 lots.
The declarations provide for 43 lots and the City is intervening and changing the specs
for what the HOA is doing. Torgerson is not saying that is inappropriate, but they need a
step in there to change it. Torgerson’s suggestion would be to put in the condition
suggested by Commissioner Dorschner to protect the HOA.
M/S/P: Dorschner/Dodson, move to add a condition of approval that the applicant shall
provide evidence that they have settled the issue of the discrepancy of the combined lot
assessment of HOA dues for going from one lot to two lots, Vote: 4-0, motion carried
unanimously.
Weeks is still not sure how the City would enforce this. The HOA could change how they
do the assessments. For instance it could be based on square footage of homes or lots
or something like that.
3
Lake Elmo Planning Commission Minutes; 10-10-18
Dorschner stated that this is still going to the City Council and the City Attorney can
advise on how enforceable this is. Dorschner stated that his concern is with the other
people in the HOA who purchased lots based on the HOA bylaws and that should not
change based on the decisions of the City.
Weeks stated that she will vote for this amendment based on the fact that this will
probably be resolved by the time it gets to the City Council and if it isn’t, they can be
advised by the City Attorney if the condition is enforceable.
M/S/P: Dorschner/Dodson, move to recommend approval of the vacation of easements
described as the east 5 feet of Lot 2, all in Block 1 Whistling Valley 2 nd Addition,
Washington County which lies north of the following described “Line A” and south of
“Line B” as described on the survey, as approved by the City Engineer, being recorded ,
with the additional condition of approval, Vote: 4-0, motion carried unanimously.
Emerson is wondering if this will include vacating all of the easement. Prchal stated that
he will work with the applicant to make sure that is corrected. It could be that the legal
is correct and the graphic is wrong. Prchal will get that co rrected when it goes to City
Council.
Business Item – Planned Unit Development Ordinance
Prchal started his presentation regarding the Planned Unit Development Ordinance.
The City Council has requested that the Planning Commission take another look in
regards to why affordable housing would warrant 10 amenity points.
M/S/F: Dorschner/Weeks, move to send back to the City Council for a vote, Vote: 1-3,
motion fails.
Dorschner feels that they have already spent enough time on this discussion. If the City
Council doesn’t like the suggestion of 10 amenity points, they can change it. Dorschner
stated that the Comprehensive Plan is already out there. Dorschner did not f eel the City
Council gave a reason for sending it back.
Emerson is wondering if there was any reason why it was 10 points vs 5 points. Prchal
stated that there was not a whole lot of discussion about it. Prchal stated that the
Commission felt that 10 points was reasonable because it is encouraged by the
Comprehensive Plan.
Weeks is wondering if Prchal has any other experience with what other Cities do with
PUD ordinances and how they award amenity points. Prchal stated that Lake Elmo
would not be unique to give incentives for amenities. Weeks thinks that the point
system seems confusing, but understands the idea of giving incentives.
4
Lake Elmo Planning Commission Minutes; 10-10-18
Emerson stated that the amenity points and how they are rewarded is pretty vague and
open to interpretation. Weeks stated that is why she feels the amenity points are
confusing.
Weeks stated that in the PUD ordinance, the City Council has the discretion to not allow
a PUD on any given property. Dodson stated that he feels the amenity point system
makes it a little more flexible. Dodson feels that the amenity points of 10 for af fordable
housing would be the upper limit of the points that would be awarded.
Emerson doesn’t believe that the city will get a developer to come into this town with a
proposal that includes affordable housing because of the cost of the land, lots, sewe r,
etc. Emerson asked if a PUD is allowed in Medium and High Density because the only
place he sees affordable housing going in would be for an apartment building. Prchal
stated that the parcel needs to be at least 5 acres and needs to meet certain crite ria.
Weeks read the Comprehensive Plan and didn’t think 10 points was too much of an
incentive to give. Weeks feels there is a need to balance the housing types that would
be affordable for younger and older people.
Dorschner stated that all of the points that have been discussed are the reasons why the
Planning Commission chose 10 amenity points in the first place. Dorschner does not see
the value in continuing the discussion. Dorschner is wondering why the amenity points
are not a range like some of the other categories. Depending on what type of
affordable housing, different points could be awarded.
Dodson thinks the language on page 5 which states that some amenities may be
awarded a range of amenity points needs to be clarified. Dodson wants to know if a
category states a specific number, is it up to that number or is just that number.
Dodson feels that all categories should be zero to the maximum, with the City having
discretion. Prchal stated that this would give the City more flexibility and he doesn’t see
that as being a bad thing.
The Planning Commission would like to change the title in table 16 to say “points range”
and for each amenity put a range from minimum to the maximum.
Dorschner is wondering if the amenities are standard for most communities or if these
are unique to us. Dorschner stated that Lake Elmo is in a high radon area and he would
like to see radon mitigation systems or vapor intrusion system installed in new ho mes in
Lake Elmo. If amenity points were awarded, it would provide a safer house and it is
cheaper for the homeowner to have it installed when the home is built. Dorschner
would like to see a radon mitigation system or vapor intrusion system to be instal led to
be compliant with state standards added to the amenity table.
5
Lake Elmo Planning Commission Minutes; 10-10-18
M/S/P: Dorschner/Dodson, move to add amenity points for the installation of active soil
vapor intrusion systems (radon) into residential properties with a range of 1-5 amenity
points, Vote: 4-0, motion carried unanimously.
City Council Updates – September 18, 2018
1. Environmental Performance Standards Tree Preservation – passed
2. Boulder Ponds 4th Addition – passed
3. Boulder Ponds 4th Addition Developer Agreement – passed
4. River Valley Christian Church CUP Amendment – Passed
City Council Updates – October 2, 2018
1. No Parking Ordinance Update -
Staff Updates
2. Upcoming Meetings
a. October 22, 2018
b. November 14, 2018 (Wed)
Meeting adjourned at 8:13 pm