HomeMy WebLinkAbout12-02-86 CCMSince we do not have time to discuss every point presented, it may seem
that decisions are preconceived. However, background information is
provided for the City Council on each agenda item in advance from City
Staff and appointed Commissions; and decisions are based on this
information and past experiences. In addition, some items may also have
been discussed at previous Council meetings. If you are aware of
information that hasn't been discussed, please fill out a "Request to
Appear Before the City Council" slip; or, if you came late, raise your
hand to be recognized. Comments that are pertinent are appreciated.
Items requiring excessive time may be continued to another meeting.
AGENDA
LAKE ELMO CITY COUNCIL
DECEMBER 2, 1986
7:00 p.m. MEETING CONVENES
1.. Agenda
2. Minutes: November 18, 1986
3. Claims
4. Public Inquiries
A. Street Light Petition, Guardian Angels Church
B. Water Problems on 31st Street, Area Residents
7:30 p.m. 5. Public Hearing : Request for Variance to Allow a
Second Accessory Structure in the R-1 District;
Request to Exceed the Maximum Square Footage for
Two Accessory Buildings; Request to Exceed the
Sideyard Setback -Russell Anderson,
3373 Lake Elmo Avenue N.
8:00 p.m. 6. Public Hearing : Request for Variance to the
Size of an Accessory Structure in the RR District -
Walter Goetschel, 11825 50th Street N.
-------------B R E A
7. CITY ENGINEER'S REPORT
A. Protected Waters Permit: Channel Crossing
at Eagle Point Lake Inlet Channel.,
Washington County
B. Resolution on CSAH 1.5 (Manning Avenue)
C. Resolution for MnDOT Project on TH 36
(over)
D. Shoreland Permit: Tartan Park
E. Protected Waters Permit: Temporary
Dewatering & Discharge to Eagle Point
Lake
8. CITY ATTORNEY'S REPORT
A. Castle Design Appeal Results
9. CITY ADMINISTRATOR'S REPORT
A. Application by Med Plus Transportation
Services for a scheduled advanced life
support transportation service license
k=
APPROVED
LAKE ELMO CITY COUNCIL MINUTES
DECEMBER 2, 1986
Acting Mayor Christ called the City Council meeting to order at
7:02 p.m. in the City Council Chambers. Present: Christ,
Armstrong (arrived 7:08 p.m.), Dunn, Mazzara, City Engineer
Bohrer, City Attorney Knaak, and City Administrator Overby.
Absent: Morgan
1. Agenda
Add: 9B. Cottage Grove Ravine Representative, 9C. Fire
Department CIP: Tanker Purchase, 9D. Evaluation of City
Administrator
M/S/P Dunn/Mazzara - to approve the Agenda for the December 2,,
1986 City Council meeting as amended.. (Motion carried. 3-0).
2. Minutes: November 18, 1986
M/S/P Christ/Mazzara - to table the November 18, 1986 City Council
minutes for added information. (Motion carried 4-0).
3. Claims
M/S/P Dunn/Ma.zzara - to approve the December 2, 1986 claims #88067
thru #88131 as presented. (Motion carried 4-0).
4. Public Inquiries
A. Street Light Petition, Guardian Angels Church (Amended 12-16-86)
request
The Church of Guardian Angels had presented the City with a f-arffia-1-
petit-'ran for a street light at the intersection of Guardian Angels
Avenue and 4th Street. The City Policy is that the petitioner pay
the cost of installation and the City pay for the electricity
cost.
The City Council recommended that this request be passed on to the
City Engineer for his review of the proposed area and to consult
with NSP as to the electricity cost per year. The City
Administrator will. clarify the City's Street Light Policy. A
report will be brought back to the City Council at their next
meeting.
B. Water Problems on 31st Street, Area Residents
Residents of the 31st Street area (Friedrichsvi.11e) wanted to
discuss their water problems and ask for the support of the
Mayor/City Council in their request to the Valley Branch Watershed
District to order/petition for a drainage project to alleviate the
high water. problems.
LAKE ELMO CITY COUNCIL MINUTES DECEMBER 2, 1986 PAGE 2
City Administrator Overby reported that the residents had met with
the VBWD at their last meeting. Nels Nelson was said to have
indicated that a project could be designed to help that area.
However, Overby thought that the residents misunderstood the
managers' comments and bad the opinion that a project could be
started. Allen Dornfeld had told Overby that this could not
possibly happen since they need to be sure that the Project 1007
system is working properly before additional flow is allowed into
that system. Dornfeld thought that 1 to 3 years might be needed
to prove that the system was working properly.
Rose Armstrong added that in the VBWD minutes it was stated that
their Engineer was to report water and basement levels in that
area back to the board.
The City Council suggested that the City Administrator contact the
person that requested this to be on the agenda and explain that
the City Council was unable to address their concerns since nobody
showed up for the meeting.
5. PUBLIC HEARING: Request for Variance to Allow a Second
Accessory Structure in the R-1 District; Request to
Exceed. the Maximum Square Footage for Sideyard Setback --
Russell Anderson, 3373 Lake Elmo Avenue N.
Acting Mayor Christ opened up the public hearing at 7:38 p.m. in
the City Council Chambers.
Russell Anderson would like to build a new 30' by 32' (960 square
feet) garage in the R-1 zoning District. This building would
replace an existing second accessory structure (garage) that will
be removed. A one-story detached residential garage up to 1000
sq.ft. is allowed under section 301.130 C. l.b. "Types of
Accessory Buildings". The proposed garage is just under the limit
at 960 sq.ft.
1. A variance to allow the second accessory structure (the
new garage) would be needed, as Section 301.130 C. 14
"Number of Accessory Structures" indicates that only
one building is allowed.
2. A variance to exceed the maximum square footage for two
accessory buildings would be needed. The new garage and
the existing storage shed. have a total square footage of
1482, where the code allows up to 1000 total square footage.
3. A variance from the sideyard setback of 10 feet would be
needed to allow the new garage to be built in the location
indicated on the site plan. The plan indicates that the
garage would be approximately 6 feet from the side yard
property line.
Mr. Anderson stated he was not willing to take down the 18 x 29
storage shed. He would like the larger building because he has
LAKE ELMO CITY COUNCIL MINUTES DECEMBER 2, 1986 PAGE 3
plans for retirement and needs the extra room for his hobbies. A
hardship given was the inability to use the current garage for
vehicle turnaround, but there was not a hardship given for the
size variance. If the garage was made smaller, it could meet the
sideyard setback.
City Attorney Knaak suggested amending the accessory building code
to allow it later.
Arlyn Christ closed the public hearing at 7:45 p.m.
Because there was no hardship stated for the size of building, Mr.
Anderson stated he would come back with a revised plan before
Spring.
6. PUBLIC HEARING: Request .for Variance to the Size of an
Accessory Structure in th RR District --
Walter Goetschel, 11825 50th Street N.
Mr. Walter Goetschel wants to build an accessory structure to
serve as a machine shed to shelter farm equipment, lawn mowers, a
wood splitter, tractors and snow removal equipment. This type of
accessory structure is referred to in the City Code (Section
301.130 C.) as a "Detached Rural Storage Building". A building of
this type is allowed up to 1000 sq.ft. in size, if it is located
on a parcel less than 10 acres, which is the case here (5 acres).
Acting Mayor Christ opened up the public hearing at 8:00 p.m. in
the City Council. Chambers.
Mr. Goetschel was not sure if he would build this Winter. He could
not come up with a hardship for approval of the variance request.
Councilman Mazzara explained that the intent makes sense, but the
request is for a building three times larger than the code allows.
Councilwoman Armstrong suggested to Mr. Goetschel to see if he
could add on more acreage onto his .five acres. This would enable
him to build a larger building.
Will Turnbladh, neighbor, stated he had no objections to this
request.
Arlyn Christ closed the public hearing at 8:05 p.m.
Arlyn Christ suggested tha.t the Planning Commission consider the
code amendments to pro -rate accessory building size for over ten
acres.
M/S/P Armstrong/Dunn - to deny a request for a Variance to the
Size of an Accessory Structure in the RR District from Walter
Goetschel, 11825 50th St. N. based upon no hardship was
demonstrated. (Motion carried 4-0).
The City Council suggested that Mr. Goetschel meet with the City
Administrator to go over other possible options.
LAKE
ELMO
CITY COUNCIL MINUTES
DECEMBER 2, 1986 PAGE 4
7.
CITY
ENGINEER'S REPORT
A. Protected Waters Permit: Channel Crossing at Eagle Point
Lake Inlet Channel, Washington County
The Washington County Parks Department has applied for a DNR
permit to construct a culvert crossing at the inlet channel to
Eagle Point Lake. The location of the proposed crossing is south
of the intersection of 28th Street and Ivy Avenue on park
property. The purpose of the crossing is to provide access to the
northwest area of the park for maintenance vehicles. In the City
Engineer's report of November 26, 1986 Bohrer stated that the
crossing consists of 18 lineal feet of 42" x 24" arch culvert with
aprons installed in the channel. with minimum granular fill over
the top for a driving surface. This crossing will be under water
during most spring runoffs, but be useable during summer and fall
when park maintenance is done. Bohrer understands that the
crossing was designed in coordination with. VBWD engineers so as to
cause no backup of water outside of the park boundaries. On that
basis, he has no objections to the stream crossing.
City Engineer Bohrer recommended that the City comment to the DNR
that the City has no objections to the crossing as long as no
water is backed up off' the County park land and as long as the
VBWD approves.
M/S/P Christ/Dunn - to approve the Eagle Point Park Fork Channel
Crossing, but to include the comment to the DNR that the City has
no objections to the crossing as long as no water is backed up off
the County park land and as long as the VBWD approves. (Motion
carried 4-0).
B. Resolution on CSAH 15 (Manning Avenue)
The City Council had decided at the November 18, 1986 meeting to
have the City Attorney review the language of the revised
resolution and to have the City staff meet with West Lakeland
supervisors to find out their desires on a possible agreement for
maintenance of the existing Manning Avenue that will eventually be
turned back to the City and township from the County.
Mr. Dick Herold, Design/Construction Engineer, stated in his
letter, dated December 2, 1986, that the County must maintain that
portion of Manning Avenue within the township for 2 years after
turnback. Since turnback cannot occur until the new road is
operational, the earliest that the County can relinquish
maintenance of Manning Avenue is late 1989. Work on new Manning
Avenue should be completed in late 1987. Since the County must
maintain the portion of Manning Avenue N. to be turned back to the
township, they intend to maintain that portion of Manning Avenue
N. to be turned back to the City for the same two years.
City Engineer Bohrer and Foreman Dan Olinger meet with West
Lakeland Township and discussed some maintenance difficulties. A
LAKE ELMO CITY COUNCIL MINUTES DECEMBER 2, 1986 PAGE 5
main concern is a turnaround in order to make it convenient for
Lake Elmo to maintain. The State Aid Engineer confirmed that this
extending of 20th Street meets the state aid criteria. Bohrer
recommended approval of the resolution, and at a later date the
city staff will work out a maintenance agreement with West
Lakeland Township and bring it back to the City Council.
M/S/P Mazzara/Dunn - to adopt Resolution 86-47 altering the
designation of County State Aid Highway No. 15 (C.S.A.H. 15)
within the corporate limits of the City of Lake Elmo and West
Lakeland Township, based. on the recommendations of the City
Engineer and City Attorney. (Motion carried 4•-0).
C. Resolution for MnDOT Project on TH 36
MnDot is planning to replace the two old Soo Line Railroad bridges
over TH 36 in 1987. The rail line was abandoned and has now
become a DNR trail. The bridges are deteriorating and will be
replaced with a large (concrete) culvert structure to allow the
continued use of the trail. The work will be constructed one-half
at a time in order to maintain traffic.
The City's approval is required for any trunk highway work within
its corporate limits. MnDOT has asked that the City Council
approve the "Resolution for Layout Approval".
City Engineer Bohrer has reviewed the plans for the work and
recommends that the City Council approve the resolution.
M/S/P Mazzara./Dunn - to adopt Resolution 86-48 for Layout Approval
as requested by MnDOT and as recommended by the City Engineer.
(Motion carried, 4-0).
D. Shoreland Permit: Tartan Park
The VBWD project now under construction will lower, the level of
Horseshoe Lake and Tartan Park Ponds. Tartan Park would like to
reclaim portions of the golf course that have been unusable for
the last ten years due to high water. Two years ago, Tartan Park
was granted a permit and installed a large storm sewer to enclose
the flow between Elmo and Horseshoe Lake as it passes through the
park. They would like to expand on this project by installing a
new storm sewer between fairway #10 and #11 ponds where an open
channel now exists. They would also like to extend the east and
west ends of the 36" storm sewer which they installed in 1985 to
improve the 9th tee. They want to coordinate this work with the
VBWD project this winter while Horseshoe Lake is lowered for
construction. This work is within the Shoreland District and
Shoreland Regulations apply.
City Engineer Bohrer has reviewed the construction plans for the
work and it appears that the storm sewer is designed to convey the
100 year discharge from Lake Elmo, as it should be. Bohrer added,
that since the entire drainage system must function together as
one unit, the City's approval must be conditioned upon Tartan Park
LAKE ELMO CITY COUNCIL MINUTES DECEMBER 2, 1986 PAGE 6
receiving VBWD approval. No variances from the Ci.ty's Shoreland
Regulations are required.
Bohrer recommended that a Shoreland Permit be granted to Tartan
Park for this work contingent upon Valley Branch Watershed
District approval.
M/S/P Dunn/Armstrong - to approve a Shoreland Permit for Tartan
Park and recommend that the DNR grant Tartan Park a permit to work
in protected waters as part of their storm sewer project;
contingent upon Valley Branch Watershed District approval.
(Motion carried 4--0).
E. Protected Waters Permit: Temporary Dewatering & Discharge
to Eagle Point Lake
The Valley Branch Watershed District is applying to the DNR for a
permit to remove surface and groundwater as they approach the
Tri-Lakes area from their present work area north of TH 5.
The permit would allow removal of this water as part of the
drainage project. The water would be stored behind the new Eagle
Point- Dam, presently under construction. They propose to store up
to 92 acre feet at the Eagle Point Dam, at an elevation of 896.5.
The stored water will be released when the outlet to the St. Croix
River is completed.
City Engineer Bohrer stated that this work is necessary for
construction and will not impact the downstream areas. Therefore,
he recommends the permit approval.
M/S/P Christ/Armstrong - to approve the Valley Branch Watershed
District request from the DNR for a Protected Waters Permit and
forward these comments to the DNR. (Motion carried 4-0).
8. CITY ATTORNEY'S REPORT
A. Castle Design Appeal Results
City Attorney Knaak stated the appeal was heard in September and
the State Appeals Court rendered a verdict entirely in the City's
favor. Being that the City has prevailed on all the significant
issues, this opinion will have significant impact on Lake Elmo
law. Knaak stated that the substandard. lot size was a
self-created hardship which didn't warrant granting of the
variance. The owners knew they were buying a lot which didn't
conform to city code regarding lot size and sewer requirements.
Knaak thanked City Engineer Bohrer for his information, which was
an important factor in the court's opinion. Castle Design does
have thirty days in which to appeal.
9. CITY ADMINISTRATOR'S REPORT
A. Application by Med Plus Transportation Services for a
scheduled advanced life support transportation service
license.
LAKE ELMO CITY COUNCIL MINUTES DECEMBER 2, 1986 PAGE 7
The City Council decided not to comment on the application by Med
Plus Transportation Services to the Metro Counci.l's Health
Planning Board and the MN Dept. of Health for a license to provide
scheduled advanced life support transportation service in order to
transfer patients to or from all Health One care facilities in the
seven -county metro area.
B. Cottage Grove Ravine WMO Representative
Mr. Tom Armstrong has served as the Lake Elmo representative,
which is a non-paying position, on the Cottage Grove Ravine Water
Management Organization since November 16, 1986. Mr. Armstrong
has requested that he be re -appointed for the new term which will
be for three years starting November 16, 1986.
M/S/P Dunn/Mazzara - to reappoint Tom Armstrong to serve as Lake
Elmo's representative to the Cottage Grove Ravine WMO for a three
year term starting November 16?jl986. (Motion carried 4-0).
C. Fire Dept. CIP - Tanker Purchase
Chief Fran Pott explained their intention to ,proceed with the
purchase of a new tanker truck in 1987, as scheduled in the
Capital Improvement Program. The estimated cost of the truck is
$75,000. The Fire Dept. pould like to keep the old tanker truck
as opposed to selling it. The old truck and another unit would be
placed in the old maintenance garage on Jamaca Avenue. The City
Council confirmed that they would support the direction that the
Fire Department was taking.
D. Evaluation of City Administrator
There will be an annual performance evaluation of the City
Administrator on December 16, 1986 at 6:30 p.m., before the
regular scheduled City Council meeting. Arlyn Christ will meet
with Mr. Overby before this date because he will be out-of-town
and will miss the December 16, 1986 meeting.
E. Christmas Party
The Christmas Party will be tentatively scheduled for Friday,
January 2, 1987.
M/S/P Christ/Mazzara - to schedule the Christmas Party for Friday,
January 2, 1987. (Motion carried 4-0).
M/S/P Dunn/Mazzara - to adjourn the City Council meeting at 9:07