Laserfiche WebLink
9 <br />Engineer Boehm's Report Continued <br />MSP (Rustad /Blanchard) To approve change order #2 for Schedule E, Well #3 <br />deducting $792.00 from the contract and adding $137.50, net change of $654.50. <br />r"1 Adjusted completed contract price $24,607.50. <br />MSP (Blanchard /Nelsen) To approve the final estimate for Layne- Minnesota <br />with HUD concurrence and to enter into a one year maintenance agreement on <br />1968 -3 Schedule E Well #3. <br />A number of residents questioned what was happening with the water system <br />construction which was taking place. Some discussion of HUD project ensued. <br />MSP (Hessen /Hodges) To adjourn at 11:08 P.M. 4 Ayes <br />Ryspectfully Submitted, <br />Dennis S. Zyl <br />Clerk- Administrator <br />,e& <br />4 Ayes <br />4 Ayes <br />