• Preliminary Edgewood Signal\Realignment <br /> Estimated Schedule& Submittals <br /> MnDot: Signal Justification Report Submittal- September 2nd <br /> MnDot: Signal Justification Report Verbal Approval - September 8th <br /> MnDot: Preliminary Plan Submission- Mid October Complete <br /> MnDot: Cooperative Agreement Funding - Submit with Preliminary Plan and SJR by October 31 <br /> for Fiscal Year 1999 Funding-Release in June of 1998 <br /> Ramsey County: TH 10 Turnback- Continually keep Dan Solar informed on the process <br /> MnDot : Permits (access, work on ROW) - Winter 97/98 <br /> MSA: Apply for MSA funds - Winter 97\98 <br /> Developer: Submit Plans for Development Review-October 97 <br /> Developer: Planning Commission Approvals -November/December 97 <br /> Developer: Council Approvals - January\February 98 <br /> Developer: Begin Construction-March\April 98 <br /> Developer: Opening - Fall 98 <br /> S <br />