Prepared January 24, 2008 <br />Infrastructure Improvement Program <br />Street and Utility Improvement Project <br />Typical General Schedule <br />The following is a typical generalized schedule for individual projects associated with the <br />Mounds View Street and Utility Improvement Program which was adopted on October 22, 2007. <br />Each project name will be based on the year(s) in which construction occurs. <br />Data Collection / Survey Work Begins September 1, construction year-2 <br />Neighborhood Meeting October, construction year-2 <br />Order Feasibility Report December, construction year-2 <br />Second Neighborhood Meetings (if needed)March, construction year-1 <br />Public Improvement Hearing,April, construction year-1 <br />Feasibility Report Approved, Project Ordered, <br />Preparation of Plans and Specifications Authorized <br />Plans and Specifications approved, Set Bid Date October, construction year-1 <br />Permits from Other Agencies December, construction year-1 <br />Open Bids January, construction year <br />Award Construction Contract February, construction year <br />Neighborhood Preconstruction Meeting March, construction year <br />Construction Begins (Phase 1)May/June, construction year <br />Construction Completed (Phase 1)November, construction year <br />Construction Begins (Phase 2)May/June, construction year +1 <br />Placement of Bituminous Wear Surface (Phase 1)July/August, construction year +1 <br />Construction Completed (Phase 2)November, construction year +1 <br />Placement of Bituminous Wear Surface (Phase 2)July/August, construction year +2 <br />* This is a “typical” schedule for projects associated with the Mounds View Street and Utility <br />Improvement Program. Dates for specific projects, however, may be modified and/or revised as <br />necessary to accommodate specific circumstances of that project.